The document provides a status update for structural drawings submitted for the 660 MW Lucky Power Plant Project. It includes a table listing 14 structural drawings with their submission date, current status, and the organization responsible for reviewing the structure. The majority of the submitted structures are still pending review and approval, with 9 currently under review and 34 already approved. 106 structures have yet to be submitted.
The document provides a status update for structural drawings submitted for the 660 MW Lucky Power Plant Project. It includes a table listing 14 structural drawings with their submission date, current status, and the organization responsible for reviewing the structure. The majority of the submitted structures are still pending review and approval, with 9 currently under review and 34 already approved. 106 structures have yet to be submitted.
The document provides a status update for structural drawings submitted for the 660 MW Lucky Power Plant Project. It includes a table listing 14 structural drawings with their submission date, current status, and the organization responsible for reviewing the structure. The majority of the submitted structures are still pending review and approval, with 9 currently under review and 34 already approved. 106 structures have yet to be submitted.
The document provides a status update for structural drawings submitted for the 660 MW Lucky Power Plant Project. It includes a table listing 14 structural drawings with their submission date, current status, and the organization responsible for reviewing the structure. The majority of the submitted structures are still pending review and approval, with 9 currently under review and 34 already approved. 106 structures have yet to be submitted.
Structure Submission / Revised Status Structure is
Volume Submission Date Under
S5201 CIVIL CONSTRUCTION DRAWING 2019-5-6 NESPAK Responded SEPCO III OF CIRCULATING WATER PIPE - Response From SEPCO III is awaited S5319 CIVIL CONSTRUCTION DRAWING 2019-5-12 Under Review by NESPAK OF FLOCCULATE AND NESPAK SEDIMENTATION POND S5322 CIVIL CONSTRUCTION DRAWING 2019-5-12 NESPAK Responded SEPCO III OF CHEMICAL DOSING ROOM - Response From SEPCO III is awaited S5501 CIVIL CONSTRUCTION DRAWING 2019-5-9 Under Review by NESPAK OF POTABLE WATER, SERVICE NESPAK WATER AND FIRE-FIGHTING WATER BASINS T0211 CONSTRUCTION DRAWING OF 2019-5-11 Under Review by NESPAK UNDERGROUND FACILITY AND NESPAK ANCILLARY EQUIPMENT OF MAIN POWER HOUSE T0214 FLOORS OF DEAERATOR BAY 2019-5-4 NESPAK Responded SEPCO III - Response From SEPCO III is awaited T0227 CONSTRUCTION DRAWING OF 2019-5-3 NESPAK Responded SEPCO III BOILER FRONT PLATFORM - Response From SEPCO STRUCTURE III is awaited T0305 STEEL FLUE DUCT SUPPORT IN 2019-5-15 Under Review by NESPAK REAR OF BOILER NESPAK T0702 STRUCTURAL DRAWING OF 2019-5-7 NESPAK Responded SEPCO III BOILER MAKE-UP WATER - Response From SEPCO TREATMENT ROOM III is awaited T0236 STRUCTURAL DRAWINGS OF 2019-5-3 Already Approved on SEPCO III BOILER ROOF 13-05-2019 Current Status of 660 MW Lucky Power Plant Project Overall Status of the Project
Total Submitted Structures = 43
Approved Structures = 34
Under Review Structures = 9 (Please refer to the following table for detailed status)