General: Technical Note Overwrites
General: Technical Note Overwrites
General
The steel frame design overwrites are basic assignments that apply only to
those elements to which they are assigned. This Technical Note describes
steel frame design overwrites for AISC-ASD. To access the overwrites, select
an element and click the Design menu > Steel Frame Design >
View/Revise Overwrites command.
Default values are provided for all overwrite items. Thus, you do not need to
specify or change any of the overwrites. However, at least review the default
values for the overwrite items to make sure they are acceptable. When
changes are made to overwrite items, the program applies the changes only
to the elements to which they are specifically assigned; that is, to the ele-
ments that are selected when the overwrites are changed.
Overwrites
For explanation purposes in this Technical Note, the overwrites are presented
in Table 1. The column headings in the table are described as follows.
• Possible Values: The possible values that the associated overwrite item
can have.
• Default Value: The default value that the program assumes for the asso-
ciated overwrite item.
General Page 1 of 5
Steel Frame Design AISC-ASD89 Overwrites
Overwrites Page 2 of 5
Steel Frame Design AISC-ASD89 Overwrites
Overwrites Page 3 of 5
Steel Frame Design AISC-ASD89 Overwrites
The overwrites are displayed in the form with a column of check boxes and a
two-column spreadsheet. The left column of the spreadsheet contains the
name of the overwrite item. The right column of the spreadsheet contains the
overwrites values.
Initially, the check boxes in the Steel Frame Design Overwrites form are all
unchecked and all of the cells in the spreadsheet have a gray background to
indicate that they are inactive and the items in the cells cannot be changed.
The names of the overwrite items are displayed in the first column of the
spreadsheet. The values of the overwrite items are visible in the second col-
umn of the spreadsheet if only one element was selected before the over-
writes form was accessed. If multiple elements were selected, no values show
for the overwrite items in the second column of the spreadsheet.
After selecting one or multiple elements, check the box to the left of an over-
write item to change it. Then left click in either column of the spreadsheet to
activate a drop-down box or highlight the contents in the cell in the right col-
umn of the spreadsheet. If the drop-down box appears, select a value from
the box. If the cell contents is highlighted, type in the desired value. The
overwrite will reflect the change. You cannot change the values of the drop-
down boxes.
When changes to the overwrites have been completed, click the OK button to
close the form. The program then changes all of the overwrite items whose
associated check boxes are checked for the selected members. You must click
the OK button for the changes to be accepted by the program. If you click the
Cancel button to exit the form, any changes made to the overwrites are ig-
nored and the form is closed.
Important note about resetting overwrites: The program defaults for the
overwrite items are built into the program. The steel frame overwrite values
that were in a .edb file that you used to initialize your model may be different
from the built-in program default values. When you reset overwrites, the pro-
gram resets the overwrite values to its built-in values, not to the values that
were in the .edb file used to initialize the model.