PART-III
PREAMBLE
1. The existing AP Standard data for various constructions items are based on observations made
several decades back, mostly utilising eployment of machinery was at the barest minimum. The
Board of Chief engineers have been adopting almost the same data, duly modifying the rates of
labour; materials, hire charges of limited machinery, every year. The advent of construction
machinery and its usage in construction industry has changed the structure and methodology of
data formulation & rate structure and hence, the present estimation of work item rates are not
reflecting ground reality. The CWC(Ministry of Irrigation) has also recommended that ”where
standard or schedule of rates are revised or where is necessary to do so, the primary guiding
principle should be escalation in labour and material cost and not on trend of rates quoted by
contractors”. But the above recommended principle is not being followed by the Board of Chief
Engineers in Andhra Pradesh.
2. Government, in GO 7326 (GAD-GPM& AR) Dated 26-10-05, has observed that the age old
“Standard data” requires revision and updation with reference to the latest machinery and
contemporary practices and has constituted a High Level Committee to advise on updating and
revision of standard data and schedule of rates. The work has been taken up by CGG and SPIU-
irrigation. The secretary (Irrigation ) is the member- convener of the committee Accordingly the
data has been revised adopting the procedures and guidelines given by CWC, Report on
“committee on cost control of river valley Projects, BIS specifications, NHAI, MORTH, MORD, CPWD
and Government of Karnataka and revised data and formulated schedule of rates for all
infrastructure Departments (I&CAD, R&B, PR and PH). The team of senior engineers interacted
with the S.R Committee of Karnataka on implementation and improvements needed. For irrigation
works the data pattern as adopted by Karnataka has been considered and for other Departments
the data adopted by MORTH,MORD and NHAI etc., is adopted
(a) The first step is the revision and formulation of standard data for each work
component
(b) The second step is to work out the details of inputs. This enables to generate the unit
work item rates, by incorporating the use rates of machinery, materials, labour charges
and other supplementary parameters
(c) The third step is to develop software tool to generate unit rate using the software
(completed for irrigation works by the SPI Unit of Irrigation)
4. The Detailed draft data was communicated to all the HODs and interacted through many
seminars and discussions and incorporated the relevant features.The Board of chief engineers in
their meetings have recommended for acceptance to the data formulated and schedule of rates.
2
STANDARD DATA – USER GUIDELINES
It was proposed to examine the recommendations on important parameters, to refer to high level
committee, for their specific recommendations for adoption, as they are common to all
departments. The committee made in depth study on the methodology and systems followed by
the reputed National organizations and other States and made detailed deliberations with HODs
and representatives of Builders Association of India and made recommendations to the
Government, on adoption of such parameters in A.P.
5. The Chief Secretary held a detailed discussions on 04-07-2007,with the Secretaries of the
Departments and Heads of Departments.
B. GUIDELINES
1) The Revised Standard Data is formulated under four Parts which are applicable to all the
Engineering Departments and other Organisations.
PART -1: Irrigation& CAD (Dam and Allied Works, Canals And Allied Works, Canal C.D.
Works, Tunnels and Allied Works, Preliminary and Maintenance Works, Hydraulic
Gates and allied works and Leads and Lifts applicable to all Departments
PART -2: Roads and Bridges
PART -3: Buildings including Electrical Works
PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS DONE BY MANUAL
MEANS)
3
STANDARD DATA – USER GUIDELINES
hours for the purpose of equipment planning and utilisation. The daily out-put is computed duly
considering the actual available working time and feed back from the field.
For gate and hoist works it is the general practice to specify the quantity of work in
terms of number of sets of embedded parts / gates. The requirement of machinery and work-
force for cutting, bending, fabrication, erection, painting etc., is assessed to commensurate with
the task involved.
The data for gates and E.M. Parts is arrived per Ton quantity.
The data for Hoists and Gantry Cranes is worked out on the basis of capacity in tonnage
4) The lead and lift charges provided in PART-I (B) are generally applicable and common to all
Departments. Any item is not covered in this part, the rates as provided in the data of the
relevant works may be adopted in preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in the data. The
requirements are analyzed and the specifications adopted shall confirm to Standards published by
the BIS.
The labour and material rates will be communicated by the Board of Chief engineers.
Unless otherwise specified, all material rates shall be inclusive of all taxes, duties, levies,
royalty/seigniorage, transportation and handling costs up to project area.
For sand, gravel , murum, stones , course aggregates etc, the rates are to be fixed for
delivery at Quarry, adding seigniorage ( royality) charges, loading charges by machinery /
manual means and idle hire charges of machinery (as per table under chapter “
conveyance or lead and lift charges”), as applicable.
For earth/ soil for embankment works from borrow areas, which is not included in the
material list of schedule of rates, seigniorage charges are to be added separately,if
applicable.
For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs, the rates are
to be taken prevailing at major commercial centre near project area. The lead charges, as
applicable are to be added in preparing estimates.
The specifications of the aggregates for sizes and gradation and its adoption shall be as
per IS 383.
6) The labour component in the data is mentioned for unit work.
No allowance towards labour importation and labour amenities added extra as they are
included in the recommended overheads.
On Labour Component: Certain additional allowances are added extra to the wages of
labour (,i.e. only on labour component in the work item) in the form of percentage, as
recommended by the Government/Board of chief engineers,due to statutory and other
provisions.
4
STANDARD DATA – USER GUIDELINES
However, If more than one area allowances, such as those for (1) Municipalities (2)
Agency / Tribal areas (3) Industrial areas are applicable for a particular situation, only the
maximum out of the allowable percentages is to be allowed.
The hire charge of a machinery / equipment is worked out based on the guidelines
published by CWC and BIS codes.
For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH.
8) Lead Charges
The high level committee has recommended to adopt, for conveyance by head load, a
minimum lead of 50 meters and additional lead up to 150 meters in the intervals of 50
meters. Beyond 150 meters lead ,only machinery rates are to be adopted.
The basic item rates provided in the schedule of rates include 50 m or 1 km as initial lead
and no lead charges shall be allowed where the source of material is within the initial
lead specified in item rate. Additional lead charges shall be allowed for the lead
exceeding initial lead specified in the item rate.
The lead charges per unit quantity for conveyance of the materials are worked out,and
included in the schedule of rates in increment of 50 m for head load and in increment of
1 km for mechanical mode.
The rates for lead charges by head load upto 150 meters and by machinery up to 5 km,
shall be cumulative and inclusive of lead charges for preceding lead. For lead beyond 5
km the lead charges shall be worked out on per km basis.
9) Loading and Unloading charges for Materials
The following features are considered:
(a) Loading and unloading charges are not payable for conveyance by head load.
(b) Loading and unloading charges are not payable for conveyance by mechanical
means, for disposal of excavated material unless specified.
(c) The rates for unloading of materials except earth, sand, gravel, coarse aggregate,
rubble, size stone and cut stone, are inclusive of stackingwherever applicable.
10) LIFT CHARGES :
5
STANDARD DATA – USER GUIDELINES
The data includes initial lift charges of 3 meters ,for materials conveyance by head load,
Additional leads in the interval of 1.0 meters are worked out, as additional labour input
and incorporated in the chapter on” Lead and lifts” .
Where the conveyance / lifting of material is done by mechanical means, lift charges shall
not be considered, as the cycle time of operation of the machine includes lifts involved.
The data and rates for lift charges is cumulative and are inclusive of rates for preceding
lifts also.
11) Wastage of Materials
Cement : No wastage allowance is recommended towards the quantity of cement
used in works, as the wastage is already included in the input and in major works
bulk quantities are used.
steel : The wastage of steel @ 2.5% is allowed for gates and allied structures. For
RCC works the wastage is @2.5% for the reinforcement rods above 36mm did and
@ 5% for rods below 36mm dia. including overlaps, if they are not welded. If welding
is adopted for the reinforcement rods even for below 36mm dia, 2.5% of wastage is
only recommended.
12) Provision for rate for water:-
The Committee has recommended not considering the water charges in the Irrigation
Project works. But, it may be considered in specific cases as per the site conditions.
13) In respect of RCC works the rate for cement concrete for 1 cum is worked separately for
all grades based on Indian Standards. The rate for ton is calculated separately and to be added
separately in the estimates of RCC works as a separate item.
14) Soil classification: The Committee recommended to allow uniform classification of soils for all
Departments and data is worked out accordingly.
1. All soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)
6
STANDARD DATA – USER GUIDELINES
High Level Committee has recommended to add 14% plus 4% towards VAT or as
applicable on item rate towards overheads labour including importation and amenities &
contractor profits, which includes various items recommended in MORTH.
This also includes 4% of VAT and should be exhibited separately. In the
agreements, it should be mentioned that it will be reimbursed as per actuals. The
provisions allowed in Go Ms. No. 94, I & CAD, Dt. 1-7-03, need not be added separately.
The overhead charges include the following elements:
Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements.
Office furniture, equipment and communications
Expenditure on:
Corporate office of contractor
site supervision
Documentation and “as built” drawings
Mobilisation/ de-mobilisation of resources
Labour camps with minimum amenities and transportation to work sites.
Light vehicles for site supervision including administrative and managerial requirements.
Laboratory equipment and quality control including field and laboratory testing.
Minor T & P and survey instruments and setting outworks, including verification of line,
dimensions, trial pits and bore holes, where required.
Watch and ward
Traffic management during construction
Expenditure on safeguarding environment
Sundries
Financing Expenditure
Sales/ Turn overtax
Work Insurance/ compensation
17) EXCISE DUTY ON SUPPLIES :
In respect of gates, hoists and allied works excise duty is applicable on the value of
fabricated components supplied to site. Excise duty is not applicable on erection charges.
Further, the excise duty shall not be considered in the rate analysis on material
component, as basic material rates are inclusive of excise duty.
Therefore, excise duty is considered in the rate analysis only on
machinery and labour components required for fabrication of gates and hoists at the
central fabrication yard. It is difficult to determine the machinery and labour components
separately for fabrication and erection.
7
STANDARD DATA – USER GUIDELINES
For the purpose of computation of excise duty to be included in the rate analysis the
machinery and labour components may apportioned at 75 % for central fabrication yard
and 25 % for field erection and commissioning. Therefore, 75 % of the machinery and
labour components may be considered for assessing the extent of excise duty to be
added in the rate analysis.
i) Please select the item of work, as given in Index Code, and view the relevant data.
ii) The common data items like, lead, lift, conveyance and manual excavation (without involving
contracting agencies) is applicable to all Departments (volume-1)
iii) The departments have to adopt the relevant data from other Departments, if such works are
executed by them
iv) The unit rate /hire charges, of machinery not covered in the Irrigation data, the MORTH data
may be taken with the approval of Board of Chief Engineers
v) For “Drinking water Supply works”(PART-IV), the data incorporated is generally applicable
only for manual means of execution. The rates deploying machinery have to be worked out
by the Board of Chief engineers and approved for adoption.
8
STANDARD DATA – USER GUIDELINES
Materials rates:
The basic input material rates common to all departmental works are listed out and
incorporated (in the chapter “Basic inputs”) The material specifications adopted shall confirm to
Standards published by the BIS The Prevailing market rates for all basic input materials shall be obtained
from the major commercial centers near the project areas. Average of the rates, ignoring freak rates, shall
be reckoned as the prevailing market rate. Unless otherwise specified, all material rates shall be inclusive
of all taxes, duties, levies, royalty, transportation and handling costs up to project area. For sand, gravel,
murrum, stones , aggregates etc, the rates are For delivery at Quarry including seigniorage, loading
charges and idle hire charges. For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs,
the rates prevailing at major commercial centre near project area has to be adopted.
He shall communicate the uniform Schedule of rates arrived from Standard Data, to all users for
uniform and direct adoption in all infrastructure Departments, as applicable
9
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH
Basic approach and General conditions and assumptions for the preparation of Standard Data
Book for Building Works.
The Basic approach for the preparation of Standard Data for Building works is indicated as under.
1. Description of Items: The description of items is given briefly and linked with the relevant
specifications in AP Standard Specifications.
2. Use of Machinery: For concrete work mixing is proposed with machinery as well as
manually. For laying concrete, lifting is proposed with either by winches or machinery.
Manual means have been proposed for all other items.
3. Working Conditions: The inputs for the Data have been analyzed for the average working
conditions prevailing in the state.
i. Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements
v. Labour camps with minimum amenities required as per labour laws and transportation
to work sites
vi. Light vehicles for site supervision including administrative and managerial requirements
vii. Setting up of Laboratories for quality control, field and laboratory testing for control of
quality of various items of work and documentation of test results as per requirement of
the Specifications.
viii. Minor T&P including vibrators for concrete work and survey instruments and setting
outworks, including verification of line, dimensions, taking trial pits and bore holes,
where required.
10
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH
xii. Sundries
4.1 Sales/Turnover Tax / VAT: Allow 4% and which should be exhibited separately. In
agreements it should be mentioned that it will be reimbursed as per actuals.
5. Contractor’s Profit : It is considered to allow 14% towards over head charges (Item 4) and
Contractor Profits put together.
6. General :
b) The sources of all materials and samples of materials are required to be approved by the
Engineer-in- Charge before starting of the work.
c) For reinforced steel both HYSD and TMT bars continuing to IS 1786 and MS bars upto 36
mm dia as per IS 432 – Part 1 have been considered.
d) The Data includes inputs for testing of soil, materials and works.
e) The contractor shall arrange and to provide and maintain an adequate equipped field
laboratory.
g) Sundries to cater for unforeseen contingency and miscellaneous items have been added
in the overheads.
h) The various activities of works shall also be documented in photographs and video
cassettes.
i) The Data for various Earth Work Excavation Items including classification of soils shall be
as in Standard Data for Roads and Bridges.
11
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH
7. Basic Inputs :
Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items. The rates for labour, material and usage charges of machinery
for the area where the project is located are to be ascertained from local authorities/enquiries
to prepare Schedule of Rates for the area. The basic rates of materials, such as, stone
boulders, stone for masonry, stone ballast, stone dust, moorum, gravel, lime, manure,
sludge, quarry sweep, kankar, bricks, brick ballast, crushed slag, etc. at quarry / crusher sites
shall be fixed by the Board of Chief Engineers yearly (effective from 1st June to 31st May).
However, the basic rate of materials hand broken / machine broken, crushed aggregates
shall be based on Analysis in Chapter 1 of Roads & Bridges. The cost of materials should
include the cost at source and the cost of their carriage (as per Schedule of rates arrived in
Chapter 1 of Roads & Bridges for conveyance, loading and unloading charges) upto the work
site.
8. Labour
The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the
minimum wages fixed as per Minimum Wages Act. Skilled labour include mason, carpenter,
blacksmith, mechanics and other trades.
9. Materials :
Quantities of materials considered in the rate analysis are approximate for the purpose of
estimation and include normal wastages. Actual consumption would depend on mix design.
The rates of material should include basic cost at locations of stone crushers/factory/rail head
and cost of its carriage to the site of work/plant including loading, unloading and stacking.
Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and
other local taxes, etc.
10. The Data for the following items of work shall be as per Data Items covered in AP Standard
Data for Roads & Bridges
12
STANDARD DATA BOOK – BUILDING WORK ITEMS – BASIC APPROACH
For Concrete Work, the Grades of Concrete covered by Data Book is in accordance to IS 456 :
2000. The nominal mix of concrete shall be used upto M 20 Grade only. For RCC Work, M 20
Grade nominal mix may be used in exceptional cases of Remoteness. The design mix shall
invariably used for M 20 and above Grades of Concrete as per IS 456 : 2000. The Data
accounts for inputs of Material by Weight and use of ordinary mixture or ordinary mixer with
weight batch arrangement. The Hire charges for vibrators are included in overhead charges.
10% extra cement may be provided for concreting under water, where ever required. Steel
requirement of cement concrete work is required to be provided separately.
12. Plants and Equipment : The usage charges for machines include ownership charges, cost of
repair and maintenance including replacement of tyres and running and operating charges
which includes crew, fuel and lubricants. The hire charges shall be worked out based on the
Guidelines issued CWC for machinery covered in CWC Guidelines.
Measurement of various items and their units shall be as defined in the respective Clauses
of AP Standard Specifications. The rates for various items of work shall include all sub items
defined in the respective Clauses of AP Standard Specifications.
The Standard Data Book is for Department use only. It should not be produced in any court of
law as reference/ authority and to that extent it is a privileged document.
13
STANDARD DATA BOOK – BUILDING WORK ITEMS
14
STANDARD DATA BOOK – BUILDING WORK ITEMS
15
STANDARD DATA BOOK – BUILDING WORK ITEMS
16
STANDARD DATA BOOK – BUILDING WORK ITEMS
Note : Cost of dewatering upto 5 per cent of (a+b) may be added, where required.
Assessment for dewatering shall be made as per site conditions.
BLD-CSTN- 12 Ordinary rock (not requiring blasting)-Manual
2-4 Means-Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 5.20
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : Cost of dewatering upto 5 per cent of labour cost may be added, where
required as per site condition.
17
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 5.20
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hour 6.00
hammers of pneumatic breaker at 1 cum per
hour
c) & d) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d)/10
Note : Cost of dewatering up to 5 per cent of
(a+b) may be added, where required as per
site conditions.
Filling with useful available excavated earth
(excluding rock) in trenches, sides of
foundations and basement with initial lead in
layers not exceeding 15 cm thick,
consolidating each deposited layer by
watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire
charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)
18
STANDARD DATA BOOK – BUILDING WORK ITEMS
19
STANDARD DATA BOOK – BUILDING WORK ITEMS
20
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 1cum
A. MATERIALS:
Cement kg 129.60
Coarse aggregate 40 mm cum 0.90
Fine aggregate (Sand) cum 0.54
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.54
Water (including for curing) kl 1.20
21
STANDARD DATA BOOK – BUILDING WORK ITEMS
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Grand Total
BLD-CSTN- 27 Plain Cement concrete - Nominal Mix (1:3:6)
3-10
using 40mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement Kg 220.00
Coarse aggregate 40mm cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
Grand Total
BLD-CSTN- 28 Plain Cement concrete (M 20) Nominal Mix
3-11 using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 330.00
Coarse aggregate 40mm graded cum 0.90
Fine aggregate (Sand) cum 0.45
Seigniorage charges for C.A cum 0.90
Seigniorage charges for F.A cum 0.45
Water (including for curing) kl 1.20
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 1.39
Grand Total
BLD-CSTN- 29 Plain Cement concrete (M 15) Nominal Mix
3-12 1:2.5:5
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 275.000
Coarse aggregate 40mm cum 0.540
Coarse aggregate 20mm cum 0.270
Coarse aggregate 10mm cum 0.090
Fine aggregate (Sand) cum 0.480
Seigniorage charges for C.A cum 0.900
Seigniorage charges for F.A cum 0.480
22
STANDARD DATA BOOK – BUILDING WORK ITEMS
23
STANDARD DATA BOOK – BUILDING WORK ITEMS
24
STANDARD DATA BOOK – BUILDING WORK ITEMS
25
STANDARD DATA BOOK – BUILDING WORK ITEMS
26
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 25 sqm
A. MATERIALS:
Cement kgs 320.00
Coarse aggregate 12mm cum 0.90
Fine aggregate (sand) cum 0.45
Seigniorage charges of coarse aggregate cum 0.90
Seigniorage charges of sand cum 0.45
Form work L.S.
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00
capacity
C. LABOUR:
st
Mason 1 class day 0.1
Mazdoor (unskilled) day 1.98
D. Grand Total for 25 sqm
Rate per Sqm = D/25
BLD-CSTN- 33 Damp proof course 50mm thick with 1:2:4
3-21 cement concrete Nominal mix, using 12mm
hard broken stone aggregate including cost
of all materials, seigniorage charges,
excluding conveyance charges of materials
including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished
item of work. (Using concrete mixer)
Unit = 20 sqm
A. MATERIALS:
27
STANDARD DATA BOOK – BUILDING WORK ITEMS
28
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = t
(a) Material
TMT bars including 5 per cent for overlaps t 1.05
and wastage
Binding wire kg 6.00
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender day 2.00
Mazdoor (Unskilled) day 6.40
(c) Overheads on (a+b)
(d) Contractor’s profit on (a+b+c)
Rate per t = a+b+c+d
37 Supplying, fitting and placingTMT bar
reinforcement in VRCC works complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars
36 mm dia and above, where welding
required to be done compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage t 1.025
29
STANDARD DATA BOOK – BUILDING WORK ITEMS
30
STANDARD DATA BOOK – BUILDING WORK ITEMS
Grand Total
BLD-CSTN- 42 Brick Masonry in CM (1:6) with 2nd class
5-4 Bricks traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement kg 48.00
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
BLD-CSTN- 43 Brick Masonry in CM (1:8) with Bricks
5-5 traditional size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement kg 36.00
Bricks traditional size 23 x 11 x 7 cms 2nd Nos 512.00
class
Fine aggregate (Sand) cum 0.20
Seigniorage charges for F.A cum 0.20
B. LABOUR:
st
Mason 1 class day 0.24
nd
Mason 2 class day 0.56
Mazdoor (unskilled) day 1.89
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5,
1:6 and 1:8, proportionate quantity of cement has to
be substituted. No change in other data.
2. When First class Modular Bricks are used provide
570 nos bricks of size 19 x 9 x 9 cms.
BLD-CSTN- 44 Brick Masonry in CM (1:3) with Modular
5-6 Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement kg 100.60
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00
31
STANDARD DATA BOOK – BUILDING WORK ITEMS
Cement kg 75.60
Bricks modular size 19 x 9 x 9 cms 2nd class Nos 520.00
32
STANDARD DATA BOOK – BUILDING WORK ITEMS
Grand Total
BLD-CSTN- 49 11.5 cm wide Brick masonry for super-
5-11 structure on ground floor in cm (1:3) using
second class traditional size bricks including
cost of all materials, seigniorage charges,
labour and all operations for constructing
half brick masonry, mixing cement mortar,
curing etc., complete for finished item of
work, but excluding conveyance charges of
materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size nos 565.000
23x11x7cm
Cement kg. 106.000
Sand cum 0.220
Seigniorage charges for sand cum 0.220
B. LABOUR:
st
Mason 1 class day 0.600
nd
Mason 2 class day 0.600
Mazdoor (unskilled) day 2.750
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 50 Reinforced Brick Masonary walls of 11.5cm in
5-12 CM(1:6) using 2nd bricks having a crushing
strength of not less than 35.00kg/cm2 and
using two mild steel bars of 6m dia in every
third layer of brick masory, with free joints of
the main block work including cost and
seignorage charges and conveyance of all
materials and water from approved sources
to work site and all operational, incidental,
labour charges such as scaffolding mixing
mortor constructing masonary lift charges,
curing etc. complete but excluding the cost of
steel and its fabrication charges for finished
item of work as per SS 509
Ground Floor :
A. MATERIALS:
II Class Bricks Nos 512.000
C.M.(1:6) cum 0.200
B. LABOUR:
st
Mason 1 class day 0.600
nd
Mason 2 class day 0.600
Mazdoor (unskilled) day 2.750
Grand Total
33
STANDARD DATA BOOK – BUILDING WORK ITEMS
unit:1cum
A. MATERIALS:
Wire cut bricks or moulded bricks size nos 520.000
19x9x9cm
Cement kg. 48.00
Sand cum 0.20
Seigniorage charges for sand cum 0.20
B. LABOUR:
st
Mason 1 class day 0.57
nd
Mason 2 class day 0.57
Mazdoor (unskilled) day 2.54
Add water charges 1% 1.00%
Grand Total
Note : Compressive strength of individual
2
Brick shall not be less than 70 kg / cm
BLD-CSTN- 52 Brickwork in arches in cement mortar 1:4
5-14 complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD
Unit = cum
a) Material
Wire cut bricks or moulded bricks size Nos. 525.00
19x9x9cm
Cement mortar (1:4) cum 0.24
b) Labour
Mazdoor (Unskilled) day 1.88
Mason (1st Class) day 2.00
c) Add for centering and shuttering @ 110%
of (a+b)
Grand Total
Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.
2) Quantity of bricks for arches will be about 10 per cent more than that for
ordinary brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken
as 580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
BLD-CSTN- 53 Honey Comb work with Bricks of traditional
5-15 Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum
34
STANDARD DATA BOOK – BUILDING WORK ITEMS
a) Material
Brick 2nd class 23 x 11 x 7 Nos. 750.00
Cement mortar (1:5) cum 0.67
b) Labour
Mazdoor (Unskilled) day 6.60
Mason (1st Class) day 2.41
Mason (2nd Class) day 6.21
White Washing 2 Coats LS LS
Grand Total
BLD-CSTN- 54 Honey Comb work with Bricks of Modular
5-16 Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9 Nos. 790.00
Cement mortar (1:5) cum 0.67
b) Labour
Mazdoor (Unskilled) day 6.60
Mason (1st Class) day 2.41
Mason (2nd Class) day 6.21
White Washing 2 Coats LS LS
Grand Total
BLD-CSTN- 55 Masonry work in CM (1:8) prop with Flyash
5-17 Cement solid blocks of size 290 x 225 x 140
mm for manufacturing of flyash solid blocks
using flyash of 80 kgs, cement of 15 kgs.
Gypsum of 5 kgs. and stone dust including
cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and
curing etc., cpomplete with a compresive
strength not lessthan 50 kg/sqm for walls for
Superstructure Walls.
Ground Floor
Unit = 1 cum
A. MATERIALS:
No of blocks required for one cum of Nos 110.000
Masonry
Cost of Cement Mortar (1:6) cum 0.100
B. LABOUR
Mason 1st class day 0.420
Mason 2nd class day 0.920
Man Mazdoor day 0.700
Woman Mazdoor day 2.100
Total
BLD-CSTN- STONE MASONRY, DAMP PROOF COURSE,
6 DRY STONE PACKING, QUARRY RUBBISH &
GRAVEL BACKING
BLD-CSTN- 56 Cut Stone Masonry in CM 1:2
6-1
Unit = 1cum
A. MATERIALS:
Cement kg 115.20
35
STANDARD DATA BOOK – BUILDING WORK ITEMS
36
STANDARD DATA BOOK – BUILDING WORK ITEMS
37
STANDARD DATA BOOK – BUILDING WORK ITEMS
38
STANDARD DATA BOOK – BUILDING WORK ITEMS
39
STANDARD DATA BOOK – BUILDING WORK ITEMS
A. MATERIALS:
Cement kg 59.40
CR Stone cum 0.44
Rough Stone cum 0.50
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Fine aggregate (Sand) cum 0.33
Seigniorage charges for F.A cum 0.33
Seigniorage charges for Stone cum 1.10
B. LABOUR:
st
Mason 1 class day 1.20
Mazdoor (unskilled) day 2.00
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data
BLD-CSTN- 69 Dry Stone Masonry for Retaining Walls
6-14
Unit = 1cum
A. MATERIALS:
Rough Stone cum 1.04
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = cum 0.16
0.16cum
Seigniorage charges for Stone cum 1.20
B. LABOUR:
st
Mason 1 class day 0.33
nd
Mason 2 class day 0.77
Mazdoor (unskilled) day 1.10
Grand Total
BLD-CSTN- 70 Dry Stone Masonry for Well steining
6-15
Unit = 1cum
A. MATERIALS:
Rough Stone cum 1.04
Bond Stones cum 0.16
Seigniorage charges for Stone cum 1.20
B. LABOUR:
st
Mason 1 class day 0.45
nd
Mason 2 class day 1.05
Mazdoor (unskilled) day 1.10
Grand Total
BLD-CSTN- 71 Damp Proof, Course Damp Proof (or anti
6-16 Proof) Course with Cuddapah / Shabad slabs
50 mm. thick in CM (1:3) (Unit - 10 sqm)
A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick sqm 10.50
Cement Mortar 1:3 cum 0.15
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class day 0.90
40
STANDARD DATA BOOK – BUILDING WORK ITEMS
nd
Mason 2 class day 2.10
Mazdoor (unskilled) day 2.00
Grand Total
BLD-CSTN- POINTING
7
BLD-CSTN- 72 Flush Pointing with CM (1:3) to Brick / CRS
7-1 Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40
Fine aggregate (Sand) cum 0.03
Seigniorage charges for F.A cum 0.03
B. LABOUR:
nd
Mason 2 class day 0.50
Mazdoor (unskilled) day 0.74
Grand Total
BLD-CSTN- 73 Flush Pointing with CM (1:3) to RR Masonry
7-2
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40
Fine aggregate (Sand) cum 0.03
Seigniorage charges for F.A cum 0.03
B. LABOUR:
nd
Mason 2 class day 0.50
Mazdoor (unskilled) day 0.74
Grand Total
BLD-CSTN- 74 Raised Pointing with CM (1:3) to RR Masonry
7-3
Unit = 10 sqm
A. MATERIALS:
Cement kg 28.80
Fine aggregate (Sand) cum 0.06
Seigniorage charges for F.A cum 0.06
B. LABOUR:
nd
Mason 2 class day 0.50
Mazdoor (unskilled) day 0.74
Grand Total
BLD-CSTN- 75 Raised and cut pointing on coursed or Ashlar
7-4 stone masonry or concrete block walling in
white cement mortar 1 : 3 (1 white cement :
3 marble dust).
Details of cost for 10 sq.m
Materials :-
Cement mortar 1 :4 cum 0.038
Labour :—
Mason llnd class day 1.460
Mazdoor (unskilled) day 2.260
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Note : When Mortar mix is changed as CM 1:4
41
STANDARD DATA BOOK – BUILDING WORK ITEMS
42
STANDARD DATA BOOK – BUILDING WORK ITEMS
43
STANDARD DATA BOOK – BUILDING WORK ITEMS
44
STANDARD DATA BOOK – BUILDING WORK ITEMS
45
STANDARD DATA BOOK – BUILDING WORK ITEMS
46
STANDARD DATA BOOK – BUILDING WORK ITEMS
47
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
48
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm sqm 10.50
thick) (0.457 x 0.457 m)
Cement for CM (1:8) proportion for base coat kg. 21.60
49
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Marble slab of size… mm….thick…. mm sqm 10.50
Cement for CM (1:8) proportion for base coat kg. 48.00
Cement for slurry for bedding kg. 33.00
White Cement for pointing kg. 5.00
Sand for CM (1:6) cum 0.20
Seigniorage charges of sand cum 0.20
B. Machinery
Machine for rubbing of floor day 1.00
C. LABOUR:
st
Mason 1 class day 2.10
nd
Mason 2 class day 3.00
Mazdoor (unskilled) day 5.00
Add water charges 1%
Grand Total
BLD-CSTN- 102 Flooring with chequrred terrazzo tiles of 22
9-4 mm thick (medium shade) set over base coat
of cement mortar (1:6) 12 mm thick over CC
bed already laid or RCC roof slab, including
near cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed with
neat cement to full depth mixed with
pigment of matching shade including cost of
all materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
complete for finished item of work, .
Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick sqm 10.50
(medium shade)
Cement for CM (1:6) proportion for base coat kg. 28.80
Cement for slurry kg. 33.00
Cement for jointing & pointing kg. 6.00
Pigment kg.
Sand for CM (1:6) proportion cum 0.12
50
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
st
Vitrified tiles of 1 quality of size sqm 10.50
Cement for CM (1:8) proportion for base coat kg. 21.60
51
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
High polished granite slab other than black … sqm 10.50
mm thick
Cement for CM (1:8) proportion for base coat kg. 36.00
Cement for slurry kg. 33.00
White cement for jointing & pointing kg. 6.00
Cement for jointing kg.
Sand for CM (1:8) cum 0.20
Seigniorage charges of sand cum 0.20
B. LABOUR
st
Mason 1 class day 3.00
nd
Mason 2 class day 1.00
Mazdoor (unskiled) day 8.00
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 106 Flooring with marble tiles polished 8 mm
9-8 thick set over base coat of cement mortar
(1:8), 12 mm thick over CC bed already laid or
RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste mixed with pigment of matching shade
to full depth, including cost of all materials
like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work,
Unit = 10 sqm
52
STANDARD DATA BOOK – BUILDING WORK ITEMS
A. MATERIALS:
Marble tiles polished 8 mm thick sqm 10.50
Cement for CM (1:8) for base coat kg. 36.00
Cement for slurry kg. 33.00
White cement for jointing & pointing kg. 5.00
Sand for CM (1:8) cum 0.20
Seigniorage charges of sand cum 0.20
B. LABOUR (including for polishing & rubbing)
st
Mason 1 class day 4.00
Mazdoor (unskiled) day 8.00
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 107 Flooring with granite stone tiles 8 mm thick
9-9 (mirror polished of all shades) set over base
coat of cement mortar (1:6), 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete
for finished item of work, .
Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror sqm 10.50
polished of all shades)
Cement for CM (1:6) for base coat kg. 48.00
Sand for CM (1:6) cum 0.20
Seigniorage charges of sand cum 0.20
B. LABOUR
st
Mason 1 class day 0.96
nd
Mason 2 class day 2.24
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 108 Flooring with decorated white back ground
9-10 glazed tiles, set over base coat of cement
mortar (1:6), 12 mm thick over CC bed
already laid or RCC roof slab, including neat
cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work,
Unit = 10 sqm
A. MATERIALS:
53
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
20 X 20 cm pressed clay flooring tiles 1000 0.255
Nos
Cement for CM (1:8) for base coat kg. 21.600
Cement for jointing & pointing kg. 6.000
Pointing with CM (1:3) 10sqm 1.000
Deduct CM (1:3) cum 0.040
Sand for CM (1:8) cum 0.120
Seigniorage charges of sand cum 0.120
B. LABOUR
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskiled) day 4.30
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 110 Flooring with Plain Cement tiles, set over
9-12 base coat of cement mortar (1:8) 12 mm
thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm &
jointed neatly with cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,
54
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Plain cement Tiles 20 x 20 cms 1000 0.255
Nos
Cement for CM (1:8) for base coat kg. 21.600
Cement for jointing & pointing kg. 6.000
Pointing with CM (1:3) 10sqm 1.000
Deduct CM (1:3) cum 0.040
Sand for CM (1:8) cum 0.120
Seigniorage charges of sand cum 0.120
B. LABOUR
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskiled) day 3.30
Add water charges 1% 1.00%
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted for all above
Flooring Items. The same data holds good for stones
with all colours. Adopt same data for polished Kadapa
Stones and Bethamcherla stones.
BLD-CSTN- 111 Gronolithie Concrete Flooring 20 mm thick
9-13 with (1:1:2), using 6mm to 12 mm size hard
granite machine crushed metal laid over CC
bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m
and finishing the top surface to required
smoothness and slopes and thread lining
including cost of all materials like cement,
metal, sand and water etc., complete,
including seigniorage charges, etc., complete
for finished item of work,
Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine cum 0.17
crushed)
Cement kg 120.00
Sand cum 0.085
Seigniorage charges of sand cum 0.085
B. LABOUR
st
Mason 1 class day 1.25
nd
Mason 2 class day 0.06
Mazdoor (unskiled) day 3.00
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 112 Flooring with 100mm thick Cement Concrete
9-14 1:6:10, using 40mm metal, 100mm thick and
20 mm Cement Concrete surface (Ellis
Pattern, 1st Sort)
Unit = 10 sqm
A. MATERIALS:
55
STANDARD DATA BOOK – BUILDING WORK ITEMS
56
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Marble Powder kg 17.000
Marble Chips cum 0.060
Cement for top layer kg. 50.000
Cement for base coat in CM (1:3) kg. 96.000
Sand for base coat cum 0.200
Seigniorage charges of sand cum 0.200
B. MACHINERY
Polishing Charges sqm 10.000
C. LABOUR
st
Mason 1 class day 0.960
nd
Mason 2 class day 2.240
Mazdoor (unskiled) day 3.30
Grand Total
BLD-CSTN- 116 Providing skirting to internal walls to 15 cm
9-18 height/risers of steps with ceramic tiles 7.30
mm thick length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick sqm 10.50
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 6.00
Seigniorage charges of sand cum 0.12
B. LABOUR
st
Mason 1 class day 0.77
Mazdoor (unskiled) day 0.80
Grand Total
57
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Marble slab………mm thickness sqm 10.50
Sand for base coat cum 0.12
Cement for base coat kg 57.60
Cement for slurry kg 33.00
White cement for jointing & pointing kg 5.00
Flate nosing charges RM 66.67
Machine cutting charges RM 67.67
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 2.10
Man mazdoor (Beldar) day 4.90
Man mazdoor (Beldar) for polishing & day 4.00
rubbing
Woman mazdoor day 4.00
Grand Total
BLD-CSTN- 118 Providing skirting to internal walls to 15 cm
9-20 height/risers of steps with vitrified tiles
length equal to flooring stones, set over base
coat of CM (1:5) 12 mm thick with cement
slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like tiles, cement, sand and
water etc., complete including seigniorage
charges, etc., complete for finished item of
work,
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality sqm 10.50
Sand for cm 1:5 base coat cum 0.12
Cement for cm 1:5 base coat kgs 34.56
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 2.00
Seigniorage charges of sand cum 0.12
B. LABOUR
58
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles sqm 10.50
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
White cement for jointing & pointing kgs 5.00
Seigniorage charges of sand cum 0.12
B. LABOUR
Mason Ist class day 2.10
Mazdoor (unskiled) day 0.80
nd
Mason 2 class 4.90
Add water charges 1% 1.00%
Grand Total
BLD-CSTN- 120 Providing skirting to internal walls to 15 cm
9-22 height/risers of steps with polished kadapa
stone ... mm thick length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
Cuddapah stone, cement, sand and water
etc., complete including seigniorage charges,
etc., complete for finished item of work,
Unit = 10 sqm
A. MATERIALS:
Polished kadapa stone …. mm thick sqm 10.50
Sand for cm 1:3 base coat cum 0.12
Cement for cm 1:3 base coat kgs 57.60
Cement for slurry kgs 33.00
Seigniorage charges of sand cum 0.12
B. LABOUR
59
STANDARD DATA BOOK – BUILDING WORK ITEMS
60
STANDARD DATA BOOK – BUILDING WORK ITEMS
B. LABOUR
Carpenters 1st Class day 1.95
Carpenters 2nd Class day 4.55
Man mazdoor day 5.40
Note : Deduct 4.3 Nos Carpenters if plank rate is for
tongued and grooved ready planned.
Grand Total
BLD-CSTN- 123 Flooring with Gravel 150 mm thick including
9-25 cost of all materials, labour, watering etc.,
complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage) cum 1.53
B. LABOUR
Man mazdoor day 1.10
Woman mazdoor day 0.50
Grand Total
BLD-CSTN- ROOFING & CEILING
10
BLD-CSTN- 124 Roofing with corrugated G.I sheets 0.80mm
10-1 thick fixed with G.I ‘J’ bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (up to a
0
pitch of 60 ) and seigniorage charges, etc.,
complete, excluding the cost of purlins,
rafters, trusses & cost of conveyance of all
materials
61
STANDARD DATA BOOK – BUILDING WORK ITEMS
Grand Total
Rate per 10 sqm = Grand Total/10
BLD-CSTN- 125 Roofing with corrugated G.I sheets 1.00mm
10-2 thick fixed with G.I ‘J’ bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
0
pitch of 60 ) and seigniorage charges,
turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials
62
STANDARD DATA BOOK – BUILDING WORK ITEMS
63
STANDARD DATA BOOK – BUILDING WORK ITEMS
Grand Total
Rate per 10 sqm = Grand Total/10
BLD-CSTN- 128 Best Tiled Roofing with Pan tiles over Flat
10-5 Tiles and Lime mortar Borders including Teak
Reapers.
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 1560
No
Flat Tiles 150 x 150 x 15 mm 1000 470
No
Teak Reepers 50 x 12 mm 10RM 75.000
Wire Nails 40 mm long kgs 0.500
Lime cum 0.008
Lime Mortar cum 0.300
B. LABOUR
Carpenter day 0.800
Bricklayers day 2.200
Man mazdoor day 1.100
Woman mazdoor day 5.400
Sundries including tarring reepers, extra LS LS
labour / for pointing the underside of flat
tiles and white washing the same.
Grand Total
Sub Analysis :
Lime Mortar 1:2
lime cum 0.500
Sand cum 1.000
Grinding Lime Mortar day 1.000
Total
BLD-CSTN- 129 Best Tiled Roofing with Pan tiles and Lime
10-6 mortar Borders including Teak Reapers at
100 mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick 1000 1560
No
Teak Reepers 50 x 12 mm 10RM 107.000
Wire Nails 40 mm long kgs 0.700
Lime Moratar cum 0.120
B. LABOUR
Carpenter day 1.100
Bricklayers day 1.400
Man mazdoor day 1.100
Woman mazdoor day 3.200
Grand Total
64
STANDARD DATA BOOK – BUILDING WORK ITEMS
Grand Total
BLD-CSTN- 132 Best Tiled Roofing with Mangalore tiles
10-9 including Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification) 1000 160
No
Teak Reepers 50 x 12 mm 10RM 36.000
65
STANDARD DATA BOOK – BUILDING WORK ITEMS
Add
Terracing tiles 100 156
No
B. LABOUR
Bricklayers day 0.500
Woman mazdoor day 1.100
Grand Total
Common note Applicabable for Items 196 to
201 :-
1. The quantity proposed for Pan Tiles /
Mangalore Tiles includes allowance for cost
of special tiles for ridges and hips.
2. Reepers size is for rafter spacing 600 mm.
including allowance for eves and valleys.
66
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Reinforced Concrete Roofing slab 125 mm 10 10.000
thick (for rate - vide relevant schedule item) sqm
67
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing 10 1.000
125 mm thick and 2 courses of Flat Tiles at sqm
Top including pointing with Cement Mortar
(1:3)"
Add :
For extra thickness of roofing slab cum 0.150
Grand Total
BLD-CSTN- 138 Reinforced cement Concrete Roofing 150 mm
10-15 thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)
Unit = 10 sqm
Reinforced Concrete Roofing slab 100 mm 10 1.000
thick (for rate - vide relevant schedule item) sqm
68
STANDARD DATA BOOK – BUILDING WORK ITEMS
Sub Analysis :
Mazdoor (unskilled) Day
Mate Day
Sundries including crude oil LS
Grand Total
BLD-CSTN- 142 Best Sloping Bengal Terrace with 3 courses of
10-19 Flat Tiles at Top including Teak Wood
Reepers
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm 1000 1350
No
Lime cum 0.008
Lime Moratar (1:1.5) cum 0.150
Teak Reepers 52 x 12 mm 10 RM 75.000
Wire Nails 40 mm long kgs 0.500
Plastering with lime mortar 3 coats (for rate - 10 1.000
vide relevant schedule item) sqm
B. LABOUR
Carpenter day 0.800
Bricklayers day 2.200
Woman mazdoor day 2.200
Sundries including tarring reepers LS
Grand Total
Note : 1. Reepers size is for rafter spacing 600
mm. including allowance for eves and valleys.
69
STANDARD DATA BOOK – BUILDING WORK ITEMS
70
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 cum 0.210
Water proof compound kg 2.000
B. LABOUR
st
Mason 1 class day 0.660
nd
Mason 2 class day 1.540
Mazdoor (unskiled) day 3.70
Grand Total
BLD-CSTN- 149 Providing & fixing insulating board ceiling of
10-26 approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board sqm 11.00
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
BLD-CSTN- 150 Providing & fixing hard board sheet ceiling of
10-27 approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board sqm 11.00
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
71
STANDARD DATA BOOK – BUILDING WORK ITEMS
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
BLD-CSTN- 152 Providing & fixing plain AC sheet ceiling of
10-29 approved quality with necessary nails etc.,
complete, excluding the cost of frame work
for base and cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling sqm 11.00
B. LABOUR
Carpenter Ist class day 2.50
Man mazdoor day 2.00
Grand Total
BLD-CSTN- 153 Providing 10 mm thick plaster of paris
10-30 (Gypsum anhydrous) ceiling upto a height of
5 m above floor level over first class BT wood
strips 25 x 6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to
wooden frame excluding cost of wooden
frame for base & cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
st
Wooden strips 1 class BT wood 25 x 6 mm cum 0.05
size
Nails kg 0.75
Rabbit wire mesh sqm 10.20
Plaster of paris kg 219.76
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class day 2.60
Man mazdoor (beldar) day 1.60
For doing plaster of paris over wooden strips
72
STANDARD DATA BOOK – BUILDING WORK ITEMS
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards sqm 1.03
Ceiling Angle
25 mm x 10 mm x 0.55 mm RM 0.64
Connecting Clips Nos 1.84
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick RM 2.30
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm RM 0.84
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm RM 0.40
thick
Rawl Plug Nos 0.64
Soffit Cleats Nos 0.64
Drywall Screws - 25 mm Nos 18.00
Jointing Compound Kgs 0.55
Jointing Paper Tape RM 1.46
Drywall Top Coat Lits 0.15
B) LABOUR CHARGES
1st Class Carpenter day 0.40
2nd Class Carpenter day 0.40
73
STANDARD DATA BOOK – BUILDING WORK ITEMS
Scaffolding charges 1%
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling
BLD-CSTN- 155 Supplying and fixing Gyp Board Fine Line Grid
10-32 false ceiling (GS-FLC-4.6 as per India Gypsum)
in size 600 mm x 600 mm using 12.5 mm
thick/ 9.5 mm thick Gyp Board sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm conforming to IS 2095 - 1982 fixing to
Gyp steel precoated GI wall angle of size 25
mm x 25 mm x of 0.70 mm thick along the
perimeter of ceiling screw fixed to brick
work/ partition at 610 mm c/c and
suspending the frame work using precoated
GI Tee section (24 mm x 38 mm x 0.7 mm)
from soffit at 1220 mm c/c fixed with GI
Soffit Cleat, rawl plugs and steel expansion
fasteners & connecting clip to the GI T
section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding
clips system at 1200 mm c/c and fixing the
12.5 mm / 9.5 mm Gypboard Sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm and finishing two coats of drywall
topcoat complete for finished item of work
as per Idia Gypsum Ltd specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
74
STANDARD DATA BOOK – BUILDING WORK ITEMS
Scaffolding charges 1%
BASIC COST per 1 sqm
Armstrong False ceiling
BLD-CSTN- 156 Providing and fixing in true horizontal level
10-33 600 mm x 600 mm 15 mm thick Arm strong
false ceiling system manufactured by M/s
Arm strong world Industries using hot dipped
Galvanised Steel section exposed surface
with pre-coated capping, main Tee of size 24
x 32 mm at every 1200 mm c/c maximum
and rotary stiched cross tee of size 24 x 27
mm at evry 600 mm c/c and sub-cross tee of
size 24 mm x 25 mm at 1200 mm c/c and wall
angle of size 19 x 19 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick pre-straightened GI Wire laying
fine fissured butt edge ceiling tiles of 15 mm
thick mineral fiber Board manufactured by
M/s Arm Strong World Industries Ltd., having
RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials
and labour charges such as cutting , fixing of
standing of frame work exposing roof making
complete for finished item of work
UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x sqm 1.00
600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm RM 0.40
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross RM 1.60
Tee)
75
STANDARD DATA BOOK – BUILDING WORK ITEMS
Scaffolding charges 1%
BASIC COST per 1 sqm
Thermocole False ceiling
BLD-CSTN- 157 Providing and fixing Thermocole False ceiling
10-34 in true horizontal level 600 mm x 600 mm
using 15 mm/ 19 mm thick Thermocole
sheet anodised Aluminium Tee sections of
size 24.50 mm x 24.0 mm x 2.4 mm in grid
with cross tee of size 24 x 24.5 mm at every
600 mm c/c and anodised aluminium wall
angle of size 24 x 24 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick GI Wire for finished of size 600
x 600 mm including Cost &conveyance of all
materials and labour charges such as cutting ,
fixing of standing of frame work exposing
roof making complete for finished item of
work
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600 sqm 1.00
Alumninium Angle
24 mm x 24 mm RM 0.40
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm RM 3.20
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod Nos 1.28
Rawl Plugs Nos 1.28
B) LABOUR CHARGES
1st Class Carpenter day 0.36
76
STANDARD DATA BOOK – BUILDING WORK ITEMS
Scaffolding charges 1%
BASIC COST per 1 sqm
BLD-CSTN- WHITE WASHING, COLOUR WASHING &
11 DISTEMPERING
BLD-CSTN- 158 White washing one coat with lime of
11-1 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime cum 0.005
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
Brick Layers day 0.11
Mazdoor (unskilled) day 0.22
Sundries including brushes etc., LS
Total cost for 10 sqm
BLD-CSTN- 159 White washing two coats with lime of
11-2 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime cum 0.007
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
Brick Layers day 0.160
77
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime cum 0.009
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
White washer day -
Brick Layers day 0.220
Man Mazdoor day -
Women mazdoor day -
Mazdoor (unskilled) day 0.43
Sundries including brushes, ladders etc., LS
Total cost for 10 sqm
BLD-CSTN- 161 White washing one coat with whiting of with White Cement Grade
11-4 approved quality to give an even shade after II
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 1.20
kg
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.11
Mazdoor (unskilled) day 0.22
Sundries including brushes, ladders, etc., 0.50%
Total cost for 10 sqm
78
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 2.00
kg
Gum, conjee water, or prickly pear juice L.S
including necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.210
Mazdoor (unskilled) day 0.320
Sundries including brushes, ladders, etc., 1.00%
Total cost for 10 sqm
BLD-CSTN- 163 White washing three coats with whiting of
11-6 approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / 2.800
kg
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers / Painter day 0.300
Mazdoor (unskilled) day 0.430
Total cost for 10 sqm
BLD-CSTN- 164 Colour Washing, One Coat
11-7
Unit: 10 sqm
Rate for "White Washing" one coat 10 1.000
sqm
Add: For Colours, etc., (50 percent of above
rate)
Total
BLD-CSTN- 165 Colour Washing, Two Coats
11-8
Unit: 10 sqm
79
STANDARD DATA BOOK – BUILDING WORK ITEMS
PRIMARY COAT:
Cost of Primer Lts 0.50
Painter I st class Nos 0.08
Pianter Iind class Nos 0.19
Cost of washable Oil Bound Distemper Lts 1.70
1st class painter Nos 0.36
II class painter Nos 0.84
Total cost
BLD-CSTN- 169 Painting, Priming Coat on New Plastered
12-2 Surface
Unit: 10 sqm
A. MATERIALS :
Cement Primer kg 1.00
B. LABOUR
80
STANDARD DATA BOOK – BUILDING WORK ITEMS
81
STANDARD DATA BOOK – BUILDING WORK ITEMS
82
STANDARD DATA BOOK – BUILDING WORK ITEMS
B. LABOUR
Painter day 1.200
Sundries including brushes, soap, putty etc., LS
83
STANDARD DATA BOOK – BUILDING WORK ITEMS
B. LABOUR
Painter day 1.600
Sundries including brushes, soap, putty etc., LS
84
STANDARD DATA BOOK – BUILDING WORK ITEMS
B. LABOUR
Painter day 1.100
Sundries including brushes, soap, putty etc.,
85
STANDARD DATA BOOK – BUILDING WORK ITEMS
86
STANDARD DATA BOOK – BUILDING WORK ITEMS
New Work :
A. MATERIALS :
Readymade wax polish kg 0.500
B. LABOUR
Painter day 0.800
Helper day 0.800
Sundries including brushes, soap, cloth etc., LS
87
STANDARD DATA BOOK – BUILDING WORK ITEMS
88
STANDARD DATA BOOK – BUILDING WORK ITEMS
89
STANDARD DATA BOOK – BUILDING WORK ITEMS
90
STANDARD DATA BOOK – BUILDING WORK ITEMS
91
STANDARD DATA BOOK – BUILDING WORK ITEMS
92
STANDARD DATA BOOK – BUILDING WORK ITEMS
93
STANDARD DATA BOOK – BUILDING WORK ITEMS
94
STANDARD DATA BOOK – BUILDING WORK ITEMS
Each Door
BLD-CSTN- 246 Ledged Braced and Planked Doors (Schedule
13-14 Item No. 299)
Single Shutter :
800 x 2000 mm
*Teak wood cum 0.083
Labour, wrought and putup in position frame sqm 1.600
& shutters
Sundries inclusive of hold fasts and wind LS
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for LS
size - 2 Nos Chain and slopes country make.
95
STANDARD DATA BOOK – BUILDING WORK ITEMS
96
STANDARD DATA BOOK – BUILDING WORK ITEMS
97
STANDARD DATA BOOK – BUILDING WORK ITEMS
98
STANDARD DATA BOOK – BUILDING WORK ITEMS
99
STANDARD DATA BOOK – BUILDING WORK ITEMS
100
STANDARD DATA BOOK – BUILDING WORK ITEMS
800 x 500 mm
*Teak wood cum 0.012
Glass sqm 0.240
Wire netting sqm 0.190
Labour, wrought and putup in position sqm 0.400
Sundries inclusive of putty brads and iron LS
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
278 1000 x 500 mm
*Teak wood cum 0.014
Glass sqm 0.310
Wire netting sqm 0.240
Labour, wrought and putup in position sqm 0.500
Sundries inclusive of putty brads and iron LS
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
279 1200 x 600 mm
*Teak wood cum 0.018
Glass sqm 0.480
Wire netting sqm 0.290
Labour, wrought and putup in position sqm 0.720
Sundries inclusive of putty brads and iron LS
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
*Note : Average rate for respective size
scantlings
BLD-CSTN- 280 Swing Ventilators - Glazed (Schedule Item
13-26 No. 313)
800 x 500 mm
*Teak wood cum 0.021
Glass sqm 0.190
Labour, wrought and putup in position frame sqm 0.400
& shutters
Sundries inclusive of putty brads sash centres LS
brass ring iron cleats and window card - vide
relevant standard specifications.
101
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.947
2nd Class Carpenter day 1.158
Power Saw Cutter - Hand Operated - day 0.105
Operator
Power Drill - Hand Operated - Operator day 0.211
Unskilled Mazdoor day 0.632
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.842
charges
Power Drill - Hand Operated - Hire Charges Hrs 1.684
Supervision Charges Nos 0.211
Power charges for Motors 1%
BASIC COST per 1 sqm
Aluminimum Partition partly glazed
102
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
PARTICLE BOARD - Prelaminated sqm as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
B) LABOUR CHARGES
1st Class Carpenter day 1.042
2nd Class Carpenter day 1.042
Power Saw Cutter - Hand Operated - day 0.104
Operator
Power Drill - Hand Operated - Operator day 0.139
Unskilled Mazdoor day 0.347
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.833
charges
Power Drill - Hand Operated - Hire Charges Hrs 1.111
103
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum.Anodised.PC Friction stay casement Each as per design
hinges
Alum.Anodised.PC Handles Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.360
2nd Class Carpenter day 1.081
Power Saw Cutter - Hand Operated - day 0.360
Operator
Power Drill - Hand Operated - Operator day 0.360
Unskilled Mazdoor day 1.081
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 2.883
charges
Power Drill - Hand Operated - Hire Charges Hrs 2.883
104
STANDARD DATA BOOK – BUILDING WORK ITEMS
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum.Anodised.PC Handles Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.347
2nd Class Carpenter day 1.042
Power Saw Cutter - Hand Operated - day 0.347
Operator
Power Drill - Hand Operated - Operator day 0.347
Unskilled Mazdoor day 1.042
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 2.778
charges
Power Drill - Hand Operated - Hire Charges Hrs 2.778
105
STANDARD DATA BOOK – BUILDING WORK ITEMS
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION Kgs as per design
GLAZING with GLASS sqm as per design
SILICON SEALANT Kgs as per design
RUBBER BEADING RM as per design
Alum.Anodised.PC Handles Each as per design
Hydraulic Floor Spring/ Door Closure Each as per design
B) LABOUR CHARGES
1st Class Carpenter day 0.417
2nd Class Carpenter day 0.833
Power Saw Cutter - Hand Operated - day 0.417
Operator
Power Drill - Hand Operated - Operator day 0.417
Unskilled Mazdoor day 1.250
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 3.333
charges
Power Drill - Hand Operated - Hire Charges Hrs 3.333
106
STANDARD DATA BOOK – BUILDING WORK ITEMS
Scaffolding
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
BLD-CSTN- 289 Removing white wash or colour wash by steel
14-2 wire brushing and/or scraping; sand papering
and preparing the ceiling and/or sloping
roofs surface smooth including necessary
repairs to scratches complete
Deatailed cost for 10 sqm
Rate as per above item 10
sqm
Add 10 % extra for ceiling / sloping roof
Cost per 10 sq.m
Cost per sq.m
BLD-CSTN- 290 Removing white wash or colour wash by steel
14-3 wire brushing and/or scraping; sand papering
and preparing the wall surface smooth
including necessary repairs to scratches
complete for the wall surface spoiled by
smoke soot
Rate as per Item No (203) 10
sqm
For washing the wall surface spoiled by
smoke soot with clear water before sand
papering the surface smooth and including
necessary repairs to the scratches complete
107
STANDARD DATA BOOK – BUILDING WORK ITEMS
108
STANDARD DATA BOOK – BUILDING WORK ITEMS
R.C.C. work
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 4.320
Sundries
Cost per cu m
299 Brick work:
Details of cost for 1 cu.m.
Labour :-
Mazdoor (unskilled) day 4.090
Sundries
Cost per cu m
BLD-CSTN- 300 Extra over item 14.2.ii for cutting steel bars in
14-10 R.C.C. of R.B. work (sectional area of R.C.C. or
R.B. Work to be measured) Details of cost for
one Sq.m. of sectional area—
Reinforced area considering 1% Labour for
cuttings 0.01 Sq.m. reinforcement
Blacksmith 2nd class day 0.500
Mazdoor (Male) day 0.500
Sundries
Cost per sq m
BLD-CSTN- 301 Dismantling doors, windows and clear storey
14-11 windows, ventilators etc.; (wood or steel)
shutters including chowkhats, architraves,
hold fasts and other attachments etc.,
complete and stacking them within 100
metre lead
Not exceeding 3 sq.m. in area:
Details of cost per each
Labour :-
Mason, II class day 0.100
Mazdoor (male) day 0.200
Blacksmith II class day 0.050
Sundries
Cost per each
302 Exceeding 3 sq.m. in area
Details of cost per each
Labour :-
Mason, II class day 0.130
Mazdoor (male) day 0.270
Blacksmith II class day 0.070
Sundries
Cost per each
BLD-CSTN- MISCELLANEOUS BUILDING ITEMS
15
BLD-CSTN- 303 Providing and fixing aluminium step edging
15-1 'L' shape of size 38 mm x 12 mm x 3 mm
(thick) to stairs
109
STANDARD DATA BOOK – BUILDING WORK ITEMS
110
STANDARD DATA BOOK – BUILDING WORK ITEMS
111
STANDARD DATA BOOK – BUILDING WORK ITEMS
112
STANDARD DATA BOOK – BUILDING WORK ITEMS
113
STANDARD DATA BOOK – BUILDING WORK ITEMS
Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable
concentrate of 20%
1 liter : 19 Parts water Therefore: 868.55 L Lit 4.100
/20
Add 12%wastage Liters 0.41
Total Quantity 4.51
B) Add Water Charges @ 1% 1%
C) Labour Charges
Man Mazdoor day 3.0
Sprayer day 0.22
D) Hire charges
Sprayer, drilling machine etc 10%
sundries & contingencies 3%
Water charges & electricity 1.50%
Add OH & CP
BASIC COST per 1 sqm
BLD-CSTN- CENTERING, FORM WORK etc.
17
BLD-CSTN- 312 Providing traditional centering, shuttering
17-1 and scaffolding using Casurina balli props and
bracings supporting wooden brackets,
wooden wall plates, wooden runners and
steel plate form work as per the approved
plan and other accessories as per the
standard trade practice including hire
charges for ballies, runners, wooden
members and cost and conveyance of all
other consumable accessories, taxes etc
complete for finished item of work
114
STANDARD DATA BOOK – BUILDING WORK ITEMS
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 2.40
Height
Wall Plate Brackets / beam bottom supports Nos 1.44
115
STANDARD DATA BOOK – BUILDING WORK ITEMS
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Approximately 33'-0" x 33'-0" roof area
Span Beams - 2.4 M Long (Acro Spans) -
Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates -
9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates - Kgs 62.51
Appx -
B) LABOUR CHARGES
1st Class Carpenter day 0.22
2nd Class Carpenter day 0.38
Unskilled Mazdoor day 0.72
116
STANDARD DATA BOOK – BUILDING WORK ITEMS
117
STANDARD DATA BOOK – BUILDING WORK ITEMS
UNIT 1 sqm
118
STANDARD DATA BOOK – BUILDING WORK ITEMS
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0" Nos 1.74
Height
Scaffold Boards - Bamboo scaffolds - Nos 0.72
Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter day 0.07
2nd Class Carpenter day 0.11
Unskilled Mazdoor day 0.2
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
BLD-CSTN- 321 Providing STAGE SCAFFOLD using Steel
17-5 Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 39.26
B) LABOUR CHARGES
1st Class Carpenter day 0.04
2nd Class Carpenter day 0.34
Unskilled Mazdoor day 0.60
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
322 Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins
119
STANDARD DATA BOOK – BUILDING WORK ITEMS
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 112.635
B) LABOUR CHARGES
1st Class Carpenter day 0.12
2nd Class Carpenter day 0.58
Unskilled Mazdoor day 1.20
Supervision Charges day 0.08
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - PLAN AREA
BLD-CSTN- 323 Providing ACCESS SCAFFOLD using Steel
17-6 Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for ELEVATION AREA
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx - Kgs 19.7496
B) LABOUR CHARGES
1st Class Carpenter day 0.07
2nd Class Carpenter day 0.11
Unskilled Mazdoor day 0.24
Supervision Charges day 0.04
Consumables like Rope, Nails, de-shuttering 1%
oil
Tape, cover plates 1%
Tools like Hammers etc., 1%
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
324 Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
120
STANDARD DATA BOOK – BUILDING WORK ITEMS
A) MATERIAL REQUIREMENT
a. MS Iron Angle Posts using ISA 65x65x6 mm
- 1.5 M long - 329 Nos in 1000 RM length -
3015 Kgs
b. GI Pipes of 32 mm dia Nominal Bore
medium grade 2000 RM in 1000 RM length -
6300 Kgs
c. Nuts & Bolts - 329 posts x 4 Nos = 1316
Nos in a length of 1000 RM - 130 Kgs
Total Barricading Weight - Appx 9445 Kgs
(if departmental material is used no hire
charges shall be calculated)
B) LABOUR CHARGES
a. for materials loading & carriage to work
spot
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
1 Night - (2 Days - 16 Hrs) 16 + 16 Numbers
b. for removal, unloading & return to stores
back
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
Total 64 Numbers day 64.00
c. for fixing the barricading materials
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
½ Night - (1 Day - 8 Hrs) 16 Numbers
Total 32 Numbers day 32.00
BASIC COST per 1000 RM
121
STANDARD DATA BOOK – BUILDING WORK ITEMS
A) MATERIAL REQUIREMENT
Cost of Cinder cum 1.00
Cement Kgs 95.00
B) LABOUR CHARGES
st
Mason 1 class day 0.10
Mazdoor (unskilled) day 2.36
122
STANDARD DATA BOOK – BUILDING WORK ITEMS
b Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates,etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years = C
Life of Scaffolding materials, in years = D
[(Rs. A - Rs. B)*C]
Therefore, Hire Charges of scaffolding Materials: D
1 RATE ANALYSIS FOR HIRE CHARGES OF CENTRING & SCAFFOLDING MATERIALS FOR ALL R.C.C. STRUCTURAL MEMBERS - ANY HEIGHT
H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 Rs.
L Labour Charges Rs.
123
STANDARD DATA BOOK – BUILDING WORK ITEMS
member
7 BEAMS 9.350 sqm per 1 cum of concrete
member
8 SLABS - Up to 150 mm thick 1.050 sqm per 1 sqm of concrete
member
9 SLABS - above 150 mm - Up to 300 mm thick 1.090 sqm per 1 sqm of concrete
member
10 SLABS - above 300 mm thick 1.140 sqm per 1 sqm of concrete
member
11 WAFFLE(GRID)SLABS(Rib Beams with Slabs) 3.850 sqm per 1 sqm of concrete
member
12 PERGOLA SLABS (Only Rib Beams) 2.700 sqm per 1 sqm of concrete
member
13 ARCHE BEAMS - up to 1.5 M Span 10.630 sqm per 1 cum of concrete
member
14 ARCHE BEAMS - above 1.5 M Span 10.780 sqm per 1 cum of concrete
member
15 DOME SLABS 17.190 sqm per 1 cum of concrete
member
16 HELICAL STAIRCASES 1.310 sqm per 1 sqm of concrete
member
124
STANDARD DATA BOOK – BUILDING WORK ITEMS
2 RATE ANALYSIS FOR HIRE CHARGES SCAFFOLDING MATERIALS FOR BRICK & STONE MASONRY
H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items Rs.
L Labour Charges - as per Access Scaffolds items Rs.
Hire Duty
SCAFFOLDING CHARGES FOR BRICK / STONE Labour Charges Lift Charges Scaffolding Charges
Sl Qty Unit Charges Factor C1
MASONRY
H L (f) * (g) C1 [(e)+(h)]*(i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 1st Floor 1.00 sqm 100%
2 2nd Floor 1.00 sqm 150%
3 3rd Floor 1.00 sqm 200%
4 4th Floor 1.00 sqm 250%
5 5th Floor 1.00 sqm 300%
6 6th Floor 1.00 sqm 350%
7 7th Floor 1.00 sqm 400%
8 8th Floor 1.00 sqm 450%
9 9th Floor 1.00 sqm 500%
10 10th Floor 1.00 sqm 550%
11 11th Floor 1.00 sqm 600%
12 12th Floor 1.00 sqm 650%
13 13th Floor 1.00 sqm 700%
14 14th Floor 1.00 sqm 750%
15 15th Floor 1.00 sqm 800%
16 .... ... ... ...
125
STANDARD DATA BOOK – BUILDING WORK ITEMS
3 RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR WALL PLASTERINGS, RCM WORKS - ANY THICK
H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items Rs.
Hire Duty
SCAFFOLDING CHARGES FOR BRICK / STONE Labour Charges Lift Charges Scaffolding Charges
Sl Qty Unit Charges Factor C1
MASONRY
H L (f) * (g) C1 [(e)+(h)]*(i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 1st Floor 10.00 sqm 100%
2 2nd Floor 10.00 sqm 150%
3 3rd Floor 10.00 sqm 200%
4 4th Floor 10.00 sqm 250%
5 5th Floor 10.00 sqm 300%
6 6th Floor 10.00 sqm 350%
7 7th Floor 10.00 sqm 400%
8 8th Floor 10.00 sqm 450%
9 9th Floor 10.00 sqm 500%
10 10th Floor 10.00 sqm 550%
11 11th Floor 10.00 sqm 600%
12 12th Floor 10.00 sqm 650%
13 13th Floor 10.00 sqm 700%
14 14th Floor 10.00 sqm 750%
15 15th Floor 10.00 sqm 800%
16 .... ... ... ...
126
STANDARD DATA BOOK – BUILDING WORK ITEMS
4 RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR CEILING PLASTERINGS - ANY THICK
H Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Stage Scaffold items Rs.
L Labour Charges - as per Stage Scaffolds items Rs.
Hire Duty
SCAFFOLDING CHARGES FOR BRICK / STONE Labour Charges Lift Charges Scaffolding Charges
Sl Qty Unit Charges Factor C1
MASONRY
H L (f) * (g) C1 [(e)+(h)]*(i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 1st Floor 10.00 sqm 100%
2 2nd Floor 10.00 sqm 150%
3 3rd Floor 10.00 sqm 200%
4 4th Floor 10.00 sqm 250%
5 5th Floor 10.00 sqm 300%
6 6th Floor 10.00 sqm 350%
7 7th Floor 10.00 sqm 400%
8 8th Floor 10.00 sqm 450%
9 9th Floor 10.00 sqm 500%
10 10th Floor 10.00 sqm 550%
11 11th Floor 10.00 sqm 600%
12 12th Floor 10.00 sqm 650%
13 13th Floor 10.00 sqm 700%
14 14th Floor 10.00 sqm 750%
15 15th Floor 10.00 sqm 800%
16 .... ... ... ...
127
STANDARD DATA BOOK – BUILDING WORK ITEMS
Note
1 For Material Lift Charges & Labour rate for scaffolding above 7.32 M - increase @ 50% on labour component for each upper
floor on First Floor Rate (7.32 M)
2 For Hire Charges of scaffolding Materials following ratesmay be allowed:
a Number of uses of Scaffolding materials (C )
b Wooden Materials - No of Uses - 10 Times (C)
c Period of Hire of Steel Scaffolding materials, in years =
1.64 (C )
d Life of Steel Forms & Scaffolding Material - 3
Years (D)
e Duty Factor - Steel Scaffolding C1 0.500
f Duty Factor - Wooden Scaffolding C1 0.333
3 Add Area Allowances as applicable on labour
charges
128
STANDARD DATA BOOK – BUILDING WORK ITEMS
b Steel Barricading G.I. Pipes, Mild Steel IS Angles (As per relevant data item)
Cost of Barricading materials = Rs. A
Scrap value of Barricading materials = Rs. B (Usually B = A * 10%)
Period of Hire of Barricading materials, in years = C
Life of Barricading materials, in years = D
[(Rs. A - Rs. B)*C]
Therefore, Hire Charges of Barricading Materials: D
H Hire Charges of Steel Barricading: a/365 (OR) Wooden Barricading: b/10 - as per Barricading Item Rs.
L Labour Charges: as per Barricading work Rs.
data items
No of
Hire Duty MaterialHire Labour
Days of Barricading Charges
Sl NAME OF THE STRUCTURE COMPONENT Qty Unit Charges Factor charges Charges
Hire
H R C1 (e*f*g) L (h) + (i)
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)
1 STEEL BARRICADING 1000.00 RM
WOODEN BARRICADING
3 2 - TIER 100.00 RM
4 3 - TIER 100.00 RM
129
STANDARD DATA BOOK – BUILDING WORK ITEMS
Note
1 25% extra over the corresponding labour rates in respect of the work to be done during night time subject to issue of
certificate accordingly by the concerned estimate sanctioning authority for providing in the data and by concerned
Executive Engineer in charge of the work for payment. The night time allowance is applicable only to the works done under
Greater Hyderabad Municipal Corporation limits only
2 For Hire Charges of Barricading Materials following ratesmay be allowed:
a Number of uses of woodenBarricading
materials (U )
b Wooden Materials - No of Uses - 10 Times (U)
c Period of Hire of Steel Barricading materials, in years =
1.64 (C )
d Life of Steel Forms & Barricading Material - 3
Years (D)
e Duty Factor - Steel Barricading C1 0.500
f Duty Factor - Wooden Barricading C1 0.333
3 Add Area Allowances as applicable on labour
charges
130
STANDARD DATA BOOK – BUILDING WORK ITEMS
1. For Lift Charges of Labour, increase @ 10% on labour charges for each upper floor on Ground Floor Rate
2. For Lift Charges of Materials only, for lifting Concrete above 6.1 M (2nd floor onwards) Winch/ Lift hire charges may be
allowed at following rates:
8 LIFT CHARGES - for Brick Masonry, all Plastering items, all Flooring items, HYSD Steel fabrication, impervious coats, RCM Works
1 For Lift Charges of Labour, increase @ 10% on labour charges of respective item for each upper floor on Ground Floor Rate
2 Add Area Allowances as applicable on labour
charges
131
STANDARD DATA BOOK – LEAD CHARGES
2 LEAD UP TO 150 m
A) LABOUR
Mazdoor day 2
Cost for 7 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
4 LEAD UP TO 150 m
A) LABOUR
Mazdoor day 2
Cost for 12 MT =
Contractor's profit and overhead
charges
RATE PER 1 CUM
132
STANDARD DATA BOOK – LEAD CHARGES
6 LEAD UP TO 150 m
A) LABOUR
Mazdoor day 2
Cost for 5.5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
COM-LDLFT-2 (Lead) Conveyance charges for machinery
per kilometer for transporting materials
by tippers and trucks excluding loading,
unloading and hire charges of machinery
8 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
9 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
10 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
133
STANDARD DATA BOOK – LEAD CHARGES
11 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
15 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges Hr 0.21
Fuel Charges Hr 0.21
134
STANDARD DATA BOOK – LEAD CHARGES
16 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
17 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
18 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
135
STANDARD DATA BOOK – LEAD CHARGES
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
22 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
23 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
24 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
25 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
136
STANDARD DATA BOOK – LEAD CHARGES
WATER
28 LEAD UP TO 1 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
29 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
30 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
137
STANDARD DATA BOOK – LEAD CHARGES
31 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
32 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Water Tanker Charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
BRICKS
35 LEAD UP TO 1 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.15
Fuel Charges Hr 0.15
Crew charges Hr 0.15
138
STANDARD DATA BOOK – LEAD CHARGES
36 LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.21
Fuel Charges Hr 0.21
Crew charges Hr 0.21
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
37 LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.28
Fuel Charges Hr 0.28
Crew charges Hr 0.28
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
38 LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.34
Fuel Charges Hr 0.34
Crew charges Hr 0.34
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
39 LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Truck 10 T Charges Hr 0.40
Fuel Charges Hr 0.40
Crew charges Hr 0.40
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
139
STANDARD DATA BOOK – LEAD CHARGES
COM-LDLFT-3 LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks
are not added)
42 LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.02
Mazdoor day 0.50
Contractor's profit and overhead
charges
RATE PER 1 CUM
43 UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM
44 LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
Contractor's profit and overhead
charges
RATE PER 1 CUM
45 UNLOADING
50% of the loading charges i.e.,
140
STANDARD DATA BOOK – LEAD CHARGES
46 LOADING
Loading of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
Contractor's profit and overhead
charges
RATE PER 1000 Nos
48 LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.06
Mazdoor day 1.50
Contractor's profit and overhead
charges
RATE PER 1 MT
50 LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.07
Mazdoor day 1.80
Contractor's profit and overhead
charges
RATE PER 1 MT
141
STANDARD DATA BOOK – LEAD CHARGES
COM-LDLFT-4 LOADING AND UNLOADING CHARGES BY MANUAL MEANS (Including idle hire charges
of trucks )
52 LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.02
Mazdoor day 0.50
B) MACHINERY
TRUCK - 10 T Hour 0.50
Contractor's profit and overhead
charges
RATE PER 1 CUM
53 UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM
54 LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
B) MACHINERY
TRUCK - 10 T Hour 0.500
Contractor's profit and overhead
charges
RATE PER 1 CUM
55 UNLOADING
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor day 0.005
Mazdoor day 0.125
B) MACHINERY
TRUCK - 10 T Hour 0.166
Contractor's profit and overhead
charges
RATE PER 1 CUM
142
STANDARD DATA BOOK – LEAD CHARGES
56 LOADING
Loading of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor day 0.01
Mazdoor day 0.25
B) MACHINERY
TRUCK - 10 T Hour 0.33
Contractor's profit and overhead
charges
RATE PER 1000 Nos
58 LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.06
Mazdoor day 1.50
B) MACHINERY
TRUCK - 10 T Hour 1.00
Contractor's profit and overhead
charges
RATE PER 1 MT
143
STANDARD DATA BOOK – LEAD CHARGES
60 LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor day 0.07
Mazdoor day 1.80
B) MACHINERY
TRUCK - 10 T Hour 1.00
Contractor's profit and overhead
charges
RATE PER 1 MT
COM-LDLFT-5 LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire
charges of trucks)
62 LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone by mechanical
means including a lead upto 30 m
placing a tipper at loading point ,
loading with front end loader
excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading Min 1.00
point
ii) Loading by front end loader 1 Min 7.33
cum bucket capacity
@ 45 / 25 cum per hour
iii) Manoevouring, reversing, Min -
dumping and turning
for return
iv) Waiting time, unforeseen Min 2.00
contingencies, etc.
Total Min 10.33
A) MACHIENRY
Tipper 10 t capacity hour 0.17
144
STANDARD DATA BOOK – LEAD CHARGES
64 UNLOADING
Unloading of Earth, Sand,
Murrum, Gravel, Manure, Fly-Ash,
Lime, Aggregate, Stone Boulder,
Brick Aggregate, Kankar, Building
Rubbish, Building Rubbish, Crushed
Slag, Stone by mechanical means
including a lead upto 30 m placing
a tipper at loading point , loading
with front end loader excluding
time for haulage and return trip
145
STANDARD DATA BOOK – LEAD CHARGES
146
STANDARD DATA BOOK – LEAD CHARGES
147
STANDARD DATA BOOK – LEAD CHARGES
148
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE
The Standard Data for Electrical Works are prepared based on the relevant BIS
Specifications in conjunction with National Electric Code. Similarly the method of execution
shall be as per the provisions contained in IE Rules and National Electric Code.
The following are the Chapters.
CHAPTER 1 : CONDUIT LAYING
This chapter contains conduit laying i.e. M.S. Conduit, PVC Pipe and PVC Casing and
Capping. The MS Conduit shall be finished with stone enameled surface. The MS Conduit
accessories shall be threaded type only. The conduit shall be joined by means of screwed
couplers and screwed accessories only.
The PVC Pipe should confirm with relevant IS Specifications. PVC casing and capping
is meant of emergency and additional points only.
For LAN / Telephone / Computer Separate Conduit should be laid.
CHAPTER 2 : WIRING
This unit comprises of copper wiring for light points and fan points. Further,
electrical accessories such as Plug Sockets, Batten Holders, Call Bells etc., are provided in this
chapter.
The PVC insulated and flexible copper wires shall be Fire – Retardant and confirm to
IS 694. The colour code for wires shall be followed strictly for the entire installation as
follows :
R – Red
Y – Yellow For Phases
B – Blue
B – Black --- For Neutral
G – Green --- For Earth
All Switch boards for neutral conduit wiring shall be fabricated with CRCA Sheet
Steel from 1.6 mm (16 SWG) thick with 7 – tank process and powder coating or Hot dip
galvanized boxes.
The mounting height of boards (Bottom of Box) shall be as follows :
a) All Switch Boards : 1.32 m from FFL (Finished Floor Level)
b) 16 A Power Plugs
and Metal Sockets : Sill Level of the Window
c) 16 A Power Plugs
and Metal Sockets in Kitchen : Above 30 cm on Platform
d) MCB Distribution Board : 2 m from FFL
The entire installation shall be tested for
(i) Installation Resistance
(ii) Earth Continuity
149
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE
150
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE
151
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE
All the Steel Work used in the construction of the panel boards should have
undergone a rigorous metal treatment process i.e. 7- tank process.
152
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE
of 63 KVA / 100 KVA shall be proposed. Where HT supply is required, only copper wound
distribution transformers are to be proposed.
The lightening arrestors shall confirm to IS : 3070 and the protection against the
lightening shall be in accordance with Rule 92 of IE Rules.
153
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
154
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
155
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
156
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Helpers day 3
Mason Ist class day 3
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
NOTE : For Laying MS Concealed Conduit pipe in roof
Slab, deduct the Cost of Cement and U' Nails.
BLD-ELEC-1- 1.3 P.V.C. Conduit (Surface)
3
1.3.1 Supply and Fixing of 20mm dia 1.5mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles and
decolam board for switches for Light,
Fan and separate plug point including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
20mm 1,2,3, & 4 way Junction boxes Each 12
20mm PVC Bends Each 12
8" x10" Decolam Board Each 3
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
1.3.2 Supply and Fixing of 25mm dia 1.5mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.
Taking Output = 100 M
a) Material
25mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
25mm 1,2,3, & 4 way Junction boxes Each 12
25mm PVC Bends Each 12
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
157
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
158
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
50mm dia 1.5mm thick PVC pipe 100 M 1
Rawl Plugs 100 Nos 2
35mm Screws 100 Nos 2
Chromium Plated saddles with base Each 200
50mm 1,2,3, & 4 way Junction boxes Each 12
50mm PVC Bends Each 12
Cement kg 25
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
BLD-ELEC-1- 1.4 P.V.C. Conduit (Concealed)
4
1.4.1 (a) Supply and Fixing of 20mm dia 2mm
thick P.V.C. pipe (ISI MARK) concealed
in wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned wooden deep box including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 2mm thick PVC pipe 100 M 1
U' Links 100 Nos 2
10" x 8" Wooden deep box Each 3
20mm dia 1,2,3 & 4 way deep Junction Each 12
Box
20mm PVC bends Each 12
Cement kg 50
b) Labour charges :
Skilled Electrician day 2
Semi skilled Electrician day 2
Helpers day 2
Mason Ist class day 2
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
(b) Supply and Fixing of 20mm dia 1.5mm
thick P.V.C. pipe (ISI MARK) concealed
in wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned wooden deep box including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 1.5mm thick PVC pipe 100 M 1
U' Links 100 Nos 2
10" x 8" Wooden deep box Each 3
159
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
160
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
161
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
162
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
163
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
164
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
165
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
166
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
167
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
b) Labour charges :
Skilled Electrician day 0.67
Semi Skilled Electrician day 2
Helpers day 0.67
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.2 Supply and run of 1 of 14 /0.3mm (1.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire 100 M 1
b) Labour charges :
Skilled Electrician day 0.34
Semi Skilled Electrician day 1
Helpers day 0.34
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.3 Supply and run of 2 of 22/0.3mm (1.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
22/0.3mm FR PVC copper wire 100 M 2
b) Labour charges :
Skilled Electrician day 0.67
Semi Skilled Electrician day 2
Helpers day 0.67
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.4 Supply and run of 2 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper 100 M 2
wire
b) Labour charges :
Skilled Electrician day 0.67
Semi Skilled Electrician day 2
Helpers day 0.67
168
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.4 (a) Supply and run of 1 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper 100 M 1
wire
b) Labour charges :
Skilled Electrician day 0.34
Semi Skilled Electrician day 1
Helpers day 0.34
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
3.1.5 Supply and run of 2 of 56/0.3mm (4
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
56 /0.3mm (4 sqmm)FR PVC flexible 100 M 2
copper wire.
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 3
Helpers day 1
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
3.1.6 Supply and run of 2 of 84/0.3mm (6.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
84 /0.3mm (6 Sq.mm) FR PVC flexible 100 M 2
copper wire.
b) Labour charges :
Skilled Electrician day 1
Semi Skilled Electrician day 3
Helpers day 1
Sundries
C) Cost for 100 RM
169
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
170
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
171
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
172
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
173
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
174
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
175
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
176
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
177
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
178
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
complete.
179
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 0.5
Helpers day 1
Sundries such as hardware, cement LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.3 Supply and fixing TPN Distribution
board with IP-20 protection suitable
for 3 phase ELCB / RCCB / FP Isolator as
incomer and 10kA SP MCBs as outing
going including internal connection
and labour charges for surface / flush
mounting etc., complete.
A 40A FP Isolator/ RCCB / ELCB - 1 No
for incomer, 10kA-6-32A SP
MCBs - 12Nos for outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection each 1
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 12
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
B 63A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection each 1
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 12
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
C 80A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 18Nos for
180
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
outgoing.
181
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
C 80A FP Isolator - 1 No for incomer, 6-
32A SP MCBs - 18Nos for outgoing.
Taking Output = each
a) Material
6 way TPN, D.B with IP-42 Protection each 1
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB each 1
10kA - 6-32A range SP MCBs each 18
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
4.4.5 Supply and fixing TPN - Vertical type
Distribution board with IP - 20
Protection suitable for 3 phase ELCB /
RCCB / FP Isolator as incomer and 10
kA TP / SP MCBs as outing going
including internal connection and
labour charges for surface / flush
mounting etc., complete.
A Incomer : 63A FP Isolator / ELCB /
RCCB
Outgoing : 32A TP MCBs 2 Nos and
6-32A SP MCBs 6 Nos
a) Material
4way TPN - Vertical type DB with IP-20 Nos 1
protection suitable for 3 Phase ELCB /
RCCB / 4 Pole Isolator as in commer
and TP / SP MCBs as outgoing with
Bus-bar arrangment etc.,
63Apms, 4 Pole Isolator / ELCB / RCCB Nos 1
32A TP MCBs Nos 2
10kA -6-32A SP MCBs Nos 6
b) Labour charges :
Skilled Electrician day 0.5
Semi Skilled Electrician day 1
Helpers day 1
Sundries, suchas T.W plugs, Screws, LS
Cement etc,
Rate per each
182
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
183
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
184
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
185
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
1 Phase Distribution board with 20A Nos 1
plug and socket.
10/16/20A SP MCB Nos 1
b) Labour charges :
Skilled Electrician Nos 0.25
Semi skilled Electrician Nos 0.25
Helpers Nos 0.25
Sundries such as Cement, Sand, T.W. LS
Plugs, Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 4 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
4.4.10 Supply and fixing Distribution board
with 20A 3 phase plug and Socket, in
sheet steel enclosure with 16/20A TP
MCB including internal connection and
labour charges for surface / flush
mounting etc., complete.
a) Material
Distribution board with 3 Ph. 20A Plug Each 1
and Socket .
32A TP MCB, 10 kA Each 1
b) Labour charges :
Skilled Electrician Nos 0.33
Semi skilled Electrician Nos 0.33
Helpers Nos 0.33
Sundries such as Cement, T.W. Plugs,
Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 3 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
BLD-ELEC-5 5 EARTHING
BLD-ELEC-5- 5.1 EARTHING
1
5.1.1 Providing independent earthling by
excavating a trench to a depth of 2.1 M
in all soils, as per size specified in the
Data, using 40mm dia 'B' class GI pipe
of 2.5 Mtrs length with necessary
accessories with hume pipe ring duly
providing staggered holes including
filling with equal proportion of Salt and
Charcoal in layers and all labour
charges etc., complete for small
quarters.
a) Material
186
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
187
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
188
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
SSR).
40mm dia G.I pipe Class 'B' (Civil SSR) Mtr 2.5
19mm dia G.I pipe Mtr 0.3
40mm x 19mm reducer Each 1
G.I Funel covered with wire mesh Each 1
25mm x 6mm x 200 mm length G.I Each 1
Strip (Flat) with 4 Nos. Holes of 12mm
dia.
600mm x600mm x 3.15mm thick kg 10.00
copper plate
Drilling of staggered holes of 12mm Each 16
dia to G.I pipe.
G.I Bolts, Nuts and Washers. Set 4
Hard Coke. kg 4
Salt. kg 20
Cost Iron cover 400 mm x 400mm x L.S
50mm.
b) labour charges for fixing pipe
Skilled Electrician Nos 1
Sundries such as Lugs and Saddles
Rate per each
BLD-ELEC-5- 5.2 G.I Wire and Strip
2
5.2.1 Supply and Run of No.8 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.8 SWG G.I wire 100 M Length 10.4
(0.104 Kg / Mtr) Kg
U' Nails 100Nos 1.5
b) labour charges
Helpers day 2
Sundries.
C) Cost for 100 M
Rate per mtr c/100
5.2.2 Supply and Run of No.10 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.10 SWG G.I wire 100 M Length 6.7
(0.067 Kg / Mtr) Kg
U' Nails 100Nos 1.5
b) labour charges
Helpers day 2
Sundries.
C) Cost for 100 M
Rate per mtr c/100
5.2.3 Supply and Run of No.12 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
189
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
190
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
191
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Helper Nos 2
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
5.3.5 Supply and Run of 32mm x 6mm LS
copper strip including cost of all
accessories and labour charges etc.,
complete.
a) Material
32mmx 6mm Copper strip (1.697 Kg / Kg 169.7
Mtr) 100 M Length
b) labour charges
Skilled Electrician Nos 2
Helper Nos 2
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
BLD-ELEC-6 6 SERVICE MAINS & LTOH Lines
BLD-ELEC-6- 6.1 WPSC (Weather Prrof Single Core)
1 (PVC Cleats)
6.1.1 Supply and Run of 2 of 2.5 Sq.mm
WPSC (Whether Proof Single Core)
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
2.5 Sq.mm WPSC Aluminium cable 100 M 2
No.10 SWG G.I wire. (0.026 Kg / Mtr) kg 6.7
Length 100 RM
PVC Cleats 100 Nos 1
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.2 Supply and Run of 2 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
6 Sq.mm WPSC Aluminium cable 100 M 2
No.10 SWG G.I wire. (0.026 Kg / Mtr) kg 6.7
Length 100 RM
PVC Cleats 100 Nos 1
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
192
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Helper day 1
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.3 Supply and Run of 2 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable 100 M 2
No.10 SWG G.I wire. (0.026 Kg / Mtr kg 6.7
)Length 100 RM
PVC Cleats 100 Nos 1
b) labour charges
Skilled Electrician day 1
Semi skilled day 1
Helper day 1
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.4 Supply and Run of 4 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire on both sides
through PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
6 Sq.mm WPSC Aluminium cable 100 M 4
No.10 SWG GI Wire (6.7kg x 2) Length kg 13.4
200 RM
Binding wire kg 0.25
PVC Cleats / Separters 4 W. 100 Nos 1
b) labour charges
Skilled Electrician day 2
Semi skilled day 2
Helper day 2
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.5 Supply and Run of 4 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire on both
sides through PVC cleats with all
accessories including labour charges
etc., complete for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable 100 M 4
193
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
194
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
195
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
196
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
197
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
198
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Unit = 10 sqm
a) Material
Cement Mortor (1:5) cum 0.15
b) labour charges
st
Mason 1 class day 0.6
Mazdoor (unskilled) day 0.96
Rate per cum
6.3.8 (c) CRS Masonry in CM (1:6) 2nd Sort
Unit = 1cum
a) Material
199
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
200
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
201
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
202
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
203
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
204
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
205
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
206
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
207
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
208
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
cable
Pipe bending charges LS
M.S flat and welding charges LS
b) Labour charges
Skilled Electrician/carpenter day 0.2
Mason day 0.2
Semi skilled Electrician / Helper day 0.2
Rate per each
Note : Labour Charges considered for 5
fixtures / day .
7.9.6 Fixing of CFL street light luminary with
1.0 Mtr., 25mm dia GI pipe bracket
and anti tilting MS flat etc., including
giving connections and labour charges
etc., complete.
a) Material
25mm dia G.I pipe M 1
23/0060 twin core flexible copper M 2
cable
Pipe bending charges LS
M.S flat and welding charges LS
b) Labour charges
Skilled Electrician/carpenter day 0.125
Mason day 0.125
Helper day 0.125
Rate per each
Note : Labour Charges considered for 8
fixtures / day .
7.9.7 Fixing of mirror optic tube light
luminaire in false ceiling / pop with
necessary arrangment including giving
connections and all labour charges
etc., complete.
a) Material
28/0060 twin core flexible copper M 1
cable
Aluminium flat (as per requirment) LS
b) Labour charges for cutting P.O.P /
false ceiling and Fixing MOT
Skilled Electrician day 0.125
Carpenter day 0.125
Semi skilled Electrician / Helper day 0.125
Rate per each
Note : Labour Charges considered for 8 Nos MOT
lights in a day
7.9.8 Fixing of MV / SV/MH luminaire on
wall with 1.0mt 40mm dia GI pipe
bracket and anti-tilting MS flat, 2.5
Sq.mm flexible copper cable
etc.,including all labour charges for
mason work and giving connections
etc., complete.
a) Material
40mm G.I pipe for Bracket M 1
209
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
210
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
211
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
1x40 patty type T.L. fitting each 1
40W FTL each 1
Sundires and rounding off
Rate per each
Bldngs_Elec- 8.3 INDUSTRIAL luminaire
8-3
8.3.1 Supply and Transportation of white
vitreous 1x36 / 40W industrial box
type luminaire with Copper / VPIT
Choke, Condensor, Starters etc., with
reflector including 1No 40W tube etc.,
complete.
a) Material
1x36/40W Industrial box type T.L. each 1
fitting
36/40W FTL each 1
Sundries and rounding off
Rate per each
8.3.2 Supply and Transportation of white
vitreous 2x36 / 40W industrial box
type luminaire with 2Nos Copper /
VPIT Choke, Condensor, Starters
etc.,complete with reflector including
2Nos 40W tube etc., complete.
a) Material
2x36/40W Industrial box type T.L. each 1
fitting
36/40W FTL each 2
Sundries and rounding off
Rate per each
Bldngs_Elec- 8.4 MIRROR OPTIC luminaire
8-4
8.4.1 Supply and Transportation of 2x36 /
40W surface mounting mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror reflectors with VPIT chokes,
Starters, Condensor etc., complete
with 2Nos 36/40W tubes
etc.,complete.
a) Material
2x36/40 Surface M.O.L fitting each 1
40/36 FTL each 2
Sundries and rounding off
Rate per each
8.4.2 Supply and transportation of
2x36/40W recessed mounting mirror
optic (darklite) luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror reflector with VPIT
Chokes, Starter, Condensor etc.,
complete with 2Nos 36/40W tubes
etc., complete.
212
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
2x36/40 Recessed M.O. L fitting each 1
36/40 FTL each 2
Sundries and rounding off
Rate per each
8.4.3 Supply and transportation of 2x11W
surface mounting mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror refector with VPIT Chokes and
2Nos 11W CFL lamps etc., complete.
a) Material
2x11W CFL surface M.O.L fitting each 1
11W CFL each 2
Sundries and rounding off
Rate per each
8.4.4 Supply and transportation of 2x11W
Recessed type luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror refector with VPIT
Chokes and 2Nos 11W CFL lamps etc.,
complete.
a) Material
2x11W CFL recessed M.O.L fitting each 1
11W cfl each 2
Sundries and rounding off
Rate per each
8.4.5 Supply and transportation of 2x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 36w CFL lamps.
a) Material
2x36 CFL PS paralite Louvars fitting each 1
36w CFL each 2
Sundries and rounding off
Rate per each
8.4.6 Supply and transportation of 3x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 3x36w CFL
lamps.
a) Material
3x36 CFL PS paralite Louvars fitting each 1
36w CFL each 3
Sundries and rounding off
Rate per each
Bldngs_Elec- 8.5 T- 5 Luminaires.
8-5
213
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
214
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
215
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
216
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
217
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
218
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
219
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
220
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
221
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
222
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
3 KVA / 4 KVA / 5 KVA Stabilizer each 1
b) Labour Charges
Skilled Electrician day 0.1
Helper day 0.1
Transportation Charges on Unit Cost 2%
Rate per Each
Note : Labour is Considered for 10
jobs / day
Bldngs_Elec- 9.7 Fans
9-5
9.7.2 Supply of 900 mm (36") / 1200 mm
(48") / 1400 mm (56") sweep 230V, A.C
50 Hz.Ceiling fan with 3 Blades and
double ball bearings with all standard
accessories.
a) Material
900 mm (36") / 1200 mm (48") / 1400 each 1
mm (56") Ceiling Fan
Transportation Charges on Unit Cost 1%
Rate per Each
9.7.7 Supply and erecting wall mounting fan
400mm (16") / 450 mm (18") sweep
A.C. 50Hz.. 1350 r.p.m oscillating type
with regulator.
a) Material
400mm (16") / 450 mm (18") wall each 1
mounting Fan
b) Labour Charges
Semi Skilled Electrician day 0.1
Helper day 0.1
Rate per Each
Note : Labour is Considered for 10
jobs / day
9.7.10 Supply of pedastal fan (16") 400mm,
250 Volts, 50Hz. oscillating type
complete with all standard accessories.
a) Material
400mm (16") Pedastal Fan each 1
Transportation Charges on Unit Cost 2%
Rate per Each
9.7.16 EXHAUST FANS
Supply of fresh air exhaust fan of light
duty 250V A.C.50Hz.. 225 mm (9") /
300mm size (12") 1350 R.P.M Metallic
body plastic blades, wire mesh, etc.,
complete.
a) Material
225 mm (9") / 300mm (12") L.D. each 1
Exhaust Fan
Transportation Charges on Unit Cost 1%
Rate per Each
223
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
224
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
225
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
226
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
227
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
228
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
229
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
230
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
231
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
232
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
233
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
234
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
235
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
236
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
237
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
3HP, 3 Ph 4 stage submerisible pump each 1
set. Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.4 Supply and erecting, ISI mark
submersible 3 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump each 1
set. Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
238
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
239
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.7 Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 6 stage submerisible pump each 1
set including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter day 1
Helper day 2
Plumber day 1
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off LS
Rate per Each
11.3.8 Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 12 stages submerisible pump each 1
set Including all taxes
Special M.S. clamps with bolts and nuts each 2
Transportation Charges on Unit Cost 2%
240
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
241
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
242
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
243
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
244
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
245
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
246
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
247
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
248
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
249
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
250
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
251
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Top spor
tatio
n
and
Fabr
icati
on
6a 6b 6c 7 8 9 10 11
114.3x4.5 88.9x4.05 76.1x3.25 73 5 78
114.3x5.4 88.9x4.85 76.1x3.25 85 5 90
114.3x4.5 88.9x4.05 76.1x3.25 79 5 84
114.3x5.4 88.9x4.85 76.1x3.25 93 5 98
114.3x4.5 88.9x4.05 76.1x3.25 83 5 88
114.3x5.4 88.9x4.85 76.1x3.25 97 5 102
114.3x45 88.9x4.05 76.1x3.25 92 5 97
114.3x5.4 88.9x4.85 76.1x3.25 108 5 113
139.7x4.85 114.3x4.5 88.9x3.25 135 5 140
139.7x5.4 114.3x4.5 88.9x3.25 144 5 149
139.7x4.85 114.3x4.5 88.9x3.25 147 5 152
139.7x5.4 114.3x4.5 88.9x3.25 164 5 169
165.1x4.85 139.7x4.5 114.3x3.65 197 5 202
165.1x5.4 139.7x4.5 114.3x3.65 208 5 213
193.7x5.4 165.1x4.85 139.7x4.50 312 10 322
193.7x5.9 165.1x5.4 139.7x4.50 336 10 346
193.7x5.4 165.1x4.85 139.7x4.50 341 10 351
193.7x5.9 165.1x5.4 139.7x4.50 367 10 377
252
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
13-3
13.3.1 Supply and fixing of 50mm dia 0.5 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
0.5Mtr length 50mm 'B' class pipe. Kg 2.55
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and enamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.2
Fitter day 0.2
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
13.3.2 Supply and fixing of 50mm dia 0.5 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire
a) Material
2 x 0.5Mtr length 50mm 'B' class pipe. Kg 5.1
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and enamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.33
Fitter day 0.33
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
13.3.3 Supply and fixing of 50mm dia 0.5 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 0.5Mtr length 50mm 'B' class pipe. Kg 7.65
45cm length , 10cm dia and cap. Kg 5.4
Painting with red oxid and enamel job 1
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician day 0.5
Fitter day 0.5
Rate per Each
253
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
254
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
255
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
256
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
257
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
258
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
259
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
260
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
261
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
262
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
263
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
264
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
265
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
266
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
267
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
268
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
269
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
270
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
271
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
272
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
273
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
274
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
275
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
276
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
277
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Helper day 2
Man Mazdoor for concreting and day 2
embedding of cable way indicators
Sundires and Rounding off
Rate per 100mts
Note : Labour Charges Considered for
100 Mts / day
15.6.2 Earth work excavation of Trench in
hard ground soil, laying of U.G cables
from 70 sqmm to 400 Sq,mm on sand
cushion covering the cable with bricks
and back filling of Trench duly
providing route indicator embedded in
C.C including cost and conveyance of
materials and labour charges etc.,
complete.
a) Material
Excavation of earth 100 x 0.3 X 0.9 m cum 27
Cost of bricks (Civil SSR) 1000 Nos 0.92
278
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
b) Labour charges
Skilled Electrician day 1
Helper day 4
Sundires such as Cement, Sand etc.,
Rate per Each
Note : Labour Charges Considered for
100 Mts / day
15.6.4 Supply and laying of one number
double walled corrugated (DWC) HDPE
pipe of following sizes having
corrugation on the outer wall and plain
surface inner wall confirming to IS :
14930 Part - I and II complete with
necessary HDPE fittings for protection
of 1.1 KV grade U.G cable directly in
ground at a depth of 60Cms including
excavation and refilling the trench as
required.
a) 50mm outer dia nominal size
b) 78mm outer dia nominal size
c) 90mm outer dia nominal size
d) 120mm outer dia nominal size
a) Material
Double wall corrugated HDPE pipe RM 6
confirming to IS : 14930.
Snap-fit coupler each 1
Excavation of earth work & Refilling for cum 0.18
a size of 1.0x0.3x0.6Mtr.
Rate per Metre
Bldngs_Elec- 16
16 TEMPORARY ILLUMINATION
data shown seperately at the end.
Bldngs_Elec- 17
17 GENERATORS AND TRANSFORMERS
Supply, Transportation, erection and commissioning of following specifications
Bldngs_Elec- of D.G. Set consists of Engine and alternator which are directly coupled by
17-1 means of flexible cooping with guard and mounted on a common base plate of
Robust construction and complete with control panel having IP 53 protection.
A Alternator : KIRLOSKAR / STAMFORD / CROMPTON on D.G.S & D approved
make. The alternator of the output rating shall be 1 Ph / 3 Ph, 240V / 415V, 50
Hz., A.C., 0.8 P.f lagging at 1500 RPM. The alternator is self excited, self
regulated, screen protected drip proof and shall confirm to IS : 13364 of 1992
with regulation of + 5% from no load to full load. degree of protections shall be
IP 21.
B Diesel Engine : KIRLOSKAR / GREAVES / CUMMINS / ASHOK LEY LAND or
DGS&D approved. Diesel Engine start, developing suitable BHP output at 1500
RPM with class A2 Governing so as to enable the alternator to give required
KVA continuous output at 0.8 P.F. lagging at NTP conditions. the Diesel Engine
will be capable of providing 10% O/L for 1 Hr for every 11 HRs of continuous
running at full load. The Diesel Engine shall confirm to IS 10001 or IS 10002.
C Control Panel : Control Panel shall be fabricated with 16 SWG CRCA sheet steel.
The control panel shall be totally enclosed, dust and vermin proof, floor
mounted / wall mounted type and shall be comprising the following
instruments and component.
1. Voltmeter with selector switch 2. Ammeter with Selector
279
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
Switch
3. MCCB / MCB incomer of suitable rating 4. P.F. Meter and frequency
Meter
5. Indication Lamp Set 6. KWH Meter of required
rating
7. Instrument and control fuses.
ACOUSTIC ENCLOSURE
Supply & providing & installation of acoustic enclosure (sound proof enclosure
cum container) for the above Genset with the following specification.
Construction : The panel of acoustic enclosure shall consists of self supporting
frame work put together with help of fasteners, which is for assembling and
dismantling. The vertical and Horizontal structure 8is to be fabricated with
14/16 SWG CRCA sheet and should be fixed on heavy duty MS Channel which
will form the base frame of the acoustic enclosure. the paneling of ht container
is to be carried out using 18 SWG CRCA sheets. the enclosure should be self
supporting type and does not require any grouting or separate foundation. But
it should be the independent of the DG set and to placed around the DG set.
The frame work shall also have provision for fitting hinged / sliding doors to
open either sides of the enclosure.
17.1 Generating Sets
17.1.3 Supply, Transportation, erection of 3
(a) Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz., each 1
D.G.Set.
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation, erection of 3
(b) Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz., each 1
D.G.Set
cost of acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.
cost 5%
of acoustic enclosure
Transportation at 2% on unit cost 2%
Sundires and Rounding off
Rate per Each
280
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
281
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
cost 5%
of acoustic enclosure
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3
(g) Phase Water cooled / Air Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., as per
specifications mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set each 1
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 Supply, Transportation , erection of 3
(h) Phase Water Cooled / Air-Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., with
acoustic enclosure as per specifications
mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set each 1
Cost of Acoustic enclosure each 1
Erection and commissioning charges :
the 10%
cost of the DG set.
cost 5%
of acoustic enclosure
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 (i) Supply, Transportation , erection of 3
Phase Water cooled 125 KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., as per specifications
mentioned above.
a) Material
125KVA, Water Cooled, 3Ph, 415V each 1
D.G.Set.
Erection and commissioning charges @ 10%
10% of the cost of the set.
Transportation at 2% 2%
Sundires and Rounding off
Rate per Each
17.1.3 (j) Supply, Transportation, erection of 3
Phase Water-Cooled 125KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., with acoustic enclosure as
per specifications mentioned above.
a) Material
282
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
283
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
a) Material
each 1
100 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(d ) 160 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
160 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(e) 200 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
200 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(f) 250 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
250 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(g) 315 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
315 KVA Copper wound Transformer
Transportation including loading and 2%
unloading
(b) Labour charges for erection and 10%
commissioning.
Rate per Each
(h) 500 KVA, 3Ph, copper wound
Tansformer
a) Material
each 1
500 KVA Copper wound Transformer
284
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
285
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
286
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
287
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
288
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
289
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
290
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
291
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
292
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
293
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
294
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
295
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
296
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
297
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
298
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
299
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
300
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
301
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
302
STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS
303
STANDARD DATA-ELECTRICAL ITEMS – BUS BARS
12 BUS BARS
12.1.1 Supply and fabrication and erection of following sizes of 4Nos of copper bus bars in the existing sheet steel enclosure with resin cast
insulator supports etc., complete including cost and conveyance of all materials all labour charges.
D.No. Size of each bar No.of 1 Current Weight / Rate per Kg Cost of Cost of Labour charges for Total Rounding
in mm mtr rating in mtr in Kg copper 8Nos. fabrication and Amount off
bars each bar bars Resin cast fixing of insulators mtr
insulator. providing with PVC
@ Rs.35/- heat shrinkable
Each sleeves.
304
STANDARD DATA-ELECTRICAL ITEMS – BUS BARS
Aluminum Bus
12.2 Bars
12.2.1 Supply and fabrication and erection of following sizes of 4Nos of aluminum bus bars in the existing sheet steel enclosure with resin
cast insulator supports etc., complete including cost and conveyance of all materials all labour charges.
D.No. Size of each bar No.of 1 Current Weight / Rate per Kg Cost of Cost of Labour charges for Total Rounding
in mm mtr rating in mtr in Kg copper 8Nos. fabrication and Amount off
bars each bar bars Resin cast fixing of insulators mtr
insulator. providing with PVC
@ Rs.35/- heat shrinkable
Each sleeves.
305
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
306
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.3 Hire charges for Temporary 1 No tube 3years i.e 0.06 Skill
illumination, consisting of tube light light, 4 Mtrs 3 x 60 = electrician
with patti type 4'-40W complete with 7/20 service 180 days 0.06Helper
required wire leads duly erected and wire
dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.4 Hire charges for Temporary 1 No tube 3years i.e 0.06 Skill
illumination, consisting of tube light light, 4 Mtrs 3 x 60 = electrician
with patti type 4'-40W complete with 7/20 service 180 days 0.10Helper
required wire leads duly erected and wire
dismantled with scaffolding including
cost and conveyance of all materials
and labour charges etc., complete for
one day.
16.5 a Hire charges for Temporary 1 No 1000W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
1000W hallogen with lamp complete Mtrs 7/20 180 days 0.25Helper
with required wire leads duly erected service wire
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.5 b Hire charges for Temporary 1 No 500W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
500W hallogen with lamp complete Mtrs 7/20 180 days 0.25Helper
with required wire leads duly erected service wire
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
307
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.5 c Hire charges for Temporary 1 No 250W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
250W metal halide fitting with lamp 30 Mtrs 180 days 0.25Helper
complete with required wire leads 7/20 service
duly erected and dismantled without wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.5 5 Hire charges for Temporary 1 No 400W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
400W metal halide fitting with lamp 30 Mtrs 180 days 0.25Helper
complete with required wire leads 7/20 service
duly erected and dismantled without wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.6 a Hire charges for Temporary 1 No 1000W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
1000W hallogen with lamp complete Mtrs 7/20 180 days 0.30Helper
with required wire leads duly erected service wire
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.6 b Hire charges for Temporary 1 No 500W 3years i.e 0.25 Skill
illumination, consisting of flood light Halogen, 30 3 x 60 = electrician
500W hallogen with lamp complete Mtrs 7/20 180 days 0.30Helper
with required wire leads duly erected service wire
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
308
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.6 c Hire charges for Temporary 1 No 250W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
250W metal halide fitting with lamp 30 Mtrs 180 days 0.30Helper
complete with required wire leads 7/20 service
duly erected and dismantled with wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.6 d Hire charges for Temporary 1 No 400W 3years i.e 0.25 Skill
illumination, consisting of flood light Metal halide, 3 x 60 = electrician
400W metal halide fitting with lamp 30 Mtrs 180 days 0.30
complete with required wire leads 7/20 service Helper
duly erected and dismantled with wire
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.7 Hire charges for Temporary 1000 Nos 1 year i.e 0.5 Skill
illumination, consisting of white / bulbs & 30 60 days electrician
colour series light 6.2v complete with Mtrs 7/20 0.5Helper
1000 Nos. with required wire leads service wire
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
16.8 Hire charges for Temporary 1000 Nos 1 year i.e 0.5 Skill
illumination, consisting of white / bulbs & 30 60 days electrician
colour series light 6.2v complete with Mtrs 7/20 1.0 Helper
1000 Nos. with required wire leads service wire
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
309
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.9 Hire charges for Providing and fixing Cost of 10 5 years 0.25
rotating machine to give running KW rotating i.e 5 x 30 Helper
effect to strip lights and miniature machine = 150
lights upto a load of 10KW with days
required wire leads duly dismantled
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.10 Hire charges for Providing oscillating 18" pedestal 3years i.e 0.10
type pedestal fan 16" / 18" with fan, 30 3 x 40 = Helper
connected wire leads duly dismantled Mtrs 7/20 120 days
including cost and conveyance of all service wire
materials and labour charges etc.,
complete for one day.
16.1 Hire charges for Providing air cooler Air cooler, 3years i.e 0.20 semi-
connected with necessary mains 30 Mtrs 3 x 40 = skilled
switch gear with continues earth lead 7/20 service 120 days electrician
during function duly dismantled wire
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
16.12 Hire charges for Providing 1.5 ton/2.0 Air 8years 1 skilled
ton capacity window air conditioning conditioned, i.e. 8 x 15 electrician,
unit complete with suitable stabilizer stabilizer = 120 2 Helpers,
with temporary frame and fabrication days 1 carpenter
work and required materials achieve
cooling, temperature connected with
necessary mains switch gear with
continues earth lead during function
duly dismantled including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
310
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.1 Hire charges for Providing temporary 16 Amps 5 in 3years i.e 0.05 semi-
plug point with 5 pin 6 Amps/16 Amps one power 3 x 40 = skilled
with necessary mains switch gear with plug, 30 120 days electrician
continues earth lead during function Mtrs 7/20
duly dismantled including cost and service wire
conveyance of all materials and
labour charges etc., complete for one
day.
Note : 1) The rates are for one
glowing/working day.
2) Allow 50% of rate for each day upto
3 days (i.e. 2nd and 3rd day)
3) For each additional day after 3
days, but not exceeding 15 days,
allow 25 % rate of glowing/working
days
4) For more than 15 days allow 10%
per day but total rental charges shall
not exceeded 80% of capital cost of
item.
16.14 a Hire charges for supply and 125 KVA DG 10years 1.Skill
maintaining 125 KVA, 415 voltage, 50 Set, 200 i.e 10 x Electrician
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.14 b Hire charges for supply and 82.5 KVA DG 10years 1.Skill
maintaining 82.5 KVA, 415 voltage, 50 Set, 200 i.e 10 x Electrician,
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
311
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.14 c Hire charges for supply and 62.5 KVA DG 10years 1.Skill
maintaining 62.5 KVA, 415 voltage, 50 Set, 200 i.e 10 x Electrician,
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.14 d Hire charges for supply and 30 KVA DG 10years 1.Skill
maintaining 30 KVA, 415 voltage, 50 Set, 100 i.e 10 x Electrician,
C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.14 e Hire charges for supply and 5 to 15 KVA 10years 1.Skill
maintaining 5 to 15 KVA, 415 voltage, DG Set, 63 i.e 10 x Electrician,
50 C/s AC generating set with all Amps main 60 = 600
standard accessories such as control switch days
panel, batteries etc complete for one
day excluding cost of fuel.
16.2 Hire charges for supply and 125 KVA DG 10years 1.Skill
maintaining of 125 KVA DG set with Set, acoustic i.e 10 x Electrician,
acoustic enclosure as per IS enclosure, 60 = 600
specification with DCM 4 wheeler 200 Amps days
vehicle with all standard accessories main switch
such as control panel, batteries etc with 4
complete for one day excluding cost wheeler
of fuel. DCM vehicle.
NOTE: 1) The above rates are applicable per one day only.
2) For subsequent days the above rte shall be reduced by 25% after 8th day
reduce the rate by 50%
3) Diesel cost will be paid extra for running hours at the prevailing rates.
4) For test run,. The minimum req2uirement of the fuel shall be born by the
contractor.
5) The D.G.set should be in good condition and the life of set shall not b e beyond
10 years
312
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
313
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.2 Hire charges for providing industrial 250 Amps 10years 0.5 Skilled
type panel board consisting of bus bar bus bar, 250 i.e 10 x electrician,
chamber with 200/250 amps TPN/MCCB, 15 = 150 1 Helper
incoming TP/MCCB as incomers 12 nos 100 days
switch, 12 nos 100 amps fuse unit, Amps fuse
earth wire erected and dismantled all units
accessories etc., complete for
distribution for one day.
16.18 a Hire charges for supply and 100 Amps 10years 0.125
maintaining towards supply and fixing COS/ TPN i.e 10 x Skilled
of 100 amps 4 pole change over 15 = 150 electrician,
switch/TPN switches including days 0.125
erection and dismantled all Helper
accessories etc., complete for one
day.
16.18 b Hire charges for supply and 200 Amps 10years 0.125
maintaining towards supply and fixing COS/ TPN i.e 10 x Skilled
of 200 amps 4 pole change over 15 = 150 electrician,
switch/TPN switches including days 0.125
erection and dismantled all Helper
accessories etc., complete for one
day.
16.18 c Hire charges for supply and 400 Amps 10years 0.2 Skilled
maintaining towards supply and fixing COS/ TPN i.e 10 x electrician,
of 400 amps 4 pole change over 15 = 150 0.2 Helper
switch/TPN switches including days
erection and dismantled all
accessories etc., complete for one
day.
314
STANDARD DATA-ELECTRICAL ITEMS – TEMPORARY ILUMINATION
16.19 a Hire charges for supply and erection 24 Mtrs 80/ 15years 0.5 fitter,
and dismantle of 4 pole structure of 4 50mm C i.e 15 x 0.5 skilled
of 20' GI pipe of 50/80mm structure class GI pipe, 12 = 180 electrician,
complete necessary cross arms and 50/50 MS days 2 Helpers,
hardware materials for fixing cross arms 54 Cum.
halogen/ metal halide fitting with weight of 72
suitable earthing arrangements Kgs & 1 No.
including cost conveyance of all coil earthing
materials and labour charges for
maintaining one day.
16.19 b Hire charges for supply and erection 36 Mtrs 15years 0.5 fitter,
and dismantle of 4 pole structure of 4 80/50mm C i.e 15 x 0.5 skilled
of 30' GI pipe of 50/80mm structure class GI pipe, 12 = 180 electrician,
complete necessary cross arms and 50/50 MS days 2 Helpers,
hardware materials for fixing cross arms 54 Cum.
halogen/ metal halide fitting with weight of 72
suitable earthing arrangements Kgs & 1
including cost conveyance of all No.coil
materials and labour charges for earthing
maintaining one day.
NOTE: 1) The rates are for one glowing/working day.
2) Allow 50% of rate for each day upto 3 days (i.e. 2nd and 3rd day)
3) For each additional day after 3 days, but not exceeding 15 days, allow 25 % rate
of glowing/working days
4) For more than 15 days allow 10% per day but total rental charges shall not
exceeded 80% of capital cost of item.
Note : Service Tax and VAT as applicable shall be extra
for all Items.
315
STANDARD DATA-ANNEXURE
ORDER:
The basic components for preparing any estimate are Standard Specifications, Standard Data,
and Schedule of Rates for construction materials, skilled and un-skilled labour and hire charges of
machinery utilized on works. To get the work done, as per the standard specifications, required
quantities of recommended materials, requirement of specific need based manpower, deployment of
proper utility based machinery and duration of its utilization are to be observed and quantified for
each unit of work, and this is called Standard Data. Thus, the Standard Data gives the details of
various inputs in terms of quantities required for one Unit of any work. Schedule of rates for material,
skilled and unskilled labour are fixed and revised by the Board of Chief Engineers’ once in a year and
these are called Standard Schedule of Rates. When the Standard Schedule of Rates and Hire charges
of machinery are incorporated in the inputs of Standard Data and Standard Schedule of Rates it will
have direct bearing on the preparation of project Estimates and consequent finalization of Tenders.
2. The existing AP Standard Data for various construction items were based on observations made
several decades back mostly by utilizing manpower for execution of all items of works, and
deployment of machinery was at the barest minimum. The advent of latest machinery and their
extensive use has changed the structure and methodology of data formulation and rate structure.
There is a need to revise the present “Standard Data” for all items of worksdealing with Public works.
Realizing the urgency and importance to haverealistic data, Government in the GO.Rt.No.7326 G.A
(GPM & AR) Departmentdated 26-10-2005 constituted a High Level Committee under the
chairmanshipof Special Chief Secretary, General Administration (GPM&AR) Department, to advise on
“Updating and Revising the A.P.Standard Data”. A project for Standard Data (revision) and Schedule of
Rates was conceived and entrusted to the Centre for Good Governance. Keeping in view the strategy,
factors considered and classification of works, a number of High Level Committee meetings and
review meetings were conducted at Centre for Good Governance/ A.P.Secretariat and in the offices of
concerned Engineers-in-Chief I&CAD, Public Health, Panchayati Raj and Roads & Buildings
Departments etc. Their specific views, suggestions and recommendations were taken into account,
besides collecting the data from various sources while finalizing the Draft AP standard Data and
Standard Schedule of Rates. This has been cleared by the Board of Chief Engineers’ and finally by the
High level Committee. The Standard Data has been revised and updated in four parts considering
nature of work, location of work and magnitude of work as indicated below.
1. PART – I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
3. The revision of Standard Data and Schedule of Rates in respect of works items of Irrigation
Department has been taken up by the SPIU (Irrigation) and completed as per the C.W.C guidelines and
B.I.S standards and also observations and recommendations made by the High Level Committee. In
316
STANDARD DATA-ANNEXURE
respect of other Departments, MORTH data is adopted for Roads & Bridges, where higher capacity
machinery can be deployed and MORD data is adopted for Roads & Bridges in Rural areas. For other
works data as per MORTH, MORD, and C.P.W.D. etc., is adopted. The comparative estimates have
been prepared by the T.R. &B Dept. , Engineering-in-Chief (Irrigation) and MA & UD Department for
various types of works of a magnitude of Rs.15-20 crores, based upon the earlier data and the newly
revised and proposed data .
4. After detailed deliberations and discussion on the above issue, the Govt. accept the
recommendations of Board of Chief Engineers and High level Committee and accordingly issue the
orders for adoption of the Revised and Updated Standard data in all Engineering/ Public works
Department and other organisations in four parts considering nature of work, location of work and
magnitude of work as indicated below. The four parts of Standard Data booklets are forwarded to
Engineer-in-Chief (AW), who in turn will publish the authenticated version and circulate a copy to all
works Departments.
1. PART – I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
5. The Revised Data now approved is to be adopted by all Engineering Departments/ all Public
Works Department and other organisations, duly superseding all the earlier orders issued on the
subject. 6. These orders shall come into force from the date of issue.
7. This order issues with the concurrence of Finance Department vide their
U.O.No.5532/520/Exp.PW.I Dept/08, dated 13-5-2008.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
317