COMPANY’S DOC. NO.

7461-ORH-AQ-Q-87016
URHOUD-Organisation Ourhoud JOB No. DOC. NO. REV.

0-1800 S-000-1520-009 1
DATE 5-Oct-’00 SHEET 1 OF 10
PROJECT SPECIFICATION Prep’d Y. Tazawa
Chk’d H. Miura
App’d KN Yoshida

ORGANISATION OURHOUD
REALISATION DES INSTALLATIONS DE PRODUCTION D’HUILE
OURHOUD, ALGERIE
CT-99-010-040

DIST’N
SCOPE OF INSPECTION
CLIENT
OY
OM FOR
OH
OS
JGC/INITEC
PJ-PMT
PJ-CONST
INSTRUMENT MATERIALS
PJ-ENG
PJ -CONTROL

PROCESS
PIPING
PLINE
CIVIL
INST
ELEC
ROTARY
FIRE
HSE
EQUIP
PAINT/INSU
SOLID-H
PKG
FUR
BLDG/HVAC
ACOUSTIC
OPER’T
LABO
EN-IT
EN-IT(MAT’L)
LEGAL
PPM
P- EQUIP
P- PIPING
P- INST
Rev. Date Page Description Prep’d Chk’d App’d
P- ELEC
EXPED’G 0 5-Oct-‘00 All Issued for Approval Y.Tazawa H.Miura KN Yoshida
SHIPPING
QA 0a 06-Dec-00 As
marked Re-issue for Approval Y.Tazawa H.Miura KN Yoshida
QC
JPC 1 22-Dec-00 For Construction
JGCSITE
JM (INITEC)
JUS
JEU
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud
JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 2 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MTL

1. SCOPE

This procedure specifies Purchaser’s/ Company’s scope of inspection at Supplier’s shop for
instrument equipment & materials to be used for REALISATION DES INSTALLATION DE
PRODUCTION D’HUILE.

2. SCOPE OF INSPECTION

2.1 When witness inspection is required, Supplier is requested to perform a successful pre-test by
himself prior to Purchaser and / or Company inspection to avoid failure of test.

2.2 When witness inspection is required, Supplier shall note the following:

1) Supplier shall provide all test equipment and facilities required for the inspection at his
cost if requested by Company’s/ Purchaser’s Inspector.

2) Supplier shall furnish sufficient personnel to perform the inspection at his cost.

3) All applicable documents such as the latest specifications, vendor’s drawings shall be
available at Supplier’s shop for Company’s/ Purchaser’s Inspector

2.3 For all inspections, Supplier shall make available for the Company’s/ Purchaser’s Inspector
all test records and certificates, whether witnessed or non-witnessed.

2.4 Company/Purchaser reserve the right to witness or audit Supplier ’s quality control at
Supplier’s facilities.

2.5 Completion of the witnesses inspections and document review by the Purchaser’s/
Company’s Inspector does not relieve supplier of his responsibilities or obligations under the
purchase order.

2.6 The attachment summarizes the scope of inspection.

2.7 The attachment also specifies the necessary records and certificates that shall be prepared by
Supplier.

2.8 Inspection grade may be increased or decreased based on Supplier’s performance.

2.9 Based on this procedure, Inspection and Test Plan (ITP) shall be developed and submitted to
Purchaser for approval prior to inspection.
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud
JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 3 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MTL

2.10 These parties reserve the right to observe any inspections or tests during fabrication.

Abbreviations

DPP: Algerian Government Ministry Of Energy and Mines


Direction du Patrimoine Energetique et Minier

Company: Organization Ourhoud

Purchaser: JGC Corporation

3. EXTENT OF WITNESSED INSPECTIONS

3.1 Abbreviations and Definitions

Abbreviations used in this specification are as follows:

FW : Full witness inspection/test


The Supplier shall submit witness inspection notice to Purchaser. Should the Purchaser
decide not to witness the inspection and the Supplier is advised in writing from
Purchaser, the Supplier can proceed to the next stage.

SW : Spot Witness inspection/test


The Supplier shall submit witness inspection notice to Purchaser. Should the Purchaser
not attend the inspection, the Supplier can proceed to the next stage irrespective of such
notice in writing from the Purchaser.

R: Verify by reviewing the Supplier’s inspection/test record.

3.2 Supplemental Explanations

“Spot witness” means to carry out the witnessed test on sampled (e.q.10% random)
instruments from a lot per type unless otherwise specified. The minimum quantity to be
inspected shall be one per lot.

Instruments with accessories of the same specification being ordered under an issue of
Purchase Order are defined “one-lot”.
(These instruments shall be manufactured under the same process from same material batch.)
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud
JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 4 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MTL

Inspection/test records of FW,SW and R shall be included in MRB.


The records of SW shall cover all items. i.e., SW records and vendors inspection/test records
for not spot inspected items.

The test/inspection items to be carried out by the Vendor/Purchaser/ Principal in the Tables I
through V attached.

4. Manufacturing Record Book (MRB)


At the final acceptance of the equipment or materials, Supplier ’s test and inspection
records/reports shall be compiled into Manufacturing Record Book (MRB) and shall be
submitted for review to inspector.
For the detail, refer to S-000-1530-101 for “Inspection Coordination Procedure with
Supplier”.
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 5 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MATERIALS

TABLE I (IN-LINE INSTRUMENTS)

Inspected by

Non-Destructive test

Performance test
Certificates 1)
Pre-Inspection

Seat Leakage
(TSO Valve)
Pressure test
Dimensions

Calibration
Accessories
Appearance
Quantities
Company

Purchaser

Supplier

Physical
Meeting

Material
Description

DPP
1 Orifice Plate NO - - X - R R - R R - - - - -
2 Multi Phase Flow Meter YES X X X - FW FW FW R R R - FW - SW
3 Turbine Meter NO - - X - R R R R R R - - - R
4 PD Meter NO - - X - R R R R R R - - - R
5 Control Valve YES X X X FW FW FW SW R SW SW SW SW SW
6 Relief Valve YES - X X - FW FW FW SW R SW SW - - SW
7 Shutoff Valve YES X X X X 3) FW FW FW SW R SW SW SW SW -
8 Level Gauge NO - - X - R R R R R R - - - -
9 Displacement Type Level Inst NO - - X - R R R R R R - - - -
10 Analyzer Sample Prove NO - - X - R R - R R R - - - -
11 Ultrasonic Flow Meter NO X R R - R R R - - - R

FW : Full witness
SW : Spot witness
R : Verify Supplier’s Test/Inspection Record

Notes

1) Certified mill test report for Wet Parts only.


2) Actual flow calibration is not required, only electrical calibration is required.
3) Only 1,500# and higher by DPP
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 6 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MATERIALS

TABLE II (ON-LINE INSTRUMENTS)

Inspected by

Performance Test
Certificates 1)
Pre-Inspection

Pressure test
Dimensions

Calibration
Appearance

(Leak test)
Quantities
Company

Purchaser

Supplier

Physical
Meeting

Material
Description Remarks

Transmitter
1 NO - - X R R - R - - R
(Flow/Press/Level/Temp)
2 Pressure Gauges NO - - X R R - R R - R
3 Pressure Switch NO - - X R R - R R - R
4 Purge Set NO - - X R R - R R R -
5 Tank Gauges NO - - X R R R R - - R
6 Analysers YES X X X FW FW SW R R FW SW

FW : Full witness
SW : Spot witness
R : Verify Supplier’s Test/Inspection Record

Notes

1) Certificate of Compliance for the material for Wet Parts only.


COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 7 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MATERIALS

TABLE III (SYSTEM INSTRUMENTS)

Inspected by

Function and/or

including spares
Performance test
Pre-Inspection

Dimensions

Calibration
Appearance
Quantities
Company

Purchaser

Supplier

Physical
Meeting

I/O test
Description Remarks

1 DCS YES X X X FW FW SW FW FW 1) R
2 ESD System YES X X X FW FW SW FW FW R
3 F&G System YES X X X FW FW SW FW FW 1) R
4 Training Simulator YES X X X FW FW SW FW FW 1) -
5 Tank Gauging System YES X X X FW FW SW FW SW SW

FW : Full witness
SW : Spot witness
R : Verify Supplier’s Test/Inspection Record

Notes

1) FW to be basically applied, but subject to change to SW by considering inspection program and schedule.

2) Including RTU.
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 8 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MATERIALS

TABLE IV (OFF-LNE INSTRUMENTS)

Inspected by

Performance test or
Pre-Inspection

Pressure test
Dimensions
Calibration
Appearance
Quantities
Company

Purchaser

Supplier

Physical
Meeting
Description Remarks

1 Thermocouple/RTD & Well NO - - X R R R R R


2 Dial thermometer & Well NO - - X R R R R R
3 Local Controller NO - - X R R R - -
4 Flame Detector NO - - X R R R - -
5 Gas Detector NO - - X R R R - -
6 Heat Detector NO - - X R R R - -

FW : Full witness
SW : Spot witness
R : Verify Supplier’s Test/Inspection Record
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 9 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MATERIALS

TABLE V (PREFABRICATED INSTRUMENTS)

Inspected by

Function and/or

including spares
erformance Test
Pre-Inspection

Construction

Dimensions

Calibration
Appearance
Quantities
Company

Purchaser

Supplier

Physical
Meeting

I/O test
Description Remarks

1 Auxiliary Cabinet YES - X X FW FW SW SW FW FW -


2 Local Panel YES - X X FW FW SW SW FW FW -
3 Wellhead Control Panel YES X X X FW FW SW SW FW FW -

FW : Full witness
SW : Spot witness
R : Verify Supplier’s Test/Inspection Record
COMPANY’S DOC. NO. 7461-ORH-AQ-Q-87016
URHOUD - Organisation Ourhoud JOB No. DOC. No. REV.
0-1800 S-000-1520-009 1
PROJECT SPECIFICATION
SHEET 10 OF 10
SCOPE OF INSPECTION FOR INSTRUMENT MATERIALS

TABLE VI (BULK METERIALS)

Inspected by

Materials Certificate

Continuity Test
Pre-Inspection

Electrical Test
Dimensions

Press. Test
Appearance
Quantities
Company

Purchaser

Supplier

Physical
Meeting

1)
Description Remarks

1 Instrument Cable NO - - X R R R R - R -
2 Wiring Materials NO - - X R R R R - R -
3 Inst.Air Piping/Tubing Materials NO - - X R R R - - - R
4 Cable Trunking NO - - X R R R - - - -
5 Field Junction boxes NO - - X R R R R - - -
6 Tube & Fittings NO - - X R R R - R - R
7 Valve Manifold/Gauge Block NO - - X R R R - R - R

FW : Full witness
SW : Spot witness
R : Verify Supplier’s Test/Inspection Record

Notes

1) Certificate of Compliance for the material for Wet Parts only.