Itp 1
Itp 1
SHOP INSPECTION
RDMP – 2A – WK – ITP – 70 – 0003
1 IFA 13-Mei-2019
0 IFR 3-Mei-2019 DKO FAA ADW
DIBUAT DIPERIKSA DISETUJUI DIPERIKSA OLEH DISETUJUI OLEH
REV. STATUS TANGGAL
PT.WIJAYA KARYA (PERSERO) TBK PT. PERTAMINA (PERSERO)
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T
INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
No Owner Comment Name & Title Contractor response Name & Title
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
TABLE OF CONTENTS
1. GENERAL.............................................................................................................................................................5
2. SCOPE...................................................................................................................................................................5
3. REFERENCES.....................................................................................................................................................5
4. DEFINITIONS......................................................................................................................................................6
5. EQUIPMENT AND MATERIAL TO BE INSPECTED / TESTED................................................................6
6. DEFINITIONS AND ABBREVIATIONS..........................................................................................................7
7. CIVIL AND STRUCTURAL.............................................................................................................................8`
1. GENERAL
PT Pertamina Balikpapan (here in after referred to as "OWNER") to develop and implement a
Proyek Site Development 2A RDMP RU-V located at PT. PERTAMINA ( PERSERO ),
Balikpapan, East Kalimantan, Indonesia, adjacent to OWNER plants.
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
2. SCOPE
This Inspection and Test Plan (ITP) provides an inspector with a systematic tool that covers
each phase of electrical work it will likely be performed at Proyek Site Development 2A
RDMP RU-V Balikpapan.
3. REFERENCES
NEC National Electrical Code.
NEMA National Electrical Manufacturers Association.
ANSI American National Standards Institute.
ASA American Standards Association.
IEC International Electrotechnical Commission
RDMP-2A-WK-DWG-30-0001 Single Line Diagram Of Drainage Pump.
RDMP-2A-WK-DWG-30-0002 Electrical Power & Control Cable Routing Layout.
RDMP-2A-WK-DWG-30-0003 Outdoor Street Lighting Layout.
RDMP-2A-WK-DWG-30-0004 Lighting Panel Schedule Of Outdoor Street
Lighting.
RDMP-2A-WK-DWG-30-0005 Grounding Layout Of Outdoor Street Lighting.
RDMP-2A-WK-DWG-30-0006 Lighting And Small Power Layout Of Telecom
Server
Building.
RDMP-2A-WK-DWG-30-0007 Panel Schedule Server Building.
RDMP-2A-WK-DWG-30-0008 Lightning Protection Layout Of Telecom
Server Building.
RDMP-2A-WK-DWG-30-0009 Grounding Layout Of Telecom Server Building.
RDMP-2A-WK-DWG-30-0010 Lighting Installation Detail.
RDMP-2A-WK-DWG-30-0011 Grounding & Lightning Protection Installation.
4. DEFINITIONS
PROJECT Proyek Site Development 2A RDMP RU-V
Balikpapan
OWNER PT. Pertamina ( Persero )
CONTRACTOR PT. Wijaya Karya (Persero) Tbk
SUBCONTRACTOR The subcontractor of WIKA who is
responsible for carrying out activities required
by Contractor.
VENDOR Vendors supplying materials or equipment to
Contractor.
INSPECTION An activity such as measuring, examining or
gauging one or more characteristic of an
entity and compare the results with specified
requirements in order to establish whether
conformity is reached for each characteristic.
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
H : Hold
Witness the operation test / examination where Contractor’s Inspector and / or
OWNER’s Inspector must be notified in advance and must be present during
the specified activity and no test / examination can be proceeded without
attendance of the related representative(s)
W : Witness
Witness the operation test / examination where the Contractor’s Inspector and /
or OWNER’S Inspector must be notified in advance and shall present during
the specified activity.
SW : Spot Witness
Sample check could be performed for Typicall material. Personnel doing the
work shall notify assigned Quality representative when the work is to be
performed so that witnessing activities could take place. Work does not stop if
assigned representative is not present.
R : Review
Review and acceptance of documents and reports (include films of
radiographic testing).
M : Monitoring
Verifying work and testing activities on an on-going basis as deemed necessary.
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
7.2 PC Piles
1. Pre-inspection meeting (if required) M W R
2. Documents M R R
a. Mixing Formula
b. Material certificate of Rebar
c. Ultimate Strength Test Report
d. Bending Strength Test Report
3. Final Inspection M SW R
a. Dimensional check
b. Visual inspection
c. MarkingPacking
d. Quantity check
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
7.4 Concrete
1. Documents M R R
a. Draft Mix formula
2. Trial Mix Formula M W SW
a. Mixing
b. Slump test
c. Compressive strength test
3. Final Document M R R
a. Mix Formula
b. Slump test report
c. Compressive strength test report
1
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T
INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
8.6 Pump
1. Pre-inspection meeting P W R
2. Material certificates M R R
a. Pump
Pressure Casing
Impeller(s)
Piston or Plunger
Shaft
Shaft Sleeves
Case and Impeller Wear Rings (if
applicable)
b. Auxiliary Process Fluid Piping and Pressure
Containing Components.
c. Coupling
Hub (flange)
Spacer
3. Non-destructive Examination, for following items: M R R
a. Casing
MT or PT for Plate Edge
MT or PT for All Accessible Welds
MT or PT for Connecting Welds
Visual Check on Casting
NDE on Repair Welds
PT on Cast Iron Repairs
b. Impeller
Visual Inspection on Casting
MT or PT on impeller surface
c. Shaft
MT or PT on shaft if welded
4. Rotor Inspection M R R
a. Run-out Test
b. Dynamic Balancing Test (for each rotating
component and completely assembled rotor)
5. Performance / Running Test (FAT) M W R
a. Performance Test
b. Vibration Measurement
c. Sound Level Test
d. Mechanical Running Test
6. Appearance and dimensional check M R R
7. Final Inspection M R R
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T
INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
8.8 Conveyor
1. Pre-inspection meeting (if required) P W R
2. Procedure P R R
a. Fabrication procedure
b. WPS/PQR
c. Installation procedure
d. Painting Procedure
3. Material certificates P R R
a. Structural steel
b. Belt
c. Gear
4. Non-destructive Examination, for following items: M R R
a. Visual check on welding joint
b. MT/PT
5. Appearance and dimensional check M R R
6. Function and calibration test for all P R R
instrumentations
7. Pre-assembly check M W R
8. For Tripper Conveyor, trial assembly for its rail M W R
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T
INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
8.12 Screen
1. Pre-Inspection Meeting (if required) P W R
2. Procedure P R R
a. Drawing, Design, Calculation Document
b. WPS&PQR
c. Welder Qualification Certificates
d. Fabrication Procedure
e. Installation Procedure
3. Materials P R R
a. Material Certificates
b. Material Identification
c. Visual, Dimension and Marking Control
(Decks, Frame, Frame Support, Hopper,
Cover, Bearings and etc.)
4. During Fabrication M R R
a. Components Visual Inspection
b. Components Dimensional Check to Drawing
Requirements
c. Visual Examination of Welded parts
d. Components Confirmation of Satisfactory
NDE
e. Ducting inspection (Welded, Riveted, Rolled)
f. Auxiliary Equipment
5. Factory Acceptance Test P W R
a. Mechanical Running Test
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN TINSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
8.13 Furnace
1. Pre-Inspection Meeting (if required) P W R
2. Procedure P R R
a. Drawing, Design, Calculation Document
b. WPS&PQR
c. Welder Qualification Certificates
d. Fabrication Procedure
e. Installation Procedure
3. Materials P R R
a. Material Certificates
b. Material Identification
c. Visual, Dimension and Marking Control
(Burner, Shell, Refractory and Dilution Shell)
4. During Fabrication M R R
a. Components Visual Inspection
b. Components Dimensional Check to Drawing
Requirements
c. Visual Examination of Welded parts
d. Components Confirmation of Satisfactory
NDE
e. Ducting inspection (Welded, Riveted, Rolled)
f. Auxiliary Equipment
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T
INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
8.20 Cyclone
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T
INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)
9. PIPING
9.3 Flanges
1. Material certificates, including P R R
a. Chemical composition
b. Mechanical property
2. Inspection P SW R
a. Visual
b. Dimensional
3. Final inspection P R R
a. Dimensional including face finish
b. Visual
c. Facing finish
d. Marking / tagging
e. Protection for shipping
f. Manufacturer's reports
9.4 Fittings
1. Material certificates, including P R R
a. Chemical composition
b. Mechanical property
2. Inspection P SW R
a. Visual
b. Dimensional
3. Final inspection P R R
a. Dimensional including face finish
b. Visual
c. Facing finish
d. Marking / tagging
e. Protection for shipping
f. Manufacturer's reports
9.6 Gasket
1. Material certificates, including P R R
a. Chemical composition
b. Mechanical property
2. Gasket visual and dimensional control H SW R
(Sampling test is required as per manufacturer's
standard)
3. Gasket marking and color coding check H SW R
4. Final inspection, including: H SW R
a. Marking / tagging
b. Protection for shipping
c. Manufacturer's reports
d. Packaging and quantity control
10. INSTRUMENTATION
e. Loading Inspection
f. Manufacturer Data Record
1. Document P R R
a. Mill Certificates
b. Hydrostatic Procedure
c. Detail Drawing
2. Visual Inspection M R R
3. Inspection and Test M W W
a. Hydrostatic Test
b. Function Test
c. Popping Test
d. Seat Leakage Test
5. Pre‐Shipment Inspection P R R
a. Preservation and Packing
b. Loading Inspection
c. Manufacturer Data Record
d. Manufacture Name Plate
11. ELECTRICAL
11.8 Cables
1. Pre-Inspection Meeting (when required) P W R
2. Documents P R R
a. Testing Procedure
PT WIJAYA KARYA (Persero)
INDUSTRIAL PLANT DEPARTMEN T INSPECTION AND TEST
PLAN PEKERJAAN
ELECTRICAL (SITE)