Professional Documents
Culture Documents
14072017I6DKO6NAConceputal PlanDMIC IITGNL
14072017I6DKO6NAConceputal PlanDMIC IITGNL
For
DMIC Integrated Industrial Township Greater Noida
Greater Noida, Tehsil Dadri
Dist: Gautam Buddh Nagar in Uttar Pradesh
Prepared for
TABLE OF CONTENTS
1 INTRODUCTION ................................................................................................. 1
1.1 Project Background .................................................................................................... 1
1.2 Project Proponent....................................................................................................... 2
1.3 Brief on the Project ..................................................................................................... 2
1.3.1 Nature, Size, Location of the Project ................................................................... 2
1.3.2 Environmental Clearance Required ..................................................................... 3
2 PROJECT DESCRIPTION .................................................................................. 6
2.1 Regional Context ........................................................................................................ 6
2.2 Site Description .......................................................................................................... 8
2.3 Land Use Zoning ...................................................................................................... 12
2.4 Layout Plan- DMIC IITGNL ....................................................................................... 14
2.5 Land Area and Built up Area-DMIC IITGNL .............................................................. 15
2.5.1 Implementation horizon ..................................................................................... 17
2.6 Infrastructure Plan .................................................................................................... 19
2.6.1 Water Supply ..................................................................................................... 19
2.6.2 Waste Water Management ................................................................................ 20
2.6.3 Storm Water Drainage ....................................................................................... 22
2.6.4 Solid Waste Management ................................................................................. 26
2.6.5 Power Requirement ........................................................................................... 30
2.6.6 Master Plan Provision for Green Area Development.......................................... 32
2.7 Transportation .......................................................................................................... 38
2.7.1 Roadway Cross-Sections .................................................................................. 39
2.7.2 Parking Guidelines ............................................................................................ 39
2.7.3 Parking Requirements ....................................................................................... 45
2.8 Project Cost.............................................................................................................. 45
ii | P a g e
EIA of DMIC Integrated Industrial Township Greater Noida [DMIC IITGNL]
LIST OF TABLE
Table 2-1: Categorization Project as per EIA Notification ...................................................... 3
Table 2-1: List of Non-polluting Industries proposed in DMIC IITGNL ................................. 14
Table 2-2: Proposed Landuse Distribution & Built-up area statement .................................. 16
Table 2-3: Water Demand-Potable, Non-Potable ................................................................ 19
Table 2-4: Summary of Waste Water Generation ................................................................ 21
Table 2-5: Catchment details .............................................................................................. 26
Table 2-6: Type of Waste and Generation as per CPHEEO & Regional Centre for Urban and
Environmental Studies, (RCUE) Lucknow ........................................................................... 27
Table 2-7: List of Plant Species for Green Belt .................................................................... 35
Table 2-8: List Shrubs for Groundcover............................................................................... 37
Table 2-9: Parking Norms – GNIDA Building Regulations ................................................... 43
Table 2-10: Parking Requirement for DMIC IIT, Greater Noida ........................................... 45
iii | P a g e
EIA of DMIC Integrated Industrial Township Greater Noida [DMIC IITGNL]
LIST OF FIGURES
Figure 1-1: Location of DMIC Integrated Industrial Township with respect to DMIC Influence
Zone ..................................................................................................................................... 1
Figure 1-2: DMIC IIT GN Site and Surroundings (Depicted on SOI- Toposheet) ................... 5
Figure 2-1: Project Site and Proposed Surrounding land uses in GNIDA Master Plan 2021 .. 7
Figure 2-2: Proposed GNIDA Master Plan Road ................................................................. 10
Figure 2-3: Existing Road Network ...................................................................................... 10
Figure 2-4: Proposed and Existing DMIC IITGNL Access Road .......................................... 11
Figure 2-5: Project Site Photographs .................................................................................. 12
Figure 2-6: Proposed Land Use Zoning............................................................................... 13
Figure 2-7: Pie – Chart showing Landuse Distribution for Layout Plan ................................ 16
Figure 2-8: Landuse Distribution for Site Layout Plan.......................................................... 17
Figure 2-9: IIT, GN Lease Plan Areas ................................................................................. 18
Figure 2-10: Water Mass Balance Diagram. ........................................................................ 23
Figure 2-11: Surrounding drainage features of project area ................................................ 24
Figure 2-12: Proposed Storm Water Drainage network – DMIC IITGNL .............................. 25
Figure 2-13: Location of the Solid Waste Transfer Station with Waste Management Facility30
Figure 2-14: DMIC IITGNL Green Belt Plan ........................................................................ 33
Figure 2-15: Roadway Classification Map ........................................................................... 40
Figure 2-16: 30m ROW Roadway Cross-Section ................................................................ 41
Figure 2-17: 30m ROW Roadway Cross-Section (SCR-1 between sector road and central
spine) .................................................................................................................................. 41
Figure 2-18 : 45m ROW Roadway Cross-Section ............................................................... 42
Figure 2-19: 60m ROW Roadway Cross-Section ................................................................ 42
Figure 2-20 : 80m ROW Roadway Cross-Section ............................................................... 42
iv | P a g e
Conceptual Plan of DMIC Integrated Industrial Township Greater Noida [DMIC IITGNL]
1 INTRODUCTION
The proposed site for “DMIC Integrated Industrial Township” is situated within the
notified Greater NOIDA Master Plan – 2021 planning area and is located at its south.
The IIT, GN which falls in Gautam Budha District, is expected to be the largest of all
of the industrial nodes to be developed within the DMIC. IIT, GN alignment and DMIC
influence area is shown in Figure 1-1. Project site and surrounding 10 km area
demarcated on Survey of India (SOI) Toposheet shown in the figure 1-2.
The site is located at a road distance of 11 km from Pari Chowk, Greater Noida. The
site abuts the Delhi-Howrah Railway line and Ajayabpur Railway Station is situated
near the north eastern periphery of the site.
The aerial distance of the Sikandrabad (South east) town and NH-91 (North East) are
approximately 10 and 6 km, respectively. The Dadri railway Junction is also located
close to the site. It is situated approximately 9.5 km from the site. In terms of
administrative boundaries, the proposed site falls under Gautam Buddha Nagar
district.
The proposed IIT is connected to Greater Noida, Noida and Delhi through the Noida
– Greater Noida Expressway. A 60m North-South road is being constructed along the
western boundary of the site which will provide connection to proposed eastern
peripheral Expressway service roads, and the proposed metro station at Boraki.
There is an existing railway station at 1 km. from the central commercial core. There
is proposed MRTS feeder connection along the 60m Sector road to the West outside
the township. Boraki Railway Station is 4 km. north of the township. The nearest
airports to the site are in New Delhi to the East and Meerut to the North.
1.3.2 Environmental Clearance Required
Environmental Impact Assessment Notification, 2006
Projects or activities listed in the Schedule to this notification shall require prior
environmental clearance from the Expert Appraisal Committee (EAC) of Ministry of
Environment and Forests & Climate Change (MoEF&CC) for developmental activities
falling under Category ‘A’ of the Schedule and from the State Environmental Impact
assessment Authority (SEIAA) at the State level for development activities falling
under Category 'B' of the said schedule, before any construction work, or preparation
of land by the project proponent (PP).
Implication: The IIT project requires Environmental Clearance from the State Expert
Appraisal Committee (SEAC) and State Environmental Impact Assessment Authority
(SEIAA) of the state of Uttar Pradesh under the Category 8(b) Township and Area
Development Projects as per the EIA Notification 2006. The General Condition (GC)
clause as per the EIA Notification is not applicable for this project vides Amendment
22nd December 2014 (SO No-3252E) of EIA Notification 2006.
The EIA Notification is further amended on 9 th December 2016 and the ‘Area
Development project’ is categorized as below Table 2-1:
Table 1-1: Categorization Project as per EIA Notification
Project or Activity
“8” Building/ Construction projects/ Area Development projects and Townships
A B Conditions (if any)
(1) (2) (3) (4) (5)
8(a) Building and >20,000 sq. The term “built up area” for the purpose
Project or Activity
“8” Building/ Construction projects/ Area Development projects and Townships
A B Conditions (if any)
(1) (2) (3) (4) (5)
Construction mtrs and of this notification is the built up or
projects <1,50,000 sq. covered area on all floors put together
mtrs of built up including its basement and other service
area areas, which are proposed in the
buildings and construction projects.
Note 1. The projects or activities shall not
include industrial shed, universities,
college, hostel for educational
institutions, but such buildings shall
ensure sustainable environmental
management, solid and liquid and
implement environmental conditions
given at Appendix-XIV.
Note 2.-General Condition shall not
apply.
Note 3.-The exemptions granted at Note
1 will be available only for industrial shed
after integration of environmental norms
with building permissions at the level of
local authority.
8(b) Townships ≥3,00,000 ≥1,50,000 sq. Note. - General Condition shall not
and Area sq. mtrs mtrs and apply”.
Development of built up <3,00,000 sq.
projects area or mtrs built up
Covering area
an area or
≥150 ha covering an
area ≥50 ha
and <150 ha
The project category for IIT, GN would be under 8(b), Category ‘A’ project as per the
above notification. The project will be appraised at Expert Appraisal Committee
(EAC), MoEFCC.
The individual units (Industrial, commercial, residential etc.) have to take separate
environmental clearance and consent as per the Category 8(a) notification given in
the above EIA Notification amendment at the later stage of the project.
Figure 1-2: DMIC IIT GN Site and Surroundings (Depicted on SOI- Toposheet)
2 PROJECT DESCRIPTION
The proposed site for “Integrated Industrial Township” is situated within the notified
Greater NOIDA Master Plan – 2021 planning area and is located at its south-eastern
edge abutting the proposed Eastern Peripheral Expressway (EPE). The proposed
EPE runs parallel to the site on the southern boundary and adjoins the site on Delhi-
Howrah railway line in the east.
The proposed site for “Integrated Industrial Township” has an area of approximately
302.63 hectares. The “Integrated Industrial Township” project has been
conceptualized to harness the potential of an already existing manufacturing cluster
(Greater Noida), which is in very close proximity to its proposed location. Some of the
key objectives associated with setting up of “Integrated Industrial Township” at
Greater Noida are:
To act as catalyst for the industrial development of the investment region by
attracting skilled human resources at the Township,
To create benchmark for comprehensive built environment for future smart
cities, in DMIC investment region.
To strengthen the status of Greater NOIDA and NOIDA as a manufacturing
destination in the National Capital Region (NCR).
To encourage creation and growth of new business and economy as whole
by fostering collaboration and innovation, also enhancing the development,
transfer and commercially viable application of latest technology.
To foster collaboration between industries and existing/ proposed
educational institutes.
To promote new industries with value addition to existing industries.
2.1 Regional Context
The project site is surrounded by various land uses when analyzed with respect to
Draft GNIDA Master Plan 2021. The, eastern part abuts the proposed investment
region by DMIC - Dadri-Noida-Ghaziabad Investment Region. The south western and
the southern part abuts the tech zone and eco-tech zone, same have been illustrated
in Figure 3-2. Both zones are well planned industrial clusters. The southern and
eastern part of the site is surrounded by investment and intense activity oriented
zones related to industries and commercial activities and the eastern part adjoins the
residential use of Greater Noida.
The delineated site is also approximately 5km from the prime commercial centre/
central business district and Knowledge Parks proposed within Greater Noida Master
Plan. Other major land uses adjoining the Integrated Industrial Township include a
large residential zone towards the north-west, and industrial and institutional uses on
the south-eastern side.
DMIC IITGNL
Figure 2-1: Project Site and Proposed Surrounding land uses in GNIDA Master
Plan 2021
The site is also currently manifested with numerous mature trees spread across the
site. Dense tree plantation is observed particularly in some areas near the 60m elbow
road and towards the southern part of the site, near the existing settlement and
structures.
Ajayabpur settlement exists within the project site boundary as marked in GNIDA
Lease Plan. The settlement comprises of concrete structures and mostly residential.
A group of residential structures is also observed at the southern end of the site,
much smaller than Ajayabpur, and not a settlement in itself.
Rithori is another major settlement that previously was adjoining the site area at the
south-eastern part of the site. The revised Lease Plan shows the settlement to be
approximately 500m away from the site. The settlement continues to be primarily
accessed through the site on its western periphery as it is bordered by the existing
railway line on its eastern edge.
Figure 2-2: Proposed GNIDA Master Plan Road Figure 2-3: Existing Road Network
The 132 kv High tension Lines that were previous running the parallel along the
length of the site at the eastern end, have now been consciously excluded from the
project site area as per the revised Lease Plan. Although a smaller stretch of 132 Kv
HT lines still is a part of the project area on the north-eastern parcel – running along
the railway line.
The Delhi-Aligarh railway line running parallel to the eastern edge of the site has two
crossings across it along the eastern boundary of the site. One to the north of
Ajayabpur railway station and another towards the south-eastern tip of the site.
The site is currently partly under agriculture use. Even sized agriculture plots mainly
of wheat and mustard fields are observed all through the site. The site is primarily flat
in nature with a gentle slope towards Yamuna river side. However minor saucer
depressions are sighted towards the southern end of the site. Some pictures of
project site is given in Figure 3-5
East: Railway Crossing Eastern South: Built Drainage along the Edge
Boundary Road
North West: High Tension Power Line West: Main Kadala distributaries Canal
passing North East Corner
Figure 2-5: Project Site Photographs
2.3 Land Use Zoning
The proposed zoning for the lIT, GN is based on various parameters such as field
observations, site challenges and opportunities, existing built infrastructure, case
studies etc. The road network is based on the already proposed GNIDA Master Plan
Roads. The site being linear in nature, a central spine road is proposed all along the
length of the site, which is to be projected as the main development corridor for the
site. The commercial land uses are zoned along the central corridor, such that their
access is towards the central spine road. This ensures that maximum density is
proposed along the central spine.
The industrial use is proposed to cover primary four types of industries spanning fifty
percent of the site area as per the landuse distribution requirement. The industries
are zoned based on visibility, accessibility and with respective surrounding landuse
zoning of the site.
Hi-Tech Industries - Low-rise Buildings along the sector roads and at the
northernmost part.
IT Industries - High-rise Signature Buildings at the entrance imparting
impressive aesthetics right at the strategic location. buildings along the
sector road and the Expressway - almost occupying southern land parcels
located in southern/lower land parcels.
R&D Industries - mid-rise landmark structures occupy the central areas on
the eastern side of the central spine road located in central land parcels.
Commercial buildings - High-rise modern structures along the central spine
road and 60m E-W road - along the high speed transit corridor
Tall Residential Towers designed around the green spaces at the entrance
and along the western periphery of the site.
Carefully designed green spaces to offer leisure, relaxation and informal
interactive spaces for employees as well as the residents
The plan offers multiple access to the entire development
A CBD strategically located in the heart of the township caters primarily to
industrial set-up housing Business Pavilion, Convection Centre, Exhibition
Pavilion, star rated Hotels and Offices, including ample retail shops.
The CBD core is designed to impart distinct character to the entire
township, flanked by signature buildings demonstrating world-class
architectural marvel.
2.5 Land Area and Built up Area-DMIC IITGNL
The DMIC IITGNL will be developed as non- polluting Industrial, Commercial and
Residential project (Group Housing) supported by ancillary facilities like community
halls, parks, and green area for the residents and workers. DMIC has identified a site
of 302.63 ha for the development of Integrated Industrial Township for IT, Hi-tech
Industry, Bio-tech Industry, R&D as well as residential housing HIG, MIG, targeting
LIG and EWS.
The Lease Plan for Integrated Industrial Township is demarcated for 302.63 ha. This
lease Land area depicted in fig 3-9 including proposed GNIDA roads. Land required
for proposed project is 265 Ha which is without GNIDA proposed roads. No more
land acquisition or resettlement is required for the project.
Total built up area of the project will be 677.14 ha (67,71,700 Sq. m.). Detail landuse
distribution, FAR & built-up area statement given in table 3-2. It is proposed to
develop green, open spaces in 40.78 Ha (15.4%) areas inside the project area.
Additionally, as per state byelaws industrial unit has to provide 15% green area.
Proposed total industrial and residential area inside the project site is 134.57 ha
(50.78%) and 27.64 ha (10.43%) respectively. Economically Weaker Section (EWS)
housing provision 4.2 ha area allocated as per the GNIDA Bye-laws. All internal
roads area is 42.1 ha (15.89%). Percentage Landuse distribution pie chart of DMIC
IITGNL is depicted in the figure 2-7.
Figure 2-7: Pie – Chart showing Landuse Distribution for Layout Plan
by providing storage in pond was discussed. As the duration of rainfall is very less
and cost of underground reservoir for storing the rain water is very huge, option of
using underground water by drilling suitable number of bore well in the project area
was agreed. The necessary permission would be sought from the Ground Water
Authority for withdrawal of water
Initially, the construction in the DMIC IITGNL would involve infrastructure
development like roads, sewerage, water supply etc. The construction water for this
phase would be made available by tanker water supply.
2.6.1.2 Water Treatment Options
As treated water will be made available under 85 cusec Ganga Water project
scheme, no additional treatment for water is suggested. Only arrangement for
disinfection will be provided.
As bore well water will be supplied for one month duration only, no treatment for this
water has been suggested. The quality of treated water shall meet the standard set
as per “Water Supply and Treatment” manual, Central Public Health and
Environmental Engineering Organisation.
Various best practices adopted in this project are:
Un-interrupted water supply system on 24 x 7 basis
Recycling of reclaimed water
Dual piping system (Potable and Non potable)
Complete automation using SCADA system(Supervisory Control & Data
Acquisition)
Efficient water distribution network management
Pipe network of quality pipes and fittings
Pressure & Flow monitoring
Active leakage control and detection
100% meter connection
Energy efficient pumps and motors (VFD Controlled)(Variable Frequency
Drive)
Optimized design of pumping main
2.6.2 Waste Water Management
The main objective of wastewater system is to ensure that the waste water generated
from various land parcels within project area is collected, conveyed, treated and
disposed off in safe Environmental friendly manner. The wastewater system would
be designed for the expected wastewater flow based on the water demands for
various land parcels. The design flow would be based on the saturated population of
the project town.
2.6.2.1 Waste Water Generation
Wastewater flow has been computed based on potable water supply to consumer (@
80%) and non-potable for flushing purpose (@ 100%). Infiltration will be considered
as per CPHEEO manual Summary of Waste Water generated in the township is
provided as Table 2-4.
1 Residential 6.21
2 Commercial 0.20
3 Industrial 7.84
4 Provision for villages 1.39
A Total Waste water 15.64
B Infiltration @ 5000L/km/day
0.10
for approx.20 km of sewer line
C Waste Water Generation 15.74
D Treated water @ 95% recovery 14.95
While planning for providing a comprehensive sewerage system to the project
township, entire Township has been divided into three wastewater collection &
treatment zones in previously submitted master plan. However during discussion with
GNIDA, it was advised to integrate the sewerage system with existing sewerage
system and discharging the sewage to the STP-1 of 72 MLD capacity proposed
under peripheral sewerage system of 14 sectors of Greater Noida and thus
eliminating the construction of additional STP inside the project premises.
Though the proposed site is partially covered with sewerage network only the
sewerage network laid along the 60m North South Road can be used. The entire
sewage will be collected by providing sewer network and system will be
interconnected with already laid sewer line along the 60m wide North-South road,
which is already connected to the STP-1 proposed under peripheral sewerage
scheme.
Construction Period contractor will be contractually obliged to construct Pit latrines
and community toilets with septic tanks followed by soak pits will be constructed for
construction workers.
2.6.2.2 Wastewater/Sewage Treatment Plant
Proposed township is to be developed mainly as industrial hub (non-polluting)
followed by commercial and residential land use and hence the sewage generation
will be of domestic municipal nature.
Municipal sewage generally contains high BOD, suspended solids, COD, faecal coli-
forms and pathogens with respect to disposal norms of receiving water body or to
ground. The following alternative processes have been considered which appear to
be suitable for this magnitude of STP:
Moving Bed Bio-reactor (MBBR)
Sequential Batch reactor (SBR)
Membrane Bio Reactor (MBR)
Activated Sludge plant (ASP)
Factors influencing the selection of a process of STP are generally:
Performance efficiency in removal of BOD, COD, Suspended solid and
coliform
Land requirement vis-à-vis availability
Capital cost
Odour nuisance
Quality of effluent with respect to its disposal and utilization
Operation & Maintenance (O & M) cost
Considering the factors as discussed above, SBR appears to be most suitable
technology and hence recommended for the treatment of wastewater at DMIC IIT
Greater Noida. However as the proposed STP under Peripheral sewerage scheme in
Greater NOIDA is based on SBR technology, hence no additional treatment is
required inside the project area. For using recycled water, a pumping main will be
provided from the STP to the proposed Ground level reservoir inside the project area.
2.6.2.3 Zero Discharge Concept
The concept of Zero Discharge is:
By reusing treated waste water for non-potable water demand, justified
utilization of natural water resources is ensured;
Reuse of treated waste water enhances the capacity of the industry to
efficiently utilize available water as well as control its quality to the required
level.
With an increase in demand of natural resources it is essential to target
Zero Discharge system for any upcoming infrastructure development.
In view of above, the proposed township has been suggested to meet its non-potable
water demand (e.g. Landscaping, Horticulture, Flushing and makeup water for HVAC
etc.) by recycling the treated waste water, hence reducing the raw water demand
from source and making the water supply scheme more sustainable. For this
purposed Tertiary Treatment will be provided to the secondary treated wastewater to
achieve required quality of reclaimed water to be recycled. Detail Water mass
balance diagram shown in the figure 2-10.
2.6.2.4 Recycling of Wastewater
Distribution of recycled water is planned through direct pumping from Ground Level
reservoir. The reclaimed water will be collected in the ground level reservoir by
providing pumping main from the STP. From there the reclaimed water will be
pumped to each land parcel level. Recycled water will be delivered at the boundary
of each land parcel.
2.6.3 Storm Water Drainage
The Delhi-Howrah railway line passes parallel to north east boundary of the project
area, where as the Kalda distributory canal abuts south western side of the project
area. Kot escape canal passes through the north western boundary of project site.
Zone I Zone II
offices), parks (fallen branches, leaves from trees) and streets (sand, silt, clay,
concrete, bricks, asphalt, residues from air deposition and dust)
2.6.4.1 Tentative Quantity & Area Required:
IIT-Greater Noida would be an integrated township, which would have non polluting
industries, commercial activities, institutional and residential product mix. The
assessment of waste from these proposed product mix for DMIC IITGNL would be
based on metro cities, integration plan approach and current practices of Class -I
towns of U.P. State. The facilities would be independent to the extent possible and
adopt the philosophy of minimum discharge.
Table 2-6: Type of Waste and Generation as per CPHEEO & Regional Centre
for Urban and Environmental Studies, (RCUE) Lucknow
Quantity
S. N. Source Unit
CPHEEO RCUE
1 Residential Land use 24.06 14.44 kg/cap/day
Commercial Land use* -- 0.91 kg/unit/day
2 Commercial Floating Population 6.40 6.40 kg/cap/day
3 Hotel 0.20 0.20
The approach for selection of unit rate of solid waste assessment from various
sources at DMIC IITGNL has been referred from similar nature of development in
U.P. State, in absence of appropriate information, CPHEEO/ NEERI & GNIDA
reports have been referred. Thus, the solid waste generation from DMIC IITGNL has
been considered in the range of 62.86 MT/ Day to 145.98 MT/ day as per prevailing
and applicable norms. Either CPHEEO or RCUE standards/ norms may be approved
so as to work out and finalize the waste generation from integrated township.
2.6.4.2 Proposal for Solid Waste Management within Project Boundary
Waste generated in the form of biodegradable and recyclable shall be in the preview
of IITGNL. However, E-waste (Management & Handling) Rules 2016, The Hazardous
waste (Management, Handling and Trans-boundary Movement) Rules - 2016,
IITGNL would be approx. 25.86 TPD out of total 58.91 TPD (excluding E-Waste &
Biomedical Waste (BMW)). It is proposed to compost this waste by Bio-Methanation
so as to plan for sustainable process plant in terms of electricity requirement.
Compost generated from the BM plant would be used for gardening purpose in DMIC
IITGNL.
Recyclable Waste: Approx. 21.2% of total waste would be recyclable in nature
which comes out to be about 12.49 TPD. A policy would be formulated to deal with
recyclable waste and can be sold out to the authorized vendors through either PPP
or any other mode.
Non-Biodegradable Waste: Generally, about 34.9% of total MSW waste is non-
biodegradable in nature which comes out to be approx. 20.56 TPD. To cater non
biodegradable/ inert waste, it is proposed to transport these waste to the upcoming
landfill site (as per GNIDA master plan 2031). At landfill site, these waste can be
further segregated and inert/ residual can be disposed off into the landfill.
Bio-Medical Waste (BMW): As per the prevailing norms for handling & managing
BMW waste, it is the utmost responsibility of polluter to deal with these wastes
separately. The hospitals are required to get engaged with local NGOs or firms
working in the same field so as to manage their biomedical wastes. Approximately
about 25% of total wastes generated from hospitals are biomedical wastes in nature.
E-Waste: From Indian scenario, approximately 7% of total MSW is E-Waste which
comprises of old TV, printers, computers and its accessories, CFL or other lightings,
Mobiles etc. As per prevailing norms for E-Waste in India, it is mandatory to
segregate the E-Waste separately and deal with the same at premises level. A policy
may be framed to support the producers of E-Waste so as to manage the same
through external agencies. The planning for engaging external agency would be
done at PDR stage of this project.
Construction Waste: During construction stage, the contractor will provide garbage
bins in the camp and construction sites and it will be ensured that these are regularly
emptied and disposed off in a hygienic manner as per the Solid Waste Management
Plan as per Solid Waste (Handling and Management) Rule 2016. Burning of wastes
will not be allowed. Solid wastes generated at the construction site, plant & camp
sites, will be collected in covered waste bins and segregated as biodegradable (food
waste, paper, etc) and non-biodegradable (plastic, polyethylene bag, etc) wastes.
Polyethylene/plastic wastes will be stored in empty cement bags and to be sent for
recycling through scrap dealer. Biodegradable (food waste, paper, etc) solid waste
will be disposed in compost pit. The scraps like Iron materials, broken pieces of
stones, bricks, unused sand materials etc. will be generated. Since there is no
demolition work involved there is very little amount of waste will be generated.
Management of C&D wastes would be as per the provisions of construction and
demolition waste management rules, 2016. These wastes will not be mixed with the
municipal solid waste.
The construction waste generated during construction/ development of township
would be planned to get utilized within the township for filling of roads/ embankments
or for construction of pavements. Excess of same would be disposed off in a much
secured manner to the nearby low lying area along roadside. The quantity of
Figure 2-13: Location of the Solid Waste Transfer Station with Waste
Management Facility
2.6.5 Power Requirement
The site for the proposed Integrated Industrial Township is part of the delineated site
for Delhi-Noida-Ghaziabad Investment Region (DNGIR). It has a total site area of
302.63 Ha (747.5 acres). The proposed township is planned adjacent to the already
developed sectors of Greater Noida.
A landscape plan has been prepared for the whole township. Emphasis has
been laid on keeping the township green, environment friendly and pollution
free.
1
http://www.greaternoidaauthority.in/files/pdfs/mprepfin300316c.pdf
Spacing (m)
Total Height
Clear Trunk
Spread (m)
Botanical Common
Height (m)
Diameter
No Remarks
(mm)
Name Name
(m)
.
Spacing (m)
Total Height
Clear Trunk
Spread (m)
Botanical Common
Height (m)
Diameter
No Remarks
(mm)
Name Name
(m)
.
(c/c in mm)
No
Spacing
Spread
Overall
Height
(m)
1 Alocasia SPP Elephant's ear 0.75 0.5 400 min. 5 leaves, bushy
2 Bougainvillea Bougainvillea 0.6 0.4 500 Bushy, multi-branching
Glabra Red
3 Bougainvillea Bougainvillea 0.6 0.4 500 Bushy, multi-branching
Shubra White
4 Buxus Boxwood 0.3 0.3 200 Bushy, multi-branching
Semperviren
5 Bougainvillea SPP Bougainvillea 0.6 0.4 500 Bushy, multi-branching
(pink) pink
6 Bougainvillea SPP Bougainvillea 0.6 0.4 500 Bushy, multi-branching
(purple) purple
7 Crinum Asiaticum Grand Crinum 0.5 0.5 400 Min 6 Leaves, bushy
Lilly
8 Calliandra Red Powder Puff 0.75 0.5 500 Bushy, multi-branching
Haematicephala
9 Caesalpinia Dwaf Poincinia 0.75 0.5 500 Bushy, multi-branching
Pulcherima
10 Dianella Tasman flax lilly 0.2 0.2 200 Bushy, multi-branching
Tasmanica
11 Clerodendrum Glory bower 0.3 0.3 300 Bushy, multi-branching
Inerme
12 Euphorbia milii Euphorbia red 0.2 0.2 200 Bushy, multi-branching
13 Ficus Longisland Ficus Longisland 0.4 0.2 200 Bushy, multi-branching
14 Ficus Panda Ficus Panda 0.6 0.3 300 Bushy, multi-branching
15 Galphimia Glauca Gloden Shower 0.4 0.4 400 Bushy, multi-branching
16 Hamelia Patens Firebush 0.4 0.3 300 Bushy, multi-branching
17 Hymenocallis Spiderlily 0.3 0.3 300 Min 6 Leaves, bushy
Speciosa
18 Maurraya Murraya 0.5 0.4 500 Bushy, multi-branching
Paniculata
19 Nephrolepsis Sword fern 0.3 0.2 200 Bushy, multi-branching
Exaltata
20 nerium Oleander Nerium pink 0.75 0.5 500 Bushy, multi-branching
21 nerium Oleander Nerium Dwarf 0.5 0.3 300 Bushy, multi-branching
(petite pink) pink
22 Nerium Oleander Nerium Dwarf 0.5 0.3 300 Bushy, multi-branching
(white sands) white
Specification at
the time of
Procurement &
S. Installation
Botanical Name Common Name Remarks
(c/c in mm)
No
Spacing
Spread
Overall
Height
(m)
23 Ophiopogon Black mondo 0.2 0.2 200 Bushy, multi-branching
jaburan grass
24 Plumbago Blue Plumbago 0.3 0.2 450 Bushy, multi-branching
capensis
25 pennisetum Fountain Grass 0.3 0.2 300 Bushy, multi-branching
setaceum
26 pennisetum Red fountain 0.3 0.2 300 Bushy, multi-branching
setaceum (rubrum) grass
27 raphis excelsa Broadleaf lady 0.75 0.6 600 min 6 shoots, bushy
palm
28 Russelia Russelia 0.4 0.6 300 Bushy, multi-branching
Equisetiformis
29 Schefflera Schefflera green 0.5 0.3 300 Bushy, multi-branching
arboricola
30 Schefflera Variegated 0.5 0.3 300 Bushy, multi-branching
arboricola var. schefflera
31 Sanseviera mother in law 0.6 0.2 200 Min 6 Leaves
trifasciata tongue
32 Syngonium syngonium 0.3 0.2 200 Bushy, multi-branching
podophyllum
33 Turnera ulmifolia yellow alder 0.3 0.3 200 Bushy, multi-branching
34 Tacomaria cape honeysuckle 0.4 0.3 200 Bushy, multi-branching
capensis
35 Tabernaemontana veriegated 0.4 0.3 300 Bushy, multi-branching
coronaria chandni
36 Tecoma gaudichaudi 0.6 0.3 500 Bushy, multi-branching
Gaudichaudi
37 Thunbergia erecta bush clockvine 0.4 0.3 300 Bushy, multi-branching
38 Wedelia Trilobata Wedelia 0.1 0.2 150 Bushy, multi-branching
2.7 Transportation
The roads account for 26.34% of the site area with Sector roads accommodating
14.20% and Internal roads taking up 15.89% of the site area. Vehicular (motorised
and non-motorised) traffic for this site comprises mostly of cars, buses, trucks
and cyclists.
The generic road classification is based on its width and function and is classified as
Arterial (80m), Collector (60m), Distributor (30-45m), Local Road (18-30m), Access
Road (<15m) and Greenway (6-10m).
The traffic is fed in to the site from 80m sector road to the North and 60m sector road
to the West respectively, and channelled through the 60m Central Spine further
feeding to 30 and 45m
2.7.1 Roadway Cross-Sections
All the 60m ROW roads proposed as part of Layout Plan will consist of six-lane
divided sections in addition to service lanes and BRT lanes. Similarly, all 45m ROW
roads will also consist of six-lane divided sections. According to recent studies
published by the Institute of Urban Transport (India), the capacity of six-lane roads is
approximately 2,230 PCU per lane per hour, or approximately 6,700 PCUs per
direction per hour. Capacity indicates the maximum traffic volumes that can be
served by a road and represents congested conditions. Therefore, roads are
designed for desirable service volumes (design hour volume). IRC 106:1990
recommends that six-lane divided arterials can comfortably accommodate
approximately 5,400 PCUs per hour. However, IRC 106:1990 also recommends that
the design hour volumes should be approximately 70% of the road's capacity.
Therefore, a range of 5,400 PCUs/hour to 9,400 PCUs/ hour was used to determine
roadway cross-sections for the proposed roads. Graphical illustrations of roadway
cross-sections are shown in Figure 3-15 through Figure 3-20. Based on preliminary
analysis, the proposed roads will be able to accommodate the expected traffic
demand.
2.7.2 Parking Guidelines
The Regulations states for various means of Parking Provision such as:
2.7.2.1 Multi-Level Mechanised Parking
Multi-level parking should be developed in the designated parking spaces/plots.
Multi-level facilities shall be allowed in all type of plots along with mechanised
parking.
2.7.2.2 Basement Parking
In plots larger than 12,000 sq m, the basement shall be allowed upto minimum
setback of 6m. There will be no restriction on the number of levels of basements
subject to mechanical ventilation as per provision in National building Code – 2005,
water proofing and structural safety. Evergreen trees shall have to be planted in
setback as per landscaping norms of the regulation.
Height of first basement above ground will be 1.5mts below the roof slab. Where stilt
or podium parking is permitted, the first basement roof will be levelled with the
ground and the roof slab of the extended basement up to envelop line shall be
designed for the fire tender load.
The height of the basements from floor to ceiling shall be maximum up to 4.5 metres.
The ramp within setbacks shall be permissible subject to free and convenient
movement of fire tenders.
Adequate fire safety, light, ventilation and air change through mechanical means
shall be provided as per provisions in NBC 2005.
The basements may be used only for parking, services like fire rooms and storage of
non hazardous materials.
Figure 2-17: 30m ROW Roadway Cross-Section (SCR-1 between sector road and central spine)
Note: These Parking requirements are calculated considering the futuristic view –
where maximum population is envisaged to work and live within the township – so
that the design proposal are sustainable for the population, in the event, where there
will be more demand. Thus, these parking demands are based on articulated FAR,
which are purely subject to the necessary approval by the authority.