M&B Switchgear PVT LTD: Survey No. 211/1, Opp. Sector C & Metalman, Industrial Area, Sanwer Road, Indore
M&B Switchgear PVT LTD: Survey No. 211/1, Opp. Sector C & Metalman, Industrial Area, Sanwer Road, Indore
REF:-i) Your Online Offer No. MBL/13-14/131113 and subsequent letters last letter being
dated 04/07/2014.
Dear Sirs,
Your above referred offer is accepted for supply of the following transformers on the terms and
conditions mentioned below:
1.SCOPE OF SUPPLY :- Supply of transformers (Details Tech. Specs. as per enclosed Annexure-A):-
2. Total Order Value: Rs. 1071073.52 (Rupees Ten Lakhs Seventy One Thousand Seventy
Three & Paise Fifty Two only including all taxes & duties on F.O.R. Destination basis..
3. Prices: The above rates are firm throughout delivery and on F.O.R. Destination basis.
4. Excise Duty: Excise Duty will be payable at actuals against documentary proof. Current rate
applicable is 12.36% as indicated above. Necessary Excise Duty Papers will be submitted by the
supplier for availing CENVAT credit by Paying Authority, if applicable.
JVAT will be payable at actuals. Current concessional rate is 5% as indicated above. Declaration
form ‘C’ shall be issued by the Consignee, while making arrangement for payment of ordered
materials
(iii) Any increase in taxes and duties beyond the stipulated delivery period will be to your account.
No. 098081221415-129(1 MVA & Above) Dated: 11/08/2014
5. JVAT: Extra as applicable i.e. 5%. However, CCL will avail Input Tax Credit as applicable..
(NB: Any increase in taxes and duties beyond the stipulated delivery period will be to your
account).
6. Freight & Insurance : Freight & Insurance Charges: Freight & Insurance Charges including
service tax is payable Extra as indicated above against documentary evidence. However,
CCL will avail ‘CENVAT’ Credit as applicable.
7. Delivery Period: Within 04-05 months from the date of placement of supply order. An early
supply is acceptable.
8. Payment Term :
(a) 80%value of each equipment and the accessories and 100% Excise duty and full concessional
ST/CST along with 100% transportation & Insurance charges will be paid within 21 days after delivery
of the equipment and receipt and acceptance of performance bank guarantee. The equipment should
be accompanied with relevant dispatch documents like Challan, Maker’s Test Cum Inspection
Certificate Warranty Certificate, Pre dispatch inspection certificate wherever applicable etc.
(b) Balance 20% payment shall be made after successful completion of erection testing, commissioning
and final acceptance of the equipment (along with accessories) at site upon presentation of a
certificate from the project Officer the effect that the equipment has been erected and commissioned to
their entire satisfaction or within 90 days of receipt of material whichever is earlier.
NO OTHER PAYMENT TERMS WILL BE ACCEPTED.
No payment will be made for supply of incomplete equipment.
Payments will be made through e-payment system only. Authorisation for all payments through electronic
fund transfer system/RTGS/CBS/Intra Bank Transfer is to be furnished by the bidder in the prescribed format
enclosed as Annexure-“F”.
9. Security Deposit: You will have to furnish Security Deposit in the form of Demand Draft or Bank
Guarantee of any scheduled bank within 15 days of receipt of this order to the extent of 10% of
supply order value(landed value) i.e. Rs.1,07,108.00. In case you fail to deposit the security money,
the order shall be cancelled and the case shall be processed to order elsewhere and the firm’s
performance will be kept recorded for future dealings. Security Deposit money will be refunded within
30 days of satisfactory execution of the contract. For release of Security Deposit you are to submit a
written request immediately on completion of the order confirming that the order has been
completed as per terms & conditions of the supply order.
10. CONSIGNEE :- The Depot Officer, Central Stores, Barkakana, CCL, At & PO – NTS Barkakana,
Dist: Ramgarh, Jharkhand.
11. PAYING AUTHORITY: AFM (CWS/CS), BARKAKANA, CCL..
12. Inspection:
A) Pre-dispatch inspection will be carried out by M/s CMPDIL, as per their methodology. In brief the
scope and conditions of the inspection will be as follows:
i) Inspection fee @ 1.1236% of total value of stores offered, including taxes and duties, is to
be paid to CMPDIL along with inspection call letter, payable at Ranchi. Minimum 15 days
clear notice shall be given to M/s CMPDIL for arranging inspection within valid delivery
period as per contract.
ii) Checking and approval of test procedures/quality assurance plans.
iii) Verification of records and documentation of vendor works inspection.
iv) Verification of documents and test certificate of bought out items and cross checks.
v) Provide the facilities for carrying out all tests as required in specification of vendors works,
else these will be carried out at independent test house if considered so necessary by
CMPDIL at vendor cost.
vi) Final testing and checking as per specifications.
B) Final inspection shall be carried out by the Chief General Manager (E&M), CCL, Ranchi or his
authorized representative on receipt of materials at the consignee’s end. Notice for inspection shall be
given by the consignee immediately on receipt of materials.
13. Mode of Dispatch: By road transport on freight paid basis duly insured. You will be fully responsible
for safe arrival of the consignment up to destination of the consignee. It is incumbent on the supplier to
transport the contracted materials/supplies through the registered common carrier only and
documentation should be done as per provisions of the carriage by Road act,2007. Any transportation of
goods through unregistered common carrier is illegal.
No. 098081221415-129(1 MVA & Above) Dated: 11/08/2014
14. SUBMISSION OF BILLS :- For claiming payment, bills / Excise-Cum-Tax Invoice (wherever
applicable) in triplicate should be submitted to the Paying Authority for arranging payment
except in case of direct import by CCL. The following documents/certificate should also be
submitted to the paying authority along will the Bill / Excise-Cum-Tax invoice:
CENVAT credit on admissible inputs and capital goods will be availed by CCL, for
which Pre-receipted and stamped Excise cum Tax Invoice showing the amount of
excise duty, education cess and secondary & higher education cess at applicable rates
separately is required to be submitted. The Excise cum Tax Invoice must contain all the
following information as required under rule 11 of Central Excise Rule 2002:-
In case of indigenously manufactured goods, Marketing Outlets (when manufacturer does not
quote directly) who are NOT registered with Excise Department will have to submit Excise
invoice issued by the manufacturer wherein the name of CCL is mentioned as consignee, so that
CCL can avail CENVAT credit on admissible inputs and capital goods.
In case of goods of imported origin other than direct import by CCL, the Indian Agent /
Dealer should necessarily be registered with Excise Department.
In addition to the above the following documents are to be submitted as per terms of the
supply order to the consignee.
a. In case of indigenously manufactured goods.
i. One copy of the bill / Excise-Cum-Tax Invoice as the case may be.
ii Challan.
iii Packing list in original giving details of bill of materials.
iv Consignment note / RR/ PWB in original.
v Warranty / Guarantee certificate and fitment certificate (wherever applicable) in original.
vi Manfuacturers test certificate in original (wherever applicable) as per supply order
terms.
vii DGMS / BIS / Pre dispatch inspection certificates / any other document, if required
as per the contract.
viii Certficate from the auditor of the supplier certifying that excise duty has been paid as
per prevailing excise rule,and Refund / Credit, if any obtained shall be passed on to
the buyer (wherever excise duty is applicable).
No. 098081221415-129(1 MVA & Above) Dated: 11/08/2014
(c) To cancel the supply order or a portion thereof, and if so desired to purchase the stores at
the risk and cost of the defaulting supplier and also.
(d) To extend the period of delivery with or without penalty as may be considered fit and proper,
the penalty, if imposed shall not be more than the agreed Liquidated Damages referred to in
clause (a) above.
(e) To forfeit the security deposit full or in part.
(f) Whenever under this contract a sum of money is recoverable from and payable by the
supplier, Central Coalfields Ltd. shall be entitled to recover such sum by appropriating, in
part or in whole, by deducting any sum or which at any time thereafter may become due to
the successful tenderer in this or any other contract. Should this sum be not sufficient to
cover the full amount recoverable, the successful tenderer shall pay Central Coalfields
Limited on demand the remaining balance? The supplier shall not be entitled to any gain on
any such purchase.
Enclosure:
1.Terms & conditions ‐ Annexure 'IV'.
2.Detailed Technical Specification ‐ Annexure ‘A’.
3.Format of Security Deposit & PBG.
4.Copy of filled application form for JVAT504G(2‐Page‐sample copies enclosed) ‐ Annexure’C’
(Anil Kumar) (A.K Thakur)
Sr. Manager(Pur) GM(Pur.)
Copy forwarded to : -
1. The General Manager (E&M),CCL, Ranchi.
2. The General Manager (MM)/(S&IC/Ancil.),CCL,Ranchi.
5. The DGM,Central Stores,CCL,Barkakana
6. The Area Finance Manager (CWS/CS),CCL,Barkakana
7. The Manger(System) (MIS),CCL,Ranchi
8. The T.S to DT (P&P)/OPN,CCL,Ranchi.
9. Master file/Guard file/MIS Cell, Ranchi.
10. M/S. CMPDIL, Inspection wing, Gondwana Place, Kanke Road, Ranchi.
12. The Director,Commercial Audit/ CVO,CCL,Ranchi.
14. CGM(MM)/GM(MM)—
SECL,Bilaspur/WCL Nagpur/NCL,Singrauli/MCL,Sambalpur/ECL,Sanctoria
No. 098081221415-129(1 MVA & Above) Dated: 11/08/2014
Sl.
Description Qty. Ind. Regn. No. & date Project/ Area
No.
Transf. 7.5 MVA, 33KV /
1 02 098 dtd. 22.08.2013 KTW
6.6KV, 656/131.2Amp
Transf. 2.0 MVA,
2 01 098 dtd. 22.08.2013 SG Coll./KTA
11/3.3KV
02 098 dtd. 22.08.2013 Tarmi OCP/Dhori
Transf. 1.0
MVA,11KV/3.3/KV 01 098 dtd. 22.08.2013 Kedla U/g/HBZ
3.
Transf. 1.0 MVA, 11KV
01 198 dtd. 11.02.2013 CCL(HQ)
/415V