Job Safety Analysis New Revise
Job Safety Analysis New Revise
Job Safety Analysis New Revise
Revise
EQUIPMENT: Department: Date :
June / 01/2017 to July. /31/2018
Welding Machine, Grinding Machine,
Drilling Machine, Air Compressor &
Jack Hammer, Boom Truck, Dump Division/Unit :
Truck, Compactor, Concrete Vibrator, JSA#: 1
Rebar Cutter.
Description of Activity: Replace Return Sludge Pump G3 At north Building, STP, Al-Hasa. & Replace Scum Pump, G-5 At
North Building, STP, Al-Hasa.
Prepared by: Reviewed by: Approved by:(Unit Foreman)
Name: Georgy Abraham Name: Dharmaveer BV ID# :
ID# : 8175033. Date :05-22-2018 Date:
References: Saudi Aramco Hand book, Construction Safety Manual and Engineering standard.
Personal Protective Equipment: Safety shoes, Hard Hat, Gloves, Safety Glass, Dust Mask etc.
Location / Specific Hazards Classification Contractor’s Recommended Actions
No.
Area Identified. (A/B/C) (Proposed actions to the Specific Hazards Identified)
Obtain Work Permit.
ISOLATION Electric power source shall be isolated and
(Electrical & Lock-out/Tagged in accordance with the G.I
6.012.
Mechanical)
Apply lock-out and Tag out procedure as
per the GI 6.012 and to ensure that
equipment De-Energize, disconnect and
isolate from all power & utilities before
Electric shock perform work activities on any powered
Work equipment to prevent the accidental contact.
01 C/B
Site Only qualified/certified electrician shall
perform the work.
Wear all proper PPE as needed.
Provide insulated rubber floor mat.
Ensure the equipment/ tools are properly
grounded.
Provide fire extinguisher.
Appoint a fire watch.
Proper housekeeping should be done.
Wear all proper PPE like Hard Hat, Gloves,
safety Shoe etc. as needed.
Use proper and good condition/ good
Pinch points C quality tools, equipments and materials.
The involved employees should be trained &
certified.
Implement good housekeeping throughout the
work .
Slip, Trip & Do not throw the tools/ materials. Keep it in a
C
Fall proper place. Don’t let the materials
scattered.
Use proper PPEs like hard hat, hand gloves,
goggles, Safety Shoes etc.
DEMOLITION
Place and maintain warning labels nearby pinch
(Mechanical). point’s hazards.
Do not operate any hand tool equipment or
(Demolition of Existing
machinery without required guards or
piping and accessories) C shields.
Cover sharp edges or sharp point by cloth or
other safety materials. Capping and Maintain
Pinch points. the sharp edges or sharp points tools separately
Job site Before/After use.
02
area Do the house keeping though out the work and
segregate the materials.
Slip / Trip. Implement good housekeeping by sorting out /
segregating and arrange all materials properly.
C Install proper barricades and warning signs
around the material loading area.
Do not block the aisles.
C Use hearing protection like ear plug/ ear
muff.
Noise
Prepare a good work schedule and take
adequate rest.
DEMOLITION
(Civil). Use proper PPEs like dust mask etc.
Provide proper ventilation.
(Foundation repair C Provide proper ventilation.
works – Chipping) Pour/ Spray little water to avoid flying of
dust (Be careful any power cable is there).
Dust
Job site
03
area Use proper PPEs like hard hat, hand gloves,
goggles, Safety Shoes etc.
Place and maintain warning labels nearby pinch
point’s hazards.
Pinch points. C
Do not operate any hand tool equipment or
machinery without required guards or
shields.
Cover sharp edges or sharp point by cloth or
other safety materials. Capping and Maintain
the sharp edges or sharp points tools separately
Before/After use.
Do the house keeping though out the work and
segregate the materials.
Implement good housekeeping by sorting out /
segregating and arrange all materials properly.
Slip / Trip. C Install proper barricades and warning signs
around the material loading area.
Do not block the aisles.
Use hearing protection like ear plug/ ear
muff.
Noise C
Prepare a good work schedule and take
adequate rest.
Change the person alternately every 25
minutes.
Vibration C
Ensure the machine is well maintained to
avoid excessive vibration.
Use cable detectors (scan tools / equipments).
Use of manual / hand digging to expose the
underground utilities with the aid of Cable
Detector to locate the exact location of the
Damage of buried utilities.
underground C
Unnecessary personnel are prohibited from
utilities.
entering the work area.
A competent person on site whenever
employees are working.
Ensure proper communication.
Obtain Work Permit.
DEMOLITION
Only qualified/certified electrician /
(Electrical). technician shall perform the work.
(Demolition of Existing Providing safe suitable and good condition
electrical cables and electrical equipment, for example not using
conduits) leads and tools in damp or wet conditions unless
Job site they are specially designed for those conditions.
04 C
area Carrying out preventative maintenance on
electrical equipment and regular inspection
should be done prior to start work.
Electric shock Wear all proper PPE as needed.
Provide insulated rubber floor mat.
Power tools / Equipment are properly grounded.
Use GFCI extension code.
Make sure the work permit is ready and
OVERHEAD available at site.
LIFTING Conduct tool box talk prior to start the work.
EQUIPMENT. Only qualified / experienced technicians shall
perform the work.
Use proper PPEs.
Check all controls are functioning correctly
before proceeding the work.
Do not exceed safe working load.
Do a pre-job safety plan, and should have good
planning.
Recognize the areas coming in to contact with a
power source during operation.
Crane operator should be clearly notified of all
potential danger zones to avoid contact with
nearby or underground energized power lines
Equipment or while moving materials.
C/B
control failure. Operator should maintain a safe speed when
Electrical operating near power source.
Select qualified and trained Operators and
workers to do the work.
Check all electrical connections, cables and
switches / remotes is safe to work or not.
Job site
05 Housekeeping should be done throughout the
area.
work.
Qualified / trained operator should operate the
crane.
Operator should check the weight of a load and
capacity of crane.
Operator must be well trained and have a clear
understanding of load dynamics, lifting
Overloading and capacities at various configurations and the
C
Structural failure. conditions under which such lifting capacities
are valid.
Oftentimes operators mistakenly believe
they are able to rely on their instinct or
experience to determine whether a load is too
heavy. So follow the safety procedure to avoid
accidents / incidents
Secure the materials properly while lifting
otherwise the object can slip out, tip and
eventually crash to the ground below.
Inspect the equipment to avoid mechanical
Materials Falling. C
failure, it can also cause machinery to
malfunction unexpectedly and drop heavy load.
Employees working around overhead cranes
should always wear proper head, foot, hand
and eye protection.
The crane operator and any workers below
should be aware of his surroundings and viewer
walk under a lift.
Operator must always lower a load to the
ground before leaving the lift or during the idle
times.
Moving crane too quickly and jerking the hoist
when its bearing a heavy load can be hazardous
to the crane operator and workers nearby.
Changing or reversing direction should be done
slowly and carefully.
Reversing direction can cause heavy loads to
spill and swinging the load is very risky.
When mechanical problems do arise,
operators should use the lockout-tag out
procedure to prevent accidental startup or
movement of the crane until the problem has
been repaired.
Working area should be barricade and
provide warning signs.
Don’t let unauthorized people to enter the
working area.
Do the housekeeping throughout the work.
Ensure work area is clean and access and egress
Impact / allow room to avoid trapping and slipping
Crushing/ C situations.
Pinch point. Do not scattered the tools and materials, keep
it in a proper place or tool boxes.
Use proper PPEs.
NEW WORKS
(Civil)
(Foundation repair
works)
(Modification of
existing foundation - Use proper PPEs.
C Place and maintain warning labels nearby pinch
Concreting, Anchor
points hazards.
06
Job site bolt and grouting, Use proper and good condition/ good quality
area. tools, equipments and materials.
Painting / Coating)
Pinch points
Implement good housekeeping.
Slip, Trip & Use proper PPEs like Hand Gloves, Hard
Fall C Hats, Safety Glass.
Do not throw the tools/ materials. Keep it in a
proper place. Don’t let the materials scattered.
Provide proper ventilation.
Dust C Use proper dust mask.
Pour/ spray water to avoid flying of dust.
Conduct regular safety talk prior to start
work.
Only certified/ experienced welder to do the
work.
Wear PPE and appropriate clothing while
welding.
Where possible provide rubber insulating
matting.
Electrocution Check the electrical cords prior to use.
C
Avoid welding in wet areas or welding in wet or
damp clothing
Ensure equipment is regularly serviced,
tested and tagged.
Machine should be properly grounded.
Keep the fire extinguishers & fire hoses in
working condition.
Appoint trained fire watch as standby.
Fumes (During
the time of Provide proper ventilation and stand by man to
welding / cutting monitor the work.
C
works and other Use proper PPEs like mask, respiratory
related works) protection if needed.