Nghi Son 2 BOT Thermal Power Plant Project Preparation Schedule before Commencement TOA CORPORATION

Dredging Contract
ID Task Name Duration Start Finish
2019 2020
December January February March April May June July August September October November December January February March April May June July August September October November December
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W53 W54 W55 W56 W57 W58 W59 W60 W61 W62 W63 W64 W65 W66 W67 W68 W69 W70 W71 W72 W73 W74 W75 W76 W77 W78 W79 W80 W81 W82 W83 W84 W85 W86 W87 W88 W89 W90 W91 W92 W93 W94 W95 W96 W97 W98 W99 W100 W101 W102 W103 W104 W105 W106 W107 W108
1 Preapration 623 days 7/12/2018 11/12/2020

2 TOA preparation for kick-off meeting 22 days 7/12/2018 2/1/2019

3 Constractor permit 8 days 5/1/2019 15/1/2019

4 Kick-off meeting with DVN 3 days 2/1/2019 4/1/2019

5 Preapration for survey work 3 days 11/1/2019 15/1/2019

6 Site Pre-survey & proceesing data 7 days 15/1/2019 23/1/2019

7 Design works 14 days 23/1/2019 18/2/2019

8 Obtain Dumping permit 0 days 14/3/2019 14/3/2019 14/3

9 Obtain design approval (Vinamarine) 21 days 18/2/2019 14/3/2019

10 Temporary office construction (PMO) 27 days 11/2/2019 14/3/2019

11 Obtain Permit for PMO 15 days 11/2/2019 27/2/2019

12 Order, produre, delivery Oil Fence 15 days 25/2/2019 14/3/2019

13 Mob of Dredgers & hopper barges 7 days 26/2/2019 6/3/2019

14 Equipment work permit (PA) 7 days 6/3/2019 14/3/2019

15 Site Clrearance 27 days 14/12/2018 15/1/2019

16 Marine work safety plan (VMS-N & PA) 14 days 26/2/2019 14/3/2019

17 Installation of Oil Fence 15 days 14/3/2019 1/4/2019

18 Construction permit (DOC) 15 days 14/3/2019 1/4/2019

19 Commencement of dredging works 0 days 1/4/2019 1/4/2019 1/4

20 Main Dredging work 210 days 1/4/2019 30/11/2019

21 Berth front water area 78 days 1/4/2019 29/6/2019

22 Turning based 75 days 1/7/2019 25/9/2019

23 Remaining area 57 days 26/9/2019 30/11/2019

24 Secondary Dredging 78 days 1/9/2020 30/11/2020

25 Hand-over 10 days 1/12/2020 11/12/2020

26 Post-Survey work 7 days 1/12/2020 8/12/2020

27 Issue Marine Notice 2 days 9/12/2020 10/12/2020

28 Hand-over Certificate 1 day 11/12/2020 11/12/2020