Professional Documents
Culture Documents
Covered Court Estimate
Covered Court Estimate
ROOFING
M (1 side only)
M
M
M
M
M
M
8.5mx34mx2sides
1.9mx23mx2sides
DETAILED ESTIMATE
UNIT
ITEM NO. DESCRIPTION QTY UNIT MATERIAL COST
COST
I. GENERAL REQUIREMENTS
Engineer's
Professional 1 - 500 500
Fee
Reproduction
3 copies 520 1,560
of plans
Permits and
1 - 10,000 10,000
License
12mmØ RSB
deformed bar x 4 pcs 200 800
6m
10mmØ RSB
deformed bar x 16 pcs 150 2,400
6m
#16 GI Wire 3 kg 90 270
TOTAL COST FOR STEEL REBAR WORKS 7,670
V. OTHER WORKS
Painting with Red Oxide
Red Oxide 29 gal 150 4,350
Paint brush,
4 pcs 50 200
assorted sizes
1/2" thick
2 pcs 900 1,800
plywood
2"X2"X20' 23 pcs -
IX. EARTHWORKS
fencing and
1 lot 5,000 5,000
staking
ROOFING WORKS
C-purlins
198 sets 5,000 990,000
2x3x20
Fascia board
26 pcs 300 7,800
2x10x20
CONCRETE WORKS
COLUMN-FOOTING
Portland
23 bags 290 6,670
Cement
Fine Sand 2 cu.m 500 1,000
Gravel 3 cu.m 600 1,800
Paint brush,
4 pcs 50 200
assorted sizes
1/2" thick
2 pcs 900 1,800
plywood
2"X2"X20' 23 pcs 900 20,700
2"X3"X20' 71 pcs 900 63,900
4" nails 2 kgs 90 180
3" nails 1 kgs 90 90
2 " nails 1 kgs 80 80
1" nails 1 kgs 70 70
CONCRETE WORKS
COLUMN-FOOTING
Portland
23 bags 290 6,670
Cement
Fine Sand 1.5 cu.m 450 675
Gravel 3 cu.m 500 1,500
12mmØ RSB
deformed bar x 4 pcs 220 880
6m
10mmØ RSB
deformed bar x 16 pcs 150 2,400
6m
#16 GI Wire 2 kg 90 180
1/2" thick
2 pcs 900 1,800
plywood
2"X2"X20' 15 pcs 240 3,600
2"X3"X20' 15 pcs 350 5,250
4" nails 2 kgs 90 180
3" nails 1 kgs 90 90
2 " nails 1 kgs 80 80
1" nails 1 kgs 70 70
IX. EARTHWORKS
X ROOFING WORKS
C-purlins 2x3x20 243 pcs 400 97,200
Fascia board
35 pcs 500 17,500
2x10x20
Angle Bars (beam) 52 pcs 600 31,200
Angle Bars (trusses) 94 pcs 600 56,400
Gutter 50,000
Ridge Roll 50,000
GI sheets 200,000
PIPES
3"(75mm) Pipe 48 pcs 380 18,240
3"Elbow 32 pcs 60 1,920
TOTAL COST FOR ROOFING WORKS 522,460
I. GENERAL REQUIREMENTS
Engineer's and
AutoCADD -
Professional Fee
Perspective sheets
Plans sheets
Reproduction of
copies
plans
Ground breaking -
Permits and License -
TOTAL COST FOR GENERAL REQUIREMENTS
II. CONCRETE WORKS
COLUMN-FOOTING
Portland Cement bags
Crushed sand cu.m
Gravel cu.m
TOTAL COST FOR CONCRETE WORKS
STEEL REBAR WORKS
III. COLUMN-FOOTING
16mmØ RSB
pcs
deformed bar x 6m
12mmØ RSB
pcs
deformed bar x 6m
10mmØ RSB
pcs
deformed bar x 6m
#16 GI Wire kg
TOTAL COST FOR STEEL REBAR WORKS
V. OTHER WORKS AND TOOLS
Finishing Works
Cement bags
Fine Sand cu.m
Painting with Red Oxide
Red Oxide gal
Paint brush, assorted
pcs
sizes
Welding
Welding Rod boxes
Speed cutter pc
Cutting disc pcs
TOTAL COST FOR OTHER WORKS
VIII FORMWORKS & SCAFFOLDINGS
Forms and Staging
1/2" thick plywood pcs
2"X2"X20' pcs
2"X3"X20' pcs
4" nails kgs
3" nails kgs
2 " nails kgs
1" nails kgs
TOTAL COST FOR FORMWORS AND SCAFFOLDING
IX. EARTHWORKS
Demolition -
Excavation cu.m.
X ROOFING WORKS
C-purlins 2x3x20 pcs
Fascia board
pcs
2x10x20
Angle Bars pcs
Gutter
Ridge Roll
GI sheets
PIPES
3"(75mm) Pipe pcs
3"Elbow pcs
TOTAL COST FOR ROOFING WORKS
TOTAL COST FOR MATERIALS
LABOR COST AT 45% OF TOTAL COST FOR
MATERIALS
COVERED COURT TOTAL (LABOR COST+MATERIAL
COST)