Inspection Data 14032018

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 9

No.

Item No QTY PO 2
(Binder Suffix No.)

1 SS51-300-15-20-150 2

2 SS51-300-15-30-100 3

3 SS51-300-15-30-130 1

4 SS51-300-15-30-150 1

5 SS51-300-15-30-155 2

6 SS51-300-15-30-170 1

7 SS51-300-20-20-150 1

8 SS51-300-20-30-150 3

9 SS51-200-25-20-150 2

10 SS51-200-25-20-150 2

11 SS51-300-25-30-150 4

12 SS51-200-40-20-150 1

13 SS51-300-40-20-150 20

14 SS51-450-40-20-150 1

15 SS51-200-40-30-150 1

16 SS51-300-40-30-150 6

17 SS51-300-40-40-150 14

18 SS51-300-50-20-116 1

19 SS51-300-50-20-150 4

20 SS51-200-50-30-150 6

21 SS51-300-50-30-130 1

22 SS51-300-50-30-150 34

23 SS51-450-50-30-150 2

24 SS51-750-50-30-150 1

25 SS51-300-80-30-100 2
26 SS51-300-80-30-150 11

27 SS51-400-80-30-150 4

28 SS51-450-80-30-150 3

29 SS51-750-80-30-150 2

30 SS51-200-150-30-120 1

31 SS51-300-150-30-110 1

32 SS51-300-150-30-128 8

33 SS51-300-150-30-150 1

34 SS51-200-150-40-150 1

35 SS51-200-200-40-150 3

36 SS51-450-200-40-150 1

37 SS51-200-80-30-150 5

38 SS51-200-80-30-180 1

39 SS51-300-100-30-130 1

40 SS51-300-100-30-133 1

41 SS51-300-100-30-150 9

42 SS51-200-100-40-150 4

43 SS51-300-100-40-213 1

44 SS52-300-250-30-150 1

45 SS51-300-150-30-S-200 1

1cch SS51-300-50-40-150 57

2cch SS51-300-80-40-150 51

3cch SS51-300-100-40-150 27

4cch SS51-300-150-40-150 18

5cch SS51-300-150-40-190 2
6cch SS51-300-200-40-150 13

344
Quantity Balance not yet
Quantity Submit
Item Desscription to Inspection Inspected Inspect
(Check QTY) (check QTY)

Clamped PUF Shoe (Shoe Length300, Pipe Size 15, Insulation Thickness20mm ) 2 0 2

Clamped PUF Shoe (Shoe Length300, Pipe Size 15, Insulation Thickness30mm ) 3 2 1

Clamped PUF Shoe (Shoe Length300, Pipe Size 15, Insulation Thickness30mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 15, Insulation Thickness30mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 15, Insulation Thickness30mm ) 2 1 1

Clamped PUF Shoe (Shoe Length300, Pipe Size 15, Insulation Thickness30mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 20, Insulation Thickness20mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 20, Insulation Thickness30mm ) 3 0 3

Clamped PUF Shoe (Shoe Length200, Pipe Size 25, Insulation Thickness20mm ) 2 1 1

Clamped PUF Shoe (Shoe Length200, Pipe Size 25, Insulation Thickness20mm ) 1 0 1

Clamped PUF Shoe (Shoe Length300, Pipe Size 25, Insulation Thickness30mm ) 4 0 4

Clamped PUF Shoe (Shoe Length200, Pipe Size 40, Insulation Thickness20mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 40, Insulation Thickness20mm ) 20 12 8

Clamped PUF Shoe (Shoe Length450, Pipe Size 40, Insulation Thickness20mm ) 1 1 0

Clamped PUF Shoe (Shoe Length200, Pipe Size 40, Insulation Thickness30mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 40, Insulation Thickness30mm ) 6 2 4

Clamped PUF Shoe (Shoe Length300, Pipe Size 40, Insulation Thickness40mm ) 14 12 2

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN50, Insulation Thickness 20mm) 1 0 1

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN50, Insulation Thickness 20mm) 4 2 2

Clamped PUF Shoe (Shoe Length200, Pipe Size 50, Insulation Thickness30mm ) 6 4 2

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN50, Insulation Thickness 30mm) 1 0 1

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN50, Insulation Thickness 30mm) 34 21 13

Clamped PUF Shoe (Shoe Length450, Pipe Size 50, Insulation Thickness30mm ) 2 0 2

Clamped PUF Shoe (Shoe Length750, Pipe Size 50, Insulation Thickness30mm ) 1 1 0

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN80, Insulation Thickness 30mm) 2 1 1
Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN80, Insulation Thickness 30mm) 11 1 10

Clamped PUF Shoe (Shoe Length400, Pipe Size 80, Insulation Thickness30mm ) 4 1 3

Clamped PUF Shoe (Shoe Length450, Pipe Size 80, Insulation Thickness30mm ) 3 3 0

Clamped PUF Shoe (Shoe Length750, Pipe Size 80, Insulation Thickness30mm ) 2 2 0

Clamped PUF Shoe (Shoe Length200, Pipe Size 150, Insulation Thickness30mm ) 1 0 1

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN150, Insulation Thickness 30mm ) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 150, Insulation Thickness30mm ) 8 2 6

Clamped PUF Shoe (Shoe Length300, Pipe Size 150, Insulation Thickness30mm ) 1 0 1

Clamped PUF Shoe (Shoe Length200, Pipe Size 150, Insulation Thickness40mm ) 1 0 1

Clamped PUF Shoe (Shoe Length200, Pipe Size 200, Insulation Thickness40mm ) 3 3 0

Clamped PUF Shoe (Shoe Length450, Pipe Size 200, Insulation Thickness40mm ) 1 0 1

Clamped PUF Shoe (Shoe Length200, Pipe Size 80, Insulation Thickness30mm ) 5 5 0

Clamped PUF Shoe (Shoe Length200, Pipe Size 80, Insulation Thickness30mm ) 1 0 1

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN100, Insulation Thickness 30mm) 1 1 0

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN100, Insulation Thickness 30mm) 1 1 0

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN100, Insulation Thickness 30mm) 9 1 8

Clamped PUF Shoe (Shoe Length200, Pipe Size 100, Insulation Thickness40mm ) 4 3 1

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN100, Insulation Thickness 40mm) 1 1 0

Clamped PUF Shoe (Shoe Length300, Pipe Size 250, Insulation Thickness30mm ) 1 0 1

Refer to Attachment REQUISITION FOR COLD SUPPORT


RAPID-P006A-SCS-PIP-MRI-3200-0036_1 1 1 0

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN50, Insulation Thickness 40mm) 26 0 26

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN80, Insulation Thickness 40mm) 7 2 5

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN100, Insulation Thickness 40mm) 12 6 6

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN150, Insulation Thickness 40mm) 2 0 2

Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN150, Insulation Thickness 40mm) 1 0 1
Clamped PUF Shoe (Shoe Length 300mm, Pipe Size DN200, Insulation Thickness 40mm) 2 0 2

225 100 125


Kind Of Inspection Result Remark

Final Inspection Accepted


& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection
& Dimensional Accepted

Final Inspection Accepted


& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional

Final Inspection Repair due to Mechanial


damage on Clamp Shoe,
& Dimensional need to be grind flush

Final Inspection Accepted


& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection Repair due to Pin
& Dimensional Hole
Final Inspection Accepted
& Dimensional
Final Inspection Repair due to Pin
& Dimensional Hole
Final Inspection Accepted
& Dimensional
Final Inspection Accepted
& Dimensional
Final Inspection 32 of 58
Accepted (Previous Inspection,
& Dimensional 02 March 2018)

Final Inspection 45 of 52
Accepted (Previous Inspection,
& Dimensional 02 March 2018)

Final Inspection 15
Accepted (Previous Inspection,
& Dimensional 02 March 2018)

Final Inspection 16
Accepted (Previous Inspection,
& Dimensional 02 March 2018)

Final Inspection 1
Accepted (Previous Inspection,
& Dimensional 02 March 2018)
Final Inspection 11
Accepted (Previous Inspection,
& Dimensional 02 March 2018)