Professional Documents
Culture Documents
Running Head: Project Management Planning 1
Running Head: Project Management Planning 1
$500,000. The constriction of the building is governed by a contract the client signed with the
county building constriction authority. For the project to be initiated, the first thing is the
approval from the county. During planning (initial phase of project management) construction
activities were allocated time and resources and hence the resultant estimated time was 2 years.
During the initial time of execution of activities, a concern on an increase in cost by 10% arises
due to delay of the project by 3 months. The purpose of this report is, therefore, an explanation of
the delays in the project and the increased constriction cost. It also gives an outline of how the
development team is going to control the cost and schedule the project to achieve the
the delay in the processing of permits from the county authority. During the planning and
allocation of time and resource, we allocate three months for approval of construction permits.
This, later on, proved to us that we allocated a small time for this activity. It is very difficult to
understand the process of other authorities and thus one may not accurately estimate the time in
which the third party in a business sense will take to consider the request. In our case, we didn’t
have enough capacity to dig deeper to understand the time in which the construction authority
will take to process the permit. Having allocated three months to this activity, we had to wait for
another three months for them to approve. We went further to ask the authority for the reason for
such delay and we found that the answer was on the question of the land. There were some
processes that needed to be done to ascertain on whether the land is fit for construction. Such
PROJECT MANAGEMENT PLANNING 3
activities associating with the issue of land includes nearness to the public road, stability of the
basement of the land, verifiable ownership of the land. The critical issues issue in this particular
case was on the public road, where the land was seemingly to be very near to the road.
The second factor is on increased overhead costs and this best explains the reason why
the cost has a shoot from $500,000 to $600,000. From fundamental principles of project
management, an increase in time attracts other expenses (Larson & Gray, 2017). One factor that
leads to deviation in cost is subscription. Tools that will be used in construction were hired and
the lending organizations charge for the use of their tools on a monthly basis. The delay of
construction for three months implies an increase in monthly subscriptions from the lending
organizations hence attracts an increase of the overall cost by 10%. In addition to these, the
construction is under security provided by two security companies. We must submit security fee
on monthly basis to the providers and this means that an elongation of the project management
period by three months will require us to pay an extra subscription security fee on the same. Yet
another influential factor is on salaries and allowances payable to the labor (human resource).
We had already employed workers for the execution of project activities and are to be paid
monthly. Then if we attempt to account for the delay of the project, we are an oath to pay for
salaries and allowances for three months and this increase the cost of the project.
Steps on how Management Team is going to Control the Costs and Schedules
Having delayed project for three months, it is important to control its management in
order to achieve the cost and time of the initial plan. This needs to be done for two reasons: (a) to
deliver the project to the client on time and (b) to cut short on the cost of running the project. Our
management team has identified the impacted activities including the supply of contraction
security/CCTV surveillance. The project team shall have to restructure execution activities in
PROJECT MANAGEMENT PLANNING 4
order to catch up on time. The activities that had been allocated more time will have to be
executed on minimal time to allow room for other activities. Other activities will be done
concurrently. The table below shows the tasks and resources allocated to them.
Reflection on My Learning
I have learned that planning is important to phase of project management, where all
activities are assigned resources and time. I have also learned that increasing duration of project
management results in increased overhead costs due to the constant rate of subscriptions that is
imposed project management process. It is important to allocate enough time resources to project
activities to account for contingencies and other risks that may occur (Kerzner, & Kerzner,
2017). In a situation where the project tends to go in the wrong direction, it is possible to
restructure the already planned activities in to maintain overall management time and costs.
These lessons have impacted my decision on reorganizing the project in order to fit into a cost
References
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
Hill Education.