Professional Documents
Culture Documents
Haytham Ibrahim's Assignment No.3 PDF
Haytham Ibrahim's Assignment No.3 PDF
Assignment no.3
Winter 2017: ECE666 Power Systems Operation
Assignment-3
Submission due: Monday 3rd April 2017, 4:30 PM
--------------------------------------------------------------------------------------------------------------------------------
Question-1: A 4-area inter-connected power system is shown below. A transaction of 1000 MW
takes place between two parties, injecting in area-1 and extracting in area-4. In each area, the
flows on the “limiting facilities”, arising from this transaction, are shown in the parenthesis.
10
00
M
W
Area-1 Area-3
80%
(5%) (14%)
20
90
% %
15
%
Area-2 Area-4
10%
(10%) (11%)
10
00
M
W
The available loading capacity (ALC) on each limiting facilities are given as under:
Facility ALC Facility ALC
Area-1 70 MW Tie 1-2 400 MW
Area-2 200 MW Tie 1-3 1200 MW
Area-3 130 MW Tie 2-3 250 MW
Area-4 175 MW Tie 2-4 200 MW
Tie 3-4 900 MW
a. Determine if the above transaction is feasible.
b. Otherwise determine the ATC for the interconnection, and which facility determines the
ATC value in this case.
Question-2:
Area-A Area-B
Consider a 2-area, 60 Hz system shown in the figure above. Area-A has a total load of 3500 MW
and a generation of 3000 MW, and a total spinning reserve of 700 MW. Area-B has a total load
of 6,000 MW, total generation of 6,500 MW and a total spinning reserve of 1000 MW. The
following parameters are given:
D1 = 1%, D2 = 1.5%, R1 = 6%, R2 = 5%, B1 = 120 MW/0.1Hz, B2 = 200 MW/0.1Hz.
Find the steady state frequency, generation and load in each area and tie-line power for the
following cases:
i. A sudden decrease of 100 MW load in Area-A when the system is only on primary regulation.
ii. Loss of 100 MW load in Area-A. The units carrying spinning reserve in each area are on AGC.
Page 1 of 2
Question-3: Consider the 3-area, 60 Hz system, shown below.
a. Find the scheduled interchange between the three areas.
b. There is a sudden load interruption of 500 MW in Area-1. All the three systems are on
primary regulation only. Find the operating condition of each area (tie line flows, steady-
state frequency, generation and load condition) after the disturbance.
Area-1 Area-2
Load = 5,000 MW Load = 9,600 MW
Generation = 5,700 MW Generation = 9,200 MW
Spinning Reserve = 500 MW Spinning Reserve = 600 MW
R = 5%, D = 1% R = 6%, D = 2%
Area-3
Load = 7,600 MW
Generation = 7,300 MW
Spinning Reserve = 400 MW
R = 6%, D = 1.5%
Question-4: A small power system has a total installed capacity of 1000 MW. Studies reveal that
when the system demand is 950 MW, the LOLP is 0.00048, for a demand of 850 MW the LOLP is
0.00037, and 0.00025 for a demand of 750 MW.
A 100 MW gas-turbine generator with FOR = 0.1 is to be commissioned in 2017. The
system peak demand in 2017 is expected to be 925 MW.
a. What will be the LOLP of the system in 2017 with the new generator commissioned?
b. If the peak demand is expected for 500 hours, during 2016, what does the value of LOLP
signify? (6)
Question-5: Utility-A has there generators Gen-1, Gen-2 and Gen-3 whose generating capacity
and forced outage rates (FOR) are given as under:
Determine the cumulative outage probability table and hence the LOLP using the convolution
algorithm for a load of (i) 700 MW (ii) 600 MW and (iii) 550 MW.
Page 2 of 2
Problem 1:
a. Using the data given we can construct the following table:
1
Problem 2:
i. System on primary regulation: First we calculate the load damping constant and governor
regulation as follows:
0.01 ∗ 3500 100
56.67 /
0.01 ∗ 60
0.015 ∗ 6000
150 /
0.01 ∗ 60
1 3000 700
1027.78 /
0.06 ∗ 60
1 6500 1000
2500 /
0.05 ∗ 60
So,
1 1
3734.44 /
Since the areas remain interconnected, they will have the same frequency as follows:
∆ 100
∆ 0.0268
3734.44
The steady state frequency is: ∆ .
∆ ∗∆ 1.517
∆ ∗∆ 4.0167
1
∆ ∗∆ 27.522
1
∆ ∗∆ 66.944
So,
. .
. .
. .
. .
And the tie line power is:
. from area‐B to area‐A.
2
ii. For the case when the units are on AGC:
Each area will be responsible for balancing its generation and demand (to maintain its area control
error ACE at zero) and will seek to minimize its effect on the other area. So, only the generation in
area‐A will change in response to the new demand. Hence,
The steady state frequency is:
And the tie line power flow is:
from area‐B to area‐A.
3
Problem 3:
First, we calculate the load damping constant and governor regulation as follows:
0.02 ∗ 9600
320 /
0.01 ∗ 60
0.015 ∗ 7600
190 /
0.01 ∗ 60
1 5700 500
2066.667 /
0.05 ∗ 60
1 9200 600
2722.222 /
0.06 ∗ 60
1 7300 400
2138.889 /
0.06 ∗ 60
So,
1 1 1
7512.778 /
a. The scheduled power flows are as follows:
Area‐A Area‐B
PGA = 5700 MW PAB = 400 MW PGB = 9200 MW
PDA = 5000 MW PDB = 9600 MW
PAC = 300 MW PBC = 0 MW
PGC = 7300 MW
Area‐C
PDC = 7600 MW
4
b. The scheduled power flows are as follows:
Since the areas remain interconnected, they will have the same frequency as follows:
∆ 500
∆ 0.0666
7512.778
The steady state frequency is: ∆ .
∆ ∗∆ 4.99
∆ ∗∆ 21.297
∆ ∗∆ 12.645
1
∆ ∗∆ 137.543
1
∆ ∗∆ 181.173
1
∆ ∗∆ 142.35
So,
. .
. .
. .
. .
. .
. .
And the tie lines power flows are:
Area‐A Area‐B
PGA = 5562.457 MW PAB = 602.47 MW PGB = 9018.827 MW
PDA = 4504.99 MW PDB = 9621.297 MW
PAC = 455 MW PBC = 0 MW
PGC = 7157.65 MW
Area‐C
PDC = 7612.645 MW
5
Problem 4:
a. From the data given we can construct the following cumulative outage probability table:
X MW or more on outage Probability
0 1
50 0.00048
150 0.00037
250 0.00025
Now, we can convolve the new unit to the old system using the following equation:
∗ 1 100 ∗
The new cumulative outage probability table is:
New GT convolved
X MW or more on outage Old system probability
, .
0 1 1 ∗ 0.9 1 ∗ 0.1 1
50 0.00048 0.00048 ∗ 0.9 1 ∗ 0.1 0.100432
150 0.00037 0.00037 ∗ 0.9 0.00048 ∗ 0.1 0.000381
250 0.00025 0.00025 ∗ 0.9 0.00037 ∗ 0.1 0.000262
The new system capacity is 1100 with a demand of 925 . So, from the new cumulative
outage probability table, for 175 or more on outage, we get that:
.
b. In 2016 (the old cumulative outage probability table), the peak demand is 950 at which
0.00048.
This means that if this peak demand persists for hours, then this load or part of it might
not be served for:
∗ . . hours . minutes
6
Problem 5:
We’ll use a step of 50 to construct the cumulative outage probability table using the following
equation (total capacity is 850 :
∗ 1 ∗
Where: is the capacity of the new unit to be convolved as follows:
7