101.
A wall is shown below. The area of formwork required to formt the cast-in-place concrete
walls for the structures is mostly nearly ( neglect overlapping at corners):
(A) 1620 SF
(B) 4410 SF
(C) 7200 SF
(D) 8820 SF
SOLUTION:
Determine area for each type of wall
For__Load__Bearing__Wall__
For__Non-Load__Bearing__Wall__
2
AWalls ANLB ALB 8820 ft