28 May 2019 11:27:26 - 101. Quantity Take-Off Methods.

sm

101.

A wall is shown below. The area of formwork required to formt the cast-in-place concrete
walls for the structures is mostly nearly ( neglect overlapping at corners):

(A) 1620 SF

(B) 4410 SF

(C) 7200 SF

(D) 8820 SF

SOLUTION:
Determine area for each type of wall

For__Load__Bearing__Wall__

Length of Load Bearing Wall: LLB 2 100 ft 80 ft

Height of Load Bearing Wall: HLB 10 ft

Area of Load Bearing Wall: 2


ALB 2 LLB HLB 7200 ft

For__Non-Load__Bearing__Wall__

Length of Non-Load Bearing Wall: LNLB 40 ft 50 ft

Height of Non-Load Bearing Wall: HNLB 9 ft

Area of Non-Load Bearing Wall: 2


ANLB 2 LNLB HNLB 1620 ft

Then, the total area to be covered by formworks;

2
AWalls ANLB ALB 8820 ft

Therefore, the answer is (D)