Professional Documents
Culture Documents
Grid Integration of Large-Capacity Renew
Grid Integration of Large-Capacity Renew
3
Table of contents
List of abbreviations 7
Section 1 Introduction 11
4
Table of contents
5
Table of contents
References 97
6
List of abbreviations
Technical and AC Alternating current
scientific terms AGC Automatic generation control
CA Contingency analysis
DC Direct current
DR Demand response
EV Electric vehicle
7
List of abbreviations
LA Lead acid
MTDC Multi-terminal DC
PV Photovoltaic
RE Renewable energy/ies
8
List of abbreviations
UC Unit commitment
V2G Vehicle-to-grid
WT Wind turbine
9
List of abbreviations
10
Section 1
Introduction
This report discusses the challenges of synthesizing This report, produced by the International
the development and operation of RE and EES Electrotechnical Commission (IEC) Market Strategy
resources with the planning and operation of Board (MSB), is the third in a series of MSB White
the rest of the power grid, including existing Papers which already includes:
generation resources, customer requirements and
1) Coping with the Energy Challenge (September
the transmission system itself. The generation of
2010), hereafter referred to as the “MSB EEE
electricity from RE sources includes technologies
Report”;
such as hydropower, wind power, solar power, tidal
and wave power, geothermal power, and power 2) Electrical Energy Storage (December 2011),
from renewable biomass. Wind and solar power hereafter referred to as the “MSB EES Report”.
are the focus of this report, for two reasons. First, The report’s primary goal is to provide a
they are among the renewable generation types – comprehensive, global view on the state of the art
wind, solar, and wave – that are subject to natural and future directions for grid integration of large-
variability in their energy sources. This variability capacity RE sources and the application of large-
creates distinct challenges for integration into the capacity energy storage for that purpose. It is
larger power system, namely nondispatchability. directed towards the IEC’s partners worldwide, as
Secondly, wind and solar are relatively mature for well as to its own Standardization Management
use in large capacities and in wide areas, and so Board (SMB) and Conformity Assessment Board
have a significant impact on the power grid that is (CAB), such that they may act to support grid
likely to increase over time. integration efforts around the world and provide
Integration of RE is a poly-nodal problem involving guidance to the electric utility industry and policy-
multiple decision-makers at a variety of spatial makers.
and temporal scales and widely varying degrees The report is divided into seven sections:
of coordination. These decision-makers include (1) Introduction; (2) RE generation: the present,
operators of RE and energy storage resources, the future and the integration challenges;
grid operators, energy market operators and (3) Present: state of the art in integrating large-
transmission planning bodies. As such, grid capacity RE; (4) Future: technical solutions
integration is not performed by any one entity in for integrating more large-capacity RE;
the power system, but instead involves the actions (5) Application of large-capacity EES to support
of a variety of entities, some highly coordinated RE integration; (6) Standards for large-capacity
and others discrete. The burgeoning development RE integration; and (7) Conclusions and
of smart grids adds still more tools, options and recommendations. Sections 1 and 2 provide
players to the mix. Many of these actors engage background information about the report, the
with various technology standards, practices, state of RE generation, and the challenges of
procedures and policies for the operation of integrating RE sources into the grid. Section 3
individual generators, RE clusters, substations, describes the key practices and technologies
and the broader electrical energy system.
11
Introduction
12
Section 2
RE generation: the present, the future and
the integration challenges
In short: the challenge is ensuring energy availability feed-in tariffs (FiTs): guaranteed wholesale
and preserving the environment. The key elements prices for RE coupled with a requirement that
are the following: load-serving entities take renewable power
whenever it is available;
1) Stabilizing climate impact from fossil fuel use
tax credits: credits against taxable income for
2) Meeting the energy demand of a growing
generation or installation of RE;
population
the development of smart grids: advances in
3) Bringing electricity to the 1.6 B people without
the architecture, functionality and regulation
access
of electricity grids so as to enable higher
4) Ensuring stable and secure energy access for penetrations of RE; and
all nations
removal of long-standing fossil fuel subsidies.
5) Transporting electricity long distances from
We will discuss the major public policy drivers
where it is generated to where it is used. [msb10]
behind RE development in turn.
RE is implicated in all of these elements, and is
critical to transforming energy grids to meet the
environmental, economic and social challenges 2.1.1 Decarbonization
of the future. Globally, RE’s share of electricity The need to address global climate change,
generation will increase substantially over the next a worldwide environmental phenomenon that
two decades and beyond. Indeed, this is already will affect everyone on the planet, is the most
occurring: governmental action at the international, public driving force for RE deployment. The
national and subnational levels has created a Intergovernmental Panel on Climate Change
wide variety of laws and policies to promote RE (IPCC), the world’s leading authority on climate
development. These include: change science, states in its Synthesis Report
carbon taxes: taxation of greenhouse gas to the Fourth Assessment Report that “warming
emissions, so as to internalize the climate- of the climate system is unequivocal, as is now
disruption costs of fossil-fuel use; evident from observations of increases in global
13
RE generation: the present, the future and the integration challenges
14
RE generation: the present, the future and the integration challenges
0% 20 % 40 % 60 % 80 % 100 %
Figure 2-1 | Share of world electricity generation by fuel in IEA’s New Policies Scenario [weo11]
2.1.3 Expanding energy access accounts for nearly half of the total increase in
generation by 2035. Indeed, under this scenario,
Energy demand in developing countries is growing
a full third of global electricity generation will be
rapidly (see Figure 2-2). IEA’s New Policies
supplied by RE (including hydroelectricity) by 2035.
Scenario projects electricity demand in non-OECD
Figure 2-4 provides a breakdown of incremental
countries to increase at a compound average
renewables growth by technology. Note the large
annual growth rate (CAAGR) of 3.5 % to 2035.
increase in wind power.
Total non-OECD electricity demand nearly triples
from 8 000 TWh in 2009 to almost 20 000 TWh by While a world where a majority of electricity
2035 (see Figure 2-3). Asian electricity demand generation is based on renewable sources is far
grows the most rapidly, with a 4.2 % CAAGR in the beyond the horizon, it is clear that the confluence
same period. In addition to the needs outlined in of government policy, utility planning and global
the previous subsections for cleaner energy and demand growth has the potential to increase
more secure energy, the world simply needs more penetrations of RE substantially on electricity grids
energy as more people in the developing world worldwide. This shift in generation portfolios will
gain access to it. have profound effects on the operation of the
grid, which will in turn affect the operation of RE
As global energy demand increases, RE provides
resources themselves as well as the operation of
one means among many of adding energy assets
other resources and equipment connected to the
to the system alongside growth of other resources.
grid.
IEA’s New Policies Scenario projects a near tripling
of global use of RE, from 3 900 TWh in 2009 to
11 100 TWh in 2035, and growth in renewables
15
RE generation: the present, the future and the integration challenges
18 000
Mtoe
Other OECD
16 000
European Union
14 000
United States
12 000
Other non-OECD
10 000
Middle East
8 000
India
6 000
China
4 000
Inter-regional
(bunkers)
2 000
0
1990 2000 2010 2020 2030 2035
Figure 2-2 | World primary energy demand by region in IEA’s New Policies Scenario [weo11]
Figure 2-3 | Electricity demand by region in IEA's WEO 2011 Scenario (TWh) [weo11]
16
RE generation: the present, the future and the integration challenges
8 000 46 %
TWh
Other renewables
7 000 44 % Solar PV
5 000 40 % Hydro
Wind
4 000 38 %
Share of renewables
3 000 36 % in total increase in
generation (right axis)
2 000 34 %
1 000 32 %
0 30 %
2015 2020 2025 2030 2035
2.2 Present status of RE generation formally adopted and implemented [weo11]. The
and future projections New Policies Scenario is the central scenario for
IEA’s World Energy Outlook 2011, and assumes a
At 3 902 TWh, RE accounted for 19.46 % of
global CO2 price of 30 USD to 45 USD per tonne.
the world’s electricity generation in 2009.
Hydroelectricity, by far the largest contributor Figure 2-6 displays the projected growth of RE
among the renewables, accounted for over generation by region or country [weo11]. Notably,
83 % of that share. Biomass, wind and solar PV while the USA, OECD Europe, Latin America and
combined accounted for only 15 % of the global China have relatively similar numbers in 2009, the
RE contribution, or 2.9 % of world electricity growth rates are dramatically different. China’s
generation [weo11]. Thus, while RE as a whole growth substantially outpaces OECD Europe’s,
comprises a substantial portion of global electricity and OECD Europe’s growth substantially outpaces
generation, the proportion of RE that comes that of the USA and Latin America. Africa and
from variable sources such as wind and solar is the Middle East see relatively little growth in
still relatively limited. Consequently most power renewables. India exhibits an aggressive growth
system operators to date have had relatively small rate, but begins 2009 with smaller numbers than
amounts of variable generation to integrate. As we other regions, and so does not see the same
examine here, however, the situation may change degree of absolute growth as neighbouring China.
materially by 2035. It is important to note that charts in this subsection
The IEA projects that global electricity production referring to present RE capacities reflect the
from renewables (including hydroelectricity) will state of the market in 2009, which is the most
grow to 8 108 TWh by 2025, an over-100 % increase recent year for which present data is available
from 2009. By 2035, that figure rises to 11 100 from the IEA. However, RE capacity has already
TWh, as illustrated in Figure 2-5. These estimates expanded substantially since then, with some
are based on IEA’s New Policies Scenario, notable developments in 2010. We discuss these
which takes into account recently announced developments in the text when relevant.
commitments and plans, even if they are yet to be
17
RE generation: the present, the future and the integration challenges
11 100
12 000
9 540
10 000 8 108
8 000 6 712
TWh
5 394
6 000
3 902
4 000 2 317
2 000
0
1990 2009 2015 2020 2025 2030 2035
3 000 1990
TWh
2 000
2009
1 000
0 2015
US
Middle East
OECD
Japan
Russia
China
India
Africa
Latin
Brazil
2020
2025
2030
Country/Region 2035
Figures 2-5 and 2-6 | RE generation globally and by country/region to 2035 [weo11]
18
RE generation: the present, the future and the integration challenges
76
160 80
135
140 70
120 60
100 50
74
TWh
GW
80 40 35
26
60 30
40 27 20 11
18
20 3 2 2 1 10 2 0 0 1 1 1
0 0
0 0
US
Japan
Russia
China
India
Middle East
Africa
US
Latin America
Japan
Russia
China
India
Middle East
OECD Europe
Brazil
Africa
OECD Europe
Latin America
Brazil
Country/Region Country/Region
Figures 2-7 and 2-8 | Wind energy generation and capacity by country/region in 2009 [weo11]
2009
2030
2030
2035
2035
2020
2020
1990
2025
2025
2015
2015
Figures 2-9 and 2-10 | Global wind energy generation and capacity projections to 2035 [weo11]
small-capacity. With many wind-rich areas now These plans contribute substantially to Europe’s
thoroughly exploited, European wind developers regional estimate, particularly in the next decade.
are turning their attention to large-capacity
If we examine single countries rather than regions,
offshore wind farms with centralized integration
China is the world’s tour de force in wind power
to the power grid. By 2020, IEA projects wind
development. 26 GW of wind power supplied
capacity of 209 GW and 449 TWh of generation in
27 TWh of electricity in China in 2009, ranking it
Europe. By 2030, capacity reaches 289 GW and
third globally in wind capacity. A year later, China
generation reaches 675 TWh [weo11]. Germany
had jumped into first place with a total of 42 GW in
has set a target of 45.75 GW of wind capacity for
2010 [smp11] [weo11]. China is set to lead the world
2020 [ger10], and Spain a target of 38 GW [esp10].
in wind generation and wind capacity by 2035.
19
RE generation: the present, the future and the integration challenges
900
800
700 1990
600
TWh
500 2009
400
300 2015
200
100 2020
0
2025
US
OECD
Japan
Russia
China
India
Africa
Latin
Brazil
Middle East
2030
2035
Country/Region
The IEA predicts China will produce 388 TWh of producing 18 TWh of electricity, and to 15 GW by
electricity from wind in 2020, and the National 2030, producing 41 TWh of electricity [weo11].
Energy Administration (NEA) of China has set Though these numbers are dwarfed by those
a target of 150-180 GW of wind capacity by the from geographically larger regions such as China,
same date [sgc12], which matches IEA’s estimate OECD Europe and the USA, it is worth noting that
of China’s installed wind capacity of 180 GW. By the expected rate of increase of wind generation
2030, IEA projects that China will reach 280 GW and capacity on the Japanese grid is dramatic:
of wind capacity, just behind estimates for the generation is expected to grow by 650 % between
combined European countries [weo11]. 2009 and 2030 under the IEA's New Policies
Scenario.
US wind capacity stood at 35 GW in 2009,
generating 74 TWh of electricity [weo11]. Most of The figures above do not differentiate between
US wind capacity is concentrated in the states of onshore and offshore wind. However, the sorts
Texas, Iowa, California, Michigan and Washington, of integration challenges presented may differ
and is onshore [wpa12]. As a result of declining between onshore and offshore wind projects,
energy demand, an economic recession and a specifically with regard to the need for special
precipitous drop in North American natural gas transmission technologies for offshore plants. We
prices, the USA did not keep pace with Europe therefore briefly examine the offshore segment of
and China in 2010, installing only 5 GW to Europe’s the wind market, which at present exists almost
10 GW and China’s 16 GW. Still, the USA is entirely in Europe, with a few projects in China.
expected to remain a significant player in wind. Europe’s offshore wind capacity stood at 4 GW at
IEA projects that US wind generation will grow the end of 2011, with an additional 6 GW under
to 165 TWh by 2015, more than double its 2009 construction at the time and 17 GW consented to
value. By 2030, the capacity grows to 388 TWh by EU member states [ewe11]. The majority of these
from 151 GW [weo11]. projects are in the UK, Denmark and Germany, with
some projects in Belgium, the Netherlands and
Japan’s 2 GW of wind capacity produced 3 TWh
Sweden. The European Wind Energy Association
of electricity in 2009 [weo11]. IEA estimates
(EWEA), an industry association, projects that
Japanese wind capacity to grow to 7 GW by 2020,
Europe will have 40 GW of offshore wind by
20
RE generation: the present, the future and the integration challenges
2020 producing 148 TWh of energy, and 150 GW resource. This apparent discrepancy is explained
producing 562 TWh by 2030. While industry by highly favourable policy environments for solar
estimates must be taken with the proverbial grain PV in many European countries.
of salt, these numbers at least plausibly harmonize
Though solar PV capacity is many times smaller
with IEA’s OECD European wind (off- and onshore)
than wind capacity at present, it is expected to grow
projections of 209 GW by 2020 and 298 GW by
at a faster pace than wind over the next several
2030. EWEA itself identifies the availability of high
decades. The IEA projects solar PV generation of
voltage direct current transmission (HVDC) as a
230 TWh from 184 GW of capacity in 2020, an over
critical bottleneck for the development of offshore
1 000 % generation increase from 2009. By 2030,
wind in Europe.
those figures reach 551 TWh and 385 GW, more
than double the 2020 estimates. Figures 2-14 and
2-15 display IEA's projections for solar PV energy
2.2.2 Solar energy
production to 2035 [weo11].
Grid-relevant solar energy technologies can be
In the OECD Europe region, solar PV produced
divided into two types: PV and concentrated
14 TWh of electricity from 17 GW of solar PV
solar power (CSP). PV generates electricity
capacity in 2009 [weo11]. Favourable government
directly, converting sunlight to electricity through a
policies and pricing have led to higher penetrations,
semiconductor such as silicon. CSP technologies
particularly in Spain, Italy and Germany. In
produce electricity by reflecting and concentrating
Germany, the government has opted for a feed-
sunlight onto a fluid, which then heats and boils
in tariff, in which the utilities pay the owner of a
water, the steam from which then drives a turbine
solar PV system a set tariff for renewable power
that produces electricity. Presently, CSP has a
over a period of time [obo12]. Consequently, solar
lower contribution to RE production than solar PV.
PV provided 3 % of the total power in Germany in
We will discuss each market in turn, beginning with
2011 [eck11]. Germany led the world in PV capacity
the larger PV market.
in 2009 with 9 785 MW. Spain’s 2009 capacity
Solar PV generated 20 TWh of electricity from figure, at 3 386 MW, was lower but still substantial
22 GW of global capacity in 2009 (see Figures 2-12 in comparison to other countries [epa10]. Italy has
and 2-13) [weo11]. The OECD Europe region ramped up solar PV capacity dramatically since
far surpassed all other regions in both capacity then, reaching 12 750 MW and producing 10 TWh
and generation, despite its relatively weak solar of energy in 2011 [gse12].
16 18 17
14
14 16
12 14
12
10
TWh
10
GW
8
8
6 6
3 3
4 2 4 2
2 2
0 0
US OECD Japan US OECD Japan
Europe Europe
Country/Region Country/Region
Figures 2-12 and 2-13 | Solar PV energy generation and capacity in 2009 by country/region
[weo11]
21
RE generation: the present, the future and the integration challenges
800 741
700
600 551
500
TWh
369
400
300 230
200 126
100 20
0
0
1990 2009 2015 2020 2025 2030 2035
180
160
1990
140
120 2009
TWh
100
80 2015
60
2020
40
20 2025
0
US OECD Japan Russia China India Middle Africa Latin Brazil 2030
Europe East America
2035
Country/Region
Figures 2-14 and 2-15 | Energy generation from solar PV globally and by country/region [weo11]
IEA projects 90 TWh from 84 GW of OECD of capacity in 2030. [weo11] Note that the 2030
European capacity by 2020 and 139 TWh from estimate for US solar PV capacity is roughly a third
115 GW by 2030 [weo11]. Germany expects its solar of estimated US wind power capacity in the same
PV capacity to reach 52 GW by 2020 [ger10], and year.
Spain estimates 8.4 GW by the same year [esp10].
Japan generated 3 TWh of its electricity from
It is worth noting that Europe’s generation capacity
solar PV sources in 2009 from 3 GW of capacity
factors (the ratio of energy generated from a given
[weo11]. By 2010, Japan had increased its solar PV
unit of power) for solar PV are lower than those for
capacity to 3.6 GW. This increase is attributable
the USA. This disparity is explained by differences in
to a subsidy programme for residential PV system
the quality of the resource: the USA receives much
installations and another programme to purchase
more sunlight than Europe. Nevertheless, Europe’s
surplus PV power from small systems at double the
policy environment provides substantially more
retail electricity price [yam11]. IEA projects 18 TWh
support to solar power, particularly in Germany
of electricity from 17 GW of Japanese solar PV by
and Spain, than does the US policy environment,
2020, and 32 TWh from 28 GW by 2030 [weo11].
explaining the capacity estimate differences as
well as the ultimately higher generation estimates China did not produce any significant amounts
for Europe. of electricity from solar PV in 2009, but that is
changing rapidly, as it has become a manufacturing
US solar PV generated 2 TWh of electricity from
leader in the technology. IEA projects that China
2 GW of capacity in 2009 [weo11]. IEA estimates
will produce 29 TWh from 20 GW of solar PV by
US solar PV generation at 38 TWh from 25 GW
2020, and 89 TWh from 58 GW by 2030 [weo11].
of capacity in 2020 and 81 TWh from 50 GW
This places China behind the USA in solar PV
22
RE generation: the present, the future and the integration challenges
400
307
300
TWh
167
200
92
100 52
24
1 1
0
1990 2009 2015 2020 2025 2030 2035
generation in 2020, but ahead of it by 2030 will install 5 GW of CSP to produce 15.35 TWh by
[weo11]. China’s National Development and Reform 2020, more than IEA’s projection for all of Europe
Commission has set targets for China to achieve [esp10].
10 GW of solar capacity in 2015, and 50 GW of
IEA projections for US CSP closely track those for
solar capacity installed by 2020 [won11].
OECD Europe, with 14 TWh from 4 GW in 2020,
CSP’s market is much smaller than wind power and 30 TWh from 8 GW in 2030.
or solar PV, and it is less challenging to integrate
into the power system due to its thermal aspects,
which reduce variability in output. CSP produced 2.3 RE grid integration challenges
1 TWh of electricity in 2009 from a global capacity Wind and solar generation both experience
of 1 GW, located primarily in the USA, though intermittency, a combination of non-controllable
Spain has since taken the lead [weo11]. variability and partial unpredictability, and depend
CSP generation estimates are lower than those on resources that are location-dependent [per11].
for PV, but exhibit similar strength in growth rates. These three distinct aspects, explained below,
IEA projects 52 TWh of CSP-generated energy each create distinct challenges for generation
from 14 GW of capacity in 2020, and 167 TWh owners and grid operators in integrating wind and
from 45 GW in 2030. Figure 2-16 displays IEA’s solar generation.
projections for global CSP generation to 2035 Non-controllable variability: Wind and
[weo11]. solar output varies in a way that generation
Spain led the world in 2010 in CSP capacity at over operators cannot control, because wind
632 MW. Spanish CSP capacity grew by 400 MW speeds and available sunlight may vary from
in 2010 due to a Royal Decree from the Spanish moment to moment, affecting moment-to-
government that provided incentives for solar moment power output. This fluctuation in
energy. In 2011, it began construction on nearly power output results in the need for additional
1 GW of additional CSP capacity [rep11]. IEA energy to balance supply and demand on the
projects 14 TWh of electricity from 4 GW of grid on an instantaneous basis, as well as
CSP sources in OECD Europe by 2020. In 2030, ancillary services such as frequency regulation
that rises to 36 TWh from 10 GW. The Spanish and voltage support. Figure 2-17 provides
government, however, estimates that Spain alone a graphical example of hourly wind power
variability.
23
RE generation: the present, the future and the integration challenges
Figure 2-17 | Hourly wind power output on 29 different days in April 2005 at the Tehachapi
wind plant in California [haw06]
Partial unpredictability: The availability from the places where the power will ultimately
of wind and sunlight is partially unpredictable. be used. New transmission capacity is often
A wind turbine may only produce electricity required to connect wind and solar resources
when the wind is blowing, and solar PV to the rest of the grid. Transmission costs are
systems require the presence of sunlight in especially important for offshore wind resources,
order to operate. Figure 2-18 shows how and such lines often necessitate the use of
actual wind power can differ from forecasts, special technologies not found in land-based
even when multiple forecast scenarios are transmission lines. The global map in Figure 2-19
considered. Unpredictability can be managed displays the latest data on mean land-based
through improved weather and generation wind speeds around the world.
forecasting technologies, the maintenance of
Because the presence of wind and sunlight are
reserves that stand ready to provide additional
both temporally and spatially outside human
power when RE generation produces less
control, integrating wind and solar generation
energy than predicted, and the availability of
resources into the electricity grid involves
dispatchable load to “soak up” excess power
managing other controllable operations that may
when RE generation produces more energy
affect many other parts of the grid, including
than predicted.
conventional generation. These operations and
Location dependence: The best wind and activities occur along a multitude of time scales,
solar resources are based in specific locations from seconds to years, and include new dispatch
and, unlike coal, gas, oil or uranium, cannot strategies for rampable generation resources,
be transported to a generation site that is grid- load management, provision of ancillary services
optimal. Generation must be co-located with the for frequency and voltage control, expansion of
resource itself, and often these locations are far transmission capacity, utilization of energy storage
24
RE generation: the present, the future and the integration challenges
30000
25000
Wind power production [MW]
20000
15000
10000
5000
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 Forecast
31 33hour35[h]
Figure 2-18 | Example of a day-ahead forecast scenario tree for the wind power forecast for
the PJM region of the United States [mei10]
25
RE generation: the present, the future and the integration challenges
technologies, and linking of grid operator dispatch These reserves are used when another
planning with weather and resource forecasting generator on the system goes down or
[per11]. deactivates unexpectedly;
The essential insight to integration of variable non-spinning reserves: these generators serve
RE is that its variability imposes the need for the same function as spinning reserves, but
greater flexibility on the rest of the grid, from other have a slower response time;
(controllable) generators to transmission capacity
voltage support: generators used for reactive
to loads. Discussion of variable generation
power to raise voltage when necessary;
operation alone is insufficient to describe the full
impact of high penetrations of RE on power system black-start capacity: generators available to re-
operation. Thus this report explores RE integration start the power system in case of a cascading
from both a plant operator and a system operator black-out.
perspective, so as to identify the full range of Additionally, grid operators must track loads –
operations involved. demand for electricity on the consumption side of
the grid – and ensure that generation matches load
at all times. This load following function becomes
2.3.1 Non-controllable variability
particularly important at times of day when
Variability in the context of wind and solar demand for electricity increases substantially,
resources refers to the fact that their output is such as morning, a hot afternoon, or evening.
not constant. It is distinct from unpredictability, Load following may be provided through a class of
which we discuss in the following section. Even ancillary service or through a “fast energy market”,
if operators could predict the output of wind and depending on the system operator.
solar plants perfectly, that output would still be
These functions are not new. Grid operators
variable, and pose specific challenges to the grid
have been regulating frequency and voltage,
operator, which we introduce here [per11].
maintaining reserves and following shifts in load
On the seconds to minutes time scale, grid operators since the development of the electricity grid. This
must deal with fluctuations in frequency and voltage is because loads themselves are variable, and even
on the transmission system that, if left unchecked, conventional, controllable generation experiences
would damage the system as well as equipment problems and cannot perform as scheduled all of
on it. To do so, operators may order generators the time. Consumers demand electricity in ways that,
to inject power (active or reactive) into the grid not while predictable, are not controllable and have some
for sale to consumers, but in order to balance the degree of variability. Thus wind and solar generation
actual and forecasted generation of power, which does not introduce entirely novel problems with
is necessary to maintain frequency and voltage on which operators have never grappled. Indeed, at
the grid. These ancillary services go by a plethora of low penetrations, the integration challenges are
names and specific descriptions. Typical services for primarily device and local-grid specific, such as
an impressionistic overview include: subsynchronous resonance and harmonics, which
the turbine itself may cause. These issues are
frequency regulation: occurs on a seconds-to-
explained in greater detail in section 3, and their
minutes basis, and is done through automatic
solutions tend to be device-specific rather than grid-
generation control (AGC) signals to generators;
level.
spinning reserves: generators available to
However, high penetrations of wind and solar
provide power typically within 10 minutes.
generation will add more variability to the energy
26
RE generation: the present, the future and the integration challenges
system than grid operators have traditionally the cost of this function by increasing the spread
managed in the past, and thus increase demand between predicted and supplied energy, a cost that
for ancillary services and balancing energy overall. is ultimately borne by consumers.
It is more difficult, and sometimes impossible, to
Unit commitment at present is largely deterministic,
manage such challenges at the device level, and
meaning that once a generator is scheduled to
so grid-level actions, technologies and strategies
run, its full capacity is expected to be available for
are often needed. Wind and solar resources in
use. This practice reflects the relative predictability
sufficient amounts may also complicate load
and controllability of traditional coal, gas and
following functions when large demand shifts
hydropower generation resources. Operators
coincide with weather events that alter power
ensure the availability of reserves – generators that
output from wind or solar resources. Grid
withhold the supply of energy and so stand ready
operators located in more remote regions and
to balance the system in an emergency – so as
serving smaller loads may have less flexibility to
to protect against a potential transmission line or
provide ancillary services and load following than
generator outage.
their larger counterparts. Compounding matters,
plentiful RE resources are often located in these But the process of unit commitment and the
remote locations. The IEA and other bodies have calculation of reserves needed to ensure reliability
recommended consolidation of grid operators, in becomes more complex when dealing with
order to integrate RE sources over larger areas and stochastic (uncertain) generation, whose output
so reduce the variance of the power produced, at the committed time carries some degree of
as well as easing of market restrictions on sales uncertainty. Forecasting technologies aim to
of ancillary services as a solution to this problem predict weather and thus generation output
[iea09]. from wind and solar resources at various time-
scales more accurately, and communicate those
predictions to grid operators in a manner that
2.3.2 Partial unpredictability allows the operator to more effectively schedule
and dispatch resources. Properly anticipating
Partial unpredictability, also called uncertainty, is
wind and solar output levels allows the operator
distinct from variability. The variability of wind and
to modify the scheduling of other generators so as
solar generation is ever-present, a result of reliance
to more optimally utilize all assets under the grid
on the ever-changing wind and sun, and affects the
operator’s purview. The operator must, for example,
system at the moment-to-moment time scale as a
ensure that reserves are available not only to cover
cloud passes over a PV plant or the wind drops.
transmission line or generator outages, but also
Partial unpredictability, on the other hand, refers
to respond to still unanticipated changes in wind
to our inability to predict with exactness whether
and solar output. Assisting the operator in this
the wind and sun will be generally available for
process are advanced unit commitment methods,
energy production an hour or a day from now. This
which aim to prepare the system for multiple
hour-to-day uncertainty is significant because grid
potential and uncertain outcomes that cannot
operators manage the great majority of energy on
be predicted by the forecasting technologies.
the grid through “unit commitment”, the process
Unlike deterministic unit commitment processes,
of scheduling generation in advance, generally
advanced unit commitment methods must take
hours to a full day ahead of time, in order to meet
into account the stochastic nature of wind and
the expected load. When actual production does
solar generation and their relative concentration
not match the forecast, the grid operator must
on the system in recommending the scheduling of
balance the difference. RE generation increases
27
RE generation: the present, the future and the integration challenges
28
Section 3
Present: state of the art in integrating large-capacity RE
Figure 3-1 | A standard WTG with three blades and horizontal axis (SGCC)
29
Present: state of the art in integrating large-capacity RE
Rotor Blade
Tower
Nacelle
Hub
Low-speed High-speed
Shaft Shaft
30
Present: state of the art in integrating large-capacity RE
Power Grid
Step-up
transformer
Low voltage busbar
Overhead
line or cable
Wind
turbine
2) Types and characteristics of major WTGs stall designs can be adopted in improved type 1
WTGs, where the blades can pitch towards stall
WTGs currently in operation mainly include the
by a control system. Because induction generators
following four types. Each type has some unique
absorb a lot of reactive power when generating
characteristics due to its features in topology
active power, type 1 WTGs are generally equipped
[ewe05] [ner09] [sge11].
with reactive power compensators.
Type 1 – Fixed speed induction generator:
Type 2 – Variable-slip induction generator:
Introduced and widely used in the 1980s, type 1
Introduced in the 1980s and 1990s, type 2 WTGs
WTGs (see Figure 3-6) are based on a squirrel
(see Figure 3-7) are equipped with a wound rotor
cage induction generator (SCIG). They can only
induction generator (WRIG). Power electronics are
slightly vary their rotation speed (1 %-2 %), i.e.
applied to control the magnitude of the WRIG’s rotor
they are almost “fixed speed”, thus their output
current, which allows a speed variation of 10 % up
fluctuates as wind speed varies. To alleviate
and down, improving power quality and reducing
this problem, a double-speed version of the
the mechanical loading of the turbine components.
type 1 WTG was developed. Original type 1 WTGs
Type 2 WTGs are equipped with an active pitch
have few control options but passive stall. Active
31
Present: state of the art in integrating large-capacity RE
Squirrel cage
induction generator Transformer
Grid
Gear box
Reactive power
compensator
Wound rotor
induction generator
Transformer
Grid
Reactive power
compensator
control system. Like type 1 WTGs, type 2 WTGs rest directly to the grid. This design can provide
are also generally equipped with reactive power approximately 40 % up and down speed variation,
compensators. maximizing wind energy capture. The converter
provides decoupled control of active and reactive
Type 3 – Doubly fed induction generator
power, enabling flexible voltage control without
(DFIG): As the most popular WTGs at present, type
additional reactive power compensation, as well
3 WTGs (see Figure 3-8) combine the advantages
as fast voltage recovery and voltage ride-through.
of previous WTG designs with advances in power
Pitch control is also incorporated.
electronics. The WRIG’s rotor is connected to
the grid through a back-to-back insulated gate Type 4 – Full-power conversion WTG: In a
bipolar transistor (IGBT) power converter that type 4 WTG (see Figure 3-9), the stator of the
controls both the magnitude and frequency of generator is connected to the grid via a full-power
the rotor current. Up to about 40 % of the power back-to-back IGBT power converter, which means
output goes through the converter to the grid, the all the power output goes to the grid through the
32
Present: state of the art in integrating large-capacity RE
Wound rotor
induction generator Transformer
Grid
Back-to-Back IGBT
Gear box Power converter
Synchronous
or induction Back-to-Back IGBT
generator Power converter Transformer
Grid
Gear box
33
Present: state of the art in integrating large-capacity RE
34
Present: state of the art in integrating large-capacity RE
Power grid
AC AC AC
Inverter Inverter Inverter
DC DC DC
Cable
PV panel
35
Present: state of the art in integrating large-capacity RE
especially important for grid-connected PV power thermal power generation that converts thermal
plants, since it directly influences whether the PV energy into electricity, but differs in how the
power plant can meet the requirements of grid thermal energy is obtained. CSP plants use various
operation. Most inverters have low voltage ride mirror configurations (with a sun tracking system)
through (LVRT) and flexible active and reactive to reflect and concentrate direct-beam sunlight to
power control capabilities. However, since there is heat the working fluid flows (such as air, water, oil or
no rotating component, PV systems cannot supply molten salt) in the receivers to a high temperature,
inertia support to the power system. thus converting solar energy into thermal energy
(see Figure 3-14).
Compared to CSP described below, PV power
generation (except for concentrating PV) has the
advantage that it can use not only direct sunlight
n
io
receiver
re
di
CSP generation, also known as solar thermal Figure 3-14 | Principle of obtaining
power generation, is much like conventional thermal energy in CSP [dlr05]
36
Present: state of the art in integrating large-capacity RE
Using a generator driven by a steam turbine, gas A CSP plant can also be designed as a hybrid
turbine or heat engine, this thermal energy is then system that uses fossil fuel to supplement the
converted into electricity. CSP plants may also be thermal output during low solar radiation periods
equipped with thermal energy storage systems (see Figure 3-16), making the plant output more
for operating during cloudy periods or at night. A stable and dispatchable. It can also be integrated
typical stand-alone CSP plant has a configuration with a conventional combined-cycle plant to
such as that in Figure 3-15. improve energy efficiency.
Generator
Storage Grid
Tank
Solar Steam
Generator
Condenser
Storage
Tank Solar Steam
Generator
Grid
Fuel Boiler
HTF
Heater Fuel
Condenser
37
Present: state of the art in integrating large-capacity RE
38
Present: state of the art in integrating large-capacity RE
The capacity of parabolic trough, linear Fresnel high voltage DC (VSC-HVDC) transmission has
reflector and solar tower systems can reach been used for offshore wind power integration.
hundreds of megawatts, while the capacity of dish/ Examples will be given in this section. Ultra-high
engine systems is generally in the 10 kW range, voltage AC (UHVAC) and current source converter
suitable only for distributed generation. The solar- HV/UHVDC (CSC-HV/UHVDC) are planned to be
to-electricity efficiency of parabolic trough systems used in large-capacity RE power transmission;
has been demonstrated to be about 10 %-15 %, these will be described in section 4.
with a perspective of reaching about 18 % in the
medium term.
3.3.1 AC transmission
3) Characteristics of CSP generation
AC transmission is a mature technology. The ca-
CSP is advantageous in that it offers a utility-scale,
pacity of an AC transmission line is proportional to
dispatchable and firm RE option. With the inherent
the square of the voltage level and inversely pro-
energy storage capability in the form of heat that
portional to the impedance of the line, which in-
can be used to generate electricity up to hours later,
creases with the transmission distance. To achieve
and with further support from additional thermal
a large increase in the transmission capacity of
storage systems or a hybrid system design, CSP
long-distance AC lines, a natural way is to raise the
plants can continue to produce stable electricity
voltage level. The approximate transmission ca-
even when clouds block the sun or the sun sets.
pacities and distances of different voltage-level AC
So it is much less challenging to integrate CSP
lines are listed in Table 3-1 [sgc07]. For small-to-
than wind or PV generation into power systems.
medium scale RE power plants, transmission lines
Although CSP has better performance for grid below 330 kV are usually used. For large-scale,
integration, the relatively immature technology and long-distance RE power, transmission lines above
the high cost are currently limiting its large-scale 500 kV are usually needed. Some examples of AC
deployment. transmission above 500 kV for RE integration in
China and the USA are described below.
One disadvantage of CSP is that it requires
strong direct sunlight. As a result, adequate CSP 1) USA
resources are generally limited to semi-arid, hot
Currently, three major 500 kV transmission projects
regions or deserts. At the same time, like other
are under construction or have been approved in
thermal power generation plants, CSP requires
Southern California for RE power transmission
water for cooling and condensation, which
[ete11], a summary of which is given in Table 3-2.
means a tremendous challenge in exploiting CSP
resources in arid regions. Dry cooling (with air) is 2) China
an effective alternative, but with higher costs and In November 2010, a 2 398 km double-circuit
lower operating efficiencies. 750 kV transmission line was commissioned for
the interconnection of the Xinjiang power grid
and the Northwest power grid as well as for the
3.3 Transmission technology transmission of the phase I Jiuquan wind power
Large-capacity RE generation plants are usually base. Jiuquan wind power base phase I has an
far from load centres, and they therefore need installed capacity of 5 160 MW. A small portion
long-distance power transmission. Up to now, AC is locally consumed, while most is transmitted to
transmission has been used for large-capacity RE the load centre of the Northwest power grid (see
power transmission, and voltage source converter Figure 3-18). A second 750 kV transmission cor-
39
Present: state of the art in integrating large-capacity RE
Table 3-1 | Typical transmission capacities and distances of different voltage-level AC lines
RE integration
Transmission line
Project capacity provided Purpose
length (km)
by project (MW)
Enhance grid connection between
Imperial Valley and San Diego,
Sunrise Power Link 1 700 196 transmitting wind, solar and geothermal
power from Imperial Valley and Arizona to
San Diego
Tehachapi Renewable Transmitting wind and solar power in
5 850 530
Transmission Project Tehachapi area
Transmitting wind and solar power in
Colorado River Devers
4 700 270 the Blythe area between California and
Valley (CDV)
Arizona
ridor is now under construction. 500 kV transmis- among others the following major advantages
sion lines have also been built for the Jilin wind [vsc10]:
power base in Northeast China.
1) It can rapidly control both real and reactive pow-
er, independently, within its rated MVA capacity.
As a result, it can transmit very low and even zero
3.3.2 VSC-HVDC transmission
active power, which is suited to the frequent and
IGBT-based VSC-HVDC differs from the conven- wide-range output fluctuation of RE generation,
tional thyristor-based current source converter while CSC-HVDC is limited by minimum startup
HVDC (CSC-HVDC, also known as line commu- power. VSC-HVDC terminals can generate or ab-
tated converter HVDC (LCC-HVDC)) in that it is sorb a given amount of reactive power as instruct-
self-commutated via control circuits driven by ed or according to the voltage level of the connect-
pulse-width modulation, while CSC-HVDC is line- ed AC grid, providing excellent voltage support,
commutated, i.e. switched off when the thyristor while CSC-HVDC terminals always absorb reactive
is reversely-biased from the AC voltage [wei11]. power when working, requiring large amounts of
Compared to CSC-HVDC, VSC-HVDC offers reactive power compensation.
40
Present: state of the art in integrating large-capacity RE
Ov
er
10
00
Xinjiang km
Load centre
Figure 3-18 | Transmission of the phase I Jiuquan wind power base, Northwest China (SGCC)
2) It can rapidly reverse the reactive power power, as well as for grid interconnection and
direction merely by reversing the current direction, power supply to isolated systems and to crowded
without changing the voltage polarity as CSC- metropolitan areas. The fast development of RE
HVDC requires. It therefore needs no changes in has led to a rapid increase in VSC-HVDC projects
the topology and strategy of the converter station in recent years. Some VSC-HVDC projects
control system. commissioned for RE integration are listed in
3) It does not require support from the connected Table 3-3. There were also 12 VSC-HVDC
AC grid for commutation as CSC-HVDC does, and transmission projects under construction all over
can therefore be connected to weak or even passive the world at the end of October, 2011. From 2009
AC grids, while CSC-HVDC requires the connected onwards, the total capacity of VSC-HVDC projects
AC grid to be sufficiently strong. under construction in the world has reached
10 GW, which is four times higher than that of the
Due to these advantages, VSC-HVDC is desirable
projects built before 2009.
for RE integration, especially for offshore wind
41
Present: state of the art in integrating large-capacity RE
Numerical weather
prediction (NWP)
Forecast program
Power output
forecast
42
Present: state of the art in integrating large-capacity RE
Operational
Program Developer Methods Country
since
University College
HIRPOM Cork, Ireland; Danish Statistical Under development --
Meteorological Institute
Statistical,
AWPT ISET (DE) 15 GW, Germany 2001
ANN
43
Present: state of the art in integrating large-capacity RE
Operational
Program Developer Methods Country
since
AleaWind Aleasoft (ES) Statistical Spain 2004
Scirocco Aeolis (NL) Physical Netherlands, Spain 2004
Meteologica MBB Physical Spain 2004
Meteotemp No specific model name Physical Spain 2004
Physical and
WPFS CEPRI China 2009
Statistical
2) Forecast accuracy
1
The accuracy of wind power forecasting can be
measured by different indices. Root mean square 0.8
Error reduction
error (RMSE) normalized to the installed wind
0.6
power is most commonly used. Regardless of
the forecasting method used, the forecast error 0.4
40
35
30
25
20
15 2005
10 2006
5 2007
2008
0
0 1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49
Hours
Fi gure 3-21 | Wind forecast error as a percentage of wind production, as a function of the time
forward from the present [uei10]
44
Present: state of the art in integrating large-capacity RE
The error reduction shown along the vertical axis in related to wind power integration in major countries
Figure 3-20 is the ratio between the RMSE of a re- are briefly introduced below.
gional prediction and the RMSE of forecasting for
1) China
a single site, and is based on the measured power
According to the Renewable Energy Law and
production of 40 wind farms in Germany. Aggrega-
related regulations, wind power (and other
tion over a 750 km region may reduce forecasting
renewables) should be given first priority in
error by about 50 % [eis11]. If forecasting is scaled
generation scheduling and dispatching under
up to apply to the aggregated wind power of a
normal power system operating conditions. To
large area, the forecast error (RMSE) can drop to
meet this requirement, grid operators consider
below 10 % [ewe05].
predicted wind power generation in the mid-to-
On the other hand, the forecast error increases long term, day-ahead and intra-day operation
as the time horizon of the forecast increases, planning processes and fully exploit flexibility from
as shown in Figure 3-21, which also shows the conventional power plants, as well as the capacity
improvement in forecasting techniques over the of inter-grid tie-lines to accommodate the maximum
years. Generally, the error for 1-2 hours ahead for wind power while maintaining system security and
a single farm forecast can be about 5 %-7 %, and reliability (see Figure 3-22) [sgc11] [wei11].
can reach 20 % for day-ahead forecasts.
The requirement is also emphasized for WPPs to
be equipped with control and monitoring systems;
3.4.2 Operational practices these serve to enhance their controllability and
provide operational information to grid operators.
Due to the differences in RE generation
To date, all grid-connected WPPs have been
development, the conventional generation fleet,
equipped with control and monitoring systems that
grid structure as well as market and institutional
can communicate with the dispatching centres in
environments, the operational practices related
real time.
to RE integration are quite different in different
countries or regions. Some operational practices
Figure 3-22 | System operation in China taking wind power into account [sgc11]
45
Present: state of the art in integrating large-capacity RE
AVC
AGC
Figure 3-23 | The “wind power optimal dispatching decision support system” in Jilin [sgc11]
Wind power forecasting systems have been A well-functioning power market and an automatic
deployed in several regional or provincial dispatching system have been established
dispatching centres in the State Grid Corporation throughout the north European power system
of China (SGCC), but only about 30 WPPs have including Denmark, through which the hydropower
established a plant-level wind power forecasting in Norway and Sweden is often used to balance
system, a situation needing to be improved by the wind power in Denmark. Figure 3-24 shows
more stringent management. A SGCC NWP the monitoring curves of power generation and
centre has also been established in the China exchange, where line A is total power production
Electric Power Research Institute (CEPRI) to based on individual 5-minute schedules from all
provide weather information needed by the wind power plants, lines B are exchange plans with
power forecasting systems. Based on wind power neighbouring grids (Western part of Denmark (DK1)
forecasting at different time scales, a “wind power to SvK in Sweden, DK1 to Tennet in Germany, DK1
optimal dispatching decision support system” to ENDK in Denmark and DK1 to SN in Norway,
had been developed and put into operation in the from top to bottom). In general, the Nordic Power
dispatching centre of the Jilin provincial power grid System can be balanced by trading: the additional
(see Figure 3-23). electricity produced by WPPs is purchased at a
low price and sold to the other grids at a higher
2) Denmark
price. In addition co-generation plants and electric
Energinet.dk, the transmission system operator
boilers play an important role in winter in balancing
(TSO) of Denmark, mainly uses two wind power
the fluctuations caused by large-scale wind power.
forecast tools: one external and one internal. The
external forecast tool gives a 0-12 hour forecast 3) Germany
every 5 minutes and a 0-48 hour forecast every Three of the four TSOs in Germany (50Hertz, Ten-
hour. The input to the forecasting includes four net, Amprion and ENBW) have established wind
different numerical weather predictions. The power forecasting systems, covering approxi-
internal forecast tool includes a 0-6 hour short-term mately 98 % of Germany’s wind power capacity.
forecast and a 12-36 hour day-ahead forecast. For example, the Amprion company has set up a
46
Present: state of the art in integrating large-capacity RE
Figure 3-24 | Monitoring power generation and power exchange with neighbouring grids [sad11]
Front Office to manage the operation of the fore- In certain areas, the wind power output will
casting system and optimize the forecast results sometimes exceed the transmission capacity
by a combination tool (see Figure 3-25). Amprion of the grid, and the grid managers have a legal
shares wind power forecasting data (day-ahead obligation to increase power transmission capacity.
and ultra-short-term) with other members of TSC In the interim period before the additional capacity
(TSO Security Cooperation). objectives are achieved, the grid managers can
In September 2004, the German “Renewable require the wind farms to reduce their power
Energy Sources Act” amendment introduced a output or shut down some of the wind turbines.
new mechanism for wind power balancing, which 4) Japan
requires each system operator to contribute to
Japan’s power system consists of two parts, the
balancing the whole country's wind power output
Western 60 Hz network and the Eastern 50 Hz
in proportion to the size of its regional grid.
network, which are interconnected through
This mechanism allocates wind power and the frequency converter stations. The Eastern network
associated fluctuation to each system operator in consists of three utilities: the Hokkaido Electric
real time. It is more equitable in the distribution of Power Company (EP), Tohoku EP and Tokyo
balance services and related costs. The four system Electric Power Company (TEPCO). Hokkaido EP
operators have developed a real-time wind power is interconnected with Tohoku EP through DC
monitoring system to determine the wind power submarine cables, and Tohoku EP and TEPCO
balancing capacity that every system operator are connected by a 500 kV double-circuit AC
should be responsible for. In fact, as concerns transmission line (see Figure 3-26).
wind power, the regional grids have integrated into
a single large grid in Germany.
47
Present: state of the art in integrating large-capacity RE
Figure 3-25 | Schematic of a combination tool for wind power forecast (Amprion Company)
The areas suitable for wind power generation plants being reduced accordingly to absorb
are limited by geographical factors, and they are the incoming wind power. These collaboration
unfortunately concentrated in areas whose system schemes will improve the utilities’ capability to
capacities are comparatively small. Most wind accommodate wind power, but the capability is
resources are located in the smaller Hokkaido and limited by the capacity of the inter-ties. When the
Tohoku EP areas, where peak demand is around capacity of the inter-ties is insufficient, excess wind
5 GW and 15 GW respectively. In the area of TEPCO, power generation has to be curtailed.
which has an electricity demand of 60 GW including
5) Spain
the Tokyo metropolitan area, there are few suitable
locations for wind power. This situation poses a Red Eléctrica de España (REE), the only grid
challenge for wind power integration, since the company in Spain, has established the world's
amount of RE that can be integrated into a grid first RE power control centre (CECRE in Spanish),
depends on the capacity of the network where the which is responsible for scheduling and controlling
RE is located. national RE generation.
To enhance wind power integration, one option Wind farms are also required to set up real-time
is to use inter-ties between utilities efficiently to control centres, and the control centres of the
balance wind power generation output. In 2010, wind farms with an installed capacity greater
collaboration schemes were launched by the than 10 MW must connect directly to CECRE, as
three utilities for timely sharing of the wind power shown in Figure 3-27. These control centres must
forecasts in the Hokkaido and Tohoku EP areas, be able to control wind power output according to
and closely monitoring the power flow of all the setting values issued by CECRE within 15 minutes
inter-ties from Hokkaido EP to TEPCO. If there is at any time. For power system security reasons, if
room for extra power flow in the inter-ties and other necessary, REE has the right to reduce the wind
grid conditions permit, wind power generated in the power output.
Hokkaido and Tohoku EP areas can be transmitted
to TEPCO, with the output of the thermal power
48
Present: state of the art in integrating large-capacity RE
Tele
VSAT control
HUB
Wind Farm
CECRE Point
to
point Control ADSL
center
Special channel
CECRE carries out three-phase permanent can determine the maximum RE which the entire
fault simulation on the 70 different substations’ system can accommodate while still guaranteeing
buses every 20 minutes, using an assessment system security. On the other hand, using an
programme named GEMAS (Maximum Admissible optimization method, it can calculate the maximum
Wind Power Generation System). On one hand, it output of each wind farm. The resulting setting
49
Present: state of the art in integrating large-capacity RE
Figure 3-28 | Scheduled and actual daily curves of wind power output
thus calculated is sent by CECRE to every control investor-owned utilities (IOUs), federally owned
centre. Figure 3-28 shows typical scheduled and power marketing administrations (PMAs), and
actual wind power output curves in a day. municipal and rural utilities that primarily purchase
power at wholesale to serve local loads. Each utility
6) USA
has its own scheduling and dispatch procedures
Due to different grid composition, rules and wind according to the peculiarities of its generation mix,
power penetration, the various regional grids of the and energy trading between utilities is difficult
USA have developed widely varying wind power and dominated by long-term power-purchase
scheduling, dispatch and operational mechanisms. agreements. Nevertheless, many utilities integrate
For example, the California Independent System renewables into day-ahead, hour-ahead, and
Operator (CAISO), as a leader in state-of-the- real-time scheduling procedures, much like the
art mechanisms, has developed a Participating open markets of the Eastern Interconnect and the
Intermittent Resource Program (PIRP) that allows CAISO. Rule changes are underway in the WECC,
individual wind facilities to self-schedule according and utilities with higher proportions of renewable
to shared forecasting technologies. The New York power are pressing for more robust energy
Independent System Operator (NYISO) requires imbalance markets in order to ease RE integration
wind farms to behave like conventional power in costs. Though it is the least-organized of US power
order to participate in real-time electricity markets: markets, the WECC is of critical importance to the
in certain circumstances, the wind farm must USA due to its high resource concentrations of RE
reduce output power or be fined if it exceeds the and the presence of very large federal PMAs such
value specified in scheduling instructions. as the Western Area Power Administration (WAPA)
In the western portions of the USA outside CAISO, and the Bonneville Power Authority (BPA), which
which follow reliability standards set by the Western are under the direction of the US Department of
Electricity Coordinating Council (WECC), an even Energy.
greater degree of diversity is present. Because of
a lack of organized, open electricity markets, the
WECC is primarily managed by vertically-integrated
50
Section 4
Future: technical solutions for integrating
more large-capacity RE
EES
RE output fluctuation Demand response
Grid faults Grid -friendly RE generation
Conventional generation outages Conventional generation
Load variation flexibility
Variability and System
uncertainty flexibility
51
Future: technical solutions for integrating more large-capacity RE
The application of energy storage to support wind generating units to possess performance
large-capacity RE integration will be discussed comparable or even superior to those of
separately in section 5, while the other solutions conventional thermal or hydro generating units.
mentioned will be discussed in this section. Some advanced operational capabilities of wind
generating units and the methods to achieve them
are cited below from [ner09] and [bac11] with minor
4.2 Grid-friendly RE generation modifications. Most of these capabilities can also
4.2.1 Need for grid-friendly RE generation be achieved for solar PV generating units since
they share many technical characteristics with
At the beginning of its development RE generation
wind turbine generators, especially the inverter-
technology focused more on tapping the maximum
based ones.
power from RE resources. It neglected to make any
contribution to power system reliability and stability 1) Voltage/Var control and regulation
and in the absence of standards and incentives was Reactive power support and power factor control
not designed to operate in a coordinated fashion can be provided either through a built-in capability
with the rest of the system. As long as RE penetration (available for wind generating units types 3 and 4)
is low this is manageable and can be accepted by or through a combination of switched capacitor
power system operators. But as RE generation banks and power electronic based transmission
penetration grows, and especially as the capacity of technologies such as static var compensator (SVC)
RE power plants becomes larger and larger, this will and static synchronous compensator (STATCOM)
have a serious impact on system operation. (flexible AC transmission system (FACTS) equipment
For example, in 2011 several serious wind turbine as discussed in 4.4.2, applicable to all types of wind
disconnection incidents occurred in China due to generating units).
the lack of fault ride-through capability (see 4.2.2), 2) Fault ride-through
including one at the Jiuquan wind power base on The ability is needed to survive (ride through)
February 24, which led to the disconnection of 598 specific low and high voltage/frequency ranges
wind turbines from the grid (840.43 MW of power and durations caused by faults or disturbances
output) and a significant frequency drop. in the power system. Voltage ride-through can be
Therefore it is becoming increasingly important that achieved with all modern wind generating units,
RE generation should play a greater role in helping mainly through modifications to the controls. In
to maintain system reliability and stability, and this some cases, with older type 1 or type 2 wind
may be increasingly required by interconnection generating units at weak short-circuit nodes in
standards. Technologies have been developed and the transmission system, there may be a need for
are continuously improving at the generating unit, additional transmission equipment.
plant and plant cluster level to make RE generation 3) Active power control, ramping and
more predictable, controllable and dispatchable, curtailment
or in other words more grid-friendly.
This can be achieved through unit control
mechanisms for wind turbine units with active-stall
4.2.2 Advanced characteristics of RE or pitch control, or discrete tripping of units.
generating units and plants 4) Primary frequency regulation
Development of power electronics and mechanical Primary frequency regulation can be supplied by
engineering technologies, as well as the design all units that are equipped with some form of pitch
of proper control strategies, have enabled regulation (i.e. active-stall or pitch control).
52
Future: technical solutions for integrating more large-capacity RE
Power grid
Dispatch Centre
High voltage busbar
SCADA
Step-up
transformer
Reactive power /
Low voltage busbar
Voltage control Communication
Reactive
module
power
Active power /
compensation Command, Data
Frequency control
Measurement
Fault ride-through Power
control
Communication
Other control module
53
Future: technical solutions for integrating more large-capacity RE
200 MW 200 MW
200 MW 35 kV line
200 MW 200 MW
330 kV line
#2
200 MW 750kV
#1 #6 Jiuquan
substation
#7 #8
330 kV #9
substation 750 kV Anxi 200 MW
substation
280 km
Figure 4-3 | Schematic diagram of the Jiuquan Wind Power Base, Gansu, China (SGCC)
Dispatching centre
to be avoided. Taking reactive power control as an voltage and reactive power controllers in nearby
example [pei12]: with multiple wind plants having plants have been incompatible, resulting in poor
requirements to provide reactive power and control voltage control and counterproductive reactive
grid voltages, problems have emerged when the power flows. There have been numerous reports
54
Future: technical solutions for integrating more large-capacity RE
of one or more plants at maximum reactive power the same type, regardless of manufacturer, by se-
output while neighbouring plants are absorbing lecting appropriate model parameters. WECC and
reactive power. To avoid this kind of situation, IEC groups are moving forwards to refine and vali-
centralized cluster control is an attractive solution. date these generic models, for which collaboration
A centralized cluster control system, configured between the power engineering community and
in a multi-layer structure such as that depicted in wind turbine manufacturers is necessary. Efforts
Figure 4-4, can be used to coordinate the active and to develop generic models for PV have also be-
reactive power control of a RE power plant cluster, gun. However, regarding RE generator modelling,
just as cascaded hydro power plants on a river a great deal of research still needs to be carried
are controlled. Such a centralized cluster control out, e.g. to determine the short-circuit contribution
system, the so-called Large Wind Power Plants of different types of RE generators, and to repre-
Cluster Active Power Intelligent Control System, has sent the more advanced and rapidly developing
been developed and deployed at the Jiuquan Wind control characteristics of RE generation, such as
Power Base [sgc11]. those described in 4.2.2.
55
Future: technical solutions for integrating more large-capacity RE
take decades for low-cost, large-scale storage to and change their capacity by 50 % in fractions of
mature (with the exception of the widely used but a minute. Their minimum output can be very low,
topographically restricted pumped hydro storage), which means a regulation range of near 100 %
and demand response as a flexibility resource is still capacity. However, output and hence the flexibility
in its infancy. Flexibility in conventional power plants contribution of hydro power plants can be influenced
(generally referred to as “generation flexibility”) is by seasonal factors (drought and flooding seasons)
therefore the major source of power system flexibility, as well as non-electricity-sector requirements such
and “the need for increased generation flexibility as flood and drought control or environmental and
is central to the challenges posed by intermittent navigational considerations.
renewables” [eis11]. The need for generation
Gas-fi red power plants, including natural gas
flexibility differs in different countries and regions
combined cycle (NGCC) and simple cycle gas
due to their different existing generation mix.
turbine (SCGT) plants, are also flexible generation
Generally, hydro power plants with a reservoir are resources. Current designs of SCGTs in operation
most flexible, followed by gas-fired power plants, are able to ramp to 100 MW-150 MW in 10 minutes,
then coal-fired power plants and last nuclear power and NGCC plants in 60 to 80 minutes. New NGCC
plants, but it is difficult to measure flexibility so as designs with an increased focus on the ability
to allow use of the measurements in generation to operate in a system with a large proportion of
planning. intermittent renewables are expected to produce
150 MW in 10 minutes and to ramp to full load in
30 minutes. The ramping rate of NGCC and SCGT
4.3.2 Assessment of generation fl exibility plants is generally up to 8 % per minute. NGCC
1) Flexibility of conventional power plants plants can reduce their output to 80 % of capacity
The relevant technical characteristics of with only a minimal heat rate penalty, but with
conventional power plants that contribute to increasing efficiency losses at lower outputs [eis11].
operational flexibility are the cycling, ramping and Coal-fi red power plants have limited operational
partial loading capabilities. Cycling capability is a flexibility. They are not suitable for frequent cycling
generator’s ability for frequent and fast startup or since they may take several hours to start up or
shutdown. Ramping capability is the rate at which shut down. Their ramping rates are generally only
a generator can change its output, either upwards 1 %-3 % per minute; new large-capacity generators
or downwards. Partial loading capability is the can reach 5 % per minute. Their minimum output
minimum output level at which a generator can is generally 70 %-80 % of capacity; new large-
be stably operated, as well as the efficiency when capacity or specially designed peaking generators
operating at different output levels lower than rated can go down to 50 % or lower, but lower output will
capacity. Due to the differences in design and lead to higher fuel consumption per kWh generated.
technology, different types of power plants have An example is given in Table 4-1 [npg10]. The
different levels of operational flexibility, implying flexibility of specific coal-fired power plants can be
varying impacts on equipment health, service life, influenced by their size, age, operating pressure,
operational costs and GHG emissions. fuel quality and the control systems installed [eis11].
Hydro power plants with reservoirs are very flexible Nuclear power plants also have limited
in operation. They can be easily and quickly started operational flexibility and are less used for ramping
up or shut down with little impact on equipment health for economic reasons. Relatively new nuclear
or service life. They can start from off-duty status reactors can down-ramp 20 % of total output within
and ramp to full-loading status in several minutes, an hour, but require six to eight hours to ramp
56
Future: technical solutions for integrating more large-capacity RE
Table 4-1 | Standard coal consumption of typical 600 MW and 1 000 MW generators at different
loading levels
up to full load. Nuclear plant ramping operations systems with more large-capacity RE. It is much
are not fully automated, creating opportunities more difficult to measure generation flexibility
for operator error. Although operational costs for than to measure the adequacy of generation
nuclear plants running at partial load versus full capacity; the former is more complicated and
load do not significantly differ, they need to run requires more data and detailed modelling [trp11].
as base load units at high output levels to recover Collaboration between grid operators and the
their high capital costs [eis11]. research community is desirable to foster efforts
to develop more rigorous methods and tools to
With more large-capacity RE generation being
accurately quantify, monitor and assess the degree
integrated into power systems, not only the flexible
of flexibility in a given power system for a given
hydro and gas-fired power plants are required to
level of RE penetration [sad11].
adjust their output more frequently, the coal-fired
and nuclear power plants traditionally operated The research community has started to respond to
mainly as base load units are also shifting to the need for power system flexibility measurement.
more flexible operation paradigms. Much effort The emphasis is on generation flexibility, currently
is needed to better understand the impact of the major flexibility resource, butefforts also in-
flexible operation on the technical, economic and clude using demand response and energy storage
environmental performance of conventional power for flexibility. The Integration of Variable Genera-
plants, especially thermal power plants, hence to tion Task Force (IVGTF) under the NERC in 2010
support the improvement in equipment design, released a special report on the flexibility require-
retrofit and daily operation, as well as the design of ments and metrics for variable generation [ner10],
necessary financial incentives. which discussed the metrics and approaches for
flexibility measurement. The IEA Grid Integration of
2) Measuring generation fl exibility
Variable Renewables (GIVAR) project has proposed
The need for more generation flexibility is well
a semi-quantitative method supported by qualita-
recognized. However, there is currently a lack
tively described limiting constraints on flexible re-
of metrics, methods and tools to measure the
sources to assess system flexibility, and a subse-
flexibility and its related cost of provision, determine
quent project specially targeting the quantification
the flexibility required, and optimize the generation
of system flexibility is expected [fat11]. The Alberta
resources to provide the required flexibility with
Electric System Operator (AESO) has developed a
minimal cost, all of which would be needed to
dispatch decision support tool, incorporating wind
support the planning and operation of power
power forecasting, to measure system flexibility
57
Future: technical solutions for integrating more large-capacity RE
and help operators to manage the increased vari- A rigourous “effective load-carrying capacity”
ability and uncertainty [pao11]. (ELCC) method based on reliability simulation
as well as several approximate methods have
been proposed for wind power capacity value
4.3.3 Generation planning for both calculation, and are being extended to solar power.
adequate capacity and adequate But there remain a number of problems, including
fl exibility the representation of other types of generation
In power systems with higher variability and in the calculation, the accuracy of approximate
uncertainty due to the integration of more large- methods and the requirement of high-quality wind,
capacity RE, it is becoming increasingly important solar and synchronized demand data for the ELCC
for the generation planning process to consider not method to produce reliable results [bac11] [cvw11].
only the adequacy of generation capacity, but also 2) Generation planning considering fl exibility
the adequacy of generation flexibility. Simply having at the system level
a specified number of megawatts of capacity may
In order to consider flexibility requirements, a new
not be adequate for system security if that capacity
paradigm of generation planning is needed. One
is not flexible enough to respond to system variability
example is the approach proposed in [trp11], adding
[aba11].
a flexibility assessment stage into the planning
1) Planning for adequate generation capacity process, as shown in Figure 4-5.
For capacity planning, the calculation of the It starts from the relatively simple traditional capacity
“capacity value” (also known as “capacity credit”) adequacy calculation, using metrics such as loss of
of RE generation has been recognized as a major load expectation (LOLE) and expected unserved
issue. The capacity value of a generation resource energy (EUE), to form an initial generation portfolio,
can be defined as the amount of additional load that and then moves to the more data-intensive system
can be served due to its addition while maintaining flexibility assessment and production cost simulation
existing levels of reliability. The calculation of the stages. Both of these stages involve computation-
capacity value of RE generation is much more intensive unit commitment and economic dispatch
difficult than that of conventional generation due studies. This three-stage approach is designed
to its inherent variability and uncertainty. Research to reflect the aims of the planning process, i.e. to
on this issue has received much attention. Both the provide a reliable, operable, least-cost generation
IEEE Power & Energy Society (PES) and the NERC portfolio for the given study period. If excessive or
IVGTF have established task forces to study it. inadequate flexibility is observed, the generation
Capacity
System flexibility Production cost Generation
adequacy
assessment simulation portfolio
assessment
58
Future: technical solutions for integrating more large-capacity RE
portfolio or unit commitment model can be altered large-capacity RE sources, which are generally
and the whole process iterated, in order to find a located far from load centres and the existing grid.
better generation portfolio that meets the dual aims
2) Through grid expansion, the geographic diversity
of minimizing cost and meeting a specified flexibility
of RE generation can be exploited to smooth out
standard.
their aggregated variability and uncertainty and to
Again, the system flexibility assessment is possible reduce the RE power forecast error.
only when metrics measuring flexibility in the
3) Grid expansion and reinforcement can support
planning context are available, which is currently
interconnection between balancing areas, hence
not the case. A good start is the metric named
facilitating their cooperation or consolidation to
“insufficient ramping resource expectation” (IRRE)
share flexibility resources.
developed by the IEA, which applies principles
similar to those underlying the LOLE metric for As shown in [smp11], transmission for RE
capacity adequacy calculation. integration is an issue everywhere for both
technical and regulatory reasons. An inability to
3) Generation planning considering fl exibility
solve the transmission problem will jeopardize the
at resource site level
achievement of RE goals, and drive up the cost to
Besides incorporating flexibility considerations into reliably integrate these new resources into power
generation planning at the system level, special systems.
designs can also be used at resource site level
to exploit the flexibility of conventional generation
in order to compensate for the variability and 4.4.2 Application of new transmission
uncertainty of RE. technologies
Such an approach is intended for some wind 1) Higher voltage level AC transmission:
power bases in China, where the so-called “wind- UHVAC
fire bundling” design has been proposed (see UHVAC transmission lines with rated voltage levels
Figures 4-9 and 4-10): coal-fired power plants are of 1 150 kV or 1 000 kV were built and commissioned
planned near a wind power base and will share its by the former Soviet Union and Japan in the 1980s
transmission lines. Wind power output fluctuations and 1990s, but then operated at a 500 kV voltage
can be smoothed out by adjusting coal-fired level for practical reasons. China is now leading
production; thus the utilization of the transmission the research and application of 1 000 kV UHVAC
line can be improved as compared to transmitting transmission, which seems a desirable technology
only wind power and the average cost of electricity to meet the need for large-scale, long-distance
at the receiving end can be reduced [sgc11]. power transmission from the large coal, hydro, wind
and solar energy bases in the northern and western
regions to the central and eastern regions with
4.4 Transmission expansion huge and still fast-growing electricity demand. The
4.4.1 Needs for transmission expansion first 640 km single-circuit Jindongnan-Nanyang-
Jingmen 1 000 kV UHVAC test and demonstration
Accommodation of large-capacity RE generation
transmission project was commissioned in 2009,
needs large-scale transmission grid expansion and
the reinforcement which followed was completed at
reinforcement for the following reasons:
the end of 2011, and it can now transmit 5 000 MW
1) Grid expansion and inter-regional connection of power stably. Some UHVAC projects have been
are needed to transmit the energy generated by planned to form part of the large-capacity, long-
59
Future: technical solutions for integrating more large-capacity RE
distance wind power transmission installation from It was noticed when studying the integration of the
the West-Inner Mongolia and Hebei wind power Jiuquan wind power base in Northwest China that
base in Northern China [sgc11]. UHVAC has also the large wind power output fluctuations would
attracted attention from other emerging large cause large voltage fluctuations in the whole network,
economies facing similar energy delivery challenges, especially at the nodes in the transmission corridor.
such as India [tea07]. To stabilize voltage, many voltage-regulating devices
must act frequently and in a well-coordinated way,
A single-circuit 1 000 kV AC line can transmit
which is harmful for the equipment and difficult to
4 000 MW to 5 000 MW over an economic distance
implement. In order to solve this problem, a 750 kV
of 1 000 km to 1 500 km. Compared to 500 kV AC
CSR was installed on the Dunhuang substation’s
transmission, 1 000 kV AC transmission has many
750 kV bus (see Figure 4-6), with field testing
advantages in improving transmission capacity
completed at the end of 2011. Developed by CEPRI,
and distance, reducing power loss, reducing land
it has a capacity of 300 Mvar and 4 controllable
use and saving cost, as shown in Table 4-2 [sin06]
grades: 100 %, 75 %, 50 % and 25 %; the adjustment
[tgy06]. For RE energy transmission, UHVAC is
range is 25 %-100 %.
mainly suitable for transmitting power from on-
shore RE plants using overhead lines. 3) Higher voltage level DC transmission:
UHVDC
2) More fl exible AC transmission: FACTS
CSC-HVDC is a conventional HVDC transmission
Based on advanced power electronic technologies
technology that is relatively mature and has long
and innovative designs, FACTS equipment can be
been used for long-distance, large-capacity power
applied to improve the capacity, stability and flexibility
transmission without midway drop points, as well as
of AC transmission, making it more capable of
for the interconnection of asynchronous power net-
transmitting large-capacity RE. For example, thyristor
works. Compared to AC transmission, it has advan-
controlled series compensators (TCSCs) can be
tages such as lower loss, lower line cost, narrower
installed in transmission lines to reduce electrical
corridor and rapid power control capabilities. Like
distance, increase damping and mitigate system
AC transmission, DC transmission is also progress-
oscillation; SVC, STATCOM and controllable shunt
ing in the direction of ultra-high voltage levels for
reactors (CSRs) can be shunt-installed on substation
larger-capacity and longer-distance power delivery.
buses to solve the reactive power compensation
Again, China is leading in the application of ultra-high
and voltage control problems which are common in
voltage DC (UHVDC) transmission. The 1 907 km,
RE integration due to their output fluctuation. SVCs
6 400 MW, ±800 kV UHVDC demonstration project
or STATCOMs may also be used to improve the
from Xiangjiaba to Shanghai was commissioned in
performance of RE power plants to meet integration
April 2010. SGCC has planned to build more than ten
requirements on reactive power and voltage control,
±800 kV or ±1 100 kV lines to transmit power from
while keeping the design of RE generators relatively
the wind power bases in Xinjiang, Gansu and Inner
simple.
Table 4-2 | Comparison between 1 000 kV and 500 kV AC transmission: gain factors
Comprehensive
Typical Economic Corridor width
Item Power loss construction cost
capacity distance per kW
per kW
60
Future: technical solutions for integrating more large-capacity RE
Mengdong
Xinjiang Mengxi
Jiuquan
North China Grid
Northwest China Grid
800 kV-DC
1000 kV-DC
1100 kV-DC
Figure 4-7 | UHVDC transmission plan for some 10 GW-level wind power bases in China (SGCC)
Mongolia to the Northeast-Central China load cen- The “wind-fire bundling” design (see Figure 4-9)
tres, ranging in length from 1 600 km to 2 700 km can withstand common wind disturbances, but if
[sgc11], as shown in Figure 4-7. wind speeds change rapidly frequency is difficult
to control. Without strong voltage support, outages
However, there are still some problems in the use of
on the sending end may lead to voltage collapse
CSC-HVDC or UHVDC to transmit RE [hsh12]. For
and disconnection of wind generators, depending
example, when HVDC lines are used to transmit
on the electrical distance between coal and wind
only wind power to load centres (see Figure 4-8),
power plants.
not only the low utilization rate problem mentioned
in 4.3.3, but also the minimum startup power of With voltage support from the local AC grid
the HVDC lines and problems in frequency stability (see Figure 4-10), the stability problems can be
and voltage stability require more research. mitigated, but attention should be paid to the
impact of wind power fluctuation on the local grid.
61
Future: technical solutions for integrating more large-capacity RE
HVDC
DC AC
AC DC
Wind power base Load centre
Figure 4-8 | Design for transmitting wind power only with HVDC (SGCC)
HVDC
DC AC
AC DC
Load centre
HVDC
DC AC
AC DC
Load centre
Figure 4-10 | “Wind-fi re bundling” design with HVDC transmission and local grid (SGCC)
4) More fl exible DC transmission: from VSC- with an AC grid, which facilitates flexible multi-grid
HVDC to MTDC and DC grids interconnection and even DC grids. These will
The major advantages of VSC-HVDC as compared be useful in future RE integration where multiple
to conventional CSC-HVDC described in 3.3.2 make resource sites and multiple receiving ends are
it not only suitable for application in RE integration, involved.
but also more convenient to form multi-terminal The preference for VSC-HVDC for relatively long-
DC (MTDC). Three or more converter stations are distance offshore wind power integration is present-
linked to each other with DC lines, each interacting ed in Figure 4-11. It is clear that for short distances
62
Future: technical solutions for integrating more large-capacity RE
Figure 4-11 | Transmission technologies for Figure 4-12 | Benchmark test system for the
integrating offshore wind power [ern11] European transnational offshore grid [coc11]
and relatively low power high voltage alternating terminals also suffer from higher power loss. VSC-
current (HVAC) technology will suffice. As power as HVDC transmission with voltage levels less than
well as distance increases, HVAC should be aug- ±150 kV and capacity less than 200 MW is relatively
mented with FACTS devices in order to compensate mature. VSC-HVDC transmission projects with
for HVAC losses and to provide stability support. In voltage levels of 350 kV and capacity of 400 MW
order to connect remote offshore wind power plants have been commissioned, but they are still much
to a grid, VSC-HVDC technology is preferred. smaller than recent ±800 kV, 6 400 MW CSC-HVDC
projects. The power loss in a VSC-HVDC converter
In order to tap large quantities of offshore wind
station is typically 1 %-6 % currently, much higher
power from the North Sea, a transnational offshore
than the 0.5 %-1 % loss of a CSC-HVDC converter
grid based on multi-terminal VSC-HVDC has been
station. Predominantly VSC-HVDC installations
proposed. A simulation benchmark test system has
use cables as the transmission medium, although
been developed to facilitate detailed investigations
a 350 kV VSC-HVDC using overhead lines has
into operational questions, as shown in Figure 4-12.
been commissioned by ABB in Namibia at the
Study results show that extensive coordination of
Caprivi Link. One of the limits imposed on the
control systems is essential, both in order to avoid
power transfer capability of a VSC-based HVDC
unwanted DC loop flows and to find the location of
system lies in the capability of DC power cables.
the optimal slack node in the system, which also
Predominantly DC power cables are used with
depends on the selection criteria chosen [coc11].
VSC-HVDC connections to help ease right-of-
Multi-terminal VSC-HVDC has also been adopted
way discussions, and they are the only option for
in the design of the Tres Amigas Super Station
offshore VSC-HVDC connections. However, with
project proposed in the USA to interconnect its
the option of overhead lines for VSC-HVDC, power
Eastern, Western and Texas power grids, as well
levels can increase as VSC technology advances.
as to fully exploit the abundant RE resources near
Finally, since most VSC-HVDC projects have been
the project site [ete11] [tgs12]. In EU’s Super Grid
operating for only a few years, the overall long-term
plan, MTDC and DC grids based on VSC-HVDC
security and reliability of VSC-HVDC also remain
technology will also play an important role.
to be proved over time, as with any new type of
To date, VSC-HVDC has not reached voltage or technology.
capacity as high as CSC-HVDC, and VSC-HVDC
63
Future: technical solutions for integrating more large-capacity RE
Initial 7 alternatives
Environmental, societal,
and political assessment
5 alternatives
Deterministic technical
analysis, including N-1
principal
3 alternatives
64
Future: technical solutions for integrating more large-capacity RE
Probabilistic planning criteria, tools and techniques scheduling, dispatch and control processes (see
have been developed for probabilistic transmission Figure 4-14).
planning over the past several decades; however,
The operation of modern power systems is
they will require critical review for completeness
supported by a physical layer supervisory control
and applicability before they can become
and data acquisition (SCADA) system and an
accepted by industry. More research on additional
application layer energy management system
probabilistic planning techniques is required. High-
(EMS). The SCADA system covers most of the
quality, high-resolution datasets of RE generation
spread-out elements in a power system, with
are also necessary; they are currently very limited
sensors to monitor their operational conditions
and difficult to obtain [ner09].
and report them to the operations centre through
communications channels. The EMS residing in
the operations centre exploits the information
4.5 Operational enhancement
collected by the SCADA system to analyze the
4.5.1 Need for operational enhancement situation and reveal any problems in the power
When resource capacity and flexibility as well as system, make security and economic dispatch and
transmission availability have been determined by control decisions, and send real-time commands
the planning process, it is operations’ responsibility to control the relevant system elements through
to manoeuver all the system capabilities to cope the SCADA system. Since modern power systems
with the variability and uncertainty resulting from rely heavily on computerized communications
the integration of large-capacity RE generation. and control for operations, they have evolved into
The operations process, as a broad concept cyber-physical systems.
distinct from planning, can be further divided into
Figur e 4-14 | Typical processes of power system planning and operation (SGCC)
65
Future: technical solutions for integrating more large-capacity RE
66
Future: technical solutions for integrating more large-capacity RE
5HVXOWVGLVSOD\
,QSXW'DWD
:LQG
IRUHFDVW :6$70DQDJHU
3\WKRQLQWHUIDFH
5HDOWLPH
V\VWHP
VQDSVKRW
6HFXULW\DVVHVVPHQW
5HDOWLPH
FRQWLQJHQFLHV 2QOLQH 2QOLQH 6WXG\
96$7 76$7 :6$7
67
Future: technical solutions for integrating more large-capacity RE
decisions. It evaluates system security and stability eration. There is also an increasing requirement to
limits based on near-real-time network topology regulate the output of RE power plants in addition
and operating conditions, such as the transmission to that of conventional generation units, based on
line thermal limits and the system voltage/transient/ the advanced control capabilities and the monitor-
frequency stability. By incorporating the RE power ing, control and data communication systems for
forecast and modelling, an online DSA system can RE power plants described in section 4.2.
be adapted to cope with the operational risks and
6) Stochastic operations and risk-based
challenges resulting from increased levels of RE
decision making
generation. As an example of such a tool, the wind
To address the increased uncertainty, including that
security assessment tool (WSAT) implemented in
related to RE power forecasts, many researchers
EirGrid’s control centre (see Figure 4-15) is used to
believe that future EMS applications should make
assess the instantaneous secure amount of wind
greater use of stochastic modelling techniques.
generation based on voltage stability analysis (VSA)
Stochastic UC, stochastic SCED and stochastic
and transient stability analysis (TSA) under normal
optimal power flow, for example, should be feasible
operating conditions and credible faults.
by taking advantage of the greater computing
4) Security constrained economic dispatch power now available. Risk-based decision making
Security constrained economic dispatch (SCED) techniques are also needed to improve the current
determines how to dispatch generators to deterministic and binary decision-making process;
produce electricity at the lowest cost subject to for this, research on how to quantify the relevant
reliability requirements and operational limits on operational risks and the severity of contingencies
generation and transmission facilities. It is now such as extreme ramp events is critical.
evolving to accommodate two major directions of
7) Security and defence generally
power system development: the increase in high
“Security” in DSA and SCED (see above) mainly
penetration RE generation and the development
refers to the physical aspects of power system
of demand response and smart grid applications
security, or security of supply. As a cyber-physical
(see 4.6). As described in 4.3, more flexibility is
system, the power system also faces cyber-
needed from conventional generation to integrate
security challenges, including the reliability of
high levels of large-capacity RE generation, and
the communications systems serving the power
the increased ramping and cycling requirements
system, and protection of critical information
of thermal power plants will lead to a significant
related to power system monitoring and control
increase in their operational costs. These costs
as well as confidential customer information
have to be better understood before they can
[top12]. Failures in cyber-security, especially those
be taken into account to improve the economic
caused by malicious cyber attacks on the control
dispatch process.
system, may damage power system elements and
5) Automatic generation control endanger the physical power system’s security
AGC is a centralized system designed to ensure of supply. Since large-capacity RE power plants
real-time generation/load balance and frequency are usually remotely located and consist of many
stability, by regulating the power output of selected widely-distributed, small-capacity generating
generation units and exchanging power on tie-lines units, the cyber-security of their control systems
between different power systems or control are- may require more attention. Although substantial
as. Existing AGC algorithms need to be modified efforts have been made by some organizations to
so that, based on RE power forecasts, they may address control system security, such as the power
address the variability and uncertainty of RE gen- system data communication standard protocols
68
Future: technical solutions for integrating more large-capacity RE
developed by IEC Technical Committee (TC) 57 their normal consumption patterns in response to
and widely used in power equipment, SCADA and changes in the price of electricity, or to incentive
EMS, cyber vulnerability is still a salient problem, payments designed to induce lower electricity use
and is becoming even more complex with the at times of high wholesale market prices or when
development of smart grids [iig12] [sic12]. system reliability is jeopardized” [adr11]. W hile this
definition covers well the current DR practices in
Moreover, as power systems, meteorological sys-
the USA, it may not be able to reflect DR’s evolving
tems, communications networks, water, com-
capabilities, including those expected to support
merce, etc., the so-called “critical infrastructures”,
RE integration.
become more closely integrated, it becomes in-
creasingly important that the security protocols As RE penetration rises, DR’s value as an additional
in one sector are considered within the broader source of power system flexibility to compensate
context of the security protocols in connected for the variability and uncertainty of RE generation
sectors, as well as the security needs of the coun- will increase. For example, REE (Spain) created
try and region. This issue involves harmonization a demand-side management department in
of cyber-security policies both vertically (e.g. from 2007 in order to promote demand management
system operation down to individual wind turbine mechanisms such as interruptible service, electric
control) and horizontally (e.g. from the power grid vehicle integration, smart metering and time-of-
to emergency services and telecommunications). use tariffs. These mechanisms, used together, are
With regard to RE integration, this would suggest expected to enhance the ability of the system to
a need for integrated security policies between integrate increasing quantities of RE [coc11]. DR
weather forecast systems and power system op- can help RE integration in two main ways, load
eration, specifically dispatch. For example, a highly shifting and balancing.
secure power grid system with high RE concen-
1) Load shifting
trations could still be quite vulnerable to an attack
DR can be deployed to transfer a part of the load to
that targets the country’s weather forecasting ser-
off-peak periods to absorb excess RE generation,
vice, either disrupting forecasting or providing false
particularly for wind power generation, which
forecast data. A grid operator who relied on such
often exhibits inverse-peaking characteristics:
data might find himself in serious trouble, beyond
generating more power during off-peak periods
simple variations in forecast.
and less power during peak demand periods. At
off-peak periods, conventional generation plants
4.6 Demand response are often already reduced to their minimum
output, and the insufficiency in demand will make
4.6.1 Demand response applications for
wind power curtailment inevitable, reducing wind
RE integration
power plants’ capacity utilization efficiency and
Demand response (DR), the development and preventing the replacement of fossil-fuelled power
extension of traditional demand-side management generation for emission reduction. Shifting load
or load management practices, is recognized as a to off-peak periods also brings additional energy
key application of the smart grid. Currently the USA efficiency and cost benefits for customers. For
is far in the lead in research and application of DR, example, Denmark has implemented zero- and
with Europe, China and other countries catching negative-spot electricity prices to encourage
up [jef11]. The US Federal Energy Regulatory customers to use electricity during hours of excess
Commission’s (FERC) definition of DR is: “Changes wind generation, and has planned for increased
in electric use by demand-side resources from integration between the transport, heating and
69
Future: technical solutions for integrating more large-capacity RE
electricity sectors to find new sources of off-peak of certain countries. The leading DR programmes
load for wind energy [coc11]. in the USA can generally be classified into two
categories: dispatchable programmes and reactive
2) Demand-side balancing services
programmes [mit11].
Fast-acting DR can be deployed to help balance
generation and load in real time. Loads can be a) Dispatchable programmes, also known as
aggregated and directed to respond very quickly load management or control programmes, allow
and therefore be capable of following the fast direct control of load responses by the grid operator
ramps of RE generation, reducing the need for or a third-party aggregator. An incentive is often
ramping capability from conventional generation offered to customers in return for participation.
[ded10]. Some system operators are already using b) Reactive programmes rely on customers’
DR to counter down-ramps of RE generation, voluntary responses to a variety of signals
showing flexibility potentially equal to conventional communicated to them. The most common signal
generation options. But different types of load used at present is price, although other types of
have different response capabilities and different information, such as environmental signals or
costs of response, and more research is needed neighbourhood-comparative data, may prove
to identify the true aggregate value and capability useful in the future. Reactive programmes can
of DR in this area [ner09]. further be divided into wholesale programmes
administered by independent system operators
(ISOs) and regional transmission organizations
4.6.2 Demand response practices and (RTOs), and retail programmes that present
trends customers with retail prices carefully determined
The practices of DR vary not only among by specific time-varying pricing structures.
different countries due to differences in electricity Each of the dispatchable, wholesale and retail reactive
markets, technological development and goals programme categories consists of several types of
for deploying DR, but also inside the boundaries programmes, as shown in Figure 4-16. According to
(Dispatchable programmes)
Emergency payment programmes (25 %)
Load control
programmes Interruptible tariff programmes (20 %)
(62 %)
Direct load control programs (17 %)
Capacity market programmes
Demand Wholesale
programmes Energy price programmes
response (27 %)
Ancillary service programmes
Critical peak pricing programmes
Retail
programmes Peak time rebate programmes
(8 % )
Real-time pricing programmes
(Reactive programmes) Time-of-use prices programmes
70
Future: technical solutions for integrating more large-capacity RE
Emergency Real-time
Daily use
use use Frequency
Demand of calling
response
Large Small customers
customers (with aggregators) Participants
Downward Downward or
only upward Direction
a recent survey [adr11], they respectively contributed directions: from downwards, reducing load only, to
to approximately 62 %, 27 % and 8 % of the nation’s both upwards and downwards, either increasing or
potential peak load reduction (aggregate load reducing load as required.
enrolled in DR programmes). Although dispatchable
1) DR for improving system reliability
programmes still represent a high proportion of
The earliest and most commonly practiced DR
enrolment, the advent of smart metres, which allow
focuses on system reliability. A customer, often
for two-way information flows between customers
a large industrial facility, agrees to reduce load to
and utilities, has enabled the growth of reactive
guarantee system reliability under peak demand
programmes and increased engagement with
conditions or other emergency system events,
residential and commercial customers.
and is paid an incentive for doing so. Since
From the practices in the USA some trends in they are designed for emergency use, these DR
DR development can be identified, as illustrated programmes are infrequently called upon.
in Figure 4-17. The objective of deploying DR
2) DR for improving system effi ciency
has been to go further than simply improving
system reliability, and extend towards improving More recently the focus of DR has been increas-
system efficiency and then system flexibility. The ingly placed on system efficiency. Many DR pro-
frequency with which DR is called upon has been grammes have begun to focus on non-crisis peak
extending from emergency use to daily use and shaving – flattening load curves to improve the
further to real-time use. The participants in DR efficiency of long-term power system capacity use,
have been extending from large industrial and since the generation, transmission and distribution
commercial customers to smaller commercial capacity of a power system is sized to meet the
and residential customers, with more aggregators expected peak demand.
acting as intermediaries between utility or grid 3) DR for improving system fl exibility
operators and individual customers. Finally, DR This emerging application of DR is very important
has been extending from one direction to both for supporting RE integration, as mentioned in
71
Future: technical solutions for integrating more large-capacity RE
72
Future: technical solutions for integrating more large-capacity RE
73
Section 5
Application of large-capacity EES to support
RE integration
75
Application of large-capacity EES to support RE integration
Figure 5-1 | Comparison of rated power, energy content and discharge time of different EES
technologies [msb11]
Short discharge time resources discharge for Medium-to-long discharge time resources
seconds or minutes, and have an energy-to-power discharge for hours to days, and have energy-to-
ratio (kWh/kW) of less than 1. Examples include power ratios of between 5 and 30. They include
double layer capacitors (DLCs), superconducting pumped hydro storage (PHS), compressed air
magnetic energy storage (SMES), and flywheels energy storage (CAES), and redox flow batteries
(FES). These resources can provide instantaneous (RFBs). RFBs are particularly flexible in their design,
frequency regulation services to the grid that as designers may independently scale the battery’s
mitigate the impact of RE’s uncontrollable variability. power density and energy density by adjusting the
size of the cell stacks or the volume of electrolytes,
Medium discharge time resources discharge for
respectively. Technologies in this category are
minutes to hours, and have an energy-to-power ratio
useful primarily for load-following and time-shifting,
of between 1 and 10. This category is dominated by
and can assist RE integration by hedging against
batteries, namely lead acid (LA), lithium ion (Li-ion),
weather uncertainties and solving diurnal mismatch
and sodium sulphur (NaS), though flywheels may
of wind generation and peak loads.
also be used. Medium discharge time resources
are useful for power quality and reliability, power Long discharge time resources may discharge for
balancing and load-following, reserves, consumer- days to months, and have energy-to-power ratios
side time-shifting, and generation-side output of over 10. They include hydrogen and synthetic
smoothing. Moreover, specific batteries may be natural gas (SNG). Technologies in this category
designed so as to optimize for power density or are thought to be useful for seasonal time-shifting,
energy density. As such, they are relevant to both the and due to their expense and inefficiency will likely
uncontrollable variability and partial unpredictability see deployment only when RE penetrations are
that RE generation brings to the grid. very large. For example, large amounts of solar
power on the grid will produce large amounts of
energy in the summer months, but significantly
76
Application of large-capacity EES to support RE integration
less in the winter. Storing excess generation in the operator’s is not the only perspective that is
summer as hydrogen or SNG and converting it important or relevant. Individual RE generators or
back to electricity in the winter would allow a time- plants facing specific incentive policies or isolated
shift of generation from one season to the next. grids may find it in their best interests to co-locate
Such technologies can assist RE integration in the generation and storage to level output prior to grid
long term by deferring the need for transmission integration. On the demand side, expanded use of
expansion and interconnection that arises due to electric vehicles may provide substantial aggregate
the locational dependency of renewable resources. energy storage to the grid even if the storage
resource itself appears sub-optimal to the grid
operator. We avoid making any specific judgments
5.3 Roles of EES in RE integration or predictions about exactly what the distribution
5.3.1 Grid-side roles of EES of uses will or ought to be for EES in assisting RE
integration, and instead simply present all of the
The widest range of uses for EES lies in services to
potential uses from a variety of perspectives. The
the grid operator in providing generation flexibility.
actual use of EES in various countries in the future
These services also represent – from the grid
will vary significantly depending on government
operator’s perspective – the optimal use of storage
policies, utility strategies, social and cultural
as a tool to mitigate variability and uncertainty
factors, and the peculiarities of each particular
for an entire grid, rather than for specific loads or
grid.
generation assets. The optimality arises from the
fact that integration of large amounts of wind and Table 5-1 describes various grid-side roles of
solar energy over large geographic areas results energy storage and their relevance to large-
in lower net variability and output uncertainty than capacity RE integration challenges, along with
the integration of a single RE plant, and so the some examples of EES technologies currently
need for services overall is reduced. in use. These examples are impressionistic: the
suitability of an EES technology for a particular use
Nevertheless, it is simplistic to expect that this will
is highly context-dependent and will vary according
be the only use of energy storage for RE integration
to the needs of the grid operator and the specific
that emerges in future grids. Indeed, the grid
design of the EES.
77
Application of large-capacity EES to support RE integration
1) Grid-side EES case study: The national the Ministry of Science and Technology, the
wind power, solar power, energy storage National Energy Bureau and SGCC. The project is
and transmission demonstration project, located in North Zhangjiakou. The wind and solar
Zhangbei, China resources are rich, but the local load is small and
The national wind power, solar power, energy the installation is far away from the Beijing-Tianjin-
storage and transmission demonstration project Tangshan load centre. Thus the energy must be
is co-sponsored by the Ministry of Finance, transmitted to the load centre by a high-voltage
and long-distance transmission network. This
78
Application of large-capacity EES to support RE integration
project exemplifies the basic characteristics of RE regulation. The storage system has contributed to
development in China, and is a typical project for making the wind farm and PV station more grid-
studying the problem of accommodating large- friendly.
scale renewable power.
2) Grid-side EES case study: Battery storage
The planned capacity of the project is 500 MW in Southern China
wind power, 100 MW PV power and 110 MW A demonstration lithium iron phosphate battery
energy storage. Phase I of the project, which was storage station has been built in Shenzhen for
completed in 2011, consists of 100 MW wind power, both commercial and research purposes. The
40 MW PV power and 20 MW energy storage. In storage station was planned to have a capacity
order to test the performance of different types of of 10 MW/40 MWh, divided equally into two
battery storage, three types of battery storage are phases. 4 MW/16 MWh of the phase I project has
used in the 20 MW energy storage station: 14 MW already been put into operation, and of the rest
of lithium iron phosphate (LiFePO4, LFP) batteries, 1 MW/4 MWh will be installed in 2012. It is managed
4 MW of NaS batteries and 2 MW of vanadium by the Peak/Frequency Regulation and Generation
redox flow batteries (VRFBs). Company, a subordinate company of the China
The architecture of the phase I project is shown in Southern Power Grid (CSPG) which is responsible
Figure 5-2. Through a panoramic intelligent optimal for the construction, operation, maintenance and
control system, panoramic monitoring, intelligent management of the peak/frequency regulating
optimization, comprehensive control and smooth power plants in CSPG, including several hydro
mode-switching between wind, solar and storage, power plants and all pumped-hydro storage power
the project has met targets of output smoothing, plants.
schedule following, load levelling and frequency
220 kV Smart
Strong smart grid
substation
Legends:
AC 220 kV
Storage
AC 35 kV
Solar
Control signal Wind +solar
AC 35 kV 7 operation modes of
Wind
wind-solar-storage
combination
Wind +storage
Wind +solar +
storage
AC AC Two-way Solar+storage
DC DC conversion
Figure 5-2 | Architecture of the national wind power, solar power, energy storage and
transmission demonstration project, Phase I (SGCC)
79
Application of large-capacity EES to support RE integration
Battery units are connected at the 10 kV bus of the dispatch centre or a fixed curve for load levelling,
110 kV Biling substation via 10/0.4 kV transformers, or participate in advanced regulation and backup
as shown in Figure 5-3. A battery unit consists services. For example, the load forecast curve at
of battery, power conversion system (PCS) and the Biling substation of one day with and without
battery management system (BMS). The storage load shifting by the storage station is shown in
station can work in several modes. It can adjust its Figure 5-4.
output according to a scheduled curve given by the
10 kV
Storage Unit Storage Unit Storage Unit Storage Unit Storage Unit Storage Unit
(PCS (PCS (PCS (PCS (PCS (PCS
Battery Battery Battery Battery Battery Battery
BMS) BMS) BMS) BMS) BMS) BMS)
50
45
35
Power
Load forecast after
(MW) 30
load shifting
25
20
0
10 0
0
18 0
0
22 0
0
:0
:0
:0
:0
:0
:0
:0
:0
:0
:0
:0
:0
0
12
14
16
20
Time
Figure 5-4 | A daily load forecast curve at the Biling substation with/without storage (BYD)
80
Application of large-capacity EES to support RE integration
3) Grid-side EES case study: Multi- a large generator fails in an off-peak period, the
application use of pumped hydro storage PHS’s load from pumping may be immediately
in Taiwan shed to stabilize system frequency [rvp08].
Though PHS is historically associated with time-
shifting, newer units offer a considerably expanded
5.3.2 Generation-side roles of EES
range of operation, including the use of PHS for
operating reserves such as frequency regulation Operators of RE generation plants may use energy
and spinning reserves. The Taiwan Power System, storage technologies to assist in the integration
for example, contains ten PHS units: four 250 MW of a particular plant, or of several plants that feed
units located at the Ming-Hu hydro plant and six into the same substation. Using the terminology of
267 MW units located at the Ming-Tan hydro plant. section 4, EES used in this fashion serves to improve
the grid-friendliness of RE generation itself. It is
Because Taiwan’s grid is isolated, it must guarantee
important to understand that generation-side use
sufficient operating reserves to maintain system
of energy storage is not simply a shift in ownership
frequency without load-shedding in the event of
of the storage resource, but an entirely different role
the failure of its largest generating unit. In Taiwan’s
for storage from that envisioned by grid-side use of
case, this largest unit is 950 MW, a substantial
EES. Rather than using EES as a tool to balance
portion of Taiwan’s 34 630 MW of capacity. Taiwan
an entire power grid, an RE generation plant
thus uses PHS units in daily operations for both
may use EES to provide integration applications
time-shifting and operating reserve functions
prior to grid integration, either at the plant or
simultaneously. During peak demand periods,
substation level. While the technical requirements
the PHS units are operated in generating mode,
of generation-side EES applications are similar to
supplying both frequency regulation through
those of grid-side EES, greater flexibility is required
automatic generation control of the turbine speed
of generation side EES facilities, because a single
and a reduction in system operating costs by
RE plant exhibits greater variability and uncertainty
replacing peaking generators. During off-peak
than many RE plants aggregated on the same
periods, PHS units operate in pumping mode to
grid. This means that dedicating EES facilities to
consume surplus energy, and also offer emergency
specific RE generation results in proportionately
reserves by way of PHS load-shedding. That is, if
higher costs than using EES to balance net
variability and uncertainty on the grid. For isolated
and geographically-constrained grids, however,
co-location of RE generation and EES may be an
attractive option, as balancing such grids through
interregional trading, conventional backup capacity
or demand-side management is more challenging
than for larger and more interconnected grids.
81
Application of large-capacity EES to support RE integration
in effectively utilizing limited transmission capacity, Output smoothing/fl attening. Even when
particularly where the RE generation is located on RE generation is producing energy at a time
an isolated or weak grid. Generation-side uses of when it is needed, the EES resource may be
EES include: used to smooth out fluctuations in frequency
Time shifting. The dedicated energy storage and voltage that result from the inherently
facility stores energy whenever its generator variable nature of RE generation. Smoothing
produces it, and stands ready to dispatch functions require ramping capability – the ability
energy to the grid when needed. This can to rapidly change power output or uptake in
make RE output both predictable to grid order to regulate the output of the RE plant.
operators and co-temporal to demand. Time When RE output spikes, the EES technology
shifting functions require EES facilities to must be capable of storing the excess energy
store large quantities of energy for significant quickly. Conversely, when output suddenly
periods of time, from hours to days. NaS drops, the storage system must be able
batteries exemplify the qualities needed for to release energy quickly to provide extra
this function: they may store relatively large power, keeping the plant output stable. The
amounts of energy efficiently for hours at necessary function of storage facilities varies
a time as well as ramp quickly, as shown in according to the requirements. In some cases
Figure 5-6. Storage efficiency is very important just smoothing output is satisfactory, but in
for economical operation of time shifting, as other cases output is required to be kept at
an inefficient storage facility will lose significant the fixed values. Output smoothing at the plant
portions of the energy it time-shifts. Efficiency level reduces the need for power quality and
varies greatly by EES technology and also by ancillary services on the grid itself.
the operation profile, as is covered in detail in Transmission utilization effi ciency.
the MSB EES Report. Because RE generation is location-dependent,
sufficient transmission may not be available
100
Lead-acid battery
10
82
Application of large-capacity EES to support RE integration
to move energy to loads. It is often the case NAS Battery Hybrid System” (see Figures 5-7 and
that transmission may be available, but it 5-8). This plant consists of 51 MW (1 500 kW ×
may be heavily congested. Generation-side 34 units) of wind turbines and 34 MW (2 000 kW
EES resources may allow for more efficient × 17 units) of NAS batteries. The NAS battery
use of transmission capacity by allowing application regulates the output of the plant to
an RE generation facility to wait to use the produce more electricity during high demand
transmission line until congestion has cleared. (price) periods, and less during low demand (price)
periods. Output can also be reduced when system
1) Case study of EES support of RE plant
conditions require. JWD has operated its wind and
integration in Japan
EES technologies in combination according to plan
In 2008, Japan Wind Development Co. (JWD)
for 3 years.
began operating the first commercial “Wind and
Figure 5-7 | JWD’s wind and NAS battery hybrid system in Japan (NGK)
Wind power
Flat operation
Smoothing and energy
Shifting a firm capacity to higher demand period
shifting by NAS
Solar power
PV output
Power
Energy shift
83
Application of large-capacity EES to support RE integration
Figure 5-9 | Bornholm’s distribution grid and power plant locations [evf10]
84
Application of large-capacity EES to support RE integration
architecture. One of the more robust and RE- Those proportions, in turn, depend on the
integration relevant modelling efforts is located on generation profiles and interconnection status of
the Danish island of Bornholm, which relies heavily electricity grids, which will change substantially
on wind turbines with 30 MW of wind capacity that over the coming decades.
services 22 % of the island’s load. The EDISON
Because an EES technology can draw on a
project on Bornholm aims to coordinate charging
number of value streams which themselves
and discharging of EVs so as to optimize utilization
may be met by other means, there is a need for
of wind energy on the island’s grid. Successfully
optimization of storage placement and use within
implementing V2G functionality so as to support
the context of the power system as a whole, both
grid integration of RE will require a host of new
today and into the future. Research on storage
standards and grid codes [evf10] [gcr09].
optimization is already under way, but there is
relatively little convergence or organization of
results at the moment. In 2009 alone, over 500
5.4 Technology needs of large-
published articles applied optimization algorithms
capacity EES applications
to RE in some way, but a review of the literature
The interconnection and facility management needs demonstrates the experimental and highly varied
of EES technologies are discussed at length in the topics and approaches of the researchers [oma11].
MSB EES Report, and these needs do not change An “optimal” optimization strategy that is ready for
considerably when EES is used to support RE global, commercial-scale use has yet to emerge for
integration. Consequently, we do not cover those low-carbon energy system planning.
issues again here. Rather, this section focuses
In addition to their present lack of convergence,
on a larger-scale inquiry as to the role of EES in
an impressionistic review of several popular
assisting RE integration on a specific electricity
storage-specific optimization studies reveals a
grid. That is, how can a prospective operator of
focus on optimizing economic dispatch decisions
an EES facility – be it grid-side, generation-side,
for a specific type of storage facility on a known
or demand-side VPP – determine whether and
grid configuration, often a simplified or isolated
how to design, place and utilize the facility? What
grid [ede10] [mlt10] [ops08] [sco12] [vce03]. These
type of storage to install, and with what capacity,
studies treat the installation of an EES facility as
depends on how that storage will be used. How
an a priori decision. In other words, they assume
it is used depends on where it is located and the
a storage facility, and then go about determining
specifics of the power system that it serves. Where
its optimal operation. This is not to say that such
it is located depends on both what type of storage
optimization studies are not necessary and useful
is being installed and on the siting of other future
– they are most certainly both, particularly to grid
generation.
operators working with existing or planned EES
EES technologies tend to be flexible; they can facilities.
provide multiple services within a number of
But there is a need for peer-reviewed, consensus-
time scales, as explained above. A PHS plant
supported optimization tools at a higher level of
with a variable-speed turbine, for example, may
abstraction. Such tools could provide commercial-
participate in both time-shifting functions and
level decision support for the planning of storage
frequency regulation. Its design specifications
on the grid at a pre-installation stage from a more
are likely to change depending on the proportion
global perspective, and across larger time scales.
of operations that fall under time-shifting and the
Indeed, when considering the long-term needs of
proportion of operations that fall under regulation.
global electricity grids as they accommodate ever-
85
Application of large-capacity EES to support RE integration
increasing penetrations of variable RE, the decision improving the grid-friendliness of RE generation
of when and where to place certain kinds of energy itself through increasing generation flexibility to
storage in the first place is a primary question. providing demand response from electric vehicles.
The HOMER optimization model for distributed These represent the near-term uses of energy
power, which allows a user to evaluate economic storage as one means among many of providing
and technical feasibility for a wide range of remote, system flexibility. In the medium term, energy
stand-alone and distributed generation applications, storage may allow, through both balancing and
represents a potential starting point for developing time-shifting functions, for more effective and full
such tools [hey12]. utilization of transmission lines and thus assist in
Based on the topics discussed throughout this transmission expansion and siting to RE resource
paper, an EES planning and decision tool for areas. In the longer term, energy storage may
utilities and facility developers might consider the influence energy system planning in unique and
following factors, both at present and in future profound ways. Large-scale, long-term energy
scenarios: storage such as hydrogen and synthetic natural
gas may provide a means of storing seasonally-
amounts and net variability of RE generation
produced RE for months or years and thus
on the grid;
serve the need for dispatchable and controllable
interconnectivity of the grid to other grids, and generation that is currently met through fossil fuels.
balancing capabilities between them; The cost of such storage is currently considered
prohibitively expensive and the energy penalties too
conventional backup capacity available and
high by many system operators and governments.
desirable;
Advances in technology and shifts in the politics
demand-side management applications and of energy may be necessary before such a future
capabilities; becomes likely.
system costs or market prices for operating
reserves, power quality services, and balancing
energy;
5.5 Summary
EES may serve as a source of flexibility for the
integration of RE in a wide variety of ways, from
86
Section 6
Standards for large-capacity RE integration
87
Standards for large-capacity RE integration
Table 6-1 | Some wind power plant interconnection standards in some major countries
Numbering or
Country Issued by/in Title
version
Brazilian Grid Codes
ONS/2008
(Procedimentos de Rede)
Brazil
Guidelines for wind power generation expansion
EPE/2009
in Brazil
Transmission system interconnection
Manitoba Hydro/2009 Version 2
requirements
Transmission provider requirements for the
Hydro-Québec/2009 connection of power plants to the Hydro-Québec
transmission system
Canada
60 kV to 500 kV technical interconnection
BCTC/2008 Revision 0
requirements for power generators
CanWEA/2006 CanWEA base code
AESO Alberta/2004 Revision 0 Wind power facility technical requirements
Technical regulation for the properties and the
Elkraft System and
Denmark Regulation TF 3.2.5 regulation of wind turbines connected to grids
Eltra/2004
with voltages above 100 kV
Germany E.ON Netz/2006 Grid code high and extra high voltage
88
Standards for large-capacity RE integration
Table 6-2 | Major integration standards for wind and PV power in China
GB/Z 19963-2005) in China, which was issued at (e.g. E.ON Netz in Germany) also require wind
the end of 2011 and entered into force on 1 June power plants to provide reactive power during a
2012, also sets out requirements on the number fault period to help system voltage recovery.
of circuits connecting power plants to the grid,
generation forecast and report, configuration
of reactive power compensation, provision of 6.3 Future needs
simulation models and parameters, communication In order to support the integration of more large-
with the grid operator, and provision of field test capacity RE generation, much standardization
reports. To take the low-voltage ride-through effort is needed. Since it would not be useful to
requirement as a specific example, Figure 6-1 discuss detailed technical requirements here,
shows the differences among major countries some important general considerations are given
or grid companies. In addition to the LVRT below.
requirement, some countries or grid companies
89
Standards for large-capacity RE integration
1.0
0.8
0.6
0.4
0.2
0.0
-0.2
-0.2 0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8 3.0 3.2 3.4
Time (s)
ELTRA & ELKRAFT E.ON Type 1 FERC REE China
Figure 6-1 | Differences in LVRT requirements in major countries or grid companies (SGCC)
90
Standards for large-capacity RE integration
91
Section 7
Conclusions and recommendations
93
Conclusions and recommendations
Recommendations 8.2.1, 8.2.3, 8.2.4 and 8.2.9 renewables may be encouraged rather than
from the MSB EEE Report. obstructed by regulations. In particular regulators
should encourage the implementation of larger
Recommendation 7.2.1 – Coordinating all balancing areas (fully-connected grids under
actors central control), without neglecting local power
quality, so as to enable the concerted operators
Since integrating large-scale RE requires many
to reduce average variability in generation. They
actions – at different timescales, levels of control
should also set up stable and predictable financial
and points in the generation life cycle – and the
incentives which make the best technical and
tools and infrastructure must be provided by
public-policy solutions simultaneously the most
many actors both public and private, the IEC
attractive ones financially.
recommends governments and intergovernmental
organizations to take responsibility for uniting all
the relevant stakeholders in a single effort to set 7.3 Recommendations addressed
the rules, develop the standards and take the to utilities, industry and
decisions needed. research
94
Conclusions and recommendations
95
References
[aba11] Richard Piwko, et al.: A Blast of Activity: Wind Power at the IEEE Power & Energy Society, IEEE
Power & Energy Magazine, 9(6), p26-35, Nov/Dec 2011.
[adr11] Federal Energy Regulatory Commission: 2010 Assessment of Demand Response and Advanced
Metering, p21, Staff Report, Feb 2011.
[atp11] Mark Ahlstrom, et al.: Atmospheric Pressure: Weather, Wind Forecasting, and Energy Market
Operations, IEEE Power & Energy Magazine, 9(6), p97-107, Nov/Dec 2011.
[bac11] Mark G. Lauby, et al.: Balancing Act: NERC’s Integration of Variable Generation Task Force
Plans for a Less Predictable Future, IEEE Power & Energy Magazine, 9(6), p75-85, Nov/Dec
2011.
[coc11] Hannele Holttinen, et al.: Currents of Change: European Experience and Perspectives with High
Wind Penetration Levels, IEEE Power & Energy Magazine, 9(6), p47-59, Nov/Dec 2011.
[cvw11] Task Force on the Capacity Value of Wind Power, IEEE Power and Energy Society, et al.:
Capacity Value of Wind Power, IEEE Transactions on Power Systems, 26(2), p564-572, May
2011.
[ded10] Alec Brooks, et al.: Demand Dispatch: Using Real-Time Control of Demand to Help Balance
Generation and Load, IEEE Power & Energy Magazine, 8(3), p20-29, May/June 2010.
[des10] Scott Coe, et al.: Demanding Standards: Developing Uniformity in Wholesale Demand Response
Communications to Enhance Industry Growth, IEEE Power & Energy Magazine, 8(3), p55-59,
May/June 2010.
[dlr05] German Aerospace Center, et al: Concentrating Solar Power for the Mediterranean Region,
Report, April 2005.
[ede10] S. You, et al.: Economic Dispatch of Electric Energy Storage with Multi-service Provision, IPEC
2010.
[eis11] Douglas Todd: Managing Large-Scale Penetration of Intermittent Renewables, MITEI Symposium
on Managing Large-Scale Penetration of Intermittent Renewables, Cambridge/U.S.A, 20 April
2011.
[epa10] European Photovoltaic Association: Global Market Outlook for Photovoltaics until 2014, Report,
May 2010.
[ern11] Ernst Scholtz: Grid Integration of Renewables: Challenges and Technologies, MITEI Symposium
on Managing Large-Scale Penetration of Intermittent Renewables, Cambridge/U.S.A, 20 April
2011.
97
References
[esp10] Gobierno de España: Spain's National Renewable Energy Action Plan, Report, 2010.
[ete11] Yi Zhang, et al.: Overview of the Practice of Renewable Generation Integration and Transmission
Planning in North America, Energy Technology and Economics, 2011, 23(8), p1-7, 23, in Chinese.
[evf10] C. Binding, et al.: Electric Vehicle Fleet Integration in the Danish EDISON Project – A Virtual
Power Plant on the Island of Bornholm, IBM Research Report RZ 3761 (2010) # 99771.
[ewe05] The European Wind Energy Association: Large Scale Integration of Wind Energy in The European
Power Supply: Analysis, Issues and Recommendations, Report, Dec 2005.
[ewe11] The European Wind Energy Association: Wind in Our Sails: The coming of Europe’s Offshore
Wind Energy Industry, Report, 2011.
[fat11] Aidan Tuohy, et al. Flexibility Assessment Tool: IEA Grid Integration of Variable Renewables
Project, IEEE Power & Energy Society General Meeting Power System Flexibility Panel, 2011.
[gcr09] EDISON Consortium: Report: WP2.7 Grid Codes and Regulation Related to EVs, Report, 2009.
[ger10] Federal Republic of Germany: National Renewable Energy Action Plan in accordance with
Directive 2009/28/EC on the promotion of the use of energy from renewable sources, Report,
2010.
[gwe10] Global Wind Energy Council: Global Wind Energy Outlook 2010, Report, October 2010.
[haw06] D. Hawkins, et al.: Evolving Role of Wind Forecasting in Market Operation at the CAISO, Power
Systems Conference and Exposition, pp. 234-238, Atlanta/U.S.A, 29 October-1 November
2006.
[hol09] H. Hollttinen, et al. Design and operation of power systems with large amounts of wind power,
Final report, IEA Wind Task 25, 2009.
[hsh12] Hong Shen: Transmission of large scale wind power in China. IEC Workshop on Grid Integration
of Large-capacity Renewable Energy and Large-capacity Energy Storage, University of Colorado
at Boulder, March 2012.
[hts09] Benjamin Kroposki, et al. Harnessing the Sun: An Overview of Solar Technologies, IEEE Power
& Energy Magazine, 7(3), p22-33, May/June 2009.
[iea09] S. Inage: Prospects for Large-Scale Energy Storage in Decarbonized Power Grids, International
Energy Agency Working Paper, 2009.
[iea11] Adam Brown, et al: Renewable Energy: Markets and Prospects by Technology, International
Energy Agency Information Paper, 2011.
[iig12] Chen-Ching Liu, et al.: Intruders in the Grid: Cyber-vulnerability and Mitigation Studies Using a
SCADA Test Bed. IEEE Power & Energy Magazine, 10(1), p58-66, Jan/Feb 2012.
98
References
[jef11] Jeff St. John: Is Europe Ready for Automated Demand Response?, Greentechmedia, 7 Oct 2011.
[mei10] P. Meibom, et al.: Advanced Unit Commitment Strategies in the United States Eastern
Interconnection, 9th Annual International Workshop on Large-Scale Integration of Wind Power
into Power Systems as well as on Transmission Networks for Offshore Wind Power Plants,
Quebec/Canada, 18-19 October 2010.
[mev09] M. Caramanis, et al.: Management of Electric Vehicle Charging to Mitigate Renewable Generation
Intermittency and Distribution Network Congestion, Joint 48th IEEE Conference on Decision
and Control and 28th Chinese Control Conference, 2009.
[mfc11] Robert Zavadil, et al. Models for Change: Ensuring System Reliability in the Age of Large Wind
Power Plants, IEEE Power & Energy Magazine, 9(6), p88-90, Nov/Dec 2011.
[mit11] Massachusetts Institute of Technology: The Future of The Electric Grid, Report, 2011.
[mlt10] G. Corso: Multi-objective long term optimal dispatch of Distributed Energy Resources in micro-
grids, UPEC 2010.
[mma11] Abraham Ellis, et al.: Model Makers: Simulating PV Systems in Transmission and Distribution
Planning, IEEE Power & Energy Magazine, 9(3), p55-61, May/June 2011.
[msb10] International Electrotechnical Commission Market Strategy Board: Coping with the Energy
Challenge: The IEC’s role from 2010 to 2030, White Paper, September 2010.
[msb11] International Electrotechnical Commission Market Strategy Board: Electrical Energy Storage,
White Paper, December 2011.
[ner09] North American Electric Reliability Corporation, Integration of Variable Generation Task Force:
Accommodating High Levels of Variable Generation, Report, April 2009.
[ner10] North American Electric Reliability Corporation, Integration of Variable Generation Task Force:
Flexibility Requirements and Metrics for Variable Generation, Report, Aug 2010.
[npg10] Northwest Power Grid, State Grid Corporation of China: Power Demand Forecast, Power and
Electricity Balancing, and Load Following Capability Analysis of the Northwest Power Grid in the
12th Five-year Plan Period, Report, 2010, in Chinese.
[obo12] 1BOG Blog, How Solar Feed-in Tariffs (FiTs) Work, http://solarfinancing.1bog.org/feed-in-tariffs/,
Accessed 13 Feb 2012.
[oma11] R. Banos, et al.: Optimization methods applied to renewable and sustainable energy: A Review,
Renewable and Sustainable Energy Reviews 15 (2011) p1753-1766.
[opp11] North American Electric Reliability Corporation, Integration of Variable Generation Task Force:
Operating Practices, Procedures, and Tools, Report, Mar 2011.
[ops08] P.D. Brown: Optimization of Pumped Storage Capacity in an Isolated Power System with Large
Renewable Penetration, IEEE Transactions on Power Systems 23 (2008), p523-531.
[pao11] John H Kehler, et al.: Planning and Operational Considerations for Power System Flexibility,
IEEE PES General Meeting Power System Flexibility Panel, 2011.
[pei12] Richard Piwko, et al.: Penetrating Insights: Lessons Learned from Large-Scale Wind Power
Integration, IEEE Power & Energy Magazine, 10(2), p44-52, Mar/Apr 2012.
99
References
[pts11] Wenuan Li: Probabilistic Transmission System Planning, Book, IEEE-Press, 2011.
[rep11] Renewable Energy Policy Network for the 21st Century: Renewables 2011 Global Status Report,
Report, July 2011.
[rvp08] C.C. Wu, et al.: Role and Value of Pumped Storage Units in an Ancillary Services Market for
Isolated Power Systems – Simulation in the Taiwan Power System, IEEE Transactions of Industry
Applications, 44(6), Nov/Dec 2008.
[sad11] Lawrence E. Jones: Strategies and Decision Support System for Integrating Variable Resources
in Control Centers for Reliable Grid Operations: Global Best Practices, Examples of Excellence
and Lessons Learned, Report, Alstom Grid Inc., 2011.
[sco12] J. Hill, et al.: System constraints on optimal dispatch schedule for battery storage systems, IEEE
PES Innovative Smart Grid Technologies 2012.
[sgc11] State Grid Corporation of China: Promoting Wind Power Development in China, White Paper,
Apr 2011.
[sge11] State Grid Energy Research Institute, Vestas Wind Energy Technology (China): Integrated Solution
Strategies for Coordinated Wind Power and Grid Development-International Experiences and
China Practices, Report, Oct 2011.
[sic12] Julie Hull, et al.: Staying in control: Cybersecurity and the Modern Electric Grid, IEEE Power &
Energy Magazine, 10(1), p41-48, Jan/Feb 2012.
[sin12] Ivan M. Dudurych, et al.: Safety in Numbers: Online Security Analysis of Power Grids with High
Wind Penetration, IEEE Power & Energy Magazine, 10(2), p62-70, Mar/Apr 2012.
[smp11] J. Smith, B. Parsons: Wind Integration: Much Has Changed in Two Years, IEEE Power &Energy
Magazine, 9(6), p18-25, Nov/Dec 2011.
[sra12] North American Electric Reliability Corporation, Integration of Variable Generation Task Force:
Special Reliability Assessment: Interconnection Requirements for Variable Generation, Report,
Mar 2012.
[tea07] Mukhopadhyay S.: Towards electricity for all: transmission planning for the growth of India's
power system, IEEE Power & Energy Magazine, 5(3), p71-78, May/June 2007.
100
References
[tec10] C. Quinn, D. Zimmerle, T.H. Bradley: The effect of communication architecture on the availability,
reliability, and economics of plug-in hybrid electric vehicle-to-grid ancillary services, Journal of
Power Sciences 195 (2010), p1500-1509.
[tgs12] Mark Reynolds, et al.: The Golden Spike: Advanced Power Electronics Enables Renewable
Development Across NERC Regions, IEEE Power & Energy Magazine, 10(2), p71-78, Mar/Apr
2012.
[top12] Daniel E. Nordell: Terms of Protection: The Many Faces of Smart Grid Security, IEEE Power &
Energy Magazine, 10(1), p18-23, Jan/Feb 2012.
[tpd11] State Grid Corporation of China: Typical Design of Wind Farm Electrical Systems. China Electric
Power Press, 2011, Book in Chinese.
[tre10] P. Denholm, E. Ela, B. Kirby, M. Milligan: The Role of Energy Storage with Renewable Electricity
Generation, U.S. National Renewable Energy Laboratory Technical Report NREL/TP-6A2-47187,
Report, 2010.
[trp11] Eamonn Lannoye, et al.: The Role of Power System Flexibility in Generation Planning, IEEE PES
General Meeting Power System Flexibility Panel, 2011.
[uei10] The Union of the Electricity Industry: Integrating Intermittent Renewable Sources in the EU
Electricity System by 2020: Challenges and Solutions, Report, 2010.
[vce03] G. Bathurst, G. Strbac: Value of Combining Energy Storage and Wind in Short-term Energy and
Balancing Markets, Electric Power Systems Research 67 (2003), p1-8.
[vsc10] Guangfu Tang: VSC-HVDC Based High Voltage DC Transmission Technology, Book, China
Electric Power Press, 2010, in Chinese.
[wei11] Liping Jiang, et al. Wind Energy in China: Status and Prospects, IEEE Power & Energy Magazine,
9(6), p36-46, Nov/Dec 2011.
[weo11] International Energy Agency: World Energy Outlook 2011 © OECD/IEA 2011.
[yam11] M. Yamamoto, O. Ikki: Nation Survey Report of PV Power Applications in Japan, Report,
International Energy Agency, 17 June 2011.
101
Notes
ISBN 978-2-8322-0340-8
International
Electrotechnical
® Commission CHF 50.-
® Registered trademark of the International Electrotechnical Commission. Copyright © IEC, Geneva, Switzerland 2012.