Professional Documents
Culture Documents
AADE-03-NTCE-28 Process of Integrating Geomechanics With Well Design and Drilling Operation
AADE-03-NTCE-28 Process of Integrating Geomechanics With Well Design and Drilling Operation
This paper was prepared for presentation at the AADE 2003 National Technology Conference “Practical Solutions for Drilling Challenges”, held at the Radisson Astrodome Houston, Texas, April 1 - 3,
2003 in Houston, Texas. This conference was hosted by the Houston Chapter of the American Association of Drilling Engineers. The information presented in this paper does not reflect any position,
claim or endorsement made or implied by the American Association of Drilling Engineers, their officers or members. Questions concerning the content of this paper should be directed to the individuals
listed as author/s of this work.
Schlumberger Private
This paper will present examples of how wellbore type.
stability parameters were used in well design, including To minimize the mechanical instability mud of the
casing seat selection and benefits of verifying actual right density should be determined in the pre-drill well
wellbore stability while drilling. bore stability analysis. The analysis contains: study of
the mechanical and elastic rock properties, rock
strength, identifying principal stress magnitudes and
Introduction
directions, and building a pore pressure model. Image
Oil and gas industry spends over one billion dollars a
and caliper logs in conjunction with cavings morphology
year for non-productive time and lost in hole costs.
are used to identify the failure mechanism. Combined
Significant part of it is taken by the kicks, mud losses,
with results of core analysis, along with geological and
excessive circulations, stuck pipe and other instability
basin knowledge, a deformation model can be chosen.
related events. Some events occur due to lack of
This model will best represent the rock behavior once
planning, which makes it unavoidable. Some events
the hole is drilled. Using the well inclination and azimuth
occur due to lack of execution that makes the events
the far-field principal stresses are converted into the
impossible to prevent and difficult to control.
stresses around the wellbore (Hoop stresses). This is
A major concern of drillers is pore pressure.
used to gain an understanding of the principal stresses
However, even normally pressured formations do not
at each point around the circumference of the borehole
imply trouble free drilling. In many cases there is a
with depth. A preferred failure criterion is then applied.
problem of keeping the wellbore stable, at which point
This calculation gives an indication of the minimum
the mud weight is constrained by the minimum stable
required mud weight to avoid certain modes of failure.
and fracture gradients. This minimizes the permissible
The two types of the rock failure presented on Figure 1
safe mud weight window and unawareness could cause
are tensile and compressional (or shear) failure. For
overpulls, hole-cleaning problems, pack offs, lost in hole
these failures to occur certain criteria should be met.
equipment and loss of circulation. This could lead to
Different modes of the failure are presented on
costly sidetracks or the loss of the wellbore. To avoid
Figure 2. The modes of failure highly depend on the mud
and manage the unstable borehole a good
weight pressure.
geomechanics well bore stability model must be
incorporated into the drilling plan with the means for
monitoring and updating.
This paper emphasizes the process of integrating
2 NIKOLAY Y. SMIRNOV, ROI LAM, / SCHLUMBERGER, W. E. (BILL) RAU III/ CHEVRONTEXACO AADE-03-NTCE-28
Geomechanics consideration within the drilling invaluable information of actual down hole conditions.
program The following down hole parameters are essential when
After the well has been drilled, the well bore stability identifying WBS issues:
analysis can give ideas on improving future operations. • DTOR/DWOB
To achieve this, a 3D Mechanical Earth Model (MEM) 4 • ESD/ECD
should be built. • Downhole vibrations (axial, lateral, torsional)
A full 3D MEM must encompass physical properties • Collar RPM
of the rock, pore pressures, in-situ stresses, drilling • LWD Data (Resistivity, Sonic, Density, GR,
mechanics and other parameters. Based on the3D MEM Caliper)
a well bore stability forecast for the planned well
trajectory can be developed. It helps to identify the most It has been shown that these and other down hole
efficient path to the targets. This includes the parameters provide a full picture of events occurring
identification of a stable trajectory, casing point down hole.
optimization, BHA and drill string design, mud weight
and hydraulics optimization. Knowledge of unstable Decision Point
depth intervals, and failure severity facilitates in After correctly interpreting all drilling mechanics and
establishing proper drilling practices and procedures. down hole parameters in conjunction with the real time
Understanding stability provides additional information to WBS model, the information must be compared to the
analyze drilling events, which allow the alteration of pre-drill model. Compliance between models assures
drilling and completion operations. predictability ahead of the bit. The drill team can
continue drilling with confidence. However, if the models
Real time WBS Management Process disagree, calibrations must be applied.
The real time WBS Management Process has been
developed for drilling. This combines interpretation of Calibration of Models
drilling mechanics and down hole measurements with The models are calibrated with interpreted real time
the WBS model. Refer to Figure 3. data time to reduce uncertainty. Each calibration
Schlumberger Private
reliably provides predictability in front of the bit.
WBS Model
All models have assumptions, which inherently cause Knowledge Capture, Change Drilling Program, Alter
uncertainty. The WBS Model is no exception. The Drilling Practices
information gained from the correct interpretation of A host of interpretations, drilling events and data
surface and down hole measurements is invaluable points are utilized for each calibration. This information
when reducing model uncertainty. The pre-drill model is very powerful and should be captured as lessons
must be combined with all possible information while learned for future projects.
drilling to realize its full power of predictability in front of At this point, the WBS model has been calibrated
the bit. using actual drilling data, which then provides
predictability ahead of the bit. However, if the Drilling
Interpretation of Drilling Mechanics Program and Drilling Practices do not change, the WBS
All drilling mechanics measurements must be correctly model’s power has been lost. The information provided
interpreted. The following is a common list of drilling by the calibrated WBS model can be used to push
mechanics parameters that need to be interpreted while casing seats, eliminate casing strings, extend reservoir
drilling: drainage, and ultimately increase production.
• On bottom torque/Off bottom torque The Real Time WBS Management Process is very
• Pick up weight/Slack off weight/Rotating effective if each step is followed. The step which is most
weights ignored is the Knowledge Capture, Change Drilling
• ROP Program, Alter Drilling Practices step. The principal
• Cutting Removal Index, Cuttings/Cavings cause of failure is linked to drilling culture. Company
morphology men, drilling engineers, and drilling superintendents
Vibration from surface measurements (best from high must be willing to change drilling programs and drilling
speed frequency data) practices based upon interpretation of while drilling data.
Experience has shown that correct interpretation of Communications with the entire drill team (G&G, Drilling
these parameters give important clues on the stability of Department, Company Men and Rig Crew) is also
the well bore. essential for this process to be successful.
Schlumberger Private
This case study is related to the sixth ERD and its hydraulics was estimated at 60 degrees. This means
geological sidetrack in the field A-21 and A-21 ST1. allowing failure of 60 degrees along the circumference of
the borehole symmetrically on each side. This limit is
Well design represented as MW60 on Figure 5. Please note that
Petronius ERD wells have common design parameters: once the failure of the borehole wall is initiated, there is
• Previously set 20” conductor pipe no predictive answer of how the breakout is going to
• 17 ½” hole with 13 3/8” casing (the build up behave. Therefore emphasis was made on realtime
section) ESD/ECDto be greater than failure initiation pressure.
• 12 ¼” hole (the tangent section) with 9 5/8” Drilling mechanics response was modeled and
casing, inclination varies for a maximum of optimized upon the stability prediction.
79 degrees and Torque and Drag analysis was conducted and
• 8 ½” hole with 7” liner (the reservoir section) theoretical profiles calibrated with the real time of pick up
and slack off weights data (Figure 6).
As the development progressed some modifications Limitations of the most essential rig equipment were
were applied such as drilling 8 ½” by 9 ¼” hole using bi- considered in the modeling for preventing and
centered bit on the rotary steerable. eliminating potential failure.
For this particular well it was identified that instability
Objectives and challenges will be met shallower due to trajectory and structural
Petronius platform is one of the world deepest fixed features. This drove the decision for the placement of
structures positioned in over 1,750 ft of water. It is the 13 3/8” casing. This avoided the risk of setting it
located at the frontier of shelf and deep water. Water shallow, leaving a big interval of 17 ½” hole open. This
depth varies around the platform from 700 ft to 3400 ft could have jeopardized the cement job and circulation
depending on the azimuth. On the way to the reservoir efficiencies of the next hole section.
dipping formations and low-pressure sands had to be It was established that A-21 original hole could be
drilled. completed with 12 ¼” size hole. In case the reserves will
Predrill analysis identified hole cleaning, excessive not be proven the sidetrack option will be exercised and
circulation time, tight hole, over-pulls, pack offs, tools 8 ½” by 9 ¼” hole drilled with the lower mud weight to
lost-in-hole and sidetracks as the main drilling problems. avoid losses in the weaker zones. The mud weights and
These issues are exasperated as inclination increased. initial drilling parameters were identified for the both
The increase in inclination narrows the safe mud weight original well and the sidetrack.
4 NIKOLAY Y. SMIRNOV, ROI LAM, / SCHLUMBERGER, W. E. (BILL) RAU III/ CHEVRONTEXACO AADE-03-NTCE-28
Schlumberger Private
out at around 15,000 ft MD operations were suspended RPM = Revolutions per minute
due to rough weather. . As a result, overpulls and ROP = drilling rate of penetration
formation packing off were experienced. These events TD=total depth
compelled the drill team to set the contingency casing at TVD=true vertical depth
this depth to isolate the trouble zone. However, the WBS = Well Bore Stability
updated WBS model along with real time drilling WOB = weight on bit
observations provided strong evidence not to exercise
the contingency option. The drill team debated this Acknowledgments
information and collectively decided to continue drilling. For help in preparation of this article authors thank
As a result, the original hole successfully reached TD. Craig Sidwell, Tom Bratton Schumbergeg,Houston TX,
The sidetrack was started from 19,000 ft MD of the US and Curt J. Tomlinson New Orleans, LA, US of
original hole. Using real time data the 9 5/8” casing point Schlumberger.
was adjusted. This prevented drilling into the loss
circulation zone with the higher mud weight. References
The minimum horizontal stress was used as the safe 1. Bratton, T., Edwards, S., Fuller, J.: “Avoiding Drilling
upper bound. However utilizing a full wellbore stability Problems,” Oilfield Review (Summer 2001) 32-51.
prediction allowed calculations of formation breakdown 2. Addis, T., Boulter, D., Last, N., Plumb, R.A.: “The Quest
pressure gradient based on the hoop stress theory. The for Borehole Stability in the Cusiana Feld, Colombia,”
Oilfield Review (Summer 1999) 33-43.
mud weight was adjusted for the 8 ½” by 9 ¼” section. 3. Aldred, W., Plumb, R.A., Cousins, L.: “Managing Drilling
No losses were observed in further drilling. Risk,” Oilfield Review (April/July 1993) 2-19.
4. Plumb, R.A., Edwards, S., Pidcock, G., Lee, D.: The
Results and Conclusions Mechanical Earth Model Concept and Its Application to
The fifth ERD well and its geological sidetrack were High-Risk Well Construction Projects”, IADC/SPE 59128
successfully drilled applying Real Time WBS 5. Bradford, I.D.R., Aldred, W.A., Cook, J.M.: “When Rock
Management Process and integrating across various Mechanics Met Drilling: Effective Implementation of Real-
disciplines. The client and service companies Time Wellbore Stability Control” IADC/SPE 59121
communicated and debated information based on real 6. Smirnov, N.Y., Tomlinson, J.C., Brady, S.D, Rau, W.E.:
“Advanced Modeling Techniques with Real-time Updating
time information. Drilling plans and practices were alter and Managing the Par
which ultimately resulted with a well bore which was
drilled safely and efficiently.
There were no stuck pipe incidences, lost-in-hole or
AADE-03-NTCE-28 PROCESS OF INTEGRATING GEOMECHANICS WITH WELL DESIGN AND DRILLING OPERATION 5
σ1 MD ( ft)
P etroni us A 21 O H ( MD)
8000
σ3 σ3 σ3 σ3 10000
Sh
12000
PPPP
MWmin OBG
σ1 MW60 MW60
14000
MWmin
Figure 1 Rock Failure: Tensile (left) and Compressional or shear
(right)
16000
18000
20000
Sh OBG
22000
8 10 12 14 16
(pp g)
Schlumberger Private
5,000
Trip-In Theoretical
Slack-off FF=0.15
6,000
Slack -off Weight
7,000
Trip-Out Theoretical
8,000 Pick-up FF=0.15
Interpretation of Interpretation of Down hole Pick-up Weight
9,000
Drilling Mecha nics Measure me nts
Trip-In Theoretical Slack
10,000 off FF=0.18
3D MEM Trip-In Theoretical Slack
Compare Realtime and 11,000
off FF=0.12
Pre drill Models 12,000 Trip-Out Theoretical
Trip out
Continue
Measured Depth (ft)
Pick-up FF=0.18
YES Agree? 09-Sep-2002
Trip-Out Theoretical
Drilling 13,000
Pick-up FF=0.12
16,000
24,000
200 225 250 275 300 325 350 375 400 425 450 475 500 525
Hookloads (klbs)
Uncorrected for
water depth
2,000 ft pe r division
Corrected for
water depth