Work Schedule Pha Lai 1 Unit 2 LMZ 110MW ST LP Diaphragm Repair

19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 1-Mar 2-Mar 3-Mar 4-Mar 5-Mar 6-Mar 7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar
Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue
Component Descriptions 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

Sand blasting / Cleaning

Material Identification

NDT (PT or MPI)

Diaphragm #22 (Lower Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Welding repair of crack at diaphragm body near
nozzle #12
Build up weld and re-profiling of material loss &
cracks at diaphragm body

Diaphragm #22 (Upper Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body

Diaphragm #21 (Lower Half)


Build up weld and re-profiling of nozzle trailing
edge defects (all)
Build up weld and re-profiling of material loss &
cracks at diaphragm body

Diaphragm #21 (Upper Half)


Build up weld and re-profiling of nozzle trailing
edge defects (all)
Build up weld and re-profiling of material loss &
cracks at diaphragm body

Diaphragm #26 (Lower Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body

Diaphragm #26 (Upper Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body (inner rim)

Diaphragm #27 (Lower Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body (inner rim)

Diaphragm #27 (Upper Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body (inner rim)

Diaphragm #28 (Lower Half)


Build up weld and re-profiling of nozzle trailing
edge defects

LP Diaphragm Repair Schedule Page 1 of 2


Build up weld and re-profiling of material loss &
cracks at diaphragm body

Diaphragm #29 (Lower Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body (inner rim)

Diaphragm #29 (Upper Half)


Build up weld and re-profiling of nozzle trailing
edge defects
Build up weld and re-profiling of material loss &
cracks at diaphragm body (inner rim)

: Plan
: Actual

LP Diaphragm Repair Schedule Page 2 of 2