REV.

PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :

SWITCH YARD
C6 6 FOR 66KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS

X FOR CABLES WITHIN


SWITCH YARD

X, Y and Z Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY


PANEL

Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
7/8 FOR INCOMING LINES

01, 02, 03…. CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

DRAWINGS OF BMK G719EA-KG9145-W601, F601 CONTROL & PROTECTION PANEL FOR LINE BAY (601R)

KE-66PT05579BS,SB,N 66KV POTENTIAL TRANSFORMER 66KV POTENTIAL TRANSFORMER JB


KE-66CT05509N,SB,BS,S 66KV CURRENT TRANSFORMER 66KV CURRENT TRANSFORMER JB
1HYB905115 66KV CIRCUIT BREAKER
3UC0003/2927, 3C2G200/2927 66KV ISOLATOR

1 of 83 Control cable
REV. PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :
Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx4 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability
CABLE
SPECIFIC FROM TO
ATION ROUTE
CABLE TAG NO. RUNS CABLE PURPOSE LENGTH REMARKS
SIZE EQUIPMENT EQUIPMENT Drawing No (IN Mtrs.)
(IN mm2)

CT CORE-1 AS PER
SITE
C6-X-P-01 1 6cx4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509N,SB,BS,S
R,Y REQUIREM
&B - PHASE ENT

CT CORE-2 AS PER
SITE
C6-X-P-02 1 6cx4 CT JB METERING CIRCUIT KE-66CT05509N,SB,BS,S
R,Y & REQUIREM
B - PHASE ENT
FOR 66 KV- VOLTAGE - RATIO-
750/1 SHALL BE TAKEN AND
CONSIDER ONE 6CX4 CABLE
AS A SPARE.
CT CORE-3 AS PER
SITE
C6-X-P-03 1 6cx4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509N,SB,BS,S
R,Y & REQUIREM
B - PHASE ENT

CT CORE-4 AS PER
SITE
C6-X-P-04 1 6cx4 CT JB SPARE KE-66CT05509N,SB,BS,S
R,Y & REQUIREM
B - PHASE ENT

PT CORE-1 AS PER
SITE
C6-X-P-05 1 6cx4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS,SB,N TAKE ONE 6CX4 AS A SPARE
R,Y & REQUIREM
B - PHASE ENT

2 of 83 Control cable
REV. PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :
PT CORE-2 AS PER
SITE
C6-X-P-06 1 6cx4 PT JB DISTANCE PROTECTION KE-66PT05579BS,SB,N
R,Y & REQUIREM
B - PHASE ENT

PT CORE-3 AS PER
SITE
C6-X-P-07 1 6cx4 PT JB METERING CIRCUIT KE-66PT05579BS,SB,N
R,Y & REQUIREM
B - PHASE ENT

COMMON +VE OF BCU


NC CONTACT FROM BCU (STATUS)
NO CONTACT FROM BCU (STATUS)
SF6 LOCK OUT CONTACT FOR BCU
SF6 GAS LOW
SPRING CHARGE INDICATION
C6-X-P-08 1 19cx2.5 CB-P BMK-P COMMON +VE 1HYB905115

COMMON +VE FOR OPEN/CLOSE STATAUS


REMOTE-CLOSE
REMOTE-TRIP
POST CLOSE SUPERVISION-1
PROTECTION TRIP

PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


AS PER
PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION SITE
REQUIREM
ENT
PROTECTION TRIP-2
POST CLOSE SUPERVISION-2

NC CONTACT FOR REL 7SA611 (OPEN STATUS)

C6-X-P-09 1 19cx2.5 CB-P BMK-P COMMON +VE FOR INDICATION


1HYB905115
CB OPEN INDICATION
AC supply
CB CLOSE INDICATION

AUX NC FOR BKR INTERLOCKING CIRCUIT OF


ISO

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

3 of 83 Control cable
1HYB905115

REV. PREPARED BY: AM


PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :

COMMON +VE OF BCU


NO CONTACT FOR STATUS IN BCU
NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29A ISO


AS PER
3UC0003/2927, 3C2G200/2927 SITE
C6-X-P-10 1 12cx2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
REQUIREM
ENT
AUX NO FOR BKR CLOSING I/L CKT

AUX NC FOR BKR CLOSING I/L CKT


remaining core shall be taken
as spare
COMMON +VE OF BCU
NO CONTACT FOR STATUS IN BCU
NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29B ISO AS PER


SITE
C6-X-P-11 1 12cx2.5 ISO-29-B BMK-P 3UC0003/2927, 3C2G200/2927
AUX NC FOR I/L COIL OF 29A REQUIREM
ENT
AUX NO FOR BKR CLOSING I/L CKT

AUX NC FOR BKR CLOSING I/L CKT

COMMON +VE OF BCU

COMMON +VE OF BCU

NO CONTACT FOR STATUS IN BCU


NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29A ISO AS PER


SITE
C6-X-P-12 1 12cx2.5 ISO-29-L BMK-P
3UC0003/2927, 3C2G200/2927 REQUIREM
AUX NC FOR I/L COIL OF 29B ENT

4 of 83 Control cable
REV. PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED AS PER APPROVED BY: BND
INCOMING
C6-X-P-12 1 LINE-BAY-7&8
12cx2.5 ISO-29-L BMK-P
CONTRACTOR : M/S SHYAM INDUS 3UC0003/2927, 3C2G200/2927
SITE
REQUIREM Date- 05-10-2018
ENT
DOC. NO. :

AUX NO FOR BKR CLOSING I/L CKT

COMMON +VE OF BCU


NO CONTACT FOR STATUS IN BCU

INTERLOCK OF 29LE E/S

AUX NC FOR BKR CLOSING I/L CKT

AUX NC FOR I/L COIL OF 29l


AS PER
3UC0003/2927, 3C2G200/2927 SITE
C6-X-P-13 1 12cx2.5 ISO-29-LE BMK-P
COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

NC CONTACT FOR REL 7SA611 (OPEN STATUS)

CT JB AS PER
CORE-1 SITE
C6-Y-P-14 1 6cx4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9145-W601, F601
REQUIREM
ENT

CT JB AS PER
CORE-2 SITE
C6-Y-P-15 1 6cx4 CRP METERING CIRCUIT G719EA-KG9145-W601, F601
REQUIREM
ENT

5 of 83 Control cable
REV. PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :

CT JB AS PER
CORE-3 SITE
C6-Y-P-16 1 6cx4 CRP DISTANCE PROTECTION
G719EA-KG9145-W601, F601 REQUIREM
ENT

CT JB AS PER
CORE-4 SITE
C6-Y-P-17 1 6cx4 CRP LINE DIFFERENTIAL RELAY G719EA-KG9145-W601, F601
REQUIREM
ENT

AS PER
PT JB CORE-1
SITE
C6-Y-P-18 1 6cx4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9145-W601, F601
REQUIREM
ENT

AS PER
PT JB CORE-2
SITE
C6-Y-P-19 1 6cx4 CRP DISTANCE PROTECTION G719EA-KG9145-W601, F601
REQUIREM
ENT

AS PER
PT JB CORE-3
SITE
C6-Y-P-20 1 6cx4 CRP METERING G719EA-KG9145-W601, F601
REQUIREM
ENT

TO CB CLOSING CIRCUIT
AS PER
G719EA-KG9145-W601, F601 SITE
C6-Y-P-21 1 6cx4 CB-P CRP
TRIP COIL-1 REQUIREM
ENT

6 of 83 Control cable
REV. PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :

AS PER
SITE
C6-Y-P-22 1 6cx4 CB-P CRP G719EA-KG9145-W601, F601
TRIP COIL-2 REQUIREM
ENT

COMMON +VE OF BCU

CB-52 NC CONTACT FROM BCU (STATUS)

CB-52 NO CONTACT FROM BCU (STATUS)


COMMON +VE OF BCU FOR ISO

29A NO CONTACT FOR STATUS IN BCU

29A NC CONTACT FOR STATUS IN BCU AS PER


G719EA-KG9145-W601, F601 SITE
C6-Y-P-23 1 19cx2.5 BMK-P CRP
REQUIREM
29B NO CONTACT FOR STATUS IN BCU ENT

29B NC CONTACT FOR STATUS IN BCU

29L NO CONTACT FOR STATUS IN BCU

29L NC CONTACT FOR STATUS IN BCU

COMMON +VE FOR OPEN/CLOSE STATAUS

CB-52 NO CONTACT FOR REL 7SA611 (CLOSE


STATUS)
CB-52 NC CONTACT FOR REL 7SA611 (OPEN
STATUS)
COMMON +VE FOR OPEN/CLOSE STATAUS
AS PER
29LE NO CONTACT FOR REL 7SA611 (CLOSE SITE
C6-Y-P-24 1 19cx2.5 BMK-P CRP STATUS) G719EA-KG9145-W601, F601
REQUIREM
29LE NC CONTACT FOR REL 7SA611 (OPEN ENT
STATUS)

29LE NO CONTACT FOR STATUS IN BCU

LINE PT SUPPLY

7 of 83 Control cable
AS PER
SITE
C6-Y-P-24 1 19cx2.5 BMK-P CRP G719EA-KG9145-W601, F601
REQUIREM
REV.
ENT PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :

CB-52 SF6 LOCK OUT CONTACT FOR BCU


CB-52 SF6 GAS LOW
CB-52 SPRING CHARGE INDICATION
COMMON +VE
G719EA-KG9145-W601, F601 AS PER
COMMON +VE FOR INDICATION SITE
C6-Y-P-25 1 12cx2.5 BMK-P CRP CB-52 CB OPEN INDICATION REQUIREM
CB-52 CB CLOSE INDICATION ENT

FOR CB CLOSING AND TRIPPING CKT

AS PER
SITE PART OF CRP INTER PANEL
C6-Z-P-26 1 6cx4 CRP EXISTING CRP LBB TRIP CIRCUIT
REQUIREM WIRING
ENT

AS PER
LINE CB AND ISOLATOR INTER LOCK WITH DC SITE
C6-Y-P-27 1 6cx4 CRP BMK-P
SUPPLY REQUIREM
ENT

AS PER
SITE
C6-Z-P-28 1 6cx4 CRP EXISTING CRP 220V DC SUPPLY
REQUIREM PART OF CRP INTER PANEL
ENT WIRING

AS PER
SITE
C6-Z-P-29 1 6cx4 CRP EXISTING CRP AC 1 PHASE SUPPLY
REQUIREM PART OF CRP INTER PANEL
ENT WIRING

AS PER
SITE
C6-X-P-30 1 6cx4 ISO-29-LE BMK-P AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE
C6-X-P-31 1 6cx4 ISO-29-L BMK-P AC 1 PHASE SUPPLY
REQUIREM
ENT

8 of 83 Control cable
REV. PREPARED BY: AM
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS
CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 05-10-2018

DOC. NO. :

AS PER
SITE
C6-X-P-32 1 6cx4 ISO-29-A BMK-P AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE
C6-X-P-33 1 6cx4 ISO-29-B BMK-P AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE
C6-X-P-34 1 6cx4 BMK-P PTJB AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE
C6-X-P-35 1 6cx4 BMK-P CTJB AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
AC 1 PHASE SUPPLY FOR SPRING CHARGING SITE
C6-X-P-36 1 6cx4 BMK-P CRP
MOTOR REQUIREM
ENT

AS PER
SITE PART OF CRP INTERPANEL
C6-Z-P-37 1 6cx4 CRP EXISTING CRP BUS PT-1 SELECTION
REQUIREM WIRING
ENT

AS PER
SITE PART OF CRP INTERPANEL
C6-Z-P-38 1 6cx4 CRP EXISTING CRP BUS PT-2SELECTION
REQUIREM WIRING
ENT

9 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

SWITCH YARD
C3 3 FOR 33KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS

X FOR CABLES WITHIN


SWITCH YARD

X, Y and Z Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY


PANEL

Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
7/8 FOR INCOMING LINES

01, 02, 03…. CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx4 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability

10 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :
CABLE
SPECIFIC FROM TO
ATION ROUTE
CABLE TAG NO. RUNS CABLE PURPOSE LENGTH REMARKS
SIZE EQUIPMENT EQUIPMENT (IN Mtrs.)
(IN mm2)

CT CORE-1 AS PER
SITE
C3-X-P-01 1 6cx4 CT JB BCU CKT (BACK UP PROTECTION)
R- REQUIREM
PHASE ENT

CT CORE-2 AS PER
SITE
C3-X-P-02 1 6cx4 CT JB METERING CIRCUIT
R- REQUIREM
PHASE ENT

CT CORE-3 AS PER
SITE
C3-X-P-03 1 6cx4 CT JB LINE DIFFERENTIAL RELAY
R- REQUIREM
PHASE ENT

CT CORE-4 AS PER
SITE
C3-X-P-04 1 6cx4 CT JB SPARE
R- REQUIREM
PHASE ENT

11 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

CT CORE-1 AS PER
SITE
C3-X-P-05 1 6cx4 CT JB BCU CKT (BACK UP PROTECTION)
Y- REQUIREM
PHASE ENT

CT CORE-2 AS PER
SITE
C3-X-P-06 1 6cx4 CT JB METERING CIRCUIT
Y- REQUIREM
PHASE ENT

CT CORE-3 AS PER
SITE
C3-X-P-07 1 6cx4 CT JB LINE DIFFERENTIAL RELAY
Y- REQUIREM
PHASE ENT

CT CORE-4 AS PER
SITE
C3-X-P-08 1 6cx4 CT JB SPARE
Y- REQUIREM
PHASE ENT

CT CORE-1 AS PER
SITE
C3-X-P-09 1 6cx4 CT JB BCU CKT (BACK UP PROTECTION)
B- REQUIREM
PHASE ENT

12 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

CT CORE-2 AS PER
SITE
C3-X-P-10 1 6cx4 CT JB METERING CIRCUIT
B- REQUIREM
PHASE ENT

CT CORE-3 AS PER
SITE
C3-X-P-11 1 6cx4 CT JB LINE DIFFERENTIAL RELAY
B- REQUIREM
PHASE ENT

CT CORE-4 AS PER
SITE
C3-X-P-12 1 6cx4 CT JB SPARE
B- REQUIREM
PHASE ENT

PT CORE-1 AS PER
SITE
C3-X-P-13 1 6cx4 PT JB BCU CKT (BACK UP PROTECTION)
R- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C3-X-P-14 1 6cx4 PT JB SPARE
R- REQUIREM
PHASE ENT

PT CORE-3 AS PER
SITE
C3-X-P-15 1 6cx4 PT JB METERING CIRCUIT
R- REQUIREM
PHASE ENT

13 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

PT CORE-1 AS PER
SITE
C3-X-P-16 1 6cx4 PT JB BCU CKT (BACK UP PROTECTION)
Y- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C3-X-P-17 1 6cx4 PT JB SPARE
Y- REQUIREM
PHASE ENT

PT CORE-3 AS PER
SITE
C3-X-P-18 1 6cx4 PT JB METERING CIRCUIT
Y- REQUIREM
PHASE ENT

PT CORE-1 AS PER
SITE
C3-X-P-19 1 6cx4 PT JB BCU CKT (BACK UP PROTECTION)
B- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C3-X-P-20 1 6cx4 PT JB SPARE
B- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C3-X-P-21 1 6cx4 PT JB METERING CIRCUIT
B- REQUIREM
PHASE ENT

14 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

COMMON +VE OF BCU


NC CONTACT FROM BCU (STATUS)
NO CONTACT FROM BCU (STATUS)
SF6 LOCK OUT CONTACT FOR BCU
SF6 GAS LOW
SPRING CHARGE INDICATION
C3-X-P-22 1 19cx2.5 CB-P BMK-P COMMON +VE
COMMON +VE FOR OPEN/CLOSE STATAUS
REMOTE-CLOSE
REMOTE-TRIP
POST CLOSE SUPERVISION-1
PROTECTION TRIP

PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


AS PER
PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION SITE
REQUIREM
ENT
PROTECTION TRIP-2
POST CLOSE SUPERVISION-2

NC CONTACT FOR REL 7SA611 (OPEN STATUS)

C3-X-P-23 1 19cx2.5 CB-P BMK-P COMMON +VE FOR INDICATION


CB OPEN INDICATION
AC supply
CB CLOSE INDICATION

AUX NC FOR BKR INTERLOCKING CIRCUIT OF


ISO

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

remaining core shall be taken


as spare

15 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

COMMON +VE OF BCU


NO CONTACT FOR STATUS IN BCU
NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29A ISO


AS PER
SITE
C3-X-P-24 1 12cx2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
REQUIREM
ENT
AUX NO FOR BKR CLOSING I/L CKT

AUX NC FOR BKR CLOSING I/L CKT


remaining core shall be taken
as spare
COMMON +VE OF BCU
NO CONTACT FOR STATUS IN BCU
NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29B ISO AS PER


SITE
C3-X-P-25 1 12cx2.5 ISO-29-B BMK-P
AUX NC FOR I/L COIL OF 29A REQUIREM
ENT
AUX NO FOR BKR CLOSING I/L CKT

AUX NC FOR BKR CLOSING I/L CKT

COMMON +VE OF BCU

COMMON +VE OF BCU

NO CONTACT FOR STATUS IN BCU


NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29A ISO AS PER


SITE
C3-X-P-26 1 12cx2.5 ISO-29-L BMK-P
REQUIREM
AUX NC FOR I/L COIL OF 29B ENT

AUX NO FOR BKR CLOSING I/L CKT

16 of 83 Control cable
REV. PREPARED BY: AM
AS PER
SITE
C3-X-P-26 1 12cx2.5 ISO-29-L BMK-POUT DOOR GRID SUBSTATION AT SHAZADABAGH
PROJECT: 33/11KV R0 CHECKED BY: AS
REQUIREM
CABLE SCHEDULE FOR ENT

INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

COMMON +VE OF BCU


NO CONTACT FOR STATUS IN BCU

INTERLOCK OF 29LE E/S

AUX NC FOR BKR CLOSING I/L CKT

AUX NC FOR I/L COIL OF 29l


AS PER
SITE
C3-X-P-27 1 12cx2.5 ISO-29-LE BMK-P
COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

NC CONTACT FOR REL 7SA611 (OPEN STATUS)

CT JB AS PER
CORE-1 SITE
C3-Y-P-28 1 6cx4 CRP BCU CKT (BACK UP PROTECTION)
REQUIREM
ENT

CT JB AS PER
CORE-2 SITE
C3-Y-P-29 1 6cx4 CRP METERING CIRCUIT
REQUIREM
ENT

17 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

CT JB AS PER
CORE-3 SITE
C3-Y-P-30 1 6cx4 CRP LINE DIFFERENTIAL RELAY
REQUIREM
ENT

CT JB AS PER
CORE-4 SITE
C3-Y-P-31 1 6cx4 CRP SPARE
REQUIREM
ENT

AS PER
PT JB CORE-1
SITE
C3-Y-P-32 1 6cx4 CRP BCU CKT (BACK UP PROTECTION)
REQUIREM
ENT

AS PER
PT JB CORE-2
SITE
C3-Y-P-33 1 6cx4 CRP DISTANCE PROTECTION
REQUIREM
ENT

AS PER
PT JB CORE-3
SITE
C3-Y-P-34 1 6cx4 CRP METERING
REQUIREM
ENT

COMMON +VE OF BCU

NC CONTACT FROM BCU (STATUS)

NO CONTACT FROM BCU (STATUS)


SF6 LOCK OUT CONTACT FOR BCU

SF6 GAS LOW

SPRING CHARGE INDICATION AS PER


SITE
C3-Y-P-35 1 19cx2.5 BMK-P CRP REQUIREM
COMMON +VE ENT

18 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED
AS PER
APPROVED BY: BND

CONTRACTOR : M/S SURYA SITE Date- 25-02-2019


C3-Y-P-35 1 19cx2.5 BMK-P CRP REQUIREM
ENT
DOC. NO. :

COMMON +VE FOR OPEN/CLOSE STATAUS

REMOTE-CLOSE

REMOTE-TRIP

POST CLOSE SUPERVISION-1


PROTECTION TRIP

PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION

PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION

PROTECTION TRIP-2

POST CLOSE SUPERVISION-2

NC CONTACT FOR REL 7SA611 (OPEN STATUS) AS PER


C3-Y-P-36 1 19cx2.5 BMK-P CRP
SITE
COMMON +VE FOR INDICATION REQUIREM
ENT
CB OPEN INDICATION

CB CLOSE INDICATION

AUX NC FOR BKR INTERLOCKING CIRCUIT OF


ISO

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

29LE NO CONTACT FOR REL 7SA611 (CLOSE


STATUS)
29LE NC CONTACT FOR REL 7SA611 (OPEN
STATUS)
29LE NO CONTACT FOR STATUS IN BCU AS PER
BMK-P 29A NO CONTACT FOR STATUS IN BCU SITE
C3-Y-P-37 1 12cx2.5 CRP
(ISOLATORS) REQUIREM
29A NC CONTACT FOR STATUS IN BCU
ENT
29B NO CONTACT FOR STATUS IN BCU
29B NC CONTACT FOR STATUS IN BCU
29L NO CONTACT FOR STATUS IN BCU
29L NC CONTACT FOR STATUS IN BCU

19 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :
AS PER
SITE PART OF CRP INTER PANEL
C3-Z-P-38 1 4cx2.5 CRP EXISTING CRP LBB TRIP CIRCUIT
REQUIREM WIRING
ENT

LINE CB AND ISOLATOR INTER LOCK WITH DC AS PER


C3-Y-P-39 1 4cx2.5 CRP BMK-P SITE
SUPPLY
REQUIREM
ENT

AS PER
C3-Z-P-40 1 4cx2.5 CRP EXISTING CRP 220V DC SUPPLY SITE PART OF CRP INTER PANEL
REQUIREM WIRING
ENT

AS PER
C3-Z-P-41 1 4cx2.5 CRP EXISTING CRP AC 1 PHASE SUPPLY SITE PART OF CRP INTER PANEL
REQUIREM WIRING
ENT

AS PER
ISO-29-LE SITE
C3-X-P-42 1 4cx2.5 BMK-P AC 1 PHASE SUPPLY
(ISOJB) REQUIREM
ENT

AS PER
ISO-29-L SITE
C3-X-P-43 1 4cx2.5 BMK-P AC 1 PHASE SUPPLY
(ISOJB) REQUIREM
ENT

20 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 33/11KV OUT DOOR GRID SUBSTATION AT SHAZADABAGH R0 CHECKED BY: AS


CABLE SCHEDULE FOR
INCOMING LINE-BAY CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND

CONTRACTOR : M/S SURYA Date- 25-02-2019

DOC. NO. :

AS PER
ISO-29-A SITE
C3-X-P-44 1 4cx2.5 BMK-P AC 1 PHASE SUPPLY
(ISOJB) REQUIREM
ENT

AS PER
ISO-29-B SITE
C3-X-P-45 1 4cx2.5 BMK-P AC 1 PHASE SUPPLY
(ISOJB) REQUIREM
ENT

AS PER
SITE
C3-X-P-46 1 4cx2.5 BMK-P PTJB AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE
C3-X-P-47 1 4cx2.5 BMK-P CTJB AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE
C3-X-P-48 1 4cx2.5 BMK-P CRP AC 1 PHASE SUPPLY
REQUIREM
ENT

AS PER
SITE PART OF CRP INTERPANEL
C3-Z-P-49 1 4cx2.5 CRP EXISTING CRP BUS PT-1 SELECTION
REQUIREM WIRING
ENT

AS PER
SITE PART OF CRP INTERPANEL
C3-Z-P-50 1 4cx2.5 CRP EXISTING CRP BUS PT-2SELECTION
REQUIREM WIRING
ENT

21 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :

SWITCH YARD
C6 6 FOR 66KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS

X FOR CABLES WITHIN


SWITCH YARD

X, Y and Z Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY


PANEL

Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
7/8 FOR INCOMING LINES

01, 02, 03 etc CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx2.5 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability
CABLE
SPECIFIC FROM TO
ATION ROUTE
CABLE TAG NO. RUNS CABLE PURPOSE LENGTH REMARKS
SIZE EQUIPMENT EQUIPMENT (IN Mtrs.)
(IN mm2)

22 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :

CT CORE-1 AS PER
SITE consider one spare cable for
C6-X-P-01 1 4CX2.5 CT JB BCU CKT (BACK UP PROTECTION)
R- REQUIREM CT & PT of 4cx2.5
PHASE ENT

CT CORE-2 AS PER
SITE
C6-X-P-02 1 4CX2.5 CT JB METERING CIRCUIT
R- REQUIREM
PHASE ENT

CT CORE-3 AS PER
SITE
C6-X-P-03 1 4CX2.5 CT JB LINE DIFFERENTIAL RELAY
R- REQUIREM
PHASE ENT

CT CORE-4 AS PER
SITE
C6-X-P-04 1 4cx2.5 CT JB SPARE
R- REQUIREM
PHASE ENT

CT CORE-1 AS PER
SITE
C6-X-P-05 1 4cx2.5 CT JB BCU CKT (BACK UP PROTECTION)
Y- REQUIREM
PHASE ENT

CT CORE-2 AS PER
SITE
C6-X-P-06 1 4cx2.5 CT JB METERING CIRCUIT
Y- REQUIREM
PHASE ENT

23 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :

CT CORE-3 AS PER
SITE
C6-X-P-07 1 4cx2.5 CT JB LINE DIFFERENTIAL RELAY
Y- REQUIREM
PHASE ENT

CT CORE-4 AS PER
SITE
C6-X-P-08 1 4cx2.5 CT JB SPARE
Y- REQUIREM
PHASE ENT

CT CORE-1 AS PER
SITE
C6-X-P-09 1 4cx2.5 CT JB BCU CKT (BACK UP PROTECTION)
B- REQUIREM
PHASE ENT

CT CORE-2 AS PER
SITE
C6-X-P-10 1 4cx2.5 CT JB METERING CIRCUIT
B- REQUIREM
PHASE ENT

CT CORE-3 AS PER
SITE
C6-X-P-11 1 4cx2.5 CT JB LINE DIFFERENTIAL RELAY
B- REQUIREM
PHASE ENT

CT CORE-4 AS PER
SITE
C6-X-P-12 1 4cx2.5 CT JB SPARE
B- REQUIREM
PHASE ENT

24 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :
PT CORE-1 AS PER
SITE
C6-X-P-13 1 4cx2.5 PT JB BCU CKT (BACK UP PROTECTION)
R- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C6-X-P-14 1 4cx2.5 PT JB DISTANCE PROTECTION
R- REQUIREM
PHASE ENT

PT CORE-3 AS PER
SITE
C6-X-P-15 1 4cx2.5 PT JB METERING CIRCUIT
R- REQUIREM
PHASE ENT

PT CORE-1 AS PER
SITE
C6-X-P-16 1 4cx2.5 PT JB BCU CKT (BACK UP PROTECTION)
Y- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C6-X-P-17 1 4cx2.5 PT JB DISTANCE PROTECTION
Y- REQUIREM
PHASE ENT

PT CORE-3 AS PER
SITE
C6-X-P-18 1 4cx2.5 PT JB METERING CIRCUIT
Y- REQUIREM
PHASE ENT

PT CORE-1 AS PER
SITE
C6-X-P-19 1 4cx2.5 PT JB BCU CKT (BACK UP PROTECTION)
B- REQUIREM
PHASE ENT

PT CORE-2 AS PER
SITE
C6-X-P-20 1 4cx2.5 PT JB DISTANCE PROTECTION
B- REQUIREM
PHASE ENT

25 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :

PT CORE-2 AS PER
SITE
C6-X-P-21 1 4cx2.5 PT JB METERING CIRCUIT
B- REQUIREM
PHASE ENT

COMMON +VE OF BCU


NC CONTACT FROM BCU (STATUS)
NO CONTACT FROM BCU (STATUS)
SF6 LOCK OUT CONTACT FOR BCU
SF6 GAS LOW
SPRING CHARGE INDICATION
C6-X-P-22 1 12cx2.5 CB-P BMK-P COMMON +VE
COMMON +VE FOR OPEN/CLOSE STATAUS

REMOTE-CLOSE
REMOTE-TRIP
POST CLOSE SUPERVISION-1
PROTECTION TRIP

PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


AS PER
C6-X-P-23 1 12cx2.5 CB-P BMK-P SITE
PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION REQUIREM
ENT
PROTECTION TRIP-2
POST CLOSE SUPERVISION-2

NC CONTACT FOR REL 7SA611 (OPEN STATUS)


COMMON +VE FOR INDICATION
CB OPEN INDICATION
CB CLOSE INDICATION

C6-X-P-24 1 12cx2.5 CB-P BMK-P AUX NC FOR BKR INTERLOCKING CIRCUIT OF


ISO

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

remaining core shall be used


as spare
26 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :
COMMON +VE OF BCU
NO CONTACT FOR STATUS IN BCU
NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29A ISO


AS PER
SITE
C6-X-P-25 1 12cx2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
REQUIREM
ENT
AUX NO FOR BKR CLOSING I/L CKT
remaining core shall be used
as spare
AUX NC FOR BKR CLOSING I/L CKT

COMMON +VE OF BCU


NO CONTACT FOR STATUS IN BCU
NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29B ISO AS PER


SITE
C6-X-P-26 1 12cx2.5 ISO-29-B BMK-P
AUX NC FOR I/L COIL OF 29A REQUIREM
ENT
AUX NO FOR BKR CLOSING I/L CKT

AUX NC FOR BKR CLOSING I/L CKT

COMMON +VE OF BCU

COMMON +VE OF BCU

NO CONTACT FOR STATUS IN BCU


NC CONTACT FOR STATUS IN BCU

INTERLOCK COIL OF 29A ISO AS PER


SITE
C6-X-P-27 1 12cx2.5 ISO-29-L BMK-P
REQUIREM
AUX NC FOR I/L COIL OF 29B ENT

AUX NO FOR BKR CLOSING I/L CKT

27 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :
COMMON +VE OF BCU
NO CONTACT FOR STATUS IN BCU

INTERLOCK OF 29LE E/S

AUX NC FOR BKR CLOSING I/L CKT

AUX NC FOR I/L COIL OF 29l


AS PER
SITE
C6-X-P-28 1 12cx2.5 ISO-29-LE BMK-P
COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

NC CONTACT FOR REL 7SA611 (OPEN STATUS)

63.5V AC SUPPLY FROM PT

CT JB AS PER
CORE-1 SITE
C6-Y-P-29 1 4cx2.5 CRP BCU CKT (BACK UP PROTECTION)
REQUIREM
ENT

CT JB AS PER
CORE-2 SITE
C6-Y-P-30 1 4cx2.5 CRP METERING CIRCUIT
REQUIREM
ENT

CT JB AS PER
CORE-3 SITE
C6-Y-P-31 1 4cx2.5 CRP DISTANCE PROTECTION
REQUIREM
ENT

CT JB AS PER
CORE-4 SITE
C6-Y-P-32 1 4cx2.5 CRP LINE DIFFERENTIAL RELAY
REQUIREM
ENT

28 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8
CT JB
CORE-4 CONTRACTOR : M/S SHYAM INDUS
AS PER
SITE Date- 28-09-2018
C6-Y-P-32 1 4cx2.5 CRP LINE DIFFERENTIAL RELAY
REQUIREM
DOC. NO. : ENT

AS PER
PT JB CORE-1
SITE
C6-Y-P-33 1 4cx2.5 CRP BCU CKT (BACK UP PROTECTION)
REQUIREM
ENT

AS PER
PT JB CORE-2
SITE
C6-Y-P-34 1 4cx2.5 CRP DISTANCE PROTECTION
REQUIREM
ENT

AS PER
PT JB CORE-3
SITE
C6-Y-P-35 1 4cx2.5 CRP METERING
REQUIREM
ENT

TO CB CLOSING CIRCUIT
AS PER
SITE
C6-Y-P-36 1 12cx2.5 CB-P CRP
TRIP COIL-1 REQUIREM
ENT

AS PER
SITE
C6-Y-P-37 1 12cx2.5 CB-P CRP
TRIP COIL-2 REQUIREM
ENT

29 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :
COMMON +VE OF BCU

CB-52 NC CONTACT FROM BCU (STATUS)

CB-52 NO CONTACT FROM BCU (STATUS)


COMMON +VE OF BCU FOR ISO

29A NO CONTACT FOR STATUS IN BCU

29A NC CONTACT FOR STATUS IN BCU AS PER


SITE
C6-Y-P-38 1 12cx2.5 BMK-P CRP
REQUIREM
29B NO CONTACT FOR STATUS IN BCU ENT

29B NC CONTACT FOR STATUS IN BCU

29L NO CONTACT FOR STATUS IN BCU

29L NC CONTACT FOR STATUS IN BCU

COMMON +VE FOR OPEN/CLOSE STATAUS

CB-52 NO CONTACT FOR REL 7SA611 (CLOSE


STATUS)
CB-52 NC CONTACT FOR REL 7SA611 (OPEN
STATUS)
COMMON +VE FOR OPEN/CLOSE STATAUS
AS PER
29LE NO CONTACT FOR REL 7SA611 (CLOSE SITE
C6-Y-P-39 1 12cx2.5 BMK-P CRP STATUS) REQUIREM
29LE NC CONTACT FOR REL 7SA611 (OPEN ENT
STATUS)

29LE NO CONTACT FOR STATUS IN BCU

LINE PT SUPPLY

30 of 83 Control cable
REV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT BCWW R2 CHECKED BY: AS


CABLE SCHEDULE FOR CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: BND
INCOMING LINE-BAY-7&8 CONTRACTOR : M/S SHYAM INDUS Date- 28-09-2018

DOC. NO. :

CB-52 SF6 LOCK OUT CONTACT FOR BCU


CB-52 SF6 GAS LOW
CB-52 SPRING CHARGE INDICATION
COMMON +VE
COMMON +VE FOR INDICATION
AS PER
CB-52 CB OPEN INDICATION SITE
C6-Y-P-40 1 12cx2.5 BMK-P CRP CB-52 CB CLOSE INDICATION REQUIREM
ENT

FOR CB CLOSING AND TRIPPING CKT

AS PER
SITE PART OF CRP INTER PANEL
C6-Z-P-41 1 4cx2.5 CRP EXISTING CRP LBB TRIP CIRCUIT
REQUIREM WIRING
ENT

LINE CB AND ISOLATOR INTER LOCK WITH DC AS PER


C6-Y-P-42 1 4cx2.5 CRP BMK-P SITE
SUPPLY
REQUIREM
ENT

AS PER
C6-Z-P-43 1 4cx2.5 CRP EXISTING CRP 220V DC SUPPLY SITE PART OF CRP INTER PANEL
REQUIREM WIRING
ENT

AS PER
C6-Z-P-44 1 4cx2.5 CRP EXISTING CRP AC 1 PHASE SUPPLY SITE PART OF CRP INTER PANEL
REQUIREM WIRING
ENT

AS PER
AC 1 PHASE SUPPLY FOR SPRING CHARGING SITE
C6-X-P-45 1 4cx2.5 BMK-P CRP
MOTOR REQUIREM
ENT

AS PER
SITE PART OF CRP INTERPANEL
C6-Z-P-46 1 4cx2.5 CRP EXISTING CRP BUS PT-1 SELECTION
REQUIREM WIRING
ENT

AS PER
SITE PART OF CRP INTERPANEL
C6-Z-P-47 1 4cx2.5 CRP EXISTING CRP BUS PT-2SELECTION
REQUIREM WIRING
ENT

31 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

SWITCH YARD
C6 6 FOR 66KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS


X FOR CABLES WITHIN SWITCH YARD
X
Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY PANEL
Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
9/10 FOR INCOMING LINE-2-

OO1 CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

REFERENCE DRAWING :

2K9-645-100-02 DRAWINGS OF BMK G719EA-KG9032-E601 CONTROL & PROTECTION PANEL FOR LINE BAY (602R)

KE-66PT02592 66KV POTENTIAL TRANSFORMER 66KV POTENTIAL TRANSFORMER JB


KE-66PT05579BS 66KV CURRENT TRANSFORMER 66KV CURRENT TRANSFORMER JB
1HYB905115 66KV CIRCUIT BREAKER
66KV ISOLATOR

Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx4 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability
CABLE
FROM TO
SPECIFICATION
REFERENCE ROUTE
TER
CABLE TAG NO. RUNS CABLE TERM PURPOSE DRAWINNG & SHEET LENGTH REMARKS
CABLE MIN
SIZE EQUIPMENT INAL EQUIPMENT NO. (IN Mtrs.)
CORE ID AL
(IN mm2) NO.
NO.

32 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-1 AS PER
3 SITE consider one spare cable for
C6-X-P-01 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 R- REQUIREM CT of 4Cx4
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-02 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-03 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-04 1 4CX4 CT JB SPARE KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-05 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-06 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

33 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-07 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-08 1 4CX4 CT JB SPARE KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-09 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-10 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-11 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-12 1 4CX4 CT JB SPARE KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1 PT CORE-1 AS PER
2 SITE
C6-X-P-13 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-14 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 R- REQUIREM
PHASE ENT

34 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10
PT CORE-2
CONTRACTOR : M/S SURYA
AS PER
SITE
C6-X-P-14 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
R- DOC. NO. : ND-W-221-M-026 REQUIREM
4 PHASE ENT

1 PT CORE-3 AS PER
2 SITE
C6-X-P-15 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

35 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 PT CORE-1 AS PER
2 SITE
C6-X-P-16 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-17 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT
1 PT CORE-3 AS PER
2 SITE
C6-X-P-18 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-1 AS PER
2 SITE
C6-X-P-19 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-20 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-21 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

36 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NC CONTACT FROM BCU (STATUS) 1HYB905115-3
3 NO CONTACT FROM BCU (STATUS)
4 SF6 LOCK OUT CONTACT FOR BCU
5 SF6 GAS LOW 1HYB905115-3
6 SPRING CHARGE INDICATION
7 COMMON +VE
8 COMMON +VE FOR OPEN/CLOSE STATAUS 1HYB905115-3
9 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)
C6-X-P-22 1 19CX2.5 CB-P BMK-P
10 NC CONTACT FOR REL 7SA611 (OPEN STATUS)
1HYB905115-3
11 COMMON +VE FOR INDICATION
12 CB OPEN INDICATION
13 CB CLOSE INDICATION
14
AUX NC FOR BKR INTERLOCKING CIRCUIT OF 1HYB905115-3
15 ISO
AS PER
16-19 SITE
REQUIREM
ENT
1 REMOTE-CLOSE
2 REMOTE-TRIP 1HYB905115-3
3 POST CLOSE SUPERVISION-1
4 PROTECTION TRIP

5 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


1HYB905115-3
6 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION
C6-X-P-23 1 12CX2.5 CB-P BMK-P
7 PROTECTION TRIP-2
8 POST CLOSE SUPERVISION-2

9 1HYB905115-3

10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO
5 AS PER
6 SITE
C6-X-P-24 1 10CX2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
7 REQUIREM
8 ENT
AUX NO FOR BKR CLOSING I/L CKT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11

37 of 83 Control cable
DATE RIV. PREPARED BY: AM
AS PER
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2
SITE CHECKED BY: AS
CABLE
C6-X-P-24
SCHEDULE
1 10CX2.5
FOR INCOMING
ISO-29-A BMK-P
CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED
REQUIREM
ENT
APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


12

38 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29B ISO AS PER
5
SITE
C6-X-P-25 1 10CX2.5 6 ISO-29-B BMK-P
AUX NC FOR I/L COIL OF 29A REQUIREM
7 ENT
8 AUX NO FOR BKR CLOSING I/L CKT
10
AUX NC FOR BKR CLOSING I/L CKT
11
12 COMMON +VE OF BCU

1 COMMON +VE OF BCU

2 NO CONTACT FOR STATUS IN BCU


3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO AS PER
5
SITE
C6-X-P-26 1 10CX2.5 ISO-29-L BMK-P
6 REQUIREM
AUX NC FOR I/L COIL OF 29B ENT
7

8
AUX NO FOR BKR CLOSING I/L CKT
9
10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3
INTERLOCK OF 29LE E/S
4
5
AUX NC FOR BKR CLOSING I/L CKT
6
7
AUX NC FOR I/L COIL OF 29l
8 AS PER
SITE
C6-X-P-27 1 10CX2.5 ISO-29-LE BMK-P
9 COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

10 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

11 NC CONTACT FOR REL 7SA611 (OPEN STATUS)

12
63.5V AC SUPPLY FROM PT
13
14-19

1
2 CT JB AS PER
3 CORE-1 SITE
C6-Y-P-28 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

39 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1
2
3 CT JB AS PER
CORE-2 SITE
C6-Y-P-29 1 4CX4 4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
5 ENT

40 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB CONTRACTOR : M/S SURYA AS PER
CORE-2 SITE
C6-Y-P-29 1 4CX4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6
6

1
2 CT JB AS PER
3 CORE-3 SITE
C6-Y-P-30 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1
2 CT JB AS PER
3 CORE-4 SITE
C6-Y-P-31 1 4CX4 CRP LINE DIFFERENTIAL RELAY G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1 AS PER
2 PT JB CORE-1
SITE
C6-Y-P-32 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-2
SITE
C6-Y-P-33 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-3
SITE
C6-Y-P-34 1 4CX4 CRP METERING G719EA-KG9032-E601
3 REQUIREM
4 ENT

1
TO CB CLOSING CIRCUIT
2
3 AS PER
SITE
C6-Y-P-35 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-1 REQUIREM
5 ENT
6
7-12

1
2
3 AS PER
SITE
C6-Y-P-36 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-2 REQUIREM
5 ENT
6
7-12

41 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU

2 CB-52 NC CONTACT FROM BCU (STATUS)

3 CB-52 NO CONTACT FROM BCU (STATUS)


4 COMMON +VE OF BCU FOR ISO

5 29A NO CONTACT FOR STATUS IN BCU

6 29A NC CONTACT FOR STATUS IN BCU AS PER


G719EA-KG9032-E601 SITE
C6-Y-P-37 1 12CX2.5 BMK-P CRP
REQUIREM
7 29B NO CONTACT FOR STATUS IN BCU ENT

8 29B NC CONTACT FOR STATUS IN BCU

9 29L NO CONTACT FOR STATUS IN BCU

10 29L NC CONTACT FOR STATUS IN BCU

11-12

42 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 COMMON +VE FOR OPEN/CLOSE STATAUS

CB-52 NO CONTACT FOR REL 7SA611 (CLOSE


2
STATUS)
CB-52 NC CONTACT FOR REL 7SA611 (OPEN
3
STATUS)
4 COMMON +VE FOR OPEN/CLOSE STATAUS
AS PER
29LE NO CONTACT FOR REL 7SA611 (CLOSE G719EA-KG9032-E601 SITE
C6-Y-P-38 1 12CX2.5 5 BMK-P CRP STATUS) REQUIREM
29LE NC CONTACT FOR REL 7SA611 (OPEN ENT
6
STATUS)

7 29LE NO CONTACT FOR STATUS IN BCU

8
LINE PT SUPPLY
9
10-12

1 CB-52 SF6 LOCK OUT CONTACT FOR BCU


2 CB-52 SF6 GAS LOW
3 CB-52 SPRING CHARGE INDICATION
4 COMMON +VE
AS PER
5 COMMON +VE FOR INDICATION SITE
C6-Y-P-39 1 12CX2.5 6 BMK-P CRP CB-52 CB OPEN INDICATION G719EA-KG9032-E601
REQUIREM
7 CB-52 CB CLOSE INDICATION ENT
8
9
FOR CB CLOSING AND TRIPPING CKT
10
11-12

1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-40 1 4CX4 CRP EXISTING CRP LBB TRIP CIRCUIT
3 REQUIREM WIRING
4 ENT

AS PER
1
LINE CB AND ISOLATOR INTER LOCK WITH DC SITE
C6-Y-P-41 1 4CX4 CRP BMK-P
SUPPLY REQUIREM
2
ENT

1
AS PER
SITE PART OF CRP INTER PANEL
C6-Z-P-43 1 4CX4 CRP EXISTING CRP 220V DC SUPPLY
2 REQUIREM WIRING
ENT

43 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-44 1 4CX4 CRP EXISTING CRP AC 1 PHASE SUPPLY
3--4 REQUIREM WIRING
ENT

1 AS PER
2 AC 1 PHASE SUPPLY FOR SPRING CHARGING SITE
C6-X-P-45 1 4CX4 BMK-P CRP
3 MOTOR REQUIREM
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-47 1 4CX4 CRP EXISTING CRP BUS PT-1 SELECTION
3 REQUIREM WIRING
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-48 1 4CX4 CRP EXISTING CRP BUS PT-2SELECTION
3 REQUIREM WIRING
4 ENT

44 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

SWITCH YARD
C6 6 FOR 66KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS


X FOR CABLES WITHIN SWITCH YARD
X
Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY PANEL
Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
9/10 FOR INCOMING LINE-2-

OO1 CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

REFERENCE DRAWING :

DRAWINGS OF BMK CONTROL & PROTECTION PANEL FOR LINE BAY (602R)

66KV POTENTIAL TRANSFORMER 66KV POTENTIAL TRANSFORMER JB


66KV CURRENT TRANSFORMER 66KV CURRENT TRANSFORMER JB
66KV CIRCUIT BREAKER
66KV ISOLATOR

Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx4 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability
CABLE
FROM TO
SPECIFICATION
REFERENCE ROUTE
TER
CABLE TAG NO. RUNS CABLE TERM PURPOSE DRAWINNG & SHEET LENGTH REMARKS
CABLE MIN
SIZE EQUIPMENT INAL EQUIPMENT NO. (IN Mtrs.)
CORE ID AL
(IN mm2) NO.
NO.

45 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-1 AS PER
3 SITE consider one spare cable for
C6-X-P-01 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 R- REQUIREM CT of 4Cx4
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-02 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-03 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-04 1 4CX4 CT JB SPARE KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-05 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-06 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

46 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-07 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-08 1 4CX4 CT JB SPARE KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-09 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-10 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-11 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-12 1 4CX4 CT JB SPARE KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1 PT CORE-1 AS PER
2 SITE
C6-X-P-13 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-14 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 R- REQUIREM
PHASE ENT

47 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10
PT CORE-2
CONTRACTOR : M/S SURYA
AS PER
SITE
C6-X-P-14 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
R- DOC. NO. : ND-W-221-M-026 REQUIREM
4 PHASE ENT

1 PT CORE-3 AS PER
2 SITE
C6-X-P-15 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

48 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 PT CORE-1 AS PER
2 SITE
C6-X-P-16 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-17 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT
1 PT CORE-3 AS PER
2 SITE
C6-X-P-18 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-1 AS PER
2 SITE
C6-X-P-19 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-20 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-21 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

49 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NC CONTACT FROM BCU (STATUS) 1HYB905115-3
3 NO CONTACT FROM BCU (STATUS)
4 SF6 LOCK OUT CONTACT FOR BCU
5 SF6 GAS LOW 1HYB905115-3
6 SPRING CHARGE INDICATION
7 COMMON +VE
8 COMMON +VE FOR OPEN/CLOSE STATAUS 1HYB905115-3
9 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)
C6-X-P-22 1 12CX2.5 CB-P BMK-P
10 NC CONTACT FOR REL 7SA611 (OPEN STATUS)
1HYB905115-3
11 COMMON +VE FOR INDICATION
12 CB OPEN INDICATION
13 CB CLOSE INDICATION
14
AUX NC FOR BKR INTERLOCKING CIRCUIT OF 1HYB905115-3
15 ISO
AS PER
16-19 SITE
REQUIREM
ENT
1 REMOTE-CLOSE
2 REMOTE-TRIP 1HYB905115-3
3 POST CLOSE SUPERVISION-1
4 PROTECTION TRIP

5 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


1HYB905115-3
6 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION
C6-X-P-23 1 12CX2.5 CB-P BMK-P
7 PROTECTION TRIP-2
8 POST CLOSE SUPERVISION-2

9 1HYB905115-3

10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO
5 AS PER
6 SITE
C6-X-P-24 1 10CX2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
7 REQUIREM
8 ENT
AUX NO FOR BKR CLOSING I/L CKT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11

50 of 83 Control cable
DATE RIV. PREPARED BY: AM
AS PER
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2
SITE CHECKED BY: AS
CABLE
C6-X-P-24
SCHEDULE
1 10CX2.5
FOR INCOMING
ISO-29-A BMK-P
CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED
REQUIREM
ENT
APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


12

51 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29B ISO
5 AS PER
6 SITE
C6-X-P-25 1 10CX2.5 ISO-29-B BMK-P AUX NC FOR I/L COIL OF 29A
7 REQUIREM
8 AUX NO FOR BKR CLOSING I/L CKT ENT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11
12

1 COMMON +VE OF BCU

2 NO CONTACT FOR STATUS IN BCU


3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO AS PER
5
SITE
C6-X-P-26 1 10CX2.5 ISO-29-L BMK-P
6 REQUIREM
AUX NC FOR I/L COIL OF 29B ENT
7

8
AUX NO FOR BKR CLOSING I/L CKT
9
10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3
INTERLOCK OF 29LE E/S
4
5
AUX NC FOR BKR CLOSING I/L CKT
6
7
AUX NC FOR I/L COIL OF 29l
8 AS PER
SITE
C6-X-P-27 1 10CX2.5 ISO-29-LE BMK-P
9 COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

10 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

11 NC CONTACT FOR REL 7SA611 (OPEN STATUS)

12
63.5V AC SUPPLY FROM PT
13
14-19

1
2 CT JB AS PER
3 CORE-1 SITE
C6-Y-P-28 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
4 REQUIREM
5 ENT

52 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB
CORE-1 CONTRACTOR : M/S SURYA
AS PER
SITE
C6-Y-P-28 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6

1
2
3 CT JB AS PER
CORE-2 SITE
C6-Y-P-29 1 4CX4 4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
5 ENT

53 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB CONTRACTOR : M/S SURYA AS PER
CORE-2 SITE
C6-Y-P-29 1 4CX4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6
6

1
2 CT JB AS PER
3 CORE-3 SITE
C6-Y-P-30 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1
2 CT JB AS PER
3 CORE-4 SITE
C6-Y-P-31 1 4CX4 CRP LINE DIFFERENTIAL RELAY G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1 AS PER
2 PT JB CORE-1
SITE
C6-Y-P-32 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-2
SITE
C6-Y-P-33 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-3
SITE
C6-Y-P-34 1 4CX4 CRP METERING G719EA-KG9032-E601
3 REQUIREM
4 ENT

1
TO CB CLOSING CIRCUIT
2
3 AS PER
SITE
C6-Y-P-35 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-1 REQUIREM
5 ENT
6
7-12

1
2
3 AS PER
SITE
C6-Y-P-36 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-2 REQUIREM
5 ENT
6
7-12

54 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU

2 CB-52 NC CONTACT FROM BCU (STATUS)

3 CB-52 NO CONTACT FROM BCU (STATUS)


4 COMMON +VE OF BCU FOR ISO

5 29A NO CONTACT FOR STATUS IN BCU

6 29A NC CONTACT FOR STATUS IN BCU AS PER


G719EA-KG9032-E601 SITE
C6-Y-P-37 1 12CX2.5 BMK-P CRP
REQUIREM
7 29B NO CONTACT FOR STATUS IN BCU ENT

8 29B NC CONTACT FOR STATUS IN BCU

9 29L NO CONTACT FOR STATUS IN BCU

10 29L NC CONTACT FOR STATUS IN BCU

11-12

55 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 COMMON +VE FOR OPEN/CLOSE STATAUS

CB-52 NO CONTACT FOR REL 7SA611 (CLOSE


2
STATUS)
CB-52 NC CONTACT FOR REL 7SA611 (OPEN
3
STATUS)
4 COMMON +VE FOR OPEN/CLOSE STATAUS
AS PER
29LE NO CONTACT FOR REL 7SA611 (CLOSE G719EA-KG9032-E601 SITE
C6-Y-P-38 1 12CX2.5 5 BMK-P CRP STATUS) REQUIREM
29LE NC CONTACT FOR REL 7SA611 (OPEN ENT
6
STATUS)

7 29LE NO CONTACT FOR STATUS IN BCU

8
LINE PT SUPPLY
9
10-12

1 CB-52 SF6 LOCK OUT CONTACT FOR BCU


2 CB-52 SF6 GAS LOW
3 CB-52 SPRING CHARGE INDICATION
4 COMMON +VE
AS PER
5 COMMON +VE FOR INDICATION SITE
C6-Y-P-39 1 12CX2.5 6 BMK-P CRP CB-52 CB OPEN INDICATION G719EA-KG9032-E601
REQUIREM
7 CB-52 CB CLOSE INDICATION ENT
8
9
FOR CB CLOSING AND TRIPPING CKT
10
11-12

1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-40 1 4CX4 CRP EXISTING CRP LBB TRIP CIRCUIT
3 REQUIREM WIRING
4 ENT

AS PER
1
LINE CB AND ISOLATOR INTER LOCK WITH DC SITE
C6-Y-P-41 1 4CX4 CRP BMK-P
SUPPLY REQUIREM
2
ENT

1
AS PER
SITE PART OF CRP INTER PANEL
C6-Z-P-43 1 4CX4 CRP EXISTING CRP 220V DC SUPPLY
2 REQUIREM WIRING
ENT

56 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-44 1 4CX4 CRP EXISTING CRP AC 1 PHASE SUPPLY
3--4 REQUIREM WIRING
ENT

1 AS PER
2 AC 1 PHASE SUPPLY FOR SPRING CHARGING SITE
C6-X-P-45 1 4CX4 BMK-P CRP
3 MOTOR REQUIREM
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-47 1 4CX4 CRP EXISTING CRP BUS PT-1 SELECTION
3 REQUIREM WIRING
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-48 1 4CX4 CRP EXISTING CRP BUS PT-2SELECTION
3 REQUIREM WIRING
4 ENT

57 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

SWITCH YARD
C6 6 FOR 66KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS


X FOR CABLES WITHIN SWITCH YARD
X
Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY PANEL
Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
9/10 FOR INCOMING LINE-2-

OO1 CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

REFERENCE DRAWING :

DRAWINGS OF BMK CONTROL & PROTECTION PANEL FOR LINE BAY (602R)

66KV POTENTIAL TRANSFORMER 66KV POTENTIAL TRANSFORMER JB


66KV CURRENT TRANSFORMER 66KV CURRENT TRANSFORMER JB
66KV CIRCUIT BREAKER
66KV ISOLATOR

Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx4 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability
CABLE
FROM TO
SPECIFICATION
REFERENCE ROUTE
TER
CABLE TAG NO. RUNS CABLE TERM PURPOSE DRAWINNG & SHEET LENGTH REMARKS
CABLE MIN
SIZE EQUIPMENT INAL EQUIPMENT NO. (IN Mtrs.)
CORE ID AL
(IN mm2) NO.
NO.

58 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-1 AS PER
3 SITE consider one spare cable for
C6-X-P-01 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 R- REQUIREM CT of 4Cx4
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-02 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-03 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-04 1 4CX4 CT JB SPARE KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-05 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-06 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

59 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-07 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-08 1 4CX4 CT JB SPARE KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-09 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-10 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-11 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-12 1 4CX4 CT JB SPARE KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1 PT CORE-1 AS PER
2 SITE
C6-X-P-13 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-14 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 R- REQUIREM
PHASE ENT

60 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10
PT CORE-2
CONTRACTOR : M/S SURYA
AS PER
SITE
C6-X-P-14 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
R- DOC. NO. : ND-W-221-M-026 REQUIREM
4 PHASE ENT

1 PT CORE-3 AS PER
2 SITE
C6-X-P-15 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

61 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 PT CORE-1 AS PER
2 SITE
C6-X-P-16 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-17 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT
1 PT CORE-3 AS PER
2 SITE
C6-X-P-18 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-1 AS PER
2 SITE
C6-X-P-19 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-20 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-21 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

62 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NC CONTACT FROM BCU (STATUS) 1HYB905115-3
3 NO CONTACT FROM BCU (STATUS)
4 SF6 LOCK OUT CONTACT FOR BCU
5 SF6 GAS LOW 1HYB905115-3
6 SPRING CHARGE INDICATION
7 COMMON +VE
8 COMMON +VE FOR OPEN/CLOSE STATAUS 1HYB905115-3
9 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)
C6-X-P-22 1 12CX2.5 CB-P BMK-P
10 NC CONTACT FOR REL 7SA611 (OPEN STATUS)
1HYB905115-3
11 COMMON +VE FOR INDICATION
12 CB OPEN INDICATION
13 CB CLOSE INDICATION
14
AUX NC FOR BKR INTERLOCKING CIRCUIT OF 1HYB905115-3
15 ISO
AS PER
16-19 SITE
REQUIREM
ENT
1 REMOTE-CLOSE
2 REMOTE-TRIP 1HYB905115-3
3 POST CLOSE SUPERVISION-1
4 PROTECTION TRIP

5 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


1HYB905115-3
6 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION
C6-X-P-23 1 12CX2.5 CB-P BMK-P
7 PROTECTION TRIP-2
8 POST CLOSE SUPERVISION-2

9 1HYB905115-3

10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO
5 AS PER
6 SITE
C6-X-P-24 1 10CX2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
7 REQUIREM
8 ENT
AUX NO FOR BKR CLOSING I/L CKT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11

63 of 83 Control cable
DATE RIV. PREPARED BY: AM
AS PER
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2
SITE CHECKED BY: AS
CABLE
C6-X-P-24
SCHEDULE
1 10CX2.5
FOR INCOMING
ISO-29-A BMK-P
CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED
REQUIREM
ENT
APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


12

64 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29B ISO
5 AS PER
6 SITE
C6-X-P-25 1 10CX2.5 ISO-29-B BMK-P AUX NC FOR I/L COIL OF 29A
7 REQUIREM
8 AUX NO FOR BKR CLOSING I/L CKT ENT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11
12

1 COMMON +VE OF BCU

2 NO CONTACT FOR STATUS IN BCU


3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO AS PER
5
SITE
C6-X-P-26 1 10CX2.5 ISO-29-L BMK-P
6 REQUIREM
AUX NC FOR I/L COIL OF 29B ENT
7

8
AUX NO FOR BKR CLOSING I/L CKT
9
10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3
INTERLOCK OF 29LE E/S
4
5
AUX NC FOR BKR CLOSING I/L CKT
6
7
AUX NC FOR I/L COIL OF 29l
8 AS PER
SITE
C6-X-P-27 1 10CX2.5 ISO-29-LE BMK-P
9 COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

10 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

11 NC CONTACT FOR REL 7SA611 (OPEN STATUS)

12
63.5V AC SUPPLY FROM PT
13
14-19

1
2 CT JB AS PER
3 CORE-1 SITE
C6-Y-P-28 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
4 REQUIREM
5 ENT

65 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB
CORE-1 CONTRACTOR : M/S SURYA
AS PER
SITE
C6-Y-P-28 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6

1
2
3 CT JB AS PER
CORE-2 SITE
C6-Y-P-29 1 4CX4 4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
5 ENT

66 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB CONTRACTOR : M/S SURYA AS PER
CORE-2 SITE
C6-Y-P-29 1 4CX4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6
6

1
2 CT JB AS PER
3 CORE-3 SITE
C6-Y-P-30 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1
2 CT JB AS PER
3 CORE-4 SITE
C6-Y-P-31 1 4CX4 CRP LINE DIFFERENTIAL RELAY G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1 AS PER
2 PT JB CORE-1
SITE
C6-Y-P-32 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-2
SITE
C6-Y-P-33 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-3
SITE
C6-Y-P-34 1 4CX4 CRP METERING G719EA-KG9032-E601
3 REQUIREM
4 ENT

1
TO CB CLOSING CIRCUIT
2
3 AS PER
SITE
C6-Y-P-35 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-1 REQUIREM
5 ENT
6
7-12

1
2
3 AS PER
SITE
C6-Y-P-36 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-2 REQUIREM
5 ENT
6
7-12

67 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU

2 CB-52 NC CONTACT FROM BCU (STATUS)

3 CB-52 NO CONTACT FROM BCU (STATUS)


4 COMMON +VE OF BCU FOR ISO

5 29A NO CONTACT FOR STATUS IN BCU

6 29A NC CONTACT FOR STATUS IN BCU AS PER


G719EA-KG9032-E601 SITE
C6-Y-P-37 1 12CX2.5 BMK-P CRP
REQUIREM
7 29B NO CONTACT FOR STATUS IN BCU ENT

8 29B NC CONTACT FOR STATUS IN BCU

9 29L NO CONTACT FOR STATUS IN BCU

10 29L NC CONTACT FOR STATUS IN BCU

11-12

68 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 COMMON +VE FOR OPEN/CLOSE STATAUS

CB-52 NO CONTACT FOR REL 7SA611 (CLOSE


2
STATUS)
CB-52 NC CONTACT FOR REL 7SA611 (OPEN
3
STATUS)
4 COMMON +VE FOR OPEN/CLOSE STATAUS
AS PER
29LE NO CONTACT FOR REL 7SA611 (CLOSE G719EA-KG9032-E601 SITE
C6-Y-P-38 1 12CX2.5 5 BMK-P CRP STATUS) REQUIREM
29LE NC CONTACT FOR REL 7SA611 (OPEN ENT
6
STATUS)

7 29LE NO CONTACT FOR STATUS IN BCU

8
LINE PT SUPPLY
9
10-12

1 CB-52 SF6 LOCK OUT CONTACT FOR BCU


2 CB-52 SF6 GAS LOW
3 CB-52 SPRING CHARGE INDICATION
4 COMMON +VE
AS PER
5 COMMON +VE FOR INDICATION SITE
C6-Y-P-39 1 12CX2.5 6 BMK-P CRP CB-52 CB OPEN INDICATION G719EA-KG9032-E601
REQUIREM
7 CB-52 CB CLOSE INDICATION ENT
8
9
FOR CB CLOSING AND TRIPPING CKT
10
11-12

1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-40 1 4CX4 CRP EXISTING CRP LBB TRIP CIRCUIT
3 REQUIREM WIRING
4 ENT

AS PER
1
LINE CB AND ISOLATOR INTER LOCK WITH DC SITE
C6-Y-P-41 1 4CX4 CRP BMK-P
SUPPLY REQUIREM
2
ENT

1
AS PER
SITE PART OF CRP INTER PANEL
C6-Z-P-43 1 4CX4 CRP EXISTING CRP 220V DC SUPPLY
2 REQUIREM WIRING
ENT

69 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-44 1 4CX4 CRP EXISTING CRP AC 1 PHASE SUPPLY
3--4 REQUIREM WIRING
ENT

1 AS PER
2 AC 1 PHASE SUPPLY FOR SPRING CHARGING SITE
C6-X-P-45 1 4CX4 BMK-P CRP
3 MOTOR REQUIREM
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-47 1 4CX4 CRP EXISTING CRP BUS PT-1 SELECTION
3 REQUIREM WIRING
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-48 1 4CX4 CRP EXISTING CRP BUS PT-2SELECTION
3 REQUIREM WIRING
4 ENT

70 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

SWITCH YARD
C6 6 FOR 66KV SWYD
1 FOR 11KV SWYD

THIS FIELD WILL BE SELECTED ON FOLLOWING CONDITIONS


X FOR CABLES WITHIN SWITCH YARD
X
Y FOR CABLES FROM SWITCH YARD TO CONTROL & RELAY PANEL
Z FOR CABLES FROM WITHIN CONTROL & RELAY PANELS

BAY NUMBER
P
9/10 FOR INCOMING LINE-2-

OO1 CABLE NO STARTING FROM 01 AND INCREMENT SUBSEQUENTLY

REFERENCE DRAWING :

DRAWINGS OF BMK CONTROL & PROTECTION PANEL FOR LINE BAY (602R)

66KV POTENTIAL TRANSFORMER 66KV POTENTIAL TRANSFORMER JB


66KV CURRENT TRANSFORMER 66KV CURRENT TRANSFORMER JB
66KV CIRCUIT BREAKER
66KV ISOLATOR

Notes

1. if 6cx4 sqmm cable is not available at store, then only 4cx4 sqmm cable to be used

2. if cable mentioned in this cable schedule is not available in store, then suitable alternate cable can be used at site as per availability
CABLE
FROM TO
SPECIFICATION
REFERENCE ROUTE
TER
CABLE TAG NO. RUNS CABLE TERM PURPOSE DRAWINNG & SHEET LENGTH REMARKS
CABLE MIN
SIZE EQUIPMENT INAL EQUIPMENT NO. (IN Mtrs.)
CORE ID AL
(IN mm2) NO.
NO.

71 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-1 AS PER
3 SITE consider one spare cable for
C6-X-P-01 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 R- REQUIREM CT of 4Cx4
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-02 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-03 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-04 1 4CX4 CT JB SPARE KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6
1
2 CT CORE-5 AS PER
3 SITE
C6-X-P-05 1 4CX4 CT JB SPARE KE-66CT05509
4 R- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-06 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-07 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

72 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-08 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-09 1 4CX4 CT JB SPARE KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-5 AS PER
3 SITE
C6-X-P-10 1 4CX4 CT JB SPARE KE-66CT05509
4 Y- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-1 AS PER
3 SITE
C6-X-P-11 1 4CX4 CT JB BCU CKT (BACK UP PROTECTION) KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-2 AS PER
3 SITE
C6-X-P-12 1 4CX4 CT JB METERING CIRCUIT KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-3 AS PER
3 SITE
C6-X-P-13 1 4CX4 CT JB LINE DIFFERENTIAL RELAY KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-4 AS PER
3 SITE
C6-X-P-14 1 4CX4 CT JB SPARE KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1
2 CT CORE-5 AS PER
3 SITE
C6-X-P-15 1 4CX4 CT JB SPARE KE-66CT05509
B- REQUIREM
PHASE ENT
73 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA
CT CORE-5 AS PER
DOC. NO. : ND-W-221-M-026 SITE
C6-X-P-15 1 4CX4 CT JB SPARE KE-66CT05509
4 B- REQUIREM
5 PHASE ENT
6

1 PT CORE-1 AS PER
2 SITE
C6-X-P-16 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-17 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

1 PT CORE-3 AS PER
2 SITE
C6-X-P-18 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 R- REQUIREM
4 PHASE ENT

74 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 PT CORE-1 AS PER
2 SITE
C6-X-P-19 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-20 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT
1 PT CORE-3 AS PER
2 SITE
C6-X-P-21 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 Y- REQUIREM
4 PHASE ENT

1 PT CORE-1 AS PER
2 SITE
C6-X-P-22 1 4CX4 PT JB BCU CKT (BACK UP PROTECTION) KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-23 1 4CX4 PT JB DISTANCE PROTECTION KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

1 PT CORE-2 AS PER
2 SITE
C6-X-P-24 1 4CX4 PT JB METERING CIRCUIT KE-66PT05579BS
3 B- REQUIREM
4 PHASE ENT

75 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NC CONTACT FROM BCU (STATUS) 1HYB905115-3
3 NO CONTACT FROM BCU (STATUS)
4 SF6 LOCK OUT CONTACT FOR BCU
5 SF6 GAS LOW 1HYB905115-3
6 SPRING CHARGE INDICATION
7 COMMON +VE
8 COMMON +VE FOR OPEN/CLOSE STATAUS 1HYB905115-3
9 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)
C6-X-P-25 1 12CX2.5 CB-P BMK-P
10 NC CONTACT FOR REL 7SA611 (OPEN STATUS)
1HYB905115-3
11 COMMON +VE FOR INDICATION
12 CB OPEN INDICATION
13 CB CLOSE INDICATION
14
AUX NC FOR BKR INTERLOCKING CIRCUIT OF 1HYB905115-3
15 ISO
AS PER
16-19 SITE
REQUIREM
ENT
1 REMOTE-CLOSE
2 REMOTE-TRIP 1HYB905115-3
3 POST CLOSE SUPERVISION-1
4 PROTECTION TRIP

5 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION


1HYB905115-3
6 PRE-CLOSE CIRCUIT TRIP-1 SUPERVISION
C6-X-P-26 1 12CX2.5 CB-P BMK-P
7 PROTECTION TRIP-2
8 POST CLOSE SUPERVISION-2

9 1HYB905115-3

10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO
5 AS PER
6 SITE
C6-X-P-27 1 10CX2.5 ISO-29-A BMK-P AUX NC FOR I/L COIL OF 29B
7 REQUIREM
8 ENT
AUX NO FOR BKR CLOSING I/L CKT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11

76 of 83 Control cable
DATE RIV. PREPARED BY: AM
AS PER
PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2
SITE CHECKED BY: AS
CABLE
C6-X-P-27
SCHEDULE
1 10CX2.5
FOR INCOMING
ISO-29-A BMK-P
CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED
REQUIREM
ENT
APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


12

77 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU
2 NO CONTACT FOR STATUS IN BCU
3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29B ISO
5 AS PER
6 SITE
C6-X-P-28 1 10CX2.5 ISO-29-B BMK-P AUX NC FOR I/L COIL OF 29A
7 REQUIREM
8 AUX NO FOR BKR CLOSING I/L CKT ENT
9
10
AUX NC FOR BKR CLOSING I/L CKT
11
12

1 COMMON +VE OF BCU

2 NO CONTACT FOR STATUS IN BCU


3 NC CONTACT FOR STATUS IN BCU
4
INTERLOCK COIL OF 29A ISO AS PER
5
SITE
C6-X-P-29 1 10CX2.5 ISO-29-L BMK-P
6 REQUIREM
AUX NC FOR I/L COIL OF 29B ENT
7

8
AUX NO FOR BKR CLOSING I/L CKT
9
10

1 COMMON +VE OF BCU


2 NO CONTACT FOR STATUS IN BCU
3
INTERLOCK OF 29LE E/S
4
5
AUX NC FOR BKR CLOSING I/L CKT
6
7
AUX NC FOR I/L COIL OF 29l
8 AS PER
SITE
C6-X-P-30 1 10CX2.5 ISO-29-LE BMK-P
9 COMMON +VE FOR OPEN/CLOSE STATAUS REQUIREM
ENT

10 NO CONTACT FOR REL 7SA611 (CLOSE STATUS)

11 NC CONTACT FOR REL 7SA611 (OPEN STATUS)

12
63.5V AC SUPPLY FROM PT
13
14-19

1
2 CT JB AS PER
3 CORE-1 SITE
C6-Y-P-31 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
4 REQUIREM
5 ENT

78 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB
CORE-1 CONTRACTOR : M/S SURYA
AS PER
SITE
C6-Y-P-31 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6

1
2
3 CT JB AS PER
CORE-2 SITE
C6-Y-P-32 1 4CX4 4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
5 ENT

79 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10CT JB CONTRACTOR : M/S SURYA AS PER
CORE-2 SITE
C6-Y-P-32 1 4CX4 CRP METERING CIRCUIT G719EA-KG9032-E601
REQUIREM
DOC. NO. : ND-W-221-M-026 ENT
6
6

1
2 CT JB AS PER
3 CORE-3 SITE
C6-Y-P-33 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1
2 CT JB AS PER
3 CORE-4 SITE
C6-Y-P-34 1 4CX4 CRP LINE DIFFERENTIAL RELAY G719EA-KG9032-E601
4 REQUIREM
5 ENT
6

1 AS PER
2 PT JB CORE-1
SITE
C6-Y-P-35 1 4CX4 CRP BCU CKT (BACK UP PROTECTION) G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-2
SITE
C6-Y-P-36 1 4CX4 CRP DISTANCE PROTECTION G719EA-KG9032-E601
3 REQUIREM
4 ENT

1 AS PER
2 PT JB CORE-3
SITE
C6-Y-P-37 1 4CX4 CRP METERING G719EA-KG9032-E601
3 REQUIREM
4 ENT

1
TO CB CLOSING CIRCUIT
2
3 AS PER
SITE
C6-Y-P-38 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-1 REQUIREM
5 ENT
6
7-12

1
2
3 AS PER
SITE
C6-Y-P-39 1 10CX2.5 4 CB-P CRP G719EA-KG9032-E601
TRIP COIL-2 REQUIREM
5 ENT
6
7-12

80 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 COMMON +VE OF BCU

2 CB-52 NC CONTACT FROM BCU (STATUS)

3 CB-52 NO CONTACT FROM BCU (STATUS)


4 COMMON +VE OF BCU FOR ISO

5 29A NO CONTACT FOR STATUS IN BCU

6 29A NC CONTACT FOR STATUS IN BCU AS PER


G719EA-KG9032-E601 SITE
C6-Y-P-40 1 12CX2.5 BMK-P CRP
REQUIREM
7 29B NO CONTACT FOR STATUS IN BCU ENT

8 29B NC CONTACT FOR STATUS IN BCU

9 29L NO CONTACT FOR STATUS IN BCU

10 29L NC CONTACT FOR STATUS IN BCU

11-12

81 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026

1 COMMON +VE FOR OPEN/CLOSE STATAUS

CB-52 NO CONTACT FOR REL 7SA611 (CLOSE


2
STATUS)
CB-52 NC CONTACT FOR REL 7SA611 (OPEN
3
STATUS)
4 COMMON +VE FOR OPEN/CLOSE STATAUS
AS PER
29LE NO CONTACT FOR REL 7SA611 (CLOSE G719EA-KG9032-E601 SITE
C6-Y-P-41 1 12CX2.5 5 BMK-P CRP STATUS) REQUIREM
29LE NC CONTACT FOR REL 7SA611 (OPEN ENT
6
STATUS)

7 29LE NO CONTACT FOR STATUS IN BCU

8
LINE PT SUPPLY
9
10-12

1 CB-52 SF6 LOCK OUT CONTACT FOR BCU


2 CB-52 SF6 GAS LOW
3 CB-52 SPRING CHARGE INDICATION
4 COMMON +VE
AS PER
5 COMMON +VE FOR INDICATION SITE
C6-Y-P-42 1 12CX2.5 6 BMK-P CRP CB-52 CB OPEN INDICATION G719EA-KG9032-E601
REQUIREM
7 CB-52 CB CLOSE INDICATION ENT
8
9
FOR CB CLOSING AND TRIPPING CKT
10
11-12

1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-43 1 4CX4 CRP EXISTING CRP LBB TRIP CIRCUIT
3 REQUIREM WIRING
4 ENT

AS PER
1
LINE CB AND ISOLATOR INTER LOCK WITH DC SITE
C6-Y-P-44 1 4CX4 CRP BMK-P
SUPPLY REQUIREM
2
ENT

1
AS PER
SITE PART OF CRP INTER PANEL
C6-Z-P-45 1 4CX4 CRP EXISTING CRP 220V DC SUPPLY
2 REQUIREM WIRING
ENT

82 of 83 Control cable
DATE RIV. PREPARED BY: AM

PROJECT: 66/11KV OUT DOOR GRID SUBSTATION AT RG-DC-1 2/27/2018 R2 CHECKED BY: AS
CABLE SCHEDULE FOR INCOMING CLIENT: TATA POWER DELHI DISTRIBUTION LIMITED APPROVED BY: SRC
LINE-BAY-9&10 CONTRACTOR : M/S SURYA

DOC. NO. : ND-W-221-M-026


1 AS PER
2 SITE PART OF CRP INTER PANEL
C6-Z-P-46 1 4CX4 CRP EXISTING CRP AC 1 PHASE SUPPLY
3--4 REQUIREM WIRING
ENT

1 AS PER
2 AC 1 PHASE SUPPLY FOR SPRING CHARGING SITE
C6-X-P-47 1 4CX4 BMK-P CRP
3 MOTOR REQUIREM
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-48 1 4CX4 CRP EXISTING CRP BUS PT-1 SELECTION
3 REQUIREM WIRING
4 ENT

1 AS PER
2 SITE PART OF CRP INTERPANEL
C6-Z-P-49 1 4CX4 CRP EXISTING CRP BUS PT-2SELECTION
3 REQUIREM WIRING
4 ENT

83 of 83 Control cable