Professional Documents
Culture Documents
Acp Exa Icg Pci Qly Ps 009 Fat Procedure Rev.a
Acp Exa Icg Pci Qly Ps 009 Fat Procedure Rev.a
DOCUMENT NO. :
ACP-EXA-ICG-PETRO-QLY-PS-009
PT PETROCHINA INTERNATIONAL JABUNG LTD
CONTRAKTOR :
PROJECT NO. :
J002-18-ACP
PT INDO CIPTA GEMILANG
PACKAGER
Page
1 of 14
PT EXATRA ENJINERING PT AZYMUTH CITRA PERKASA
Approved
Approved With Comment
Resubmit For Approval
NOTES:
APPROVAL OF THIS DOCUMENT WILL NOT RELIEVE
CONTRACTOR FROM ITS OBLIGATION TO COMPLETE
ALL THE WORK IN ACCORDANCE WITH THE TERMS OF
THE CONTRACT
USER
Rev
Date Description BY CHK’D REV’D APPR
No.
REVISION LIST
TABLE OF CONTENTS
I. INDEX
Table OF Contents...................................................................................... 2
1. GENERAL DESCRIPTION
1.1. FAT Location............................................................................... 3
1.2. FAT Organization......................................................................... 3
1.3. FAT Schedule.............................................................................. 4
1.4. Safety......................................................................................... 4
1.5. Required Test Equipment............................................................. 5
1.6. Required Document..................................................................... 5
3. TEST COMPLETION........................................................................... 11
4. PUNCH LIST...................................................................................... 12
5. VARIATION LIST.............................................................................. 14
6. LIST OF ATTACHMENTS................................................................... 15
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 4 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
1. GENERAL DESCRIPTION
This document describe the test and inspection procedures for the system under test of 10
unit Gas Wellhead Shutdown Panel, Betara Gas Plant Ware House Project,
PetroChina Jabung Ltd.
Factory Acceptance Test (FAT) will be carried out the precense of representatives from client.
This FAT Procedure covers all vital system functionally test. They are demonstrative rather than
exhaustive test.
In some intances, when mutually agreed by client and MES at resting during FAT is impractical
and/or impossible, the project quality assurance records of MES and/or equipment
manufacturer shall be provided as evidence of compliance instead of testing during FAT
Test results and data shall be recorded in the Test Result Box with both Representatives initials.
There will be two lists attached the FAT Report :
Upon succesful completion of FAT, the Client is expected to sign Systems Acceptance Certificate.
1 Visual Inspection
1 Leak Test
1 Function Test
1.4. SAFETY
In the course of testing, care shall be excercised to ensure personnel safety and also
to ensure equipment is not at risk of being damaged.
1. Simulator Panel
2. Air Compressor complete with Air Dryer or N2 Bottle
3. Test Gauge
4. Installation Tools related
1. Identify and verify that each component in the system cabinets is complete refer
to Bill of Material document The result shall be recorded into Check Sheet for
Material Inspection (Attachment)
2. Verify the correct materials were used and there is no physical damage on each
of component
Comment :
Witnessed By :
PetroChina International Jabung Ltd.
Date :
Tested By :
PT. Azymuth Citra Perkasa
Date :
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 7 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
Comment :
Witnessed By :
PetroChina International Jabung Ltd.
Date :
Tested By :
PT Azymuth Citra Perkasa
Date :
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 8 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
1. The tubing pressure test for pneumatic system will be applied between the
bulkhead connection and isolation valves at the maximum operating system
pressure.
2. Test duration shall be minimum 30 minute, and check indication of the test gauge
for any decrease value
3. Perform test for all pneumatic lines of WHCP
Comment :
Witnessed By :
PetroChina International Jabung Ltd.
Date :
Tested By :
PT Azymuth Citra Perkasa
Date :
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 9 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
Functional test inspection shall be performed base on Document drawing no. ACP-EXA-
ICG-PCI-PID-002 SCHEMATIC DIAGRAM REV.0 “Schematic Diagram Wellhead Shutdown
Panel” Betara Gas Plant Ware House Project, PetroChina Jabung Ltd..
1. This test shall be performed in order to verify that the system will be started up, and
works properly as per approved design and specifications.
2. Sequences of the test shall be performed as per attached document of Check Sheet
for Start-up Sequencing.
3. Perform the test for each Wells.
Comment :
Witnessed By :
PetroChina International Jabung Ltd.
Date :
Tested By :
PT Azymuth Citra Perkasa
Date :
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 10 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
Comment :
Witnessed By :
PetroChina International Jabung Ltd.
Date :
Tested By :
PT Azymuth Citra Perkasa
Date :
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 11 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
3. TEST COMPLETION
Any equipment or material that failed in any testing and were replaces must be tested. The
system configuration sheets and test discrepancy sheets must be updated whenever the
equipment or material fails and is replaced.
Comment :
Witnessed By :
PetroChina International Jabung Ltd.
Date :
Tested By :
PT Azymuth Citra Perkasa
Date :
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 12 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
4. PUNCH LIST
PUNCH LIST
Rectified Acknowledge
Item Description Sign
Date By
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 13 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
PUNCH LIST
Rectified Acknowledge
Item Description Sign
Date By
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 14 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
5. VARIATION LIST
(If required only based on mutual agreement between PT. Azymuth Citra Perkasa
/PetroChina International Jabung Ltd.)
VARIATION LIST
Rectified Acknowledge
Item Description Sign
Date By
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
ACP-EXA-ICG-PETRO-QLY-
Doc. No. PS-009
FACTORY ACCEPTANCE TEST PROCEDURE
REV. A Page 15 of 15
WELL HOOK UP FLOW LINE INSTRUMENTATION
PACKAGE WELLHEAD CONTROL PANEL DATE. 11-Dec-18
6. ATTACHMENTS
List of Attachments :