Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

VOL.

315, SEPTEMBER 22, 1999 “Foregone


13 Profit” from the two Letters of 300,000 pieces of rattan poles at P9.65 per
Credit. Such could not be considered as actual piece for a total price of P2,895,000.00,
Domel Trading Corporation vs. Court of Appeals
damages. also to be delivered within 60 days from
G.R. No. 84813. September 22, 1999. *

DOMEL TRADING CORPORATION, the date of the opening of a letter of credit.


PETITION for review on certiorari of a
petitioner, vs. HONORABLE COURT OF The specifications and provisions of both
decision of the Court of Appeals.
APPEALS and NDC-NACIDA RAW transactions, which served as their
MATERIALS, CORPORATION, The facts are stated in the opinion of the agreement, were printed in two separate
respondents. Court. purchase orders. 2

G.R. No. 84848. September 22, 1999. * In accordance with their agreement,
NDC-NACIDA RAW MATERIALS, _______________ NNRMC, on July 9, 1981, opened a letter
CORPORATION, petitioner, vs. DOMEL of credit with Philippine National Bank
* FIRST DIVISION. (PNB) in favor of DOMEL in the amount
TRADING CORPORATION, respondent. 14
Obligations; Contracts; Damages; In of P1,997,000.00 to cover its order for
14 SUPREME COURT REPORTS
determining whether a penalty clause is 206,943 pieces of rattan poles. On July 13,
ANNOTATED
“iniquitous and unconscionable,” a court may 1981, NNRMC opened another letter of
very well take into account the actual damages Domel Trading Corporation vs. Court of Appeals
credit in favor of DOMEL in the amount of
sustained by a creditor who was compelled to Bonifacio Law Office and Omar N.C. P1,236,000.00 to cover the price of 93,057
sue the defaulting debtor, which actual Alamfor Domel Trading Corporation. pieces of rattan poles and 22,000 bundles
damages would include the interest and Castillo, Laman, Tan, Pantaleon & of buri midribs.
penalties the creditor may have had to pay on San Jose for petitioner NDC-Nacida Raw In violation of their agreement,
its own from its funding source.—In Materials, Corp.
determining whether a penalty clause is DOMEL failed to deliver the buri midribs
“iniquitous and unconscionable,” a court may and rattan poles within the stipulated pe-
YNARES-SANTIAGO, J.:
very well take into account the actual
_______________
damages sustained by a creditor who was Assailed before this Court is the
compelled to sue the defaulting debtor, which decision of the Court of Appeals in CA-
1 1 Penned by Associate Justice Fidel P. Purisima

actual damages would include the interest and (now Associate Justice of the Supreme Court) and
G.R. CV No. 08952which modified the
penalties the creditor may have had to pay on concurred in by Associate Justices Segundino G.
decision of the lower court granting Chua and Nicolas P. Lapena, Jr.
its own from its funding source. In this case,
NNRMC was only able to prove that it private respondent’s prayer for damages. 2 Exhibits “B” and “C,” Records, pp. 56 & 57.

incurred the amounts of P5,995.83 as opening On June 3, 1981, private respondent 15


charges on the two Letters of Credit and an NDC-NACIDA Raw Materials VOL. 315, SEPTEMBER 22, 1999 15
additional P1,911.85 as amendment charges Corporation (NNRMC) ordered from Domel Trading Corporation vs. Court of Appeals
on the same Letters of Credit. Other than that, petitioner Domel Trading Corporation riod. Thus, on September 23, 1981,
NNRMC failed to prove it had suffered actual (DOMEL) 22,000 bundles of buri midribs DOMEL and NNRMC agreed to
damages resulting from the nondelivery of the at P16.00 per bundle to be delivered restructure the latter’s purchase orders in
specified buri midribs and rattan poles. In within 30 working days from the date of a Memorandum of Agreement. Under the3

fact, what it allegedly suffered are what it the opening of a letter of credit. On June agreement, NNRMC extended the expiry
calls “Foregone Interest Income” and
4, 1981, private respondent again ordered date of its two letters of credit to
November 5, 1981. It also reduced the “WHEREFORE, appealed judgment is additional handling expenses in case the
quantity of the rattan poles from 300,000 modified as above-indicated and appellant is deliveries were rejected because the purchase
to only 100,000 pieces while the quantity hereby ordered to pay appellee liquidated of the supplies and materials may not conform
of buri midribs remained at 22,000 damages of P150,000.00, to reimburse the to what is being specified. If inspections were
latter the amount of P7,907.68 on subject conducted, the danger and expenses connected
bundles. Further, DOMEL undertook to
letters of credit, with interest of six (6) percent
therewith for the return of the rejected
deliver the goods on or before October 31,
per annum from August 4, 1982 on said materials would be minimized. In other words,
1981. However, no deliveries were again amounts of P150,000.00 and P7,907.68; and to the need for the inspection cannot be done
made on the said date. Consequently, pay attorney’s fees of P20,000.00. Costs away to avoid further losses not only on the
demands were made by NNRMC on against appellee.” part of the obligor but also for the benefit of
January 19, 1982 for the payment of the obligee, although indirectly, in the sense
damages, which demands were ignored by _______________ that in case the supplies and materials are
DOMEL. rejected the obligee also suffers from the
3Exhibit “F,” Records, p. 60.
Hence, NNRMC filed a complaint for diminished profits.
16
damages before the Regional Trial Court “x x x xxx xxx
16 SUPREME COURT REPORTS
of Pasig. After trial, judgment was “In other words, because of the fact that the
ANNOTATED subject supplies were understood to come from
rendered in favor of plaintiff and against Domel Trading Corporation vs. Court of Appeals
the Visayas and parts of far flung Mindanao,
defendant, the dispositive portion of which
Both DOMEL and NNRMC assail the there is indeed a need for inspection because
reads:
above-quoted decision in separate several deliveries would be made. This is so
“WHEREFORE, judgment is hereby rendered
petitions which have been consolidated because if the inspection is not conducted,
in favor of plaintiff and against defendant, what would stop the private respondent from
ordering the latter to pay the former: before this Court.
Based on the pleadings submitted by rejecting all deliveries and in such
1. 1)the sum of Nine Hundred Eight the parties, this Court has resolved to give eventuality, as the petitioner herein would be
placing said orders from suppliers from
Thousand Nine Hundred Sixty Six due course to the petition and decides the
Visayas and far flung Mindanao only to be
and 77/100 Pesos (P908,966.77), same. rejected by the private respondent upon
representing actual and contractual DOMEL submits it has not breached its delivery; hence, the losses to be shouldered by
damages, with legal interest thereon contractual obligation to NNRMC the petitioner under an inequitable
from August 4, 1982, when the inasmuch as it was the fault of the latter arrangement would be unthinkable. It thus
complaint was filed until fully paid, for not inspecting and examining the follows then that the inspection is
and rattan poles as well as the buri midribs indispensably necessary to give rise to the
2. 2)the further sum equivalent to fifteen
already shipped by the suppliers and agreement to supply.” 4

percent (15%) of the total of the


foregoing for and as attorney’s fees
stored in the former’s warehouse. Thus, it
_______________
and litigation expenses.” should not be made liable for liquidated
and other damages. DOMEL argues in 4Domel’s Petition, Rollo, G.R. 84813, pp. 17-29.
On appeal, the Court of Appeals modified this wise: 17

the decision of the lower court, as follows: “Experience had shown that it would be more VOL. 315, SEPTEMBER 22, 1999 17
expedient that goods and materials to be Domel Trading Corporation vs. Court of Appeals
delivered must first be inspected so as to avoid
In short, DOMEL claims that NNRMC stop the private respondent from rejecting signified his agreement to ship items
must first inspect the ordered items before all deliveries and in such eventuality, as according to the specifications. By affixing
delivery could be made. the petitioner herein would be placing said his signature, he signified his assurance to
We do not agree. orders from suppliers from Visayas and NNRMC that DOMEL can deliver the
The purchase order, which constitutes
5 far flung Mindanao only to be rejected by materials as specified. Accordingly,
the contract between DOMEL and the private respondent upon delivery.” DOMEL had the obligation to ensure that
NNRMC, provides the specifications for the goods ordered by NNRMC were in
_______________
the buri midribs, thus: accordance with the specifications
“20,000 bundles of buri midribs ‘Class A and 5 Exhibit “B,” Records, p. 56. provided in the purchase orders. The duty
B; Palawan, Zamboanga, Cotabato origin; 6 Exhibit “C,” Records, p. 57. of inspecting the materials did not fall on
1,000 pcs. per bundle, 6 ft. up” 18 NNRMC, otherwise, it could have dealt
“2,000 bundles of buri midribs “Class A and 18 SUPREME COURT REPORTS directly with the suppliers and not
B; Palawan, Zamboanga, Cotabato origin, ANNOTATED through DOMEL.
1,000 pcs. per bundle 3 ft.-5 ft.”
Domel Trading Corporation vs. Court of AppealsAlthough it was stated in the amended
The purchase order for rattan poles
6

DOMEL assumes that NNRMC might Letters of Credit that PNB required a
7

contains the following specifications, thus:


“300,000 pieces of rattan poles, Palasan
reject the items if they were delivered Certificate of Inspection from NNRMC,
variety, 1-1/4 and up, straightened, cleaned, without first being inspected. That nevertheless, it is the view of this Court
chemically treated, single, scraped and free assumption would, in turn, rest on the that the Certificate of Inspection was not
from molds, and pinholes, by 14 feet long, supposition that the goods and materials an indispensable requirement or condition
Cotabato/Zamboanga origin” delivered might not conform to precedent for DOMEL to comply with its
The purchase orders were duly noted and specifications or might be defective when obligation to deliver the specified buri
confirmed by Mr. Gerardo R. Jose, the Vice delivered. midribs and rattan poles. First, it was a
President of DOMEL. It is thus clear that The reasoning is flawed. First, DOMEL requirement by PNB from NNRMC.
DOMEL agreed to provide the buri was bound to deliver the goods according Second, it was only stated in the Letter of
midribs and the rattan poles in accordance to specifications. It is not for NNRMC, as Credit which is a contract entered into by
with the specifications provided by the buyer, to ensure that the goods and NNRMC with PNB. The provisions in the
NNRMC. materials ordered conform with the Letter of Credit were not carried into as
Therefore, there is no merit in specifications. Precisely, NNRMC fixed additional stipulations in the purchase
DOMEL’s argument that “goods and the specifications of the items it wanted orders which is the contract between
materials to be delivered must first be delivered. Second, it was DOMEL which DOMEL and NNRMC. As such, it should
inspected so as to avoid additional dealt with the suppliers of the goods not in any way affect DOMEL’s
handling expenses in case the deliveries needed by NNRMC. Consequently the
were rejected because the purchase of the task of inspecting the items fell on _______________
supplies and materials may not conform to DOMEL which should, therefore, ensure Exhibits “H” and “G,” Records, p. 64.
7

what is being specified.” There is likewise that the suppliers ship goods that strictly 19
no basis for DOMEL to argue that “if the comply with the specifications required by VOL. 315, SEPTEMBER 22, 1999 19
inspection is not conducted, what would NNRMC. Third, Mr. Jose of DOMEL Domel Trading Corporation vs. Court of Appeals
obligation to deliver the goods to NNRMC. In the assailed decision modifying the order to make sure that what it was procuring
At most, it may only affect DOMEL’s decision of the lower court as to the were acceptable to the appellee. It was not
collection of payment from PNB. Third, stipulated amount of liquidated damages, enough for appellant to write appellee about
granting that it was an obligation by the Court of Appeals ratiocinated thus: the matter. More follow-ups on its part were
“x x x The lower court did not err in finding a required under the circumstances. Its failure
NNRMC to conduct the inspection and
breach of contract on the part of defendant to do so exposed itself to the inevitable
issue the corresponding certificate,
appellant. The mere fact that plaintiff’s conclusion that it was actually unable to fill-
nowhere in the Letters of Credit, Purchase up the quantity and quality of buri midribs
Orders or the Memorandum of Agreement representative failed to make the requested
inspection of the initial stocks of buri midribs and rattan poles contracted for the appellee.
is it found that the inspection should be Therefore, the failure of plaintiff’s Yatco to
and rattan poles in appellant’s warehouse did
conducted before delivery of the goods. It is make the promised inspection of appellant’s
not constitute a complete defense or
NNRMC’s lookout if it does not conduct justification for the admitted failure of the stocks can only serve to mitigate appellant’s
the inspection before the goods are appellant to deliver the contracted items. At civil liability for the breach of contract
delivered. Besides, considering the best, such circumstance alone could merely litigated upon. Instead of requiring appellant
natural sequence of events in business mitigate defendant-appellant’s liability for the to pay the stipulated liquidated damages of
transactions, it is incumbent upon the liquidated damages of P2,000.00 per day of P2,000.00 for every day of delay, P1,000.00 per
delay. As correctly observed by the trial court, day should suffice under the premises.
supplier, in this case DOMEL, to first
even assuming that Conformably, the P300,000.00 of liquidated
make the delivery to NNRMC, the buyer,
20 damages awarded below should be reduced to
before it can properly inspect the items. only P150,000.00.”
In view of the above disquisition, it is 20 SUPREME COURT REPORTS
ANNOTATED While we do not agree with the Court of
clear that DOMEL breached its obligation Appeals that the failure of NNRMC to
to NNRMC by failing to deliver to the Domel Trading Corporation vs. Court of Appeals
conduct the inspection mitigated
latter the specified buri midribs and the 5,000 buri midribs and 2,000 rattan poles
then ready for inspection were really available DOMEL’s liability for liquidated damages,
rattan poles. In assailing the decision of nevertheless, we agree in the reduction of
for delivery upon satisfactory inspection
the Court of Appeals, NNRMC, in turn, the amount of liquidated damages to only
thereof, such quantities were shy of what
submits the following: P150,000.00. The amount of P2,000.00 as
appellant was bound to deliver to appellee.
But, of course, it can be perceived that the penalty for every day of delay is excessive
1. 1.DOMEL is liable to NNRMC for the failure of plaintiff to make the promised and unconscionable.
full amount of contractually inspection could have slowed down or deterred
determined liquidated damages; and
Article 1229 of the Civil Code states,
appellant’s efforts to meet its commitment, in thus:
2. 2.DOMEL is liable to NNRMC for view of its uncertainty of the acceptability of
actual and contractual damages in “The judge shall equitably reduce the penalty
its stock of buri midribs and rattan poles. when the principal obligation has been partly
the total amount of P908,966.77 with However, such failure of plaintiff to cause the
legal interest thereon from January or irregularly complied with by the
desired inspection of appellant’s stock of buri debtor. Even if there has been no performance,
19, 1982 when extrajudicial demand midribs and rattan poles did not totally excuse
was made, until fully paid and 15% of the penalty may also be reduced by the courts
appellant from increasing its supply of such if it is iniquitous or unconscionable.”
the foregoing sum for and as items. At the very least, it should have
attorney’s fees and litigation Article 2227 of the Civil Code likewise
brought samples of the buri midribs and
expenses. states, thus:
rattan poles it had to the office of appellee in
21 connection with the first assignment of error, unspecified to induce faith and reliance.
VOL. 315, SEPTEMBER 22, 1999 the21amount of liquidated damages has to be Absent the needed quantum of proof, We are
lessened to P150,000.00. But the charges of of the sense that, apart from the aforestated
Domel Trading Corporation vs. Court of Appeals
“Liquidated damages, whether intended as an P5,995.83 and P1,911.85 on the two letters of amount of liquidated damages and
indemnity or a penalty, shall be equitably credit involved should be reimbursed by reimbursement of the charges paid by appellee
reduced if they are iniquitous or appellant (tsn, p. 23, July 13, 1983 hearing). for the unutilized letters of credit, no other
unconscionable.” As regards the alleged forgone profits of damages can be granted.”
In determining whether a penalty clause P206,943.00 testified on by Jose Victorioso as WHEREFORE, the Decision of the Court
is “iniquitous and unconscionable,” a court the profit appellee could have realized had of Appeals in C.A.-G.R. CV No. 08952,
appellant been able to supply the goods in dated August 22, 1988, is AFFIRMED in
may very well take into account the actual
question, we consider such amount of expected toto.
damages sustained by a creditor who was profit highly conjectural and speculative (p.
compelled to sue the defaulting debtor, SO ORDERED.
24, id.). The aforesaid testimony regarding the
which actual damages would include the Davide,
matter of profits is utterly lacking of the
interest and penalties the creditor may requisite details on how such huge amount of Jr. (C.J.), Puno, Kapunan and Pardo,
have had to pay on its own from its profits could be made possible. Plaintiff- JJ., concur.
funding source. In this case, NNRMC was
8 appellee’s witness did not detail out how such Reviewed decision affirmed in toto.
only able to prove that it incurred the huge amount of gain could have been derived Note.—In order that the debtor may be
amounts of P5,995.83 as opening charges from the would-be exporta- in default it is necessary that the following
on the two Letters of Credit and an requisites be present: (a) that the
_______________
additional P1,911.85 as amendment obligation be demandable and already
charges on the same Letters of Credit. 8 Pacific Mills, Inc. v. Court of Appeals, 206 SCRA liquidated; (b) that the debtor delays
Other than that, NNRMC failed to prove 317 [1992]. performance; and (c) that the creditor
22 requires the performance judicially and
it had suffered actual damages resulting
22 SUPREME COURT REPORTS extrajudicially. (Social Security System vs.
from the nondelivery of the specified buri
ANNOTATED Moonwalk Development and Housing
midribs and rattan poles. In fact, what it
allegedly suffered are what it calls Domel Trading Corporation vs. Court of Appeals Corporation, 221 SCRA 119 [1993])
“Foregone Interest Income” and “Foregone tion of buri midribs and rattan poles. Well-
Profit” from the two Letters of Credit.
entrenched is the doctrine that actual, ——o0o——
compensatory and consequential damages
Such could not be considered as actual must be proved, and cannot be presumed (Hua
damages. We agree with the following Liong Electrical Equipment Corporation v.
observation of the Court of Appeals: Reyes, 145 SCRA 713). If, as in this case, the
“Necessarily, We discern some merit in the proof adduced thereon is flimsy and
second assignment of error. The trial court insufficient, no damages will be allowed
erred in holding the appellant liable for (Rubio v. Court of Appeals, 141 SCRA 488).
P908,966.72 in damages. The said unitemized Verily, the testimonial evidence on alleged
amounts and various types of damages is too unrealized profits earlier referred to is not
much and has to be reduced within reasonable enough to warrant the award of damages
limits. As already elaborated upon in appealed from. It is too scanty, vague and

You might also like