Document Review Sheet

From: KEIL To: PETROJET


Contract: KEIL/SIBA/2015/C-051
Document Title: MCC for Sour Gas Compression OH Stabilizer Compressor
Document No.: C-051-390-MCC-TR2-01-003 Revision:
Touchstone Document No.:
Please respond by: (Refer to Transmittal for Return Date)
The document as listed above has been reviewed and has been found to be:

Reviewed - no comment. Revise and re-submit. Revise and re-submit.


Work may proceed subject to incorporation Work will NOT proceed.
of comments.

*(Tick as appropriate)

Sl. No. Comments (Identify Section/Page/Paragraph) Response


Mechanical/Piping
Noted and Attached in Sec.7.2,7.3,7.4,7.9
All reports provided in section 7 for the following equipment to be
1 corrected (reports of Train1 have been provided instead Train2)
- V-2411, V-2412, V-2413, V-2414, V-2417, V-2418

Include the attached drawings of the on-skid lube oil makeup tank Noted and Attached in Sec.2-and Sec15
2 TK-2881 and provide the installation reports (if any).

Instrumentation

Page 1 of 6
Classification: General
Sl. No. Comments (Identify Section/Page/Paragraph) Response
Loop folder for all instruments related with this subsystem to be This Comment Shall be Added in ICSS System
added in ICSS subsystem MCC Dossier. Hardwired interfaces signals
from compressor 2110 to ICSS 02-ESD-16210, 02-XA-162110, 02-XA-
1 16211, 02-PIC-162111 are missing in the ICSS MCC dossier.

Safety Relief Valve 02-PSV-2418 to be included in the list of PSV-2418 Rejected in Calibration and
instrument in this MCC dossier. Also calibration report and field recalibrated and installed by KEIL.
2 instrument report shall be provided

Since that Compressor 2110 is part of this subsystem. SAT for Noted and Coverd in MPL POINT NO(8176)
Compressor 2110 will be added in this MCC dossier (Add as Punch B)
3

Instruments such as PCV-2881A, PI-2881A, PSV-2881A, LG-2881A, LG- Noted and Coverd in Sec.11.1
2881B related with Stabilizer OH compressor cylinder lube oil
makeup tank TK-2881 and stabilizer OH compressor that are part of
this subsystem. Those instruments to be included in section 11.1 List
4 of Instruments. Refer P&ID -859 - 05R2

Instrument Tag no. of 02-PI-2414 is wrong. As per P&ID should be 02- Updated in MPL as B no: 8224.
5 PI-2414 but install at site is 02-PI-2314.

Civil
No Comments

Electrical
Solo run Test Sheet for MV motor C-2110 has not been done. Once noted and coverd in MPL POINT NO(8177)
1 completed, the Checksheet to be attached.

FAT reports for the OH Compressor. noted and coverd in MPL POINT NO(8178)
2
3 Detail information of Compressor UCP including but not limited to noted and coverd in MPL POINT NO(8179)
GAD, Interconnection, FAT reports, Schematics, Operating Manual.,
etc.

Page 2 of 6
Classification: General
Sl. No. Comments (Identify Section/Page/Paragraph) Response
Name: Zainuddin/Munther/ Alaa/Dilio Name: Ehab
Date: 29/05/18 Date:5/6/2018.
Note: Please add/ insert rows for additional comments/ response(s).Do not add additional column.

Page 3 of 6
Classification: General
1

evise and re-submit. Review not Required - for


ork will NOT proceed. information only.

Conclusion

Closed.

Closed.

Page 4 of 6
Classification: General
Conclusion

Closed.

Closed.

Closed.

Closed.

Closed.

Closed.

Closed.

Closed.

Page 5 of 6
Classification: General
Conclusion
Name: Zainuddin/Munther
Date: 8/6/2018.