Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

TUN RAZAK EXCHANGE

CONTRACT 2- PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND


ROADWAY WORKS

# Activity ID Activity Name Original Start Finish 2018 2019


Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 Total 268 30-Mar-18 A 22-Dec-18 22-Dec-18, Total

2 Section 12 Programme for Priority Infrastructure 268 30-Mar-18 A 22-Dec-18 22-Dec-18, Section 12 Progra

3 Structure Work 229 30-Mar-18 A 13-Nov-18 13-Nov-18, Structure Work


4 Zone 1 (Panel P99, P100, P101) 153 14-May-18 A 13-Oct-18 13-Oct-18, Zone 1 (Panel P99, P100, P101)
5 CBD Loop L2 46 29-Aug-18 13-Oct-18 13-Oct-18, CBD Loop L2
6 Super Structure 46 29-Aug-18 13-Oct-18 13-Oct-18, Super Structure
7 A29910 Pier / Column PF 1-1 (2 Nos) 7 29-Aug-18 04-Sep-18 Pier / Column PF 1-1 (2 Nos)
8 A29920 Pier / Column PF 1-2 (2 Nos) 7 29-Aug-18 04-Sep-18 Pier / Column PF 1-2 (2 Nos)
9 A29940 Cross Beam & Bearing Pad PF 1-1 14 05-Sep-18 18-Sep-18 Cross Beam & Bearing Pad PF 1-1
10 A29950 Cross Beam & Bearing Pad PF 1-2 14 05-Sep-18 18-Sep-18 Cross Beam & Bearing Pad PF 1-2
11 A29980 Launching M-Beam PF1-1 to PF 1-2 1 26-Sep-18 26-Sep-18 Launching M-Beam PF1-1 to PF 1-2
12 A29990 Launching M-Beam PF1-2 to PF 1-3 1 26-Sep-18 26-Sep-18 Launching M-Beam PF1-2 to PF 1-3
13 A31640 Diaphram M-Beam PF1-1 to PF1-2 3 27-Sep-18 29-Sep-18 Diaphram M-Beam PF1-1 to PF1-2
14 A31650 Diaphram M-Beam PF1-2 to PF1-3 3 27-Sep-18 29-Sep-18 Diaphram M-Beam PF1-2 to PF1-3
15 A30000 Deck Slab PF1-1 to PF1-2 14 30-Sep-18 13-Oct-18 Deck Slab PF1-1 to PF1-2
16 A30010 Deck Slab PF1-2 to PF1-3 14 30-Sep-18 13-Oct-18 Deck Slab PF1-2 to PF1-3
17 A30020 Parapet PF1-1 to PF1-2 (Left & Right Side) 14 30-Sep-18 13-Oct-18 Parapet PF1-1 to PF1-2 (Left & Right Side)
18 A30030 Parapet PF1-2 to PF1-3 (Left & Right Side) 14 30-Sep-18 13-Oct-18 Parapet PF1-2 to PF1-3 (Left & Right Side)
19 L0 Level 128 14-May-18 A 18-Sep-18 18-Sep-18, L0 Level
20 Underground Road Tunnel - Section 10 128 14-May-18 A 18-Sep-18 18-Sep-18, Underground Road Tunnel - Section 10
21 Sub-Structure 30 14-May-18 A 12-Jun-18 12-Jun-18, Sub-Structure
22 A29800 Rock Excavation at Section 10 Panel P99, P100, P101 30 14-May-18 A 12-Jun-18 Rock Excavation at Section 10 Panel P99, P100, P101
23 B2 Level 28 13-Jun-18 10-Jul-18 10-Jul-18, B2 Level
24 A29880 B2 Raft Slab Panel P99 14 13-Jun-18 26-Jun-18 B2 Raft Slab Panel P99
25 A29890 B2 Raft Slab Panel P100 14 13-Jun-18 26-Jun-18 B2 Raft Slab Panel P100
26 A29900 B2 Raft Slab Panel P101 14 13-Jun-18 26-Jun-18 B2 Raft Slab Panel P101
27 A30600 B2 Wall Panel P99 14 27-Jun-18 10-Jul-18 B2 Wall Panel P99
28 A30610 B2 Wall Panel P100 14 27-Jun-18 10-Jul-18 B2 Wall Panel P100
29 A30620 B2 Wall Panel P101 14 27-Jun-18 10-Jul-18 B2 Wall Panel P101
30 B1 Level 63 18-Jul-18 18-Sep-18 18-Sep-18, B1 Level
31 A30660 B1 Slab Panel P99 14 18-Jul-18 31-Jul-18 B1 Slab Panel P99
32 A30670 B1 Slab Panel P100 14 18-Jul-18 31-Jul-18 B1 Slab Panel P100
33 A30680 B1 Slab Panel P101 14 18-Jul-18 31-Jul-18 B1 Slab Panel P101
34 A30630 B1 Wall Panel P99 14 08-Aug-18 21-Aug-18 B1 Wall Panel P99
35 A30640 B1 Wall Panel P100 14 08-Aug-18 21-Aug-18 B1 Wall Panel P100
36 A30650 B1 Wall Panel P101 14 08-Aug-18 21-Aug-18 B1 Wall Panel P101
37 A32060 Backfilling Above Tunnel P99, P100, P101 up to L0 Level 14 05-Sep-18 18-Sep-18 Backfilling Above Tunnel P99, P100, P101 up to L0 Level
38 Zone 2 (Panel P89, P90, P91) 211 10-Apr-18 A 06-Nov-18 06-Nov-18, Zone 2 (Panel P89, P90, P91)
39 Vehicle Ramp L0 to B3 142 10-Apr-18 A 29-Aug-18 29-Aug-18, Vehicle Ramp L0 to B3
40 Underground Road Tunnel - Section 12 142 10-Apr-18 A 29-Aug-18 29-Aug-18, Underground Road Tunnel - Section 12
41 Sub-Structure 85 10-Apr-18 A 03-Jul-18 03-Jul-18, Sub-Structure
42 A29810 Ground Anchor at Section 12 Panel P89 (8 Points, SP126 to SP140) 8 10-Apr-18 A 17-Apr-18 A Ground Anchor at Section 12 Panel P89 (8 Points, SP126 to SP140)
43 A29870 Ground Anchor at Section 12 Panel P91 (3 Points, SP189 to SP193) 3 18-Apr-18 A 20-Apr-18 A Ground Anchor at Section 12 Panel P91 (3 Points, SP189 to SP193)
44 A29850 Capping Beam at Section 12 Panel P89, P90, P91 (West to East) 14 21-Apr-18 A 04-May-18 A Capping Beam at Section 12 Panel P89, P90, P91 (West to East)
45 A29860 Ground Anchor at Section 12 Panel P90 (11 Points, SP157 to SP177) 11 02-Jun-18 12-Jun-18 Ground Anchor at Section 12 Panel P90 (11 Points, SP157 to SP177)
46 A30710 Rock Excavation at Section 12 Panel P89, P90, P91 21 13-Jun-18 03-Jul-18 Rock Excavation at Section 12 Panel P89, P90, P91
47 Ramp 57 04-Jul-18 29-Aug-18 29-Aug-18, Ramp
48 A30720 Ramp Raft Slab - Panel P89 14 04-Jul-18 17-Jul-18 Ramp Raft Slab - Panel P89
49 A30730 Ramp Raft Slab - Panel P90 14 04-Jul-18 17-Jul-18 Ramp Raft Slab - Panel P90
50 A30740 Ramp Raft Slab - Panel P91 14 04-Jul-18 17-Jul-18 Ramp Raft Slab - Panel P91
51 A30750 Ramp Wall - Panel P89 10 18-Jul-18 27-Jul-18 Ramp Wall - Panel P89
52 A30760 Ramp Wall - Panel P90 10 18-Jul-18 27-Jul-18 Ramp Wall - Panel P90
53 A30770 Ramp Wall - Panel P91 10 18-Jul-18 27-Jul-18 Ramp Wall - Panel P91
54 A30780 Ramp Top Slab - Panel P89 14 04-Aug-18 17-Aug-18 Ramp Top Slab - Panel P89
55 A30790 Ramp Top Slab - Panel P90 14 04-Aug-18 17-Aug-18 Ramp Top Slab - Panel P90
56 A30800 Ramp Top Slab - Panel P91 14 04-Aug-18 17-Aug-18 Ramp Top Slab - Panel P91
57 A30810 Backfilling Above Tunnel at Panel P89, P90, P91 5 25-Aug-18 29-Aug-18 Backfilling Above Tunnel at Panel P89, P90, P91
58 CBD U-Turn 112 18-Jul-18 06-Nov-18 06-Nov-18, CBD U-Turn
59 Foundation CBD 14 18-Jul-18 31-Jul-18 31-Jul-18, Foundation CBD
60 A30690 Pile Cap C11 14 18-Jul-18 31-Jul-18 Pile Cap C11
61 A30700 Pile Cap C7 14 18-Jul-18 31-Jul-18 Pile Cap C7
62 Super Structure 98 01-Aug-18 06-Nov-18 06-Nov-18, Super Structure
63 A30820 Ramp Pier / Column C7 (1 Nos) 10 01-Aug-18 10-Aug-18 Ramp Pier / Column C7 (1 Nos)
64 A30870 Ramp Pier / Column C11 (1 Nos) 10 01-Aug-18 10-Aug-18 Ramp Pier / Column C11 (1 Nos)
65 A30830 Ramp Head stock bridge C7 10 18-Aug-18 27-Aug-18 Ramp Head stock bridge C7
66 A30880 Ramp Head Stock bridge C11 10 18-Aug-18 27-Aug-18 Ramp Head Stock bridge C11
67 A30840 Ramp Box Girder at PF1-1 to C7 14 03-Oct-18 16-Oct-18 Ramp Box Girder at PF1-1 to C7
68 A30890 Ramp Box Girder at C7 to C11 14 03-Oct-18 16-Oct-18 Ramp Box Girder at C7 to C11
69 A30860 Ramp Parapet PF1-1 to C7 (Left & Right Side) 7 17-Oct-18 23-Oct-18 Ramp Parapet PF1-1 to C7 (Left & Right Side)
70 A31040 Ramp Box Girder at C11 to C13 14 17-Oct-18 30-Oct-18 Ramp Box Girder at C11 to C13
71 A30910 Ramp Parapet C7 to C11 (Left & Right Side) 7 24-Oct-18 30-Oct-18 Ramp Parapet C7 to C11 (Left & Right Side)
72 A31050 Ramp Parapet C11 to C13 (Left & Right Side) 7 31-Oct-18 06-Nov-18 Ramp Parapet C11 to C13 (Left & Right Side
73 Zone 3 (Mulia Old Gate, Panel P86, P87) 163 04-Apr-18 A 13-Sep-18 13-Sep-18, Zone 3 (Mulia Old Gate, Panel P86, P87)
74 Vehicle Ramp L0 to B3 142 04-Apr-18 A 23-Aug-18 23-Aug-18, Vehicle Ramp L0 to B3
75 Underground Road Tunnel - Section 12 142 04-Apr-18 A 23-Aug-18 23-Aug-18, Underground Road Tunnel - Section 12
76 Sub-Structure 96 04-Apr-18 A 08-Jul-18 08-Jul-18, Sub-Structure
77 A29830 Secant Pile Wall at Section 12 Panel P86, P87 (23 Nos) 40 04-Apr-18 A 13-May-18 A Secant Pile Wall at Section 12 Panel P86, P87 (23 Nos)
78 A30110 Capping Beam at Section Panel P86, P87 7 03-Jun-18 09-Jun-18 Capping Beam at Section Panel P86, P87
79 A30100 Ground Anchor at Section 12 Panel P86, P87 (8 Nos, SP68 to SP82) 8 10-Jun-18 17-Jun-18 Ground Anchor at Section 12 Panel P86, P87 (8 Nos, SP68 to SP82)
80 A31100 Rock Excavation at Section 12 Panel P86, P87 21 18-Jun-18 08-Jul-18 Rock Excavation at Section 12 Panel P86, P87
81 Ramp 46 09-Jul-18 23-Aug-18 23-Aug-18, Ramp
82 A31110 Ramp Raft Slab - Panel P86 (Half Panel) 10 09-Jul-18 18-Jul-18 Ramp Raft Slab - Panel P86 (Half Panel)
83 A31120 Ramp Raft Slab - Panel P87 (Half Panel) 10 09-Jul-18 18-Jul-18 Ramp Raft Slab - Panel P87 (Half Panel)
84 A31130 Ramp Wall - Panel P86 (Half Panel) 7 19-Jul-18 25-Jul-18 Ramp Wall - Panel P86 (Half Panel)
85 A31140 Ramp Wall - Panel P87 (Half Panel) 7 19-Jul-18 25-Jul-18 Ramp Wall - Panel P87 (Half Panel)
86 A31150 Ramp Top Slab - Panel P86 (Half Panel) 10 02-Aug-18 11-Aug-18 Ramp Top Slab - Panel P86 (Half Panel)
87 A31160 Ramp Top Slab - Panel P87 (Half Panel) 10 02-Aug-18 11-Aug-18 Ramp Top Slab - Panel P87 (Half Panel)
88 A31170 Backfilling Above Tunnel at Panel P86, P87 5 19-Aug-18 23-Aug-18 Backfilling Above Tunnel at Panel P86, P87
89 CBD Loop L2 88 18-Jun-18 13-Sep-18 13-Sep-18, CBD Loop L2
90 Foundation CBD 21 18-Jun-18 08-Jul-18 08-Jul-18, Foundation CBD
91 A30120 Rock Excavation at Section 12 Panel P86, P87 (Partial Inner CBD Side) 21 18-Jun-18 08-Jul-18 Rock Excavation at Section 12 Panel P86, P87 (Partial Inner CBD Side)
92 Super Structure 11 03-Sep-18 13-Sep-18 13-Sep-18, Super Structure
93 A30280 Launching M-Beam PF1-4 to PF 1-5 1 03-Sep-18 03-Sep-18 Launching M-Beam PF1-4 to PF 1-5
94 A30290 Deck Slab PF1-4 to PF1-5 10 04-Sep-18 13-Sep-18 Deck Slab PF1-4 to PF1-5
95 A30300 Parapet PF1-4 to PF1-5 (Left & Right Side) 10 04-Sep-18 13-Sep-18 Parapet PF1-4 to PF1-5 (Left & Right Side)
96 L0 Level 14 30-Jul-18 12-Aug-18 12-Aug-18, L0 Level
97 A32160 Backfilling area above between C17 & C19 up to L0 Level 14 30-Jul-18 12-Aug-18 Backfilling area above between C17 & C19 up to L0 Level
98 Zone 4 (Panel P84, P85, P86) 218 30-Mar-18 A 02-Nov-18 02-Nov-18, Zone 4 (Panel P84, P85, P86)

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 3
Actual Work Critical Remaining Work
TUN RAZAK EXCHANGE
CONTRACT 2- PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND
ROADWAY WORKS

# Activity ID Activity Name Original Start Finish 2018 2019


Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
99 Vehicle Ramp L0 to B3 164 30-Mar-18 A 09-Sep-18 09-Sep-18, Vehicle Ramp L0 to B3
100 Underground Road Tunnel - Section 11 164 30-Mar-18 A 09-Sep-18 09-Sep-18, Underground Road Tunnel - Section 11
101 Sub-Structure 85 30-Mar-18 A 22-Jun-18 22-Jun-18, Sub-Structure
102 A29820 Ground Anchor at Section 11 Panel P85, P86 (22 Points, SP2 t o SP66) 34 30-Mar-18 A 02-May-18 A Ground Anchor at Section 11 Panel P85, P86 (22 Points, SP2 t o SP66)
103 A31590 Capping Beam at Panel P86 7 08-Apr-18 A 14-Apr-18 A Capping Beam at Panel P86
104 A31180 Rock Excavation at Section 11 Panel P86, P85 21 02-Jun-18 22-Jun-18 Rock Excavation at Section 11 Panel P86, P85
105 B3 Level 38 03-Jul-18 09-Aug-18 09-Aug-18, B3 Level
106 A31200 Ramp Raft Slab - Panel P85 14 03-Jul-18 16-Jul-18 Ramp Raft Slab - Panel P85
107 A31190 Ramp Raft Slab - Panel P86 (Half Panel) 10 17-Jul-18 26-Jul-18 Ramp Raft Slab - Panel P86 (Half Panel)
108 A31220 Ramp Wall - Panel P85 10 24-Jul-18 02-Aug-18 Ramp Wall - Panel P85
109 A31210 Ramp Wall - Panel P86 ( Half Panel) 7 03-Aug-18 09-Aug-18 Ramp Wall - Panel P86 ( Half Panel)
110 B2 Level 17 10-Aug-18 26-Aug-18 26-Aug-18, B2 Level
111 A31240 Ramp Top Slab - Panel P85 14 10-Aug-18 23-Aug-18 Ramp Top Slab - Panel P85
112 A31230 Ramp Top Slab - Panel P86 (Half Panel) 10 17-Aug-18 26-Aug-18 Ramp Top Slab - Panel P86 (Half Panel)
113 Ramp 14 27-Aug-18 09-Sep-18 09-Sep-18, Ramp
114 A31250 Backfilling Above Tunnel at Panel P86 14 27-Aug-18 09-Sep-18 Backfilling Above Tunnel at Panel P86
115 CBD Loop L2 138 18-Jun-18 02-Nov-18 02-Nov-18, CBD Loop L2
116 Foundation CBD 44 18-Jun-18 31-Jul-18 31-Jul-18, Foundation CBD
117 A30080 Rock Excavation at Section 11 Panel P85, P86 (Partial Inner CBD Side) 14 18-Jun-18* 01-Jul-18 Rock Excavation at Section 11 Panel P85, P86 (Partial Inner CBD Side)
118 A30090 Pile Cap C18 & C19 14 02-Jul-18 15-Jul-18 Pile Cap C18 & C19
119 A30200 Foundation for PF1-6 (Raft Foundation) 30 02-Jul-18 31-Jul-18 Foundation for PF1-6 (Raft Foundation)
120 A30340 Foundation for PF 1-7 (Raft Foundation) 30 02-Jul-18 31-Jul-18 Foundation for PF 1-7 (Raft Foundation)
121 Super Structure 110 16-Jul-18 02-Nov-18 02-Nov-18, Super Structure
122 A30210 Pier / Column PF 1-5 (2 Nos) 14 16-Jul-18 29-Jul-18 Pier / Column PF 1-5 (2 Nos)
123 A30220 Pier / Column PF 1-6 (2 Nos) 14 01-Aug-18 14-Aug-18 Pier / Column PF 1-6 (2 Nos)
124 A30350 Pier / Column PF 1-7 (2 Nos) 14 01-Aug-18 14-Aug-18 Pier / Column PF 1-7 (2 Nos)
125 A30230 Cross Beam & Bearing Pad PF 1-5 14 13-Aug-18 26-Aug-18 Cross Beam & Bearing Pad PF 1-5
126 A30240 Cross Beam & Bearing Pad PF 1-6 14 15-Aug-18 28-Aug-18 Cross Beam & Bearing Pad PF 1-6
127 A30360 Cross Beam & Bearing Pad PF 1-7 14 15-Aug-18 28-Aug-18 Cross Beam & Bearing Pad PF 1-7
128 A30390 Perimeter Beam PF1-5 to PF 1-6 to PF 1-7 (Left & Right Side) 14 22-Aug-18 04-Sep-18 Perimeter Beam PF1-5 to PF 1-6 to PF 1-7 (Left & Right Side)
129 A31260 Ramp Retaining Wall (2 Side) 21 10-Sep-18 30-Sep-18 Ramp Retaining Wall (2 Side)
130 A30430 Pier / Column PF 4-9 (2 Nos) 10 11-Sep-18* 20-Sep-18 Pier / Column PF 4-9 (2 Nos)
131 A30250 Launching M-Beam PF1-5 to PF 1-6 to PF 1-7 2 19-Sep-18 20-Sep-18 Launching M-Beam PF1-5 to PF 1-6 to PF 1-7
132 A30400 Corner Portion P84 (Left) : Beam, Slab & Parapet Cast in-situ 14 21-Sep-18 04-Oct-18 Corner Portion P84 (Left) : Beam, Slab & Parapet Cast in
133 A30410 Corner Portion P84 (Right) : Beam, Slab & Parapet Cast in-situ 14 21-Sep-18 04-Oct-18 Corner Portion P84 (Right) : Beam, Slab & Parapet Cast
134 A30420 Cross Beam & Bearing Pad PF 4-9 14 21-Sep-18 04-Oct-18 Cross Beam & Bearing Pad PF 4-9
135 A31660 Diaphram M-Beam PF1-5 to PF1-6 to PF1-7 5 21-Sep-18 25-Sep-18 Diaphram M-Beam PF1-5 to PF1-6 to PF1-7
136 A30260 Deck Slab PF1-5 to PF1-6 14 26-Sep-18 09-Oct-18 Deck Slab PF1-5 to PF1-6
137 A30270 Parapet PF1-5 to PF1-6 (Right Side) 14 26-Sep-18 09-Oct-18 Parapet PF1-5 to PF1-6 (Right Side)
138 A30370 Deck Slab PF1-6 to PF1-7 14 26-Sep-18 09-Oct-18 Deck Slab PF1-6 to PF1-7
139 A30380 Parapet PF1-6 to PF1-7 (Right Side) 14 26-Sep-18 09-Oct-18 Parapet PF1-6 to PF1-7 (Right Side)
140 A31270 Ramp Backfilling Inside Retaining Wall 5 01-Oct-18 05-Oct-18 Ramp Backfilling Inside Retaining Wall
141 A30440 Launching M-Beam Perimeter Beam (PF1-6 & PF1-7) to PF 4-9 2 12-Oct-18 13-Oct-18 Launching M-Beam Perimeter Beam (PF1-6 & PF1-7)
142 A31670 Diaphram M-Beam PF1-6 to PF1-7 to PF4-9 5 14-Oct-18 18-Oct-18 Diaphram M-Beam PF1-6 to PF1-7 to PF4-9
143 A31780 Launching M-Beam PF4-8 to PF4-9 1 16-Oct-18 16-Oct-18 Launching M-Beam PF4-8 to PF4-9
144 A31830 Diaphram M-Beam PF4-8 to PF4-9 3 17-Oct-18 19-Oct-18 Diaphram M-Beam PF4-8 to PF4-9
145 A30450 Deck Slab Perimeter Beam (PF1-6 & PF1-7) to PF 4-9 14 19-Oct-18 01-Nov-18 Deck Slab Perimeter Beam (PF1-6 & PF1-7) to
146 A30460 Parapet Perimeter Beam (PF1-6 & PF1-7) to PF 4-9 (Left & Right Side) 14 19-Oct-18 01-Nov-18 Parapet Perimeter Beam (PF1-6 & PF1-7) to P
147 A31960 Deck Slab PF4-8 to PF4-9 14 20-Oct-18 02-Nov-18 Deck Slab PF4-8 to PF4-9
148 L0 Level 208 05-Apr-18 A 29-Oct-18 29-Oct-18, L0 Level
149 A31480 Rock Excavation at Section 11 Panel P84 35 05-Apr-18 A 09-May-18 Rock Excavation at Section 11 Panel P84
150 A31490 Ramp B3 Raft Slab - Panel P84 10 23-Jun-18 02-Jul-18 Ramp B3 Raft Slab - Panel P84
151 A31500 Ramp B3 Wall - Panel P84 7 10-Jul-18 16-Jul-18 Ramp B3 Wall - Panel P84
152 A31510 Ramp B2 Slab - Panel P84 10 24-Jul-18 02-Aug-18 Ramp B2 Slab - Panel P84
153 A32040 Backfilling above C18 & C19 up to L0 Level 14 30-Jul-18 12-Aug-18 Backfilling above C18 & C19 up to L0 Level
154 A31520 Ramp B2 Wall - Panel P84 14 31-Jul-18 13-Aug-18 Ramp B2 Wall - Panel P84
155 A31530 Ramp B1 Slab - Panel P84 7 21-Aug-18 27-Aug-18 Ramp B1 Slab - Panel P84
156 A31540 Ramp B1 Wall - Panel P84 14 28-Aug-18 10-Sep-18 Ramp B1 Wall - Panel P84
157 A32170 Backfilling Zone 4 up to L0 Level 14 16-Oct-18 29-Oct-18 Backfilling Zone 4 up to L0 Level
158 Zone 5 (Mulia New Gate, Panel P87, P88) 159 08-Jun-18 13-Nov-18 13-Nov-18, Zone 5 (Mulia New Gate, Panel
159 Vehicle Ramp L0 to B3 86 08-Jun-18 01-Sep-18 01-Sep-18, Vehicle Ramp L0 to B3
160 Underground Road Tunnel - Section 12 86 08-Jun-18 01-Sep-18 01-Sep-18, Underground Road Tunnel - Section 12
161 Sub-Structure 29 08-Jun-18 06-Jul-18 06-Jul-18, Sub-Structure
162 A29840 Capping Beam at Section 12 Panel P87, P88 5 08-Jun-18 12-Jun-18 Capping Beam at Section 12 Panel P87, P88
163 A30130 Ground Anchor at Section 12 Panel P87, P88 (10 Nos, SP96 to SP114) 10 13-Jun-18 22-Jun-18 Ground Anchor at Section 12 Panel P87, P88 (10 Nos, SP96 to SP114)
164 A30920 Rock Excavation at Section 12 Panel P87, P88 14 23-Jun-18 06-Jul-18 Rock Excavation at Section 12 Panel P87, P88
165 Ramp 57 07-Jul-18 01-Sep-18 01-Sep-18, Ramp
166 A30930 Ramp Raft Slab - Panel P87 (Half Panel) 10 07-Jul-18 16-Jul-18 Ramp Raft Slab - Panel P87 (Half Panel)
167 A30940 Ramp Raft Slab - Panel P88 14 07-Jul-18 20-Jul-18 Ramp Raft Slab - Panel P88
168 A30950 Ramp Wall - Panel P87 (Half Panel) 7 17-Jul-18 23-Jul-18 Ramp Wall - Panel P87 (Half Panel)
169 A30960 Ramp Wall - Panel P88 10 21-Jul-18 30-Jul-18 Ramp Wall - Panel P88
170 A30970 Ramp Top Slab - Panel P87 (Half Panel) 10 31-Jul-18 09-Aug-18 Ramp Top Slab - Panel P87 (Half Panel)
171 A30980 Ramp Top Slab - Panel P88 14 07-Aug-18 20-Aug-18 Ramp Top Slab - Panel P88
172 A30990 Backfilling Above Tunnel at Panel P87, P88 5 28-Aug-18 01-Sep-18 Backfilling Above Tunnel at Panel P87, P88
173 CBD Loop L2 93 23-Jun-18 23-Sep-18 23-Sep-18, CBD Loop L2
174 Foundation CBD 24 23-Jun-18 16-Jul-18 16-Jul-18, Foundation CBD
175 A30140 Rock Excavation at Section 12 Panel P87, P88 (Partial Inner CBD Side) 10 23-Jun-18 02-Jul-18 Rock Excavation at Section 12 Panel P87, P88 (Partial Inner CBD Side)
176 A30150 Pile Cap C17 & C15 14 03-Jul-18 16-Jul-18 Pile Cap C17 & C15
177 A30160 Pile Cap C14 & C12 14 03-Jul-18 16-Jul-18 Pile Cap C14 & C12
178 Super Structure 69 17-Jul-18 23-Sep-18 23-Sep-18, Super Structure
179 A29930 Pier / Column PF 1-3 (2 Nos) 10 17-Jul-18 26-Jul-18 Pier / Column PF 1-3 (2 Nos)
180 A30170 Pier / Column PF 1-4 (2 Nos) 10 17-Jul-18 26-Jul-18 Pier / Column PF 1-4 (2 Nos)
181 A29960 Cross Beam & Bearing Pad PF 1-3 14 10-Aug-18 23-Aug-18 Cross Beam & Bearing Pad PF 1-3
182 A30180 Cross Beam & Bearing Pad PF 1-4 14 10-Aug-18 23-Aug-18 Cross Beam & Bearing Pad PF 1-4
183 A30190 Launching M-Beam PF1-3 to PF 1-4 1 31-Aug-18 31-Aug-18 Launching M-Beam PF1-3 to PF 1-4
184 A31680 Diaphram M-Beam PF1-3 to PF1-4 3 01-Sep-18 03-Sep-18 Diaphram M-Beam PF1-3 to PF1-4
185 A30310 Deck Slab PF1-3 to PF1-4 10 04-Sep-18 13-Sep-18 Deck Slab PF1-3 to PF1-4
186 A30320 Parapet PF1-3 to PF1-4 (Left & Right Side) 10 14-Sep-18 23-Sep-18 Parapet PF1-3 to PF1-4 (Left & Right Side)
187 CBD U-Turn 120 17-Jul-18 13-Nov-18 13-Nov-18, CBD U-Turn
188 Foundation CBD 18 17-Jul-18 03-Aug-18 03-Aug-18, Foundation CBD
189 A31010 Pile Cap C16 14 17-Jul-18 30-Jul-18 Pile Cap C16
190 A31000 Pile Cap C13 14 21-Jul-18 03-Aug-18 Pile Cap C13
191 Super Structure 106 31-Jul-18 13-Nov-18 13-Nov-18, Super Structure
192 A31060 Ramp Pier / Column C16 (1 Nos) 10 31-Jul-18 09-Aug-18 Ramp Pier / Column C16 (1 Nos)
193 A31020 Ramp Pier / Column C13 (1 Nos) 10 04-Aug-18 13-Aug-18 Ramp Pier / Column C13 (1 Nos)
194 A31070 Ramp Head stock bridge C16 10 17-Aug-18 26-Aug-18 Ramp Head stock bridge C16
195 A31030 Ramp Head stock bridge C13 10 21-Aug-18 30-Aug-18 Ramp Head stock bridge C13
196 A31080 Ramp Box Girder at C13 to C16 14 17-Oct-18 30-Oct-18 Ramp Box Girder at C13 to C16

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 3
Actual Work Critical Remaining Work
TUN RAZAK EXCHANGE
CONTRACT 2- PROPOSED CONSTRUCTION AND COMPLETION OF INFRASTRUCTURE AND
ROADWAY WORKS

# Activity ID Activity Name Original Start Finish 2018 2019


Duration
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
197 A31090 Ramp Parapet C13 to C16 (Left & Right Side) 7 07-Nov-18 13-Nov-18 Ramp Parapet C13 to C16 (Left & Right S
198 L0 Level 14 27-Jul-18 09-Aug-18 09-Aug-18, L0 Level
199 A32050 Backfilling Above C12, C14, C15, C17 up to L0 Level 14 27-Jul-18 09-Aug-18 Backfilling Above C12, C14, C15, C17 up to L0 Level
200 Zone 6 (Open Portal Area) 103 30-Jun-18 10-Oct-18 10-Oct-18, Zone 6 (Open Portal Area)
201 A30510 Launching M-Beam ABUT-1 to P1-1 2 30-Jun-18* 01-Jul-18 Launching M-Beam ABUT-1 to P1-1
202 A30520 Launching M-Beam P1-1 to P1-2 2 02-Jul-18 03-Jul-18 Launching M-Beam P1-1 to P1-2
203 A32030 Diaphram M-Beam ABUT-1 to P1-1 3 02-Jul-18 04-Jul-18 Diaphram M-Beam ABUT-1 to P1-1
204 A32020 Diaphram M-Beam P1-1 to P1-2 3 04-Jul-18 06-Jul-18 Diaphram M-Beam P1-1 to P1-2
205 A30540 Deck Slab ABUT-1 to P1-1 10 05-Jul-18 14-Jul-18 Deck Slab ABUT-1 to P1-1
206 A30560 Deck Slab P1-1 to P1-2 10 07-Jul-18 16-Jul-18 Deck Slab P1-1 to P1-2
207 A30550 Parapet ABUT-1 to P1-1 (Left & Right Side) 10 15-Jul-18 24-Jul-18 Parapet ABUT-1 to P1-1 (Left & Right Side)
208 A30570 Parapet P1-1 to P1-2 10 17-Jul-18 26-Jul-18 Parapet P1-1 to P1-2
209 A30530 Launching M-Beam P1-2 to PF1-1 2 26-Sep-18 27-Sep-18 Launching M-Beam P1-2 to PF1-1
210 A32010 Diaphram M-Beam P1-2 to PF1-1 3 28-Sep-18 30-Sep-18 Diaphram M-Beam P1-2 to PF1-1
211 A30580 Deck Slab P1-2 to PF1-1 10 01-Oct-18 10-Oct-18 Deck Slab P1-2 to PF1-1
212 A30590 Parapet P1-2 to PF1-1 10 01-Oct-18 10-Oct-18 Parapet P1-2 to PF1-1
213 Zone 7 (Remaining Activity Section 11 Panel P78 - P83) 218 30-Mar-18 A 02-Nov-18 02-Nov-18, Zone 7 (Remaining Activity Section
214 Pier / Column 14 11-Sep-18 24-Sep-18 24-Sep-18, Pier / Column
215 A31690 Column PF4-8 14 11-Sep-18* 24-Sep-18 Column PF4-8
216 CBD Loop L2 218 30-Mar-18 A 02-Nov-18 02-Nov-18, CBD Loop L2
217 Cross Beam 166 26-Apr-18 A 08-Oct-18 08-Oct-18, Cross Beam
218 A31710 Cross Beam PF4-7 14 26-Apr-18 A 09-May-18 A Cross Beam PF4-7
219 A31720 Cross Beam PF4-8 14 25-Sep-18 08-Oct-18 Cross Beam PF4-8
220 M-Beam 190 01-May-18 A 19-Oct-18 19-Oct-18, M-Beam
221 A31740 Launching M-Beam PF4-4 to PF4-5 1 01-May-18 A 01-May-18 A Launching M-Beam PF4-4 to PF4-5
222 A31750 Launching M-Beam PF4-5 to PF4-6 1 02-May-18 A 02-May-18 A Launching M-Beam PF4-5 to PF4-6
223 A31790 Diaphram M-Beam PF4-4 to PF4-5 3 02-May-18 A 04-May-18 A Diaphram M-Beam PF4-4 to PF4-5
224 A31800 Diaphram M-Beam PF4-5 to PF4-6 3 05-May-18 A 07-May-18 A Diaphram M-Beam PF4-5 to PF4-6
225 A31760 Launching M-Beam PF4-6 to PF4-7 1 17-May-18 A 17-May-18 A Launching M-Beam PF4-6 to PF4-7
226 A31810 Diaphram M-Beam PF4-6 to PF4-7 10 22-May-18 A 31-May-18 Diaphram M-Beam PF4-6 to PF4-7
227 A31770 Launching M-Beam PF4-7 to PF4-8 1 16-Oct-18 16-Oct-18 Launching M-Beam PF4-7 to PF4-8
228 A31820 Diaphram M-Beam PF4-7 to PF4-8 3 17-Oct-18 19-Oct-18 Diaphram M-Beam PF4-7 to PF4-8
229 Slab 218 30-Mar-18 02-Nov-18 02-Nov-18, Slab
230 A31930 Deck Slab PF4-5 to PF4-6 14 30-Mar-18 12-Apr-18 Deck Slab PF4-5 to PF4-6
231 A31920 Deck Slab PF4-4 to PF4-5 14 01-May-18* 14-May-18 Deck Slab PF4-4 to PF4-5
232 A31940 Deck Slab PF4-6 to PF4-7 14 01-Jun-18* 14-Jun-18 Deck Slab PF4-6 to PF4-7
233 A31950 Deck Slab PF4-7 to PF4-8 14 20-Oct-18 02-Nov-18 Deck Slab PF4-7 to PF4-8
234 L0 Level 14 16-Oct-18 29-Oct-18 29-Oct-18, L0 Level
235 A32070 Backfilling Zone 7 up to L0 Level 14 16-Oct-18 29-Oct-18 Backfilling Zone 7 up to L0 Level
236 Zone 8 (Remaining Activity Section 2 (Panel P7- P9A) 83 26-Apr-18 A 17-Jul-18 17-Jul-18, Zone 8 (Remaining Activity Section 2 (Panel P7- P9A)
237 CBD Construction 83 26-Apr-18 A 17-Jul-18 17-Jul-18, CBD Construction
238 A31970 CBD Tie Beam PF3-17 to PF3-19 (6 Nos) 45 26-Apr-18 A 09-Jun-18 CBD Tie Beam PF3-17 to PF3-19 (6 Nos)
239 A31980 Launching M-Beam PF3-16 to PF3-19 10 10-Jun-18 19-Jun-18 Launching M-Beam PF3-16 to PF3-19
240 A31990 Diaphram M-Beam PF3-16 to PF3-19 7 20-Jun-18 26-Jun-18 Diaphram M-Beam PF3-16 to PF3-19
241 A32000 Deck Slab 21 27-Jun-18 17-Jul-18 Deck Slab
242 Vehicular Road Finishes 144 01-Aug-18 22-Dec-18 22-Dec-18, Vehicular Road Fi
243 Road at L0 Level 141 01-Aug-18 19-Dec-18 19-Dec-18, Road at L0 Level
244 Utilities 76 01-Aug-18 15-Oct-18 15-Oct-18, Utilities
245 Section 10 35 01-Aug-18 04-Sep-18 04-Sep-18, Section 10
246 A31570 Utilities at L0 35 01-Aug-18 04-Sep-18 Utilities at L0
247 Section 11 35 11-Sep-18 15-Oct-18 15-Oct-18, Section 11
248 A31580 Utilities at L0 35 11-Sep-18 15-Oct-18 Utilities at L0
249 Road Finishes 51 30-Oct-18 19-Dec-18 19-Dec-18, Road Finishes
250 A32090 Kerbs Installation at L0 Level 14 30-Oct-18 12-Nov-18 Kerbs Installation at L0 Level
251 A32100 Asphalt at L0 Level 7 13-Nov-18 19-Nov-18 Asphalt at L0 Level
252 A32110 Granite at Pedestrian & Vehicular Walkway 30 20-Nov-18 19-Dec-18 Granite at Pedestrian & Vehicu
253 A32130 Road Marking 5 23-Nov-18 27-Nov-18 Road Marking
254 A32140 Road Furniture - Street Lighting 14 06-Dec-18 19-Dec-18 Road Furniture - Street Lighting
255 A32120 Road Signages 5 15-Dec-18 19-Dec-18 Road Signages
256 Ramp L0 to B3 45 27-Aug-18 10-Oct-18 10-Oct-18, Ramp L0 to B3
257 Section S11 44 27-Aug-18 09-Oct-18 09-Oct-18, Section S11
258 A31400 Skim Coat at Tunnel S11 21 27-Aug-18 16-Sep-18 Skim Coat at Tunnel S11
259 A31430 VE Panel at Tunnel S11 14 10-Sep-18 23-Sep-18 VE Panel at Tunnel S11
260 A31410 MEP 1st Fix, 2nd Fix, Final Fix Tunnel S11 30 10-Sep-18 09-Oct-18 MEP 1st Fix, 2nd Fix, Final Fix Tunnel S11
261 A31420 Painting Work at Tunnel S11 7 17-Sep-18 23-Sep-18 Painting Work at Tunnel S11
262 Section S12 44 28-Aug-18 10-Oct-18 10-Oct-18, Section S12
263 A31440 Skim Coat at Tunnel S12 21 28-Aug-18 17-Sep-18 Skim Coat at Tunnel S12
264 A31460 Painting Work at Tunnel S12 14 11-Sep-18 24-Sep-18 Painting Work at Tunnel S12
265 A31470 VE Panel at Tunnel S12 21 11-Sep-18 01-Oct-18 VE Panel at Tunnel S12
266 A31450 MEP 1st Fix, 2nd Fix, Final Fix Tunnel S12 30 11-Sep-18 10-Oct-18 MEP 1st Fix, 2nd Fix, Final Fix Tunnel S12
267 CBD Ramp (U-Turn) 14 14-Nov-18 27-Nov-18 27-Nov-18, CBD Ramp (U-Turn)
268 A31280 Installation of Guard Rail 5 14-Nov-18 18-Nov-18 Installation of Guard Rail
269 A31300 Asphalt at Ramp from L2 to L0 3 14-Nov-18 16-Nov-18 Asphalt at Ramp from L2 to L0
270 A31310 Street Lighting 14 14-Nov-18 27-Nov-18 Street Lighting
271 A31290 Rain Water Down Pipe 5 14-Nov-18 18-Nov-18 Rain Water Down Pipe
272 A31330 Road Marking 1 18-Nov-18 18-Nov-18 Road Marking
273 A31320 Road Signages 3 25-Nov-18 27-Nov-18 Road Signages
274 CBD Loop L2 51 02-Nov-18 22-Dec-18 22-Dec-18, CBD Loop L2
275 A30040 Installation of Guard Rail 14 02-Nov-18 15-Nov-18 Installation of Guard Rail
276 A30490 Rain Water Down Pipe 14 02-Nov-18 15-Nov-18 Rain Water Down Pipe
277 A32150 Kerbs Installation at L2 Level 14 02-Nov-18 15-Nov-18 Kerbs Installation at L2 Level
278 A30050 Asphalt at L2 Level 7 16-Nov-18 22-Nov-18 Asphalt at L2 Level
279 A31620 Pedestrian Walkway 21 16-Nov-18 06-Dec-18 Pedestrian Walkway
280 A30470 Road Marking 5 23-Nov-18 27-Nov-18 Road Marking
281 A31600 Granite at Road Work Surface 30 23-Nov-18 22-Dec-18 Granite at Road Work Surfac
282 A30070 Street Lighting 14 09-Dec-18 22-Dec-18 Street Lighting
283 A30060 Road Signages 5 18-Dec-18 22-Dec-18 Road Signages

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 3 of 3
Actual Work Critical Remaining Work

You might also like