Professional Documents
Culture Documents
Opening Up of Coalseams
Opening Up of Coalseams
4.1 INTRODUCTION
The term opening up of a coal seam means establishing access to a coal seam and necessary
development work for its exploitation. A seam can be worked by open pit mining or by underground mining
methods. Seams which are worked by underground mining methods can be approached by shafts and or
inclines or surface drifts or adits depending on the geology and topography of the mine area. The most
common means of approach are by surface drifts or shafts or a combination of both and in a few situations
the seam is reached by an adit. Figure 4.1 illustrates the various means of access.
In the case of deposits worked by open pit mining method, opening up of a coal would comprise
driving of haul roads to the coal seam and forming benches for the removal of overburden and coal. This
has been discussed in detail in Chapter 15.
Adits may be driven parallel to or at right angles or at any angle to the strike of the coal seam.
Adits are the cheapest means of access to the coal seam. They can be equipped with locomotive
haulage or conveyors and large outputs can be transported through them.
Adits are not common in India, some seams have been opened out by adits in Assam, Kurasia and at
West Bokaro in Bihar. In the USA, some 60 % of the coal seams have been opened up by adits.
In summary, the main means of access to the coal seams are surface inclines or drifts or shafts or a
combination of inclines and shafts. Adits are rarely used unless very special topographical and geological
conditions favour them.
Inclines are one of the simplest methods of opening up coal seams in the early stage of development.
Inclines are driven from the surface at an angle of normally not exceeding 1 in 4. If the coal seam is
outcropping, the incline may be driven after the outcrop coal has been worked out by opencast mining but in
that case excavated area unless filled by overburden, forms a large water reservoir and may cause
inundation of underground workings unless substantial barrier of coal has been left against the possible
water standage. In many cases, therefore, inclines are driven right from the outcrop and the outcrop coal is
mined out by opencast method after the underground mine is exhausted. When the seam occurs at depth, the
alluvium or soft rocks are removed at the mouth of the incline to reach the firm ground; a portal is
constructed at the mouth of the incline and thereafter the drift is driven in the ordinary way to touch the
seam.
At least two inclines have to be driven to the seam to provide separate means of ingress and egress
and also to provide separate roads for intake and return. In some situations a third incline is also driven to
provide for travelling roads. An example of opening up a 12.4-m thick seam by three inclines is illustrated
in Figure 4.3.
Figure 4.3: An example of access roads to open up a coal seam, 12-m thick, Gidi A mine,
Karanpura, coalfield
After the incline touches the seam and it has been further driven along the dip or apparent dip of the
seam for some distance, level roads are driven on its either side and development work starts. Sufficient
thickness of barrier or coal is left against the outcrop so that the roadways are not driven under incompetent
rock. The main dip is continued down the dip and from it levels are driven right and left at suitable intervals
to form panels.
Fresh air is taken down the dip through one incline and return air is brought out of the mine through
the other incline. In some cases an air shaft is also sunk to facilitate ventilation. It has been experienced that
as the depth of workings below the surface increases beyond certain depth, an air shaft at a dip point
becomes essential. For example, in the Godavari Valley coalfield where majority of mines have been opened
out by surface inclines, sinking of a vertical shaft has been considered essential for ventilation and for man
winding when the depth of workings has gone beyond a depth of 250 m or so.
Figure 4.4 illustrates the layout of main haulage roads in a coal seam opened up by surface inclines.
Figure 4.6: Diagrammatic illustration to show arched cover at the mouth of an incline
In Godavari Valley coalfield, most of the mines have been opened up by inclines driven from the
surface- In this coalfield for driving inclines the common practice is first to remove the overburden soil and
then to construct brick walls on either side over which steel joists are placed and a concrete roof is laid.
Thereafter, the excavated ground is filled with overburden soil and the incline is carried forward in the
normal way. The cross-section of the inclines is generally 3.8-4.2 m wide x 2.4 high and they are fitted
either with rope haulages or conveyors. Figure 4.7 illustrates the method of construction of such inclines.
Drivage in sedimentary strata is like development in soft rock strata that is not self supporting. The
type of support used will depend on the strata and the type of machine used. In Indian coalfields, the
common support system consists of brick walls with concreted roofs on joists. In weaker rocks with
possible water percolation support must be placed immediately following rock excavation.
For British carboniferous strata it has been found (Whittaker and Pye, 1977) that when the drift is
within 100 m of the surface, surface subsidence due to a single narrow drivage becomes discernible. The
other conclusions are:
(i) The first 9 m section of the drift behind the face is a critical zone requiring immediate and
effective support.
(ii) Early temporary or permanent support of high quality and strength as close to the face as
possible is necessary; early shotcreting can provide effective supporting resistance in the critical zone.
(iii) Powered circular shields provide effective support in weak ground: even when shotfiring is
necessary in harder ground appropriate strong temporary or permanent supports are just as necessary.
(iv) Standing supports such as arched girders require a time lapse before they generate supporting
resistance.
While driving the inclines through alluvium extreme care must be taken in securing the sides and the
roof. There are many cases where inclines through alluvium driven in the dry seasons have collapsed during
the monsoons because of water soaking into the ground and exerting a building pressure.
In river valleys, particularly on account of the meanderings of the river along these valleys in
conjunction with the thick and rolling superficial deposits, the lining of drifts will require careful
consideration. The deposits may include rock, clay, gravel and running sand, heaped haphazardly, and may
change abruptly within a short distance and at sharply contrasting depths. In general, such terrains demand
reinforced concrete piles to support the surface structures and also a good drainage scheme (Nelson, 1958).
Simpson (1978) from a study of 39 drifts from the surface as well as discussions on some proposals
in the UK, has concluded that the work on surface drift may be divided into four operations:
1. Drilling Programme: The drilling programme is intended to study the strength and characteristics
of strata (to be passed through), eg., porosity, make of water, its quality, movement and pressure. The above
information is vital to decide on the design of tunnel, its profile and support, the method of driving and
precautions.
2. Construction of Portal: Usually an open cut should be made and then the portal be constructed
unless strong stratified beds lie close to the surface. The portal should be a complete box or circular or oval
structure with strong floor to resist penetration of soft beds, especially in watery strata or in rainy season.
3. The Intermediate or Soft Ground Tunnel From the portal to the point where solid stratified beds
are encountered which are self supporting, it is essential that as soon as the ground is excavated, immediate
strong support is provided. In very bad ground hydraulically propelled shield closely followed by tubings of
cast iron or (reinforced concrete) may be advisable. The tubbing should be grouted and caulked to seal out
water and it should be joined and sealed to the portal and to the next length of the tunnel below. It will be
advantageous to pre-treat the soft and week and watery strata to seal off water. Pre-treatment can be done by
drilling holes from the surface and injecting them with chemicals or cement or with both provided the depth
of holes is not more than 45.72 m. Pre-treatment could also be done by drilling holes in the strata from
within the tunnel itself. But this increases the cost by 4-6 times the normal and reduces the speed of drivage
to one-quarter of normal dry ground.
4. Drivage in Normal Dry Strata or Coal Measures: The drivage methods are normal colliery
underground tunnelling methods. The tunnel is supported by splay-legged steel arches covered by steel
mesh or corrugated steel sheets. The corrugated sheets are protected by spraying with shotcrete or fibrous
concrete. Near the surface special care is necessary because the beds may be weakened by weathering or
percolation of water which may necessitate close spacing of arches or double layer of them. Bolted tubular
strata between the arches give greater rigidity and prevent arches slewing down the slope.
Full face boring of the drift may also be considered.
Apart from the geological, hydrological and topographical consideration discussed earlier, the
location of main and ventilating and auxiliary shafts is influenced by economic considerations and the
efficiency with which the auxiliary or ventilating shaft can perform in their respective locations.
Considering these latter aspects there could be four models (Figure 4.8).
(i) Two shafts sunk in the centre of the property;
(ii) One shaft in the centre of the take and the other on the rise-most boundary,
(iii) Two shafts in the centre of the take and one shaft at the rise-most boundary in the centre, and
(iv) One shaft in the centre of the take, and two shafts one each at the corners of the rise-most
boundary.
Model I (Figure 4.8-a) offers the following advantages:
1. After the completion of the sinking, it is easy to connect the two shafts with a short connection
to provide normal ventilation to the development face.
2. It is possible to make the surface layout more compact and also to reduce the total volume of
the pit bottom excavations.
3. The total area of shaft pillar left is comparatively less.
4. In an emergency the man winding shaft can be used for coal winding also while the main shaft
is stopped for repairs.
Model II (Figure 4.8-b) has the following advantages:
1. Ventilation shaft is shallower.
2. Accessional ventilation is possible during the whole life of the pit.
But in this scheme establishing of connections between the shafts is delayed
Model III (Figure 4.8-c) is similar to model I except that the third shaft on the rise-most boundary
can be used for transporting slurry down the mine and also, it can be used for ventilation. The disadvantage
of the system is that it entails sinking of an additional shaft which could be quite costly.
Model IV (Figure 4.8-d) has diagonal disposition of ventilation shafts. In this case there are equal
lengths of ventilation circuits along the levels and water gauge is equal. But this scheme suffers from the
following disadvantages:
1. While working to the dip, there may be difficulty in ventilation.
2. Surface arrangements are spread over a long distance.
In consideration of the above advantage and disadvantages, the scheme with two shafts in the centre
is much widely used. In India, the newer deep mines have been opened up by two shafts sunk in the centre
of the take but in some older mines a third shaft on the rise side boundary was sunk for the purpose of
taking down stowing pipe lines and ventilation. After the nationalisation of coal mines, smaller collieries
have been amalgamated to form bigger units and in these units advantage has been taken to use the shafts
already in existence for ventilation purpose and in some cases diagonal ventilation as depicted in Figure 4.8-
d may be possible.
On the dip and rise centre line of the take there could be three possible positions of the shaft. They
are: (i) at the extreme rise; (ii) at the extreme dip, or (iii) in the centre (Figure 4.9).
Position I is advantageous in that the depth of the shaft is minimum and. therefore, cost and time of
sinking to the seam are also minimum. But to develop the property a long incline will have to be driven. In
position II the, cost and time of sinking are maximum and also the cost of pumping water and hoisting are
maximum. Taking all aspects into consideration shafts sunk at position III will offer advantages.
Figure 4.11 illustrates the method of opening up three seams 1, 2 and 3 in a coal mine. Seam I occurs
at a depth of 128 m. seam 2 at 244 m and seam 3 at 274 m and they have been accessed by shafts 1, 2 and 3
respectively. Further a drift connects seams 2 and 3 and a midset landing has been provided in shaft 2 at the
level of seam 1. All the shafts are used for coal and main winding and the provision of the drift between 2
and 3 and midset landing in shaft 2 at the level of seam 1 caters to the emergency requirements. When the
coal from different coal seams has to be wound separately, the opening up of the seams may be done by
sinking a winding shaft to each of the seams, provided the depth of sinking is not high. But in deeper seams,
this may not be an economical proposition.
Figure 4.12 shows how 7 coal seams occurring at depths from 325.5 to 748 m were opened up at
Hughton Main Colliery, UK (Machin, 1955). Shafts 2 and 3 were sunk to the bottom-most seam
(Thorncliffe seam) and shaft 1 to Barnsley Bed seam. A staple shaft connects the Barnsley Bed seam to the
bottom-most seam, i.e. Thorncliffe seam. An inclined drift connects the Fenton seam to Thorncliffe seam.
All the coal was wound up by skips from No. 3 shaft, the direction of coal flow is indicated by thick arrows.
Figure 4.12: An example showing the opening up of seven coal seams (After Machin, 1955)
SECTION A-B
Figure 4.13: Diagram illustrating the opening up of coal seams cut by a dip fault
Example 2: In Figure 4.14 an oblique fault of 57.9 m throw cuts the two coal seams. Koithee and
Poniati occurring 45.72 m apart. The seams have been accessed by two shafts sunk to the lower seam at the
rise end of the property. To work Poniati seam on the downthrow side of the fault another shaft has been
sunk on the downthrow side of the fault and a sloping drift driven on the strike connects upthrow and
downthrow sides of Poniati seam which is used for return air way and as second outlet.
Figure 4.14: An example of opening up coal seams cut by an oblique fault, Charanpur Colliery,
Raniganj coalfields
Example 3: In Figure 4.15, a coal seam has gentle dip on the right hand side and due to a thrust the
dip has become very steep on the left hand side. To open up seam of such structure sublevels are driven on
the steep side of the seam.
Example 4: In Figure 4.16, the coal seams present a dome structure. To open up seams in this
structure vertical shafts and crosscuts have been used.
Figure 4.15: Diagram showing the opening up of a coal seam with steep dip on one side of the take
Figure 4.16: Diagram showing the opening up of a coal seam with domed structure
4.9 CONSTRUCTION OF PIT BOTTOM
After access to the seam has been established, the connections between the shafts are made and the
pit bottom is constructed.
The term pit bottom is generally understood as meaning that portion of the main haulage road which
extends in each direction from the bottom of the shaft. In a broader sense, however, the term pit bottom may
be used to apply to all the area at the bottom of the shaft devoted to the arrangements required for the
continuous operation of the mine. This would include, generally, the shaft pillar, the inset, the pump room
and portions of the air course and haulage road. Figure 4.17 shows the main features of a pit bottom.
The following factors affect the design of the pit bottom:
1. Depth of the seam from the surface
2. Thickness of the seam and its inclination
3. The nature of the roof
4. The quantity of water to be dealt with
5. The shape of the colliery take and its area
6. The system of haulages
7. The method of winding
Factors 1, 2, and 3 govern the size of the shaft pillar, and therefore, as to how far from the pit bottom
the first cross galleries will be made, also as to how shaft levels will be supported. If the seam is thick, coal
will be left at the roof. If the seam is thin and floor weak, the floor should be ripped to got the extra height
and on the other hand if the seam is thin and the roof weak, the roof should be ripped down for the entire
length of the shaft level which should be lined or supported by arches or steel joists placed on concrete or
brick walls.
8495 m3/min which would give an air velocity through the inset of about 262.13 m per minute (Wilcox,
1961).
With cage winding, which is used in majority of mines in India, the construction of inset and landing
should conform to the requirement of clause (5) of Regulation 75 of Coal Mines Regulations 1975, which
stipulates that "protective roofing, sufficient to prevent danger from any thing falling in the shaft, shall be
provided and maintained at the bottom of the shaft. The gap, both vertical and horizontal, between the
protective roofing and the top of the cage, when the cage is at the bottom of the shaft, shall not exceed 15
centimetres". This obviously restricts the passage to the flow of air and additional passage preferably at a
level higher than the inset may be constructed to conduct the ventilating air with minimum loss of
ventilating pressure (Dalrymple, 1958).
4.9.2 Shaft Pillar
A shaft pillar is the block of solid coal left around the shaft for its protection. Excepting for the
essential excavation for ventilation, haulage and drainage no other excavation is done in the shaft pillar- The
dimensions of the shaft pillar depend on the depth of the seam, the thickness of the seam; the angle of draw;
and the area to be protected on the surface. The deeper the seam, the larger will be the shaft pillar. Similarly,
the thicker the seam, the larger will be the shaft pillar. Various empirical formulae were used to estimate the
size of the shaft pillars in the past but they do not stand to scientific analysis. All the formulae suffer from
the fact that they are too generalised and do not take into account the characteristic of rock types at a
particular site.
A scientific method for determining the size of the shaft pillar is to project from the edge of the area
to be protected at the surface the angle of draw outward from the vertical and to demarcate the area where it
cuts the seam (Figure 4.18). This will form the shaft pillar. No extraction should be done within this area to
protect the surface and the shaft. The number of seams involved is also of importance, as smaller pillar may
suffice if only one or two seams are to be extracted since the resulting subsidence and its effects will then be
less (Sinclair, 1963).
The amount of coal locked in the shaft pillar will be considerable when the seams lie at depth. It is
for this reason that in some countries especially in the Ruhr coalfield (West Germany) techniques have been
developed to extract shaft pillars without seriously damaging the shaft.
Figure 4.20 (Mishra, 1975) shows a shaft bottom sump and pump house for an Indian coal mine
designed to produce one million tonnes of coal per annum with hydraulic sand stowing of the goaf. In this
layout, the power substation, main pump room, sump, settling tank and cleaning arrangement are all
centralised and located near the service shaft. Besides normal roadway to the pump room and substation,
there is an additional roadway to the pump room from a higher landing of the service shaft which provides
for an emergency exit.
The elevation of the pump room and substation is 0.50 m above the level of the shaft level. Thus in
the event of any heavy inrush of water or failure of power for a long time, the pump room and substation
will remain safe till the water rises more than 0.5 m above the shaft level. The pumping units are provided
with separate drain pits sunk up to a depth of about one m below the floor level of the sump and all drain
pits are connected with the main sump. The pumping units in this case work with a maximum suction of
five m, which is well within the maximum possible limit. The arrangement is provided with a settling tank.
The water from the loco-road drains comes to the settling tank, sand gets deposited and the clear water runs
to the main sump. The settling tank is regularly cleaned by scrapers.
4.10 DIVISION OF THE MINE INTO BLOCKS
The mine take should be divided into blocks which will give minimum operating cost and highest
technical efficiency for a given annual output in a particular geological set up. In India, with rope haulage in
the main dips and manual tramming in levels, main haulage roads were kept about 300 m apart.
Nowadays with conveyor transport, the panels are being projected up to 1,000 m. In other words,
from the main haulage slope a block can be worked with ease up to 1,000 m on either side of the main
transport road. The optimum size of the block which will give minimum cost per ton will, however, be a
function of the strike length of the block, S and the number of levels to be worked, n. When the dimensions
of the mine area are optimum the functions ƒ (S, n) should have the minimum value.
Taking into consideration the operational efficiency, the mine is divided into blocks and the locations
of main haulage roads are marked; and the main haulages are installed. Thereafter the development is
preceded further and now the mine is opened out to a stage when production can start. Further development,
exploration and exploitation are continuous processes and end with the life of the mine.
Figure 4.20: Diagram showing the main sump in relation to other features of the pit bottom of a
stowing pit (After Misra, 1975)
4.11 IN-THE-SEAM MINING OR HORIZON MINING
So far it has been presumed that the seam has been developed on the principle of 'in-the-seam
mining', i.e., all the roads, haulage or ventilation, have been driven in the seam itself. This is normally the
case in Indian mines and also in the USA, the UK, South Africa and Australia. This type of development is
suited to the following conditions (Fritzsche, 1962):
(i) When the coal measures are flat, i.e., they have very low dip.
(ii) They are free of faults or have very few faults,
(iii) The seams have medium or high thickness,
(iv) The distance between the seams are large, i.e., the seam density is low.
(v) The seam can be worked with caving,
(vi) The seams occur at shallow or medium depths.
(vii) The size of colliery take is small.
This system does not involve costly development in stone and the seams in the take could be worked
in any order though ordinarily descending order is desirable. But when the coal measures are irregular,
though flat, have higher number of faults, the seam thicknesses are not large and stowing dirt has to be
transported, the depths are large and large outputs are economic necessity, or the seams are highly inclined
and have complex geological structure, development on the principle of 'in-the-seam mining' becomes
costly and transportation and working costs high and the working efficiency low. In such situations, the
seams are accessed by level roads driven in stone in different horizons or levels. This method of opening of
deposits is known as multi-level mining or 'horizon mining'. In this case the main haulage roads and
ventilation roads are driven in the solid rock. This method is common in Germany, France, Belgium,
Netherlands and partly in former USSR, CIS.
The cost on account of above items may be computed in terms of x-distances between horizon and
z-distances between crosscuts. Thus with two unknowns x and z, if we assume one say z then for different
values of x, we get a series of cost figures and the best value of x can be determined. Now assuming this
best value of x, we find the best value of z. In two or three successive steps the optimum value of x and z can
be determined.
Distance between staple shafts
The distance between staple shafts is influenced by the following considerations:
(i) The most convenient length of the section into which the reserves can be divided. This length is
identical with the length of coal face won out in each section. The lengths of faces vary between 150-300 m
in European practices (Fritzsche, 1962).
(ii) Position of faults which divide the seam in zones and the gradient of the seams which affect the
length of longwall faces.
Figure 4.21: Diagram illustrating the layout of a horizon with two laterals (After Fritzsche, 1962)
The crosscuts divide the take into working panels and are placed some 600 - 1200 m apart. The
position of the crosscuts is much influenced by the geological disturbances. The seam is accessed by
crosscuts and from the point they touch the seam gate roads are driven in the seam. If the distance between
them is too large, the length of the gate road will be more which will cause difficulties in ventilation and
maintenance.
The network of roadways in the ventilation level and in the haulage levels are generally identical. If
the distances are different between crosscuts in different horizons, then measures must be taken to establish
connections between corresponding crosscuts.
In flat measures, the seam is divided into suitable panels by blind shafts, the distance between them
offers as the length of the face which varies from 150 - 300 m. Blind shafts are used for the vertical
transport of coal by spiral chutes to the haulage level, whilst transport in the coal face and in the gate roads
is done by conveyors.
In the inclined or steep measures it is impossible to extend the face between haulage 'level and the
ventilation level and it becomes necessary to drive intermediate levels for the subdivision of coal faces.
These intermediate levels are known as district crosscuts and are not connected with the shaft or with each
other. The number of blind shafts serving steep seams are very much less than in flat measures. Under
favourable conditions one blind shaft may suffice.
Example
Figure 4.22 shows a layout on the principle of horizon mining for a single seam, the practice being
to work the top seam first and remaining seams afterwards in descending order. It will be appreciated that
similar areas in any of the lower seams which are intercepted by the main intake and mam return roadways
can be worked likewise*.
The main intake and main return drifts are set out level from their respective shafts to intercept the
seam at point E. and F, thus forming the extent to the dip of the first area of coal to be worked, A B C D.
The vertical interval between the two drifts in this case is 137 m, and the full dip of the seam 1 in 4½.
Roadways are driven in the seam to form return airways (giving ascensional ventilation) and to
open-out faces, and conveyor roadways, successively, E D, E C, G Z, and H Z; the latter dividing the area
into three strips, each 210 in wide, on either side of the main intake roadway, suitable for longwall
advancing single-unit working.
Coal Mining: Report of the Technical Advisory Committee" H.M.S.O., London, Cmd. 6610, 1945, pp. 20-21.
Figure 4.22: An example of a horizon mining layout (Source: Report of the Technical Advisory
Committee. The Reid Report, H.M.S.O, CMD 6610, 1945)
Two 210 m wide faces (Strip 1) are worked simultaneously to predetermined distances E D, E C-
which limit the extent to the first area to he worked, the coal being conveyed down the faces, along the
bottom roadways and loaded into tubs at Point E.
When strip 1 has been exhausted, the strip 2 is worked in a similar manner with the exception that
the coal is delivered from the roadways conveyor onto a spiral conveyor situated in the staple pit at Point
G., then loaded into tubs in the main intake drift. The strip 2 is replaced by strip 3, the coal being loaded by
way of the staple pit at Point H, into tubs in the main intake roadway.
If stowing material is required, it is sent down the upcast shaft, hauled via the main return airway to
Point R, and then transported by conveyors along the return airway to the rise end of the faces.
When the area A B C D is exhausted, another main intake-airway drift is set out from the downcast
shaft at a lower level to intercept the seam at Point J, in order to work out the area D C K L, the intake
roadway for the area A B C D becoming the return airway for the working area D C K L, and so on,
progressively.
Man riding is provided from the shafts to the inbye ends of either the main intake or main return
airways, points E and F, according to local circumstances.
In India, coal seams have been commonly developed on the principle of 'in-the-seam' mining but
some coal mines have been opened out on the principle of horizon mining also. For example, Table 4.2
gives the particulars of coal seams opened out on horizon mining system in a mine in the Jharia Coalfield.
The seams in this take are steeply inclined (22°- 60°) and are very much disturbed by faults of varying
thickness and mica peridotite sills. At this mine the seams up to 150 m depth are accessed by a surface
incline and leaving a barrier of 50 m (vertical height) have been accessed by a pair of vertical shafts and
have been opened out on the principle of horizon mining both in the "Incline mine" and in the shaft mine.
Table 4.3 gives the technical details of the placement of various horizons (Chowdhary, 1972).
Name of the Seam Thickness of the seams, m Dip of the seams degrees
X VIII Top 1.8-2.6 4
X VIII Bottom 2.3-2.9 34
XVII 4.1-5.0 42
Local II 1.7-4.5 40
XVI Bottom 1 .2- 3.2 55
XV 7.6-16.4 50-60
XIV A 1 .7-3.2 52-55
XIV 0.6-14.9 22
XI/XH 5.11-3.1 28-40
IX/X 12.1-24.4 28-30
VIII A 4.5-5.0 27-30
Local 2.5-3.0 25-30
VIII 4.0-5.0 26-30
Source:. Sen, S.K. and Chowdhary, S.K., (1982). "Pros and Cons, of Extraction of Coal Seams
Underneath Surface Features and Structures at Sudamdih Project" in Mine Subsidence, Dr. B. Singh {Ed.},
Parijat Mudranalaya Publications, pp. 38 • 46.
Level, absolute Relative depth, Function Of level Industrial reserve, Output, Life-time
depth, m m thousand tonnes tonnes/day years
-50 200 Ventilation — — 22
-150 300 Intermediate
-250 400 1 drawing 27979 6000 22
-350 500 Intermediate
-500 650 11 drawing 28791 6000 22
-700 850 III drawing 19935 3500 22
-850 1000 IV drawing 14133 2500 22
Source: Chowdhary, S.K., "Reconstruction of Sudamdih Area, Proceedings of Seminar on
"Reconstruction of Jharia Coalfiled", 12-13 Nov. 1972, The New Sketch Supplement, pp. 181-191.