Tentative BOQ For OSP Works

Rehb of Fiber Cable Work at Khawar Chowk to Shanzil Johar Exch KTR II
S# DESCRIPTION OF ITEM / WORK Unit Rate QTY
Part-I Services
1 Roding Cleaning of duct along M 60.00 1,500
2 Cable Hauling / Laying (OFC) M 25.00 1,500
3 Making of Test pit EA 1,425.00 6
Lum
4 Transportation charges per site locally 5,000.00 1
Sum

5 5-Sets of AS-Built along with GIS / Auto cade Based Daigram EA 6,000.00 1
6 Jointing, Splicing / Termination 96-FIBER EA 16,000.00 5
7 Sealing of H-Hole with Cement EA 1,000.00 8
8 Cleaning of H-Hole EA 1,584.00 5
TOTAL
ch KTR II
Amount

90,000.00
37,500.00
8,550.00
5,000.00

6,000.00
80,000.00
8,000.00
7,920.00
242,970.00