Takt Time and SAM Approaches

Takt Approach SAM/SMV/SAH Approach

Cycle time = Average of observed Standard Allowed Minute (SAM) = (Average Observed
times time x Performance Rating factor) + Allowances

𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑡𝑖𝑚𝑒 Manpower Needed =


Takt Time =
𝐶𝑢𝑠𝑡𝑜𝑚𝑒𝑟 𝑑𝑒𝑚𝑎𝑛𝑑 𝑂𝑢𝑡𝑝𝑢𝑡 𝑁𝑒𝑒𝑑𝑒𝑑 𝑑𝑒𝑚𝑎𝑛𝑑 𝑥 𝑆𝐴𝑀
𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑡𝑖𝑚𝑒 𝑥 1−𝑎𝑏𝑠𝑒𝑛𝑡𝑖𝑠𝑚 % 𝑥 𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝐿𝑖𝑛𝑒 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 %
𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒
Manpower Needed =
𝑇𝑎𝑘𝑡 𝑇𝑖𝑚𝑒 𝑆𝐴𝑀
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑎𝑛𝑐𝑒 𝑡𝑜 ≈
𝑇𝑎𝑘𝑡 𝑇𝑖𝑚𝑒 𝑥 𝐿𝑖𝑛𝑒 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 %

Overall factory/line efficiency reflects operator skill, work pace, effectiveness


compared to standard, as well line balancing factor and other disruptions in factory.
Efficiency % can be adjusted as line become more matured due operators learning
progress as well as considering product complexity, potential absenteeism,
Major difference between two employee turnover etc.
approaches: Performance Rating Factor compares an operators working pace and effectiveness
1. Cycle time vs Standard Time with Standard.
(SAM) Allowances – Personal (such as toilet usages) , Fatigue and delay, and machine
2. Line efficiency factor allowances.