IG System Operating Procedure
IG System Operating Procedure
OPERATION
SET THE SYSTEM SELECTROR TO INERT GAS POSITION
PUT MASTER SWITCH AND CARRY OUT LAMP TEST
OPEN THE BOILER UPTAKE V/V FULLY AND CONFIRM
MAKE SURE AIR SEAL V/V IS CLOSED
START THE FAN
CHECK RUNNING FAN’S DELIVERY V/V FULLY OPEN 15 SEC AFTER THE FAN
STARTS
CHECK O2 CONTENT LEVEL TO BE BELOW 5%
STOPPING
PUSH STOP BUTTON OF INERT GAS SUPPLY SWITCH
CHECK IG MAIN V/V IS SHUT
CHECK EXH V/V IS FULLY OPEN
STOP THE IG FAN
PUSH STOP BUTTON FOR BOILER UPTAKE V/V & CONFIRM IT IS SHUT
CHECK AIR SEAL V/V IS FULLY OPEN
AFTER 30 MIN STOP SEAWATER P/P TO SCRUBBER
CHIEF ENGINEER
M.T._____________