Download as pdf or txt
Download as pdf or txt
You are on page 1of 159

Document No: MHDP-08-R-01

Issue: 6.0
Date: 4th January 2017

Stage 1 & 2
Building Risk
Assessment
Report
Yanbu Distribution Hub

Prepared for:
Mustang-HDP

Prepared by:
© 2017 Risktec Solutions DMCC
This document has been prepared by Risktec Solutions DMCC.
Subject to any contractual terms between Risktec Solutions
DMCC and its client to the contrary, it is the property of Risktec
Solutions DMCC. It shall not be reproduced in whole or part, nor
Cleopatra Ong, Senior Engineer disclosed to a third party without the express written permission
of the owner. This document has been specifically prepared for
Reviewed by: the client of Risktec Solutions DMCC and no responsibility to third
parties is accepted unless expressly agreed in writing.

Office 3004 Liwa Heights


Jumeirah Lakes Towers
PO Box 450113
Sophia Chua, Senior Engineer Dubai
Approved by: United Arab Emirates
www.risktec.com

Mike Bates, Principal Consultant


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

EXECUTIVE SUMMARY
The purpose of the Yanbu Distribution Hub (YDH) Project (which is currently in the design stage) is to efficiently
meet the Kingdom’s refined product demands in Makkah province. The YDH will aggregate refined product from
the three local refineries (SAMREF, YASREF and Yanbu) and act as the origin pump station for at least two
connecting pipelines, i.e. the Yanbu to Jiddah pipeline and the Yanbu to Central Region pipeline.
Mustang-HDP (MHDP) is currently undertaking the YDH Project (BI-10-02399) for Saudi Aramco. MHDP has
contracted Risktec Solutions DMCC (Risktec) to conduct a Stage 1 and 2 Building Risk Assessment (BRA) for YDH
(including associated pipelines).
This report presents the results of the Stage 1 and Stage 2 BRA, whereby the worst case credible hazard
consequences (fire, explosion, and flammable vapour clouds) are identified, and their impact on plant buildings
evaluated.
Stage 1 BRA Results Summary
A total of 9 buildings have been assessed as occupied, and 5 buildings have been assessed as functionally
significant.
Stage 2 BRA Results Summary
Jet Fire
The following buildings will be subjected to direct flame impingement and exposed to heat radiation flux above
35kW/m2:
 B-01 SS-XXX1 Receiving Substation Transformer Yard (the maximum heat radiation flux is calculated as
171kW/m2);
 B-02 SS-XXX2 Utility Power Substation Transformer Yard (the maximum heat radiation flux is calculated
as 142kW/m2);
 B-04 RIB-XXX2 Remote I/O Building (the maximum heat radiation flux is calculated as 154kW/m2);
 B-15 Operation Shelter-1 (the maximum heat radiation flux is calculated as 138kW/m2);
 B-20 Custody Metering Shelter (Vendor Package) (the maximum heat radiation flux is calculated as
240kW/m2; and
 B-22 Operation Shelter-2 (the maximum heat radiation flux is calculated as 137kW/m2);
Although the jet fires will not impinge the B-03 RIB XXX1 Remote I/O Building, it is potentially exposed to heat
radiation flux above 35kW/m2 (the maximum heat radiation flux is calculated as 98kW/m2). The B-21 Oily Water
Metering Shelter -Marafiq is potentially exposed to heat radiation flux between 12.5kW/m2 and 35kW/m2 due to
YNJ-1 scraper launcher.
All other buildings are potentially exposed to heat radiation flux below 4.7kW/m2.
Pool Fire
The B-20 Custody Metering Shelter (Vendor Package) is potentially exposed to heat radiation flux between
12.5kW/m2 and 35kW/m2 due to release from SAM-30 and YR-22 pipelines.
The B-21 Oily Water Metering Shelter -Marafiq) is potentially exposed to heat radiation flux between 12.5kW/m2
and 35kW/m2 due to release from the YNJ-2 pipeline.
The B-22 Operation Shelter-2 is potentially exposed to heat radiation flux between 12.5kW/m2 and 35kW/m2 due
to release from YNJ-1 and YNJ-2 pipelines.
The following buildings will be subjected to heat radiation flux between 4.7kW/m2 and 12.5kW/m2 due to bund
fires within the Yanbu Distribution Hub:
 B-01 SS-XXX1 Receiving Substation Transformer Yard;
 B-02 SS-XXX2 Utility Power Substation Transformer Yard;
 B-03 RIB-XXX1 Remote I/O Building;

Risktec Solutions DMCC Page 2 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

 B-04 RIB-XXX2 Remote I/O Building;


 B-07 Security Guard House (B);
 B-08 X-Ray Building;
 B-10 Security Support Building (B);
 B-12 Operation Building;
 B-16 IDAS Shelter-001; and
 B-17 IDAS Shelter-002.
Flammable Vapour Dispersion
The flammable vapour dispersions will reach all of the buildings being assessed. All building assessed are exposed
to flammable vapour concentrations above ½ LFL with the exception of the following which are exposed to
flammable vapour concentrations below ½ LFL:
 B-05 FSF Building;
 B-06 Security Guard House (A);
 B-09 Security Support Building (A);
 B-21 Sanitary Metering Shelter – Marafiq; and
 B-19 Utility Water Metering Shelter – Marafiq.
Therefore, a flammable atmosphere could be expected in each building.
Vapour Cloud Explosions (VCE)
All buildings are only expected to suffer minor damage, which is below the SAES-B-014 damage criteria, and no
further assessment is required.
Recommendations
Building Specific Recommendations
Based on the Stage 2 BRA results summary, building specific risk mitigation measures have been developed for
each building and are presented in Table 1.

Table 1: Proposed Building Specific Risk Mitigation Measures

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Review functionality of the building. Based on review of potential business
interruption impact, consider rating the external walls to withstand direct
jet fire flame impingement (the maximum heat radiation flux is calculated
as 171kW/m2).
B-01 SS-XXX1 Also, consider relocating the building outside the flame impingement
Receiving radius of 121m from the Scraper-YNJ-1 (G) (for the scenario description
Functionally
Substation refer to Assumption A03, Appendix A).
Significant
Transformer
Yard Note: Further risk mitigation measures may not be required if the impact
of losing the buildings function does not have a catastrophic impact on
the continued operation of the plant.
Hydrocarbon gas detectors should be installed at the building to provide an
audible and visual alarm.

Risktec Solutions DMCC Page 3 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Review functionality of the building. Based on review of potential business
interruption impact, consider rating the external walls to withstand direct
jet fire flame impingement (the maximum heat radiation flux is calculated
as 142kW/m2).
B-02 SS-XXX2
Utility Power Also, consider relocating the building outside the flame impingement radius
Functionally of 60m from the PG 95 Storage Tanks outlet header.
Substation
Significant
Transformer Note: Further risk mitigation measures may not be required if the impact of
Yard losing the buildings function does not have a catastrophic impact on the
continued operation of the plant.
Hydrocarbon gas detectors should be installed at the building to provide an
audible and visual alarm.
B-03 RIB-XXX1
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Remote I/O
Significant audible and visual alarm.
Building
B-04 RIB-XXX2
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Remote I/O
Significant audible and visual alarm.
Building
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external
B-05 FSF doors should be fitted with gas-tight seals and equipped with quick acting,
Occupied adjustable door closing mechanism. Windows should be eliminated,
Building
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external
B-06 Security doors should be fitted with gas-tight seals and equipped with quick acting,
Guard House Occupied adjustable door closing mechanism. Windows should be eliminated,
(A) minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.

Risktec Solutions DMCC Page 4 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
B-07 Security dampers and put the HVAC system into re-circulation mode). Hydrocarbon
Guard House Occupied gas detectors should initiate an audible and visual alarm and all external
(B) doors should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.
B-08 X-Ray Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Building Significant note audible and visual alarm.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external
B-09 Security doors should be fitted with gas-tight seals and equipped with quick acting,
Support Building Occupied adjustable door closing mechanism. Windows should be eliminated,
(A) minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event
of an incident on the plant, hydrocarbon gas detectors should be installed
at the building to provide an audible and visual alarm.
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
B-10 Security dampers and put the HVAC system into re-circulation mode). Hydrocarbon
Support Building Occupied gas detectors should initiate an audible and visual alarm and all external
(B) doors should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event
of an incident on the plant, hydrocarbon gas detectors should be installed
at the building to provide an audible and visual alarm.

Risktec Solutions DMCC Page 5 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external
B-11 OME doors should be fitted with gas-tight seals and equipped with quick acting,
Occupied adjustable door closing mechanism. Windows should be eliminated,
Building
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
B-12 Operation
Occupied gas detectors should initiate an audible and visual alarm and all external
Building
doors should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external
doors should be fitted with gas-tight seals and equipped with quick acting,
B-13 Musalla Occupied adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event
of an incident on the plant, hydrocarbon gas detectors should be installed
at the building to provide an audible and visual alarm.
B-14 Chemical Functionally Hydrocarbon gas detectors should be installed at the building to provide
Shelter Significant note an audible and visual alarm.

Risktec Solutions DMCC Page 6 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
B-15 Operation
Occupied gas detectors should initiate an audible and visual alarm and all external
Shelter-1
doors should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.
B-16 IDAS Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Shelter-001 Significant note audible and visual alarm.
B-17 IDAS Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Shelter-002 Significant note audible and visual alarm.
B-18 Sanitary
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Metering
Significant note audible and visual alarm.
Shelter-Marafiq
B-19 Utility
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Water Metering
Significant audible and visual alarm.
Shelter-Marafiq
The functionality of the building should be reviewed and the impact of losing
the function of the building determined. If loss of the building function can
have catastrophic impact on continued safe operation of the facility, the
following risk reduction measures should be considered.
Either design the external walls of the building to withstand direct jet fire
flame impingement (the maximum heat radiation flux is calculated as
240kW/m2) or relocate the building outside the flame impingement radius
B-20 Custody
of:
Metering Shelter Functionally
(Vendor Significant note  184m from the Gasoline Custody Metering Skid (X40-U-0014A);
Package)  170m from the Gasoline Meter Prover Skid (X40-U-0014D);
 213m from the from gasoline receiving manifold outlet headers
(for PG 91 and PG 95); and
 30m from the diesel pipelines from Yasref/Samref and gasoline
pipeline from Yasref.
Hydrocarbon gas detectors should be installed at the building to provide
an audible and visual alarm.
B-21 Oily Water
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Metering Shelter
Significant note audible and visual alarm.
-Marafiq

Risktec Solutions DMCC Page 7 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in
HVAC inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
B-22 Operation
Occupied gas detectors should initiate an audible and visual alarm and all external
Shelter-2
doors should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at
the building to provide an audible and visual alarm.
Note: The B-03 RIB-XXX1 Remote I/O Building, B-04 RIB-XXX2 Remote I/O Building, B-08 X-Ray Building, B-14 Chemical Shelter,
B-16 IDAS Shelter-001, B-17 IDAS Shelter-002, B-18 Sanitary Metering Shelter-Marafiq, B-20 Custody Metering Shelter (Vendor
Package) and B-21 Oily Water Metering Shelter -Marafiq are not occupied nor functionally significant as per the requirement of
SAES-B-014. These buildings have been included for completeness and are assessed under the functional building criteria.

General Recommendations
As well as the building specific mitigation measures detailed in Table 1, the following general mitigation measures
should be considered:
 All buildings in YDH should comply with the requirements of SAES-B-055 for spacing between buildings,
and process plant, and with SAES-B-014 for fire and water system requirements. In addition, all buildings
covered by SSD-9 and SSD-26 must comply with the requirements of these directives.
 It is generally recommended, in process industries, that in-plant buildings do not have windows. This is
supported by SAES-B-014. However, Clause 5.8, Exception B of SAES-B-014 states that windows are
allowed for ‘Operator shelters that are specifically designed for personnel protection and for monitoring of
a process facility or bulk plant operation such as truck loading. Personnel protection against any
overpressures anticipated by the risk assessment shall be included in the sizing and design of the windows’.
SAES-B-014 also states that as a minimum, these windows should be double glazed with tempered glass,
internal lamination, a catch system for the glass using anchored cables or wrap bars. The glass used in
the windows will be a minimum of 6 mm (¼ in) thick and is either wired, tempered or laminated safety
glass. The glass shall meet all fire-resistive regulations and safety performance requirements of SAES-M-
100 and ASME Z97.1 and shall be labelled as such by the supplier.
 Should the design of these buildings contain windows, the design details shall be provided to the company
representative for approval by the Supervisor, Civil Engineering Unit, Consulting Services Department
(CSD), Dhahran, and by the Chief Fire Prevention Engineer or his representative.
 A qualified structural engineer should review the estimated VCE overpressures and impulses and ensure
that the building is designed to withstand the predicted results.
 The site ERP should include any of the new buildings which are designed to act as safe refuges in the
event of an emergency. Additional potential risk mitigation measures may be required for these buildings.
Additionally, the site ERP, drills and escape routes should take into account the identified fire hazard
scenarios on each building.
 Where adequate mitigations cannot be implemented, or where the cost of the mitigations is deemed
excessive, a Stage 3 BRA should be conducted to determine the risk to personnel and building functionality.

Risktec Solutions DMCC Page 8 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

 The escape arrangements (e.g. escape route, access, egress) for the following buildings could be
(depending on the direction of the release) impaired by jet/pool fire events from one or more hazard
sources:
o B-01 SS-XXX1 Receiving Substation Transformer Yard;
o B-02 SS-XXX2 Utility Power Substation Transformer Yard;
o B-03 RIB-XXX1 Remote I/O Building;
o B-04 RIB-XXX2 Remote I/O Building; and
o B-20 Custody Metering Shelter (Vendor Package).
It is recommended that a formal Escape, Evacuation and Rescue Assessment (EERA) is performed and
further risk mitigation measures identified (if required).

Risktec Solutions DMCC Page 9 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

ISSUE RECORD
Issue Date Author Reviewer Approver Revision History
Initials Initials Initials
1.0 12-Jun-16 CO MJB MJB Draft Report for Review and Approval
2.0 26-Jun-16 CO MJB MJB Draft Report updated for Review and Approval
3.0 07-Jul-16 CO MJB MJB Report issued incorporating client comments
4.0 06-Sep-16 AA MJB MJB Report issued incorporating client comments
5.0 25-Oct-16 AA MJB MJB Report issued incorporating client comments
6.0 04-Jan-17 CO SC MJB Final report incorporating client comments

DISTRIBUTION
Ahmed AlHatem Mustang-HDP, Saudi Arabia
File Risktec Solutions Limited, Dubai, UAE

Risktec Solutions DMCC Page 10 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

CONTENTS
EXECUTIVE SUMMARY................................................................................................................................ 2
ISSUE RECORD ......................................................................................................................................... 10
DISTRIBUTION ......................................................................................................................................... 10
1 INTRODUCTION ...................................................................................................................... 13
1.1 Overview .......................................................................................................................................................... 13
1.2 Objectives ........................................................................................................................................................ 13
1.3 Scope .............................................................................................................................................................. 13
2 FACILITY OVERVIEW .............................................................................................................. 14
2.1 General ............................................................................................................................................................ 14
3 BRA METHODOLOGY ............................................................................................................... 15
3.1 Approach to Building Risk Assessment ............................................................................................................... 15
3.2 Stage 2 BRA Consequence Modelling ................................................................................................................. 16
3.3 Jet Fire ............................................................................................................................................................ 17
3.4 Pool Fire (including Bund Fire) ........................................................................................................................... 17
3.5 Tank Fires ........................................................................................................................................................ 17
3.6 Flammable Dispersion ....................................................................................................................................... 17
3.7 Building Types .................................................................................................................................................. 18
3.8 Damage Level Thresholds ................................................................................................................................. 18
4 STAGE 1 BRA ........................................................................................................................... 21
5 STAGE 2 BRA ........................................................................................................................... 23
5.1 Consequence Analysis ....................................................................................................................................... 23
5.2 Separation Distances......................................................................................................................................... 23
5.3 Stage 2 BRA Results ......................................................................................................................................... 23
6 CONCLUSIONS ........................................................................................................................ 31
6.1 Stage 1 BRA ..................................................................................................................................................... 31
6.2 Stage 2 BRA ..................................................................................................................................................... 31
7 RECOMMENDATIONS .............................................................................................................. 33
7.1 Building Specific Recommendations ................................................................................................................... 33
7.2 General Recommendations ................................................................................................................................ 38
8 REFERENCES ........................................................................................................................... 39
APPENDIX A ASSUMPTIONS REGISTER ................................................................................................ A.1
APPENDIX B SEPARATION DISTANCES ..................................................................................................B.1
APPENDIX C CONSEQUENCE RESULTS ................................................................................................. C.1
APPENDIX D STAGE 2 BRA RESULTS .................................................................................................... D.1
APPENDIX E STAGE 1 SCREENING ........................................................................................................ E.1

Risktec Solutions DMCC Page 11 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

TABLES
Table 1: Proposed Building Specific Risk Mitigation Measures ............................................................................................. 3
Table 2: Building Types .................................................................................................................................................. 18
Table 3: Thermal Radiation Damage ............................................................................................................................... 18
Table 4: Flammable Vapour Damage............................................................................................................................... 19
Table 5: Explosion Overpressure Damage........................................................................................................................ 19
Table 6: Building Damage Categories .............................................................................................................................. 19
Table 7: Stage 1 BRA Results Summary .......................................................................................................................... 21
Table 8: Stage 2 BRA Results Summary .......................................................................................................................... 24
Table 9: Hazard Source for Building Impairment Exceeding Assessment Criteria ................................................................ 26
Table 10: Proposed Building Specific Risk Mitigation Measures .......................................................................................... 33

FIGURES
Figure 1: Yanbu Distribution Hub Plot Plan & Building Locations ....................................................................................... 14
Figure 2: BRA Methodology ............................................................................................................................................ 15

Risktec Solutions DMCC Page 12 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

1 INTRODUCTION
1.1 Overview
The purpose of the Yanbu Distribution Hub (YDH) Project (which is currently in the design stage) is to
efficiently meet the Kingdom’s refined product demands in Makkah province. The YDH will aggregate
refined product from the three local refineries (SAMREF, YASREF and Yanbu) and act as the origin pump
station for at least two connecting pipelines, i.e. the Yanbu to Jiddah pipeline and the Yanbu to Central
Region pipeline.
Mustang-HDP (MHDP) is currently undertaking the YDH Project (BI-10-02399) for Saudi Aramco. MHDP
has contracted Risktec Solutions DMCC (Risktec) to conduct a Stage 1 and 2 Building Risk Assessment
(BRA) for YDH (including associated pipelines).
The BRA is implemented in accordance with the Saudi Aramco Engineering Standard, SAES-B-014
(Reference 1) and the American Petroleum Institute guidance document, API RP 752 (Reference 2). The
BRA provides information on the risks to personnel located inside plant buildings and building functionality
and identifies potential risk mitigation measures to ensure these risks are reduced to a level which can be
considered As Low As Reasonably Practicable (ALARP).
This report presents the results of the Stage 1 and Stage 2 BRA, whereby the worst case credible hazard
consequences (fire, explosion, and flammable vapour clouds) are identified, and their impact on plant
buildings evaluated.
Recommendations are made for those buildings where the consequences exceed the assessment criteria.
However, where the potential worst credible impact to building occupants and/or functionality cannot be
mitigated / protected against, a recommendation is made to consider the hazards and buildings in more
detail as part of a Stage 3 BRA, which is outside of the scope of this report.
1.2 Objectives
The objectives of the BRA are to:
 Identify the various hazard sources and associated sources within the YDH (including associated
pipelines) through a desktop Hazard Identification (HAZID);
 Carry out consequence modelling using Shell FRED software package v6.1 to determine the extent of
the different hazards identified;
 Evaluate the impact of the different hazards on the occupancy and structure of the buildings;
 Where the impacts on the buildings are outside the Saudi Aramco tolerability criteria, recommend
mitigation measures to reduce the impact of the different hazards on the buildings to an acceptable
level; and
 Document the results of Stage 1 and Stage 2 BRA.
1.3 Scope
The scope for the YDH BRA is limited to the following:
 Yanbu Distribution Hub (YDH) facility;
 Yanbu to Jiddah pipeline up to 200m from the YDH fence;
 Yanbu to Central Region pipeline up to 200m from the YDH fence; and
 Tie-ins to existing refineries up to 200m from the YDH fence (SAMREF, YASREF and Yanbu refineries).
The YDH BRA will exclude the following:
 On-site facilities at SAMREF, YASREF and Yanbu refineries;
 Refinery tie-in pipelines outside of 200m from the YDH fence; and
 Export pipelines outside of 200m from the YDH fence.

Risktec Solutions DMCC Page 13 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

2 FACILITY OVERVIEW
2.1 General
The YDH is located near the city of Yanbu on the coast of the Red Sea in the Western Province of Saudi
Arabia. The overall plot plan, showing the buildings to be assessed, is presented in Figure 1.

Figure 1: Yanbu Distribution Hub Plot Plan & Building Locations

Risktec Solutions DMCC Page 14 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

3 BRA METHODOLOGY
3.1 Approach to Building Risk Assessment
The BRA has been conducted in accordance with Saudi Aramco Engineering Standard SAES-B-014 ‘Safety
Requirements for Plant Operations and Support Buildings’ (Reference 1), which requires a systematic 3-
stage approach. This approach is illustrated in Figure 2.

Figure 2: BRA Methodology

SAES-B-014 requires an assessment of the hazards associated with the siting, design and construction of
buildings for each of the three stages shown in Figure 2. Each stage represents an increasingly detailed
level of analysis to define the minimum requirements for siting, design and construction for the following
buildings:
 Onshore in-plant buildings;
 Out-of-plant (offsite) buildings within 500 m of a plant perimeter fence; and
 Service buildings, whether inside or outside of plants, that directly support in-plant operations such
as; communications facilities, centralized computer facilities and electrical substations.
The intent of the assessment process is to screen out buildings at the earliest stage in order to provide an
efficient, yet comprehensive, analysis with the main objective of ensuring that people in plant buildings
are not exposed to unacceptable levels of risk in the event of any accidental release of hydrocarbons,
which would commonly require emergency response.
3.1.1 Stage 1 BRA – Building Occupancy & Functionality Identification
In the Stage 1 BRA, the building is assessed in terms of occupancy and functionality. Buildings considered
to be occupied and/or functionally significant are identified at this stage for consideration in the Stage 2
BRA.

Risktec Solutions DMCC Page 15 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

3.1.1.1 Occupancy Screening


As per SAES-B-014 (Reference 1, Section A.4.1.1), a building is considered to be occupied, for the purposes
of occupancy screening, if:
 the building occupancy load is 300 or more man-hours per week; or
 during peak occupancy, 5 people or more are routinely expected in the building for at least one hour.
3.1.1.2 Functionality Screening
As per SAES-B-014 (Reference 1, Section A.4.1.2), a building is defined as functionally significant, if:
 people are expected to remain or take refuge in the building during an emergency. Possible reasons
for people to remain in a building include a lack of suitable evacuation options or the need for
occupants to perform emergency shutdown procedures;
 the building is required for emergency response, such as fire stations or clinic; or
 the building is necessary for continued operation or the safe shutdown of plant units that may be able
to continue to operate or may be unaffected by an incident in another area or the economic impact
on operation of loss of the building is significant. This includes operations and control centre, or
substations that control or provide power to multiple process units.
3.1.2 Stage 2 BRA – Building Hazard Evaluation
In Stage 2 of the BRA process, all buildings carried forward from Stage 1 are assessed against the worst
case credible consequences of fire, explosions and flammable vapour releases to determine the potential
impact on the buildings considered. This includes assessment of the potential harm to a building’s
occupants and/or the potential loss of a building’s functionality.
Hazards are selected based on the results of a desktop HAZID study, conducted to define the discrete
accident scenarios that could results in fire, explosion, or flammable vapour hazards.
The outcome of the Stage 2 BRA is to identify which buildings suffer harm above the tolerability criteria
defined by Saudi Aramco and to provide mitigation measures which can be put in place to reduce the
consequence to the buildings. If the mitigation measures identified are cost prohibitive then the buildings
will require further assessment in a Stage 3 BRA, which is outside of the scope of this report.
3.1.3 Stage 3 BRA – Risk Management
Based on the assessment of buildings, the frequency and consequences of the discrete accident scenarios
defined from the hazard sources are evaluated to quantitatively determine the risk to building occupants
and functionality.
The stage of the BRA can be used to focus consideration of remedial optioneering, to further prevent or
mitigate the hazards defined.
Stage 3 BRA of the BRA process is outside of the scope of this report, and therefore, excluded from the
study.
3.2 Stage 2 BRA Consequence Modelling
Consequence analysis was conducted using Shell’s FRED software v.67 and DNV Phast v6.7 (Reference 3).
The modelling assumptions are presented in Appendix A. The consequence analysis considered the
following events:
 Jet Fire: High momentum fires resulting from pressurised flammable vapour or liquid jet fire from
liquid release due to flashing;
 Pool Fire: Fires resulting from the delayed ignition of a pool of hydrocarbon liquid formed after the
release;
 Tank Top Fires: Fires resulting from the ignition of a pool of hydrocarbon liquid at the top of a tank;
 Flammable Dispersion: The release of flammable vapours measured to hazardous concentrations (i.e.
¼ of the Lower Flammable Limit (LFL) and ½ LFL) will result in a flammable cloud being formed. The

Risktec Solutions DMCC Page 16 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

flammable cloud by itself does not pose any significant threat, however, if the cloud finds an ignition
source then this can lead to either of the following consequences:
- Flash Fire: A slow deflagration of a vapour cloud with no overpressure effects; and
- Vapour Cloud Explosion (VCE): Explosion resulting from the late ignition of flammable vapour
contained within an area of congestion or confinement with associated overpressures.
The consequence results are presented in Appendix C.
3.3 Jet Fire
Reference 5 suggests that non-volatile liquids (e.g. diesel and gasoline) are unlikely to sustain a two-phase
jet fire, unless permanently piloted by an adjacent fire; however some liquid drop-out is likely including
the formation of a pool. As such, jet fires can be discounted from the assessment. However, as a
conservative approach, jet fires from gasoline releases (≤ 100 mm) have been included as the flow rates
are relatively low and less energy is required to sustain ignition (Reference 6).
Immediate ignition of a leak is assumed to result in a steady state jet fire except for the low pressure
systems where a jet fire is unlikely to be sustained for any length of time. The magnitude/impact of a jet
fire is governed by the fluid and process conditions of that fluid.
3.4 Pool Fire (including Bund Fire)
Delayed ignition of a liquid leak is assumed to result in a pool fire. The terms that define the size of the
pool fire are:
 The size of the leak;
 The total released volume (which limits the maximum size of the pool); and
 The containment features available (tank bunds, drainage pits, topography, etc.).
Bunds are assumed to be adequately sized and sufficient to contain the maximum liquid spill from the
combined volume of tanks within each bund. Kerb areas around pumps and loading bays are expected to
cope with the spillages to the extent of the kerb assuming that the drain system is not compromised at
the time.
For unconfined liquid releases, the maximum pool diameter is assumed not to exceed 25m taking into
account the topography of the site (Assumption A02, Appendix A).
3.5 Tank Fires
The releases of hydrocarbon at the top of a floating roof tank will lead to a pool being formed at the tank
top. Two scenarios are considered with respect to pools at the tank top:
 Spill on Roof Fire: Any ignited spill on a roof leading to partial covering of the roof. This assessment
assumes 25% coverage of the roof surface from events such as rim seal failure, jamming of the roof,
tilting the roof, etc.; and
 Full Surface Fire: Any ignited event which causes the full surface of the roof to be covered by
hydrocarbons such as a sunken roof. In this case, the pool size is limited by the tank diameter.
3.6 Flammable Dispersion
Flammable dispersion from a release of flammable vapours will result in a flammable cloud being formed.
Flammable dispersion are modelled in order to assess flash fire and VCE consequences. As the evolution
of large quantities of flammable vapour from diesel or kerosene is very unlikely, flammable vapour
consequences are only considered for gasoline releases.
The size and shape of this cloud is dependent upon the release itself (including the size of any associated
pool) and the weather conditions at the time. Two ignited release scenarios are considered as shown in
Section 3.6.1 and Section 3.6.2.
.

Risktec Solutions DMCC Page 17 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

3.6.1 Flash Fire


The delayed ignition of a flammable vapour cloud in open areas is assumed to result in a flash fire.
3.6.2 Vapour Cloud Explosion (VCE)
The delayed ignition of a flammable vapour cloud in a confined or congested area is assumed to result in
an explosion and associated overpressures. The explosion assessment concentrates on outdoor explosions
and uses the CAM2 model in FRED. The CAM parameters used for this project are presented in Assumption
A04. The equivalent fuel assumed in the CAM model is Propane.
3.7 Building Types
The proposed building types utilised in the BRA follows the guidance set out in SAES-B-014 (Reference 1)
and API RP752 (Reference 2) and are presented in Table 2.
These building types provide a basis for quantifying the potential building damage for the maximum
credible explosion overpressures observed.

Table 2: Building Types

Construction
Description
Type
B1 Wood, temporary buildings, trailers
B2 Steel frame with metal siding
B3 Brick/un-reinforced masonry (load bearing wall)
B4 Steel or concrete frame with masonry fill or cladding
B5 Blast resistant (reinforced concrete)
B6 Brick/moderately reinforced masonry – load bearing
B7 Steel frame building with pre-cast walls and concrete roof

3.8 Damage Level Thresholds


The consequences of the worst credible releases defined have been presented at various thresholds (end
points) which can be correlated to a level of building damage. The effects on buildings for fires, flammable
vapour and overpressure have been specified in the following tables (References 3 and 4).

Table 3: Thermal Radiation Damage

Radiation
Effect on Buildings
Level
The thermal radiation level at which glass windows would be
4.7kW/m2
expected to break.
The thermal radiation level which general/process buildings
12.5kW/m2
would be expected to withstand.
The thermal radiation level at which damage to process
35kW/m2
plant and building may be expected to occur.
Direct Flame
Process plant and buildings may fail within minutes.
Impingement

Table 3 shows that significant building damage is expected to occur when the thermal radiation exceeds
35kW/m2. This has therefore been selected as the defining criteria for building damage.

Risktec Solutions DMCC Page 18 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table 4: Flammable Vapour Damage

LFL Level Effect on Buildings

Stage 2 BRA criteria for the flammable end point inside buildings
¼ LFL (based on expected air infiltration rates and the effects of any air
handling systems).
½ LFL Stage 2 BRA criteria for flammable end point outside buildings.

The criteria in Table 4 are based on the BRA criteria presented in SAES-B-014 (Reference 1). The table
shows that based on 2 air changes per hour and the likely effects of air handling systems, a flammable
vapour mixture may exist inside a building, where a flammable vapour concentration exceeds ¼ LFL
outside the building. This has therefore been selected as the defining criteria for the onset of building
damage.
The damage interface value from a given overpressure varies depending on the building construction type.
This is presented in Table 5.

Table 5: Explosion Overpressure Damage

Pressure (psi)
Vulnerability 1 0.6 0.3 0.05 0
Damage
4/5 3/4 2B/3 2A/2B 1/2A
Interface
B1 8.01 3.00 2.10 1.31 0.59
Proposed Building Type

B2 8.01 4.00 2.49 1.49 0.59


B3 4.80 1.31 1.00 0.75 0.49
B4 8.01 3.80 2.49 1.25 0.59
B5 15.00 8.01 6.00 4.50 3.00
B6 7.01 1.49 1.00 0.75 0.49
B7 8.01 5.11 4.10 2.80 1.31

The resultant building damage (by building type) for each damage interface level is presented in Table 6.

Table 6: Building Damage Categories

Discrete
Brief
Damage Full Description
Description
Level

Onset of visible damage. Repairs are only needed for


1 Minor damage
cosmetic reasons. Building is reusable following an explosion.

Localised building damage. Building performs function and


Moderate can be used; however, major repairs are required to restore
2A
damage integrity of structural envelope. Total cost of repairs is
moderate.
Widespread building damage. Building cannot be used until
Significant
2B major repairs are completed. Total cost of repairs is
damage
significant, approaching replacement cost of building.

Risktec Solutions DMCC Page 19 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Discrete
Brief
Damage Full Description
Description
Level
Building has lost structural integrity and may collapse due to
3 Major damage environmental conditions (i.e. wind, snow, rain). Total cost
of repairs exceeds replacement cost of building.
4 Collapse Building fails completely. Repair not feasible.
5 Annihilation Occupant survival is not possible.

Risktec Solutions DMCC Page 20 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

4 STAGE 1 BRA
The results of the Stage 1 BRA are presented in Table 7 (the Stage 1 screening process is presented in
Appendix E).
The building types have been determined from the information provided and previous experience of similar
Saudi Aramco facilities.

Table 7: Stage 1 BRA Results Summary

Building Occupied /Functionally Stage 2


Building Name
Type Significant? Required?
B-01 SS-XXX1 Receiving Substation
B3 Functionally Significant Yes
Transformer Yard
B-02 SS-XXX2 Utility Power Substation
B3 Functionally Significant Yes
Transformer Yard
B-03 RIB-XXX1 Remote I/O Building B4 Functionally Significant Yes
B-04 RIB-XXX2 Remote I/O Building B4 Functionally Significant Yes
B-05 FSF Building B3 Occupied Yes
B-06 Security Guard House (A) B3 Occupied Yes
B-07 Security Guard House (B) B3 Occupied Yes
B-08 X-Ray Building B3 Not any Yes
B-09 Security Support Building (A) B4 Occupied Yes
B-10 Security Support Building (B) B4 Occupied Yes
B-11 OME Building B4 Occupied Yes
B-12 Operation Building B5 Occupied Yes
B-13 Musalla B3 Occupied Yes
B-14 Chemical Shelter B3 Not any Yes
B-15 Operation Shelter-1 B4 Occupied Yes
B-16 IDAS Shelter-001 B3 Not any Yes
B-17 IDAS Shelter-002 B3 Not any Yes
B-18 Sanitary Metering Shelter-Marafiq B3 Not any Yes
B-19 Utility Water Metering Shelter-
B3 Functionally Significant Yes
Marafiq
B-20 Custody Metering Shelter (Vendor
B3 Not any Yes
Package)
B-21 Oily Water Metering Shelter -
B3 Not any Yes
Marafiq
B-22 Operation Shelter-2 B4 Occupied Yes

It can be seen from Table 7 that a total of 9 buildings have been assessed as occupied, and 5 buildings
have been assessed as functionally significant.
The B-03 RIB-XXX1 Remote I/O Building, B-04 RIB-XXX2 Remote I/O Building, B-08 X-Ray Building, B-14
Chemical Shelter, B-16 IDAS Shelter-001, B-17 IDAS Shelter-002, B-18 Sanitary Metering Shelter-Marafiq,
B-20 Custody Metering Shelter (Vendor Package) and B-21 Oily Water Metering Shelter -Marafiq are not
occupied nor functionally significant as per the requirement of SAES-B-014. These buildings have been

Risktec Solutions DMCC Page 21 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

included in the Stage 2 assessment for completeness, and are assessed under the functional building
criteria.

Risktec Solutions DMCC Page 22 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

5 STAGE 2 BRA
The hazard consequences associated with each release source has been determined for the discrete hazard
threshold levels (end points) specified in Assumption A03 of Appendix A. The distance to each threshold
has been compared against the (point-to-point) separation distance between the release source and the
building with the worst-case hazard level and associated building damage defined.
Results are presented separately for each of the following hazards:
 Jet Fire;
 Pool Fire;
 Flammable Vapour Dispersion; and
 Vapour Cloud Explosion (VCEs).
It should be noted that there are no toxic components in the fluids at YDH and as such no toxic modelling
has been performed. In addition, the software is not able to define complex compositions for the explosion
analysis and therefore, an equivalent fuel type has been determined. For gasoline this has been defined
as Propane.
5.1 Consequence Analysis
Shell’s FRED consequence modelling software v6.1 and DNV Phast v6.7 have been used to determine the
impact of each of the flammable hazard sources. The full consequence modelling results are presented in
Appendix C.
5.2 Separation Distances
The separation distances from each hazard source to the building are presented in Appendix B. This data
has been utilised to determine the worst case hazard impact for each building and whether the building
resides within the range of the lowest threshold modelled. The results from this comparison are presented
in the following sections.
5.3 Stage 2 BRA Results
Table 8 summarises the results of the Stage 2 BRA, while a summary of process units leading to impairment
to the buildings exceeding the assessment criteria are presented in Table 9. The full Stage 2 BRA results
are presented in Appendix D.

Risktec Solutions DMCC Page 23 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table 8: Stage 2 BRA Results Summary

Maximum Credible Explosion Hazard Maximum Credible Fire Hazard

Building Can building


Building Name Maximum heat Can gas Can gas
Type Overpressure Overpressure Worst Damage be subjected
flux at building concentration concentration
(mbar) (psi) Level to flame
(kW/m2) exceed ¼ LFL? exceed ½ LFL?
impingement?
B-01 SS-XXX1 Receiving > 35 (calculated
B3 7 0.102 Minor Y Y Y
Substation Transformer Yard as 171)
B-02 SS-XXX2 Utility Power > 35 (calculated
B3 32 0.464 Minor Y Y Y
Substation Transformer Yard as 142)
B-03 RIB-XXX1 Remote I/O > 35 (calculated
B4 25 0.363 Minor N Y Y
Building as 98)
B-04 RIB-XXX2 Remote I/O > 35 (calculated
B3 26 0.377 Minor Y Y Y
Building as 154)
B-05 FSF Building B3 15 0.218 Minor N < 4.7 Y N
B-06 Security Guard House (A) B3 29 0.421 Minor N < 4.7 Y N
B-07 Security Guard House (B) B3 24 0.348 Minor N 4.7 – 12.5 Y Y
B-08 X-Ray Building B3 22 0.319 Minor N 4.7 – 12.5 Y Y
B-09 Security Support Building
B4 21 0.305 Minor N < 4.7 Y N
(A)
B-10 Security Support Building
B4 19 0.276 Minor N 4.7 – 12.5 Y Y
(B)
B-11 OME Building B4 23 0.334 Minor N < 4.7 Y Y
B-12 Operation Building B5 17 0.247 Minor N 4.7 – 12.5 Y Y
B-13 Musalla B3 16 0.232 Minor N < 4.7 Y Y
B-14 Chemical Shelter B3 27 0.392 Minor N < 4.7 Y Y
B-15 Operation Shelter B4 34 0.493 Minor Y >35 Y Y

B-16 IDAS Shelter-001 B3 4 0.044 Minor N 4.7 – 12.5 Y Y

Risktec Solutions DMCC Page 24 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Maximum Credible Explosion Hazard Maximum Credible Fire Hazard

Building Can building


Building Name Maximum heat Can gas Can gas
Type Overpressure Overpressure Worst Damage be subjected
flux at building concentration concentration
(mbar) (psi) Level to flame
(kW/m2) exceed ¼ LFL? exceed ½ LFL?
impingement?

B-17 IDAS Shelter-002 B3 3 0.044 Minor N 4.7 – 12.5 Y Y

B-18 Sanitary Metering


B3 30 0.435 Minor N < 4.7 Y Y
Shelter-Marafiq
B-19 Utility Water Metering
B3 30 0.435 Minor N < 4.7 Y N
Shelter-Marafiq
B-20 Custody Metering Shelter > 35 (calculated
B3 27 0.392 Minor Y Y Y
(Vendor Package) as 240)
B-21 Oily Water Metering
B3 2 0.029 Minor N 12.5 - 35 Y Y
Shelter -Marafiq
B-22 Operation Shelter-2 B4 7 0.102 Minor Y >35 Y Y

Risktec Solutions DMCC Page 25 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table 9: Hazard Source for Building Impairment Exceeding Assessment Criteria

Vapour Cloud Explosions Jet/Pool Fire Hazards Flammable Gas Dispersion Hazards

Building Pool Fire Maximum Worst


Building Name Jet Flame Jet Fire Heat
Type Explosion Worst Damage Heat heat flux at Flammable Vapour Flammable
Hazard Radiation
Source Level Radiation building Hazard Source Vapour
Source Source
Source (kW/m2) Concentration

B-01 SS-XXX1 Receiving X40-D-0104/0204


Scraper-YNJ- > 35 (calculated
Substation Transformer B3 CA-12AB Minor Scraper-YNJ-1 - X40-D-XXX1 LFL
1 as 171)
Yard YNJ-1
X40-D-0016A/B/C
B-02 SS-XXX2 Utility Power X40-D-0104/0204
> 35 (calculated
Substation Transformer B3 CA-12I Minor L6-42 L6-42 - X40-D-0002A/C(G) LFL
as 142)
Yard X40-D-0501
L6-42
X40-D-0016A/B/C
X40-D-0104/0204
B-03 RIB-XXX1 Remote I/O > 35 (calculated
B4 CA-12J Minor - L6-42 - X40-D-0002A/C LFL
Building as 98)
X40-D-0501
L6-42
X40-D-0016A/B/C
X40-D-0104/0204
B-04 RIB-XXX2 Remote I/O X40-G- X40-G- > 35 (calculated X40-D-0205
B3 CA-12T Minor - LFL
Building XXX3A/B/C XXX3A/B/C as 154) X40-D-0501
X40-D-XXX1
X40-G-XXX3 A/C
X40-D-0016A/B/C
X40-D-0104/0204
B-05 FSF Building B3 CA-10 Minor - - - < 4.7 X40-D-0205 1/4LFL-1/2LFL
X40-D-0002A/B/C
X40-D-0501

Risktec Solutions DMCC Page 26 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Vapour Cloud Explosions Jet/Pool Fire Hazards Flammable Gas Dispersion Hazards

Building Pool Fire Maximum Worst


Building Name Jet Flame Jet Fire Heat
Type Explosion Worst Damage Heat heat flux at Flammable Vapour Flammable
Hazard Radiation
Source Level Radiation building Hazard Source Vapour
Source Source
Source (kW/m2) Concentration
X40-D-0016A/B/C
X40-D-0104/0204
B-06 Security Guard House
B3 CA-10 Minor - - - < 4.7 X40-D-0205 1/4LFL-1/2LFL
(A)
X40-D-0002A/B/C
X40-D-0501
X40-D-0016C
B-07 Security Guard House X40-D-0006A
B3 CA-10 Minor - - 4.7 – 12.5 X40-D-0002C 1/2LFL-LFL
(B) X40-D-0009
X40-D-0501
X40-D-0016C
X40-D-0006A
B-08 X-Ray Building B3 CA-10 Minor - - 4.7 – 12.5 X40-D-0002C 1/2LFL-LFL
X40-D-0009
X40-D-0501
X40-D-0016A/B/C
X40-D-0104/0204
B-09 Security Support
B4 CA-09 Minor - - - < 4.7 X40-D-0205 1/4LFL-1/2LFL
Building (A)
X40-D-0002A/B/C
X40-D-0501
X40-D-0016C
B-10 Security Support X40-D-0006A
B4 CA-10 Minor - - 4.7 – 12.5 X40-D-0002C 1/2LFL-LFL
Building (B) X40-D-0009
X40-D-0501
B-11 OME Building B4 CA-10 Minor - - - < 4.7 X40-D-0501 1/2LFL-LFL
X40-D-0016C
X40-D-0006A
B-12 Operation Building B5 CA-12AC Minor - - 4.7 – 12.5 X40-D-0002C 1/2LFL-LFL
X40-D-0009
X40-D-0501
B-13 Musalla B3 CA-10 Minor - - - < 4.7 X40-D-0501 1/2LFL-LFL
B-14 Chemical Shelter B3 CA-10 Minor - - - < 4.7 X40-D-0501 1/2LFL-LFL

Risktec Solutions DMCC Page 27 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Vapour Cloud Explosions Jet/Pool Fire Hazards Flammable Gas Dispersion Hazards

Building Pool Fire Maximum Worst


Building Name Jet Flame Jet Fire Heat
Type Explosion Worst Damage Heat heat flux at Flammable Vapour Flammable
Hazard Radiation
Source Level Radiation building Hazard Source Vapour
Source Source
Source (kW/m2) Concentration
B-15 Operation Shelter B4 CA-12I Minor - L6-42 L6-42 > 35 L6-42 LFL
X40-D-0016A/C
X40-D-0405
B-16 IDAS Shelter-001 B3 CA-23 Minor - - 4.7 – 12.5 X40-D-0104/0204 LFL
X40-D-0501
X40-D-0002C
X40-D-0205
B-17 IDAS Shelter-002 B3 CA-23 Minor - - X40-D-XXX2 4.7 – 12.5 X40-D-0204 LFL
X40-D-XXX1
B-18 Sanitary Metering
B3 CA-10 Minor - - < 4.7 X40-D-0501 <1/4LFL
Shelter-Marafiq
B-19 Utility Water Metering
B3 CA-10 Minor - - - < 4.7 X40-D-0501 <1/4LFL
Shelter-Marafiq
X40-D-0016C
X40-U- X40-U- X40-D-0002A/B/C
0014A/D 0014A/D X40-D-0204
L1-30 L1-30 X40-U-0014A/C
B-20 Custody Metering L5-30 L5-30 > 35 (calculated
B3 CA-13A Minor - L1-30 LFL
Shelter (Vendor Package) as 240)
YAS-30 YAS-30 L5-30
SAM-30 SAM-30 YAS-30
YR-24 YR-24 SAM-30
YR-24
B-21 Oily Water Metering
B3 CA-12V Minor Scraper-YNJ-1 YNJ-2 12.5 – 35 YNJ-1 1/2LFL-LFL
Shelter -Marafiq
YNJ-1 YNJ-1
B-22 Operation Shelter-2 B4 CA-12AB Minor Scraper-YNJ-1 Scraper-YNJ-1 > 35 LFL
YNJ-2 X40-D-0015B

Risktec Solutions DMCC Page 28 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

It can be seen from Table 8 that all buildings are impacted by consequences above the Stage 2 BRA
criteria. As such, mitigations will need to be implemented as part of the building design. Where the
adequate mitigations cannot be implemented, or where the cost of the mitigations is deemed excessive,
a Stage 3 BRA can be conducted to determine the risk to personnel within the buildings.
The following sections present the Stage 2 BRA results for each hazard effects.
5.3.1 Jet fire
It can be seen from Table 8 that the following buildings will be subjected to direct flame impingement and
exposed to heat radiation flux above 35kW/m2:
 B-01 SS-XXX1 Receiving Substation Transformer Yard (the maximum heat radiation flux is
calculated as 171kW/m2);
 B-02 SS-XXX2 Utility Power Substation Transformer Yard (the maximum heat radiation flux is
calculated as 142kW/m2);
 B-04 RIB-XXX2 Remote I/O Building (the maximum heat radiation flux is calculated as 154kW/m2);
 B-15 Operation Shelter-1 (the maximum heat radiation flux is calculated as 138kW/m2);
 B-20 Custody Metering Shelter (Vendor Package) (the maximum heat radiation flux is calculated
as 240kW/m2; and
 B-22 Operation Shelter-2 (the maximum heat radiation flux is calculated as 137kW/m2);
Although the jet fires will not impinge the B-03 RIB XXX1 Remote I/O Building, it is potentially exposed to
heat radiation flux above 35kW/m2 (calculated as 98kW/m2). The B-21 Oily Water Metering Shelter -
Marafiq is potentially exposed to heat radiation flux between 12.5kW/m2 and 35kW/m2 due to YNJ-1
scraper launcher.
All other buildings are potentially exposed to heat radiation flux below 4.7kW/m2.
5.3.2 Pool Fire
The B-20 Custody Metering Shelter (Vendor Package) is potentially exposed to heat radiation flux between
12.5kW/m2 and 35kW/m2 due to release from SAM-30 and YR-22 pipelines.
The B-21 Oily Water Metering Shelter -Marafiq) is potentially exposed to heat radiation flux between
12.5kW/m2 and 35kW/m2 due to release from YNJ-2 pipeline.
The B-22 Operation Shelter-2 is potentially exposed to heat radiation flux between 12.5kW/m2 and
35kW/m2 due to release from YNJ-1 and YNJ-2 pipelines.
The following buildings will be subjected to heat radiation flux between 4.7kW/m2 and 12.5kW/m2 due to
bund fires within the YDH:
 B-01 SS-XXX1 Receiving Substation Transformer Yard;
 B-02 SS-XXX2 Utility Power Substation Transformer Yard;
 B-03 RIB-XXX1 Remote I/O Building;
 B-04 RIB-XXX2 Remote I/O Building;
 B-07 Security Guard House (B);
 B-08 X-Ray Building;
 B-10 Security Support Building (B);
 B-12 Operation Building;
 B-16 IDAS Shelter-001; and
 B-17 IDAS Shelter-002.

Risktec Solutions DMCC Page 29 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

5.3.3 Flammable Vapour Dispersion


It can be seen from Table 8 that the flammable vapour dispersions will reach all of the buildings being
assessed. All building assessed are exposed to flammable vapour concentrations above ½ LFL with the
exception of the following which are exposed to flammable vapour concentrations below ½ LFL:
 B-05 FSF Building;
 B-06 Security Guard House (A);
 B-09 Security Support Building (A);
 B-18 Sanitary Metering Shelter – Marafiq; and
 B-19 Utility Water Metering Shelter – Marafiq.
Therefore, a flammable atmosphere could be expected in each building.
5.3.4 Vapour Cloud Explosions (VCE)
It can be seen from Table 8 that all buildings are only expected to suffer minor damage, which is below
the SAES-B-014 damage criteria, and no further assessment is required.

Risktec Solutions DMCC Page 30 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

6 CONCLUSIONS
This report presents the results of the Stage 1 and Stage 2 BRA, whereby the worst case credible hazard
consequences (fire, explosion, and flammable vapour clouds) are identified, and their impact on plant
buildings evaluated. The results of the Stage 2 assessment are summarised in Table 8, from which the
following findings and conclusions are made:
6.1 Stage 1 BRA
A total of 9 buildings have been assessed as occupied, and 5 buildings have been assessed as functionally
significant.
6.2 Stage 2 BRA
6.2.1 Jet fire
The following buildings will be subjected to direct flame impingement and exposed to heat radiation flux
above 35kW/m2:
 B-01 SS-XXX1 Receiving Substation Transformer Yard (the maximum heat radiation flux is
calculated as 171kW/m2);
 B-02 SS-XXX2 Utility Power Substation Transformer Yard (the maximum heat radiation flux is
calculated as 142kW/m2);
 B-04 RIB-XXX2 Remote I/O Building (the maximum heat radiation flux is calculated as 154kW/m2);
 B-15 Operation Shelter-1 (the maximum heat radiation flux is calculated as 138kW/m2);
 B-20 Custody Metering Shelter (Vendor Package) (the maximum heat radiation flux is calculated
as 240kW/m2; and
 B-22 Operation Shelter-2 (the maximum heat radiation flux is calculated as 137kW/m2);
Although jet fires will not impinge the B-03 RIB XXX1 Remote I/O Building, it is potentially exposed to heat
radiation flux above 35kW/m2 (calculated as 98kW/m2). The B-21 Oily Water Metering Shelter -Marafiq is
potentially exposed to heat radiation flux between 12.5kW/m2 and 35kW/m2 due to YNJ-1 scraper
launcher.
All other buildings are potentially exposed to heat radiation flux below 4.7kW/m2.
6.2.2 Pool fire
The B-20 Custody Metering Shelter (Vendor Package) is potentially exposed to heat radiation flux between
12.5kW/m2 and 35kW/m2 due to release from SAM-30 and YR-22 pipelines.
The B-21 Oily Water Metering Shelter -Marafiq) is potentially exposed to heat radiation flux between
12.5kW/m2 and 35kW/m2 due to release from YNJ-2 pipeline.
The B-22 Operation Shelter-2 is potentially exposed to heat radiation flux between 12.5kW/m2 and
35kW/m2 due to release from YNJ-1 and YNJ-2 pipelines.
The following buildings will be subjected to heat radiation flux between 4.7kW/m2 and 12.5kW/m2 due to
bund fires within the YDH:
 B-01 SS-XXX1 Receiving Substation Transformer Yard;
 B-02 SS-XXX2 Utility Power Substation Transformer Yard;
 B-03 RIB-XXX1 Remote I/O Building;
 B-04 RIB-XXX2 Remote I/O Building;
 B-07 Security Guard House (B);
 B-08 X-Ray Building;
 B-10 Security Support Building (B);
 B-12 Operation Building;

Risktec Solutions DMCC Page 31 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

 B-16 IDAS Shelter-001; and


 B-17 IDAS Shelter-002.
6.2.3 Flammable vapour dispersion
The flammable vapour dispersions will reach all of the buildings being assessed. All building assessed are
exposed to flammable vapour concentrations above ½ LFL with the exception of the following which are
exposed to flammable vapour concentrations below ½ LFL:
 B-05 FSF Building;
 B-06 Security Guard House (A);
 B-09 Security Support Building (A);
 B-18 Sanitary Metering Shelter – Marafiq; and
 B-19 Utility Water Metering Room – Marafiq.
Therefore, a flammable atmosphere could be expected in each building.
6.2.4 Vapour cloud explosions
All buildings are only expected to suffer minor damage, which is below the SAES-B-014 damage criteria,
and no further assessment is required.

Risktec Solutions DMCC Page 32 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

7 RECOMMENDATIONS
7.1 Building Specific Recommendations
Based on the Stage 2 BRA results summary, building specific risk mitigation measures have been developed
for each building and are presented in Table 10.

Table 10: Proposed Building Specific Risk Mitigation Measures

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Review functionality of the building. Based on review of potential business
interruption impact, consider rating the external walls to withstand direct jet
fire flame impingement (the maximum heat radiation flux is calculated
as 171kW/m2).
B-01 SS-XXX1
Also, consider relocating the building outside the flame impingement radius
Receiving
Functionally of 121m from the Scraper-YNJ-1 (G) (for the scenario description refer to
Substation
Significant Assumption A03, Appendix A).
Transformer
Yard Note: Further risk mitigation measures may not be required if the impact of
losing the buildings function does not have a catastrophic impact on the
continued operation of the plant.
Hydrocarbon gas detectors should be installed at the building to provide an
audible and visual alarm.
Review functionality of the building. Based on review of potential business
interruption impact, consider rating the external walls to withstand direct jet
fire flame impingement (the maximum heat radiation flux is calculated
B-02 SS-XXX2 as 142kW/m2).
Utility Power Also, consider relocating the building outside the flame impingement radius
Functionally
Substation of 60m from the PG 95 Storage Tanks outlet header.
Significant
Transformer Note: Further risk mitigation measures may not be required if the impact of
Yard losing the buildings function does not have a catastrophic impact on the
continued operation of the plant.
Hydrocarbon gas detectors should be installed at the building to provide an
audible and visual alarm.
B-03 RIB-XXX1
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Remote I/O
Significant audible and visual alarm.
Building
B-04 RIB-XXX2
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Remote I/O
Significant audible and visual alarm.
Building
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external doors
B-05 FSF should be fitted with gas-tight seals and equipped with quick acting,
Occupied adjustable door closing mechanism. Windows should be eliminated,
Building
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.

Risktec Solutions DMCC Page 33 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external doors
B-06 Security should be fitted with gas-tight seals and equipped with quick acting,
Guard House Occupied adjustable door closing mechanism. Windows should be eliminated,
(A) minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
B-07 Security dampers and put the HVAC system into re-circulation mode). Hydrocarbon
Guard House Occupied gas detectors should initiate an audible and visual alarm and all external doors
(B) should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.
B-08 X-Ray Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Building Significant note audible and visual alarm.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external doors
B-09 Security should be fitted with gas-tight seals and equipped with quick acting,
Support Building Occupied adjustable door closing mechanism. Windows should be eliminated,
(A) minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.

Risktec Solutions DMCC Page 34 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
B-10 Security dampers and put the HVAC system into re-circulation mode). Hydrocarbon
Support Building Occupied gas detectors should initiate an audible and visual alarm and all external doors
(B) should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external doors
B-11 OME should be fitted with gas-tight seals and equipped with quick acting,
Occupied adjustable door closing mechanism. Windows should be eliminated,
Building
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
B-12 Operation
Occupied gas detectors should initiate an audible and visual alarm and all external doors
Building
should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
gas detectors should initiate an audible and visual alarm and all external doors
should be fitted with gas-tight seals and equipped with quick acting,
B-13 Musalla Occupied adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.

Risktec Solutions DMCC Page 35 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
B-14 Chemical Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Shelter Significant note audible and visual alarm.
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
B-15 Operation
Occupied gas detectors should initiate an audible and visual alarm and all external doors
Shelter
should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.

B-16 IDAS Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Shelter-001 Significant note audible and visual alarm.

B-17 IDAS Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Shelter-002 Significant note audible and visual alarm.
B-18 Sanitary
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Metering Room-
Significant note audible and visual alarm.
Marafiq
B-19 Utility
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Water Metering
Significant audible and visual alarm.
Room-Marafiq
The functionality of the building should be reviewed and the impact of losing
the function of the building determined. If loss of the building function can
have catastrophic impact on continued safe operation of the facility, the
following risk reduction measures should be considered.
Either design the external walls of the building to withstand direct jet fire
flame impingement (the maximum heat radiation flux is calculated as
B-20 Custody 240kW/m2) or relocate the building outside the flame impingement radius of:
Metering Shelter Functionally  184m from the Gasoline Custody Metering Skid (X40-U-0014A);
(Vendor Significant note
 170m from the Gasoline Meter Prover Skid (X40-U-0014D);
Package)
 213m from the from gasoline receiving manifold outlet headers (for
PG 91 and PG 95); and
 30m from the diesel pipelines from Yasref/Samref and gasoline
pipeline from Yasref.
Hydrocarbon gas detectors should be installed at the building to provide an
audible and visual alarm.
B-21 Oily Water
Functionally Hydrocarbon gas detectors should be installed at the building to provide an
Metering Shelter
Significant note audible and visual alarm.
-Marafiq

Risktec Solutions DMCC Page 36 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Occupied/
Name of Functionally
Proposed Risk Mitigation Measures
Building Significant
Building
Ensure that emergency escape and evacuation procedures for the building
consider potential sources of thermal radiation, ensuring escape routes and
mustering areas are outside the >4.7kW/m2 thermal radiation zone.
If building occupants are required to stay in the building in the event of an
incident on the plant, hydrocarbon gas detectors should be installed in HVAC
inlets, which automatically shutdown the HVAC system (close the fire
dampers and put the HVAC system into re-circulation mode). Hydrocarbon
B-22 Operation
Occupied gas detectors should initiate an audible and visual alarm and all external doors
Shelter-2
should be fitted with gas-tight seals and equipped with quick acting,
adjustable door closing mechanism. Windows should be eliminated,
minimised or designed to prevent flammable gas ingress. The HVAC system
installed should comply with the requirements of SAES-K-022.
If building occupants are not required to stay in the building in the event of
an incident on the plant, hydrocarbon gas detectors should be installed at the
building to provide an audible and visual alarm.
Note: The B-03 RIB-XXX1 Remote I/O Building, B-04 RIB-XXX2 Remote I/O Building, B-08 X-Ray Building, B-14 Chemical Shelter,
B-16 IDAS Shelter-001, B-17 IDAS Shelter-002, B-18 Sanitary Metering Shelter-Marafiq, B-20 Custody Metering Shelter (Vendor
Package) and B-21 Oily Water Metering Shelter -Marafiq are not occupied nor functionally significant as per the requirement of
SAES-B-014. These buildings have been included for completeness and are assessed under the functional building criteria.

Risktec Solutions DMCC Page 37 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

7.2 General Recommendations


As well as the building specific mitigation measures detailed in Table 10, the following general mitigation
measures should be considered:
 All buildings in YDH should comply with the requirements of SAES-B-055 for spacing between
buildings, and process plant, and with SAES-B-014 for fire and water system requirements. In addition,
all buildings covered by SSD-9 and SSD-26 must comply with the requirements of these directives.
 It is generally recommended, in process industries, that in-plant buildings do not have windows. This
is supported by SAES-B-014. However, Clause 5.8, Exception B of SAES-B-014 states that windows
are allowed for ‘Operator shelters that are specifically designed for personnel protection and for
monitoring of a process facility or bulk plant operation such as truck loading. Personnel protection
against any overpressures anticipated by the risk assessment shall be included in the sizing and design
of the windows’. SAES-B-014 also states that as a minimum, these windows should be double glazed
with tempered glass, internal lamination, a catch system for the glass using anchored cables or wrap
bars. The glass used in the windows will be a minimum of 6 mm (¼ in) thick and is either wired,
tempered or laminated safety glass. The glass shall meet all fire-resistive regulations and safety
performance requirements of SAES-M-100 and ASME Z97.1 and shall be labelled as such by the
supplier.
 Should the design of these buildings contain windows, the design details shall be provided to the
company representative for approval by the Supervisor, Civil Engineering Unit, Consulting Services
Department (CSD), Dhahran, and by the Chief Fire Prevention Engineer or his representative.
 The site ERP should include any of the new buildings which are designed to act as safe refuges in the
event of an emergency. Additional potential risk mitigation measures may be required for these
buildings. Additionally, the site ERP, drills and escape routes should take into account the identified
fire hazard scenarios on each building.
 Where adequate mitigations cannot be implemented, or where the cost of the mitigations is deemed
excessive, a Stage 3 BRA should be conducted to determine the risk to personnel and building
functionality.
 The escape arrangements (e.g. escape route, access, egress) for the following buildings could be
(depending on the direction of the release) impaired by jet/pool fire events from one or more hazard
sources:
o B-01 SS-XXX1 Receiving Substation Transformer Yard;
o B-02 SS-XXX2 Utility Power Substation Transformer Yard;
o B-03 RIB-XXX1 Remote I/O Building;
o B-04 RIB-XXX2 Remote I/O Building;
o B-18 Sanitary Metering Room-Marafiq; and
o B-20 Custody Metering Shelter (Vendor Package).
It is recommended that a formal Escape, Evacuation and Rescue Assessment (EERA) is performed and
further risk mitigation measures identified (if required).

Risktec Solutions DMCC Page 38 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

8 REFERENCES
Ref Title
1. Saudi Aramco Engineering Standard, Safety Requirements for Plant and Operations Support
Buildings, SAES-B-014, 3 July 2012.
2. American Petroleum Institute (API), Management of Hazards Associated With Location Of
Process Plant Buildings, Recommended Practice (RP) 752.
3. Shell Global Solutions, Fire, Release, Explosion, Dispersion (FRED) Hazard Consequence
Modelling Package Technical Guide, Issue 7.0, July 2012.
4. UK HSE, Development of Methods to Assess the Significance of Domino Effects from Major
Hazard Sites, HSE CRR 183/1998.
5. IChemE, An Overview Of The Nature Of Hydrocarbon Jet Fire Hazards In The Oil And Gas
Industry And A Simplified Approach To Assessing The Hazards, Trans IChemE, Part B, Process
Safety and Environmental Protection, 2007, 85(B3): 207–220, B. J. Lowesmith, G. Hankinson, M.
R. Acton and G. Chamberlain, 2007.
6. Email from Faisal Basaffar to Mike Bates, “Product Pipeline Event Tree”, 26th March 2015.
7. UK HSE, Development of Methods to Assess the Significance of Domino Effects from Major
Hazard Sites, HSE CRR 183/1998.
8. Shell Global Solutions, Shell Shepherd Desktop Technical Guide, Version 3.1, 2011.
9. HSE, Reducing Risks, Protecting People, HSE’s Decision-Making Process, HMSO, 2001.
10. Saudi Aramco (2006) Engineering Standard – Onshore and Nearshore Pipeline Safety, SAES-B-
064

Risktec Solutions DMCC Page 39 of 39


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

APPENDIX A ASSUMPTIONS REGISTER

Risktec Solutions DMCC Page A.1 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

ASSUMPTION SHEET

Project Title: Stage 1 & 2 BRA for Yanbu Distribution Hub

Assumption No.: A01 Revision: 2.0 Date: 7th July 2016

Subject: Meteorological Data

Assumption:
The weather conditions used in both consequence modelling (FRED and DNV Phast) are detailed below.
Weather Conditions used:
 An ambient temperature of 27°C is assumed based on the ‘Average Annual Temperature’ in
Reference 1.
 Humidity: 56.5% is assumed based on the rounded mean ‘Average Relative Humidity’, ‘Average
Morning Relative Humidity’ and ‘Average Evening Relative Humidity’ in Reference 1.
 The Pasquill Stability Class / wind speeds to be used are F1.5 and D5.
Justification:
Ambient temperature – Data was taken from Reference 1.
Ambient humidity – Data for Yanbu was taken from Reference 2.

References
1. Saudi Aramco Engineering Standard, Meteorological & Seismic Design Data, SAES-A-112, 17th
November 2008.
2. http://www.weatherbase.com/weather/weather.php3?s=93404&cityname=Yanbu%27al-Bahr-Al-
Madinah-al-Munawwarah-Saudi-Arabia

Risktec Solutions DMCC Page A.2 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

ASSUMPTION SHEET

Project Title: Stage 1 & 2 BRA for Yanbu Distribution Hub

Assumption No.: A02 Revision: 1.0 Date: 12th June 2016

Subject: Consequence Modelling Assumptions

Assumption:

Parameter QRA Criteria

 Wind speed 1.5 m/s and Pasquill stability class ‘F’


Meteorological data
 Wind speed 5 m/s and Pasquill stability class ‘D’
Flammable gas end
Distances to ¼ LFL, ½ LFL
points
Distances to the following thermal radiation (heat flux) levels will be calculated for jet and
pool fire scenarios (where appropriate)
Thermal radiation end  4.7kW/m2
points  12.5kW/m2
 37.5kW/m2
These included a solar radiation allowance of 1kW/m2.
Dispersion sampling times – instantaneous.
Dispersion Evolution of vapours from diesel/kerosene is not deemed credible and as such flash
fires/explosions have not been considered for diesel/kerosene releases.
A surface roughness of 0.1 m was used as this is considered most appropriate for the
Surface Roughness
YDH.
 Discharge Coefficient – 0.6 (liquid); 0.8 (gas)
 Pipe length – 0 m
Release Geometry
 Release orientation from vertical – 90 deg (i.e. horizontal)
 Angle clockwise from North – 0 deg
The following release heights were used:
 Pipeworks – 1 m
 Loading bays – 1 m
 Tank releases – 1 m
Release Height
 Tank top scenarios – 80% of tank height
Releases at height from the overhead piperacks are not modelled as they are fully welded,
rated pipes. The dominant release will be at the loading arms and the road tankers where
there are significantly more leak paths as well as human interactions.
YNJ-1 and YNJ-2 pipelines consequence results were taken from the pipeline QRA report
Pipelines (Reference 2). The other pipelines (i.e. the ones coming from Yasref, Samref and YR)
were modelled using the same approach used for YNJ-1 and YNJ-2 (Reference 2).
Bunds are assumed to be adequately sized and sufficient to contain the maximum liquid
spill from the tanks within each bund.
Secondary Containment
Kerb areas around pumps and loading bays are expected to cope with the spillages to the
extent of the kerb assuming that the drain system is not compromised at the time.
For unconfined liquid releases, the maximum pool diameter was assumed not to exceed
Unconfined Release
25m taking into account the topography of the site.

Large bore jet fires Reference 3 suggests that non-volatile liquids (e.g., kerosene, diesel, or gasoline) are
unlikely to be able to sustain a two-phase jet fire, unless permanently piloted by an

Risktec Solutions DMCC Page A.3 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

adjacent fire; even so, some liquid drop-out is likely and hence the formation of a pool. As
such, jet fires can be discounted from the assessment. However, as a conservative
approach, jet fires from gasoline release (≤ 100 mm) were included as the flow rates are
relatively low and less energy is required to sustain ignition (Reference 4).

Justification:
Considered to be appropriate figures from review of Reference 1.

References:
1. Shell Global Solutions, Fire, Release, Explosion, Dispersion (FRED) Hazard Consequence Modelling
Package Technical Guide, Issue 6.0
2. Risktec Solutions DMCC, Yanbu to Jeddah Product Pipelines Quantitative Risk Assessment (QRA)
Report, Doc. No. JZA-02-R-03, Issue 4.0, October 2015
3. IChemE, An Overview Of The Nature Of Hydrocarbon Jet Fire Hazards In The Oil And Gas Industry
And A Simplified Approach To Assessing The Hazards, Trans IChemE, Part B, Process Safety and
Environmental Protection, 2007, 85(B3): 207–220, B. J. Lowesmith, G. Hankinson, M. R. Acton and
G. Chamberlain, 2007.
4. Email from Faisal Basaffar to Mike Bates, “Product Pipeline Event Tree”, 26th March 2015.

Risktec Solutions DMCC Page A.4 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

ASSUMPTION SHEET

Project Title: Stage 1 & 2 BRA for Yanbu Distribution Hub

Assumption No.: A03 Revision: 3.0 Date: 7th July 2016

Subject: Hazard Sources

Assumption:
The following hazard sources have been defined for the Yanbu Distribution Hub.

Operating Operating Flow Hole


Volume Note
Description Hazard Ref. Material Pressure Temp Rate Size
(m3) #
(kPaG) (°C) (m3/hr) (inch)
Tanks
X40-D-0016A(G) Gasoline Atm Ambient - 27658 - 1

Storage Tank (PG X40-D-0016B(G) Gasoline Atm Ambient - 27658 - 1


95) X40-D-0016C(G) Gasoline Atm Ambient - 27658 - 1
X40-D-0104(G) Gasoline Atm Ambient - 54056 - 1
X40-D-0002A(G) Gasoline Atm Ambient - 27658 - 1
X40-D-0002B(G) Gasoline Atm Ambient - 27658 - 1
Storage Tank
X40-D-0002C(G) Gasoline Atm Ambient - 27658 - 1
(PG 91)
X40-D-0204(G) Gasoline Atm Ambient - 54056 - 1
X40-D-0205(G) Gasoline Atm Ambient - 54056 - 1
X40-D-0006A(D) Diesel Atm Ambient - 40842 - 1
X40-D-0006B(D) Diesel Atm Ambient - 40842 - 1
Storage Tank
X40-D-0006C(D) Diesel Atm Ambient - 40842 - 1
(DO)
X40-D-0304(D) Diesel Atm Ambient - 62781 - 1
X40-D-0305(D) Diesel Atm Ambient - 62781 - 1
X40-D-0018A(K) Kerosene Atm Ambient - 27108 - 1
X40-D-0018B(K) Kerosene Atm Ambient - 27108 - 1
Storage Tank
X40-D-0018C(K) Kerosene Atm Ambient - 27108 - 1
(DPK)
X40-D-0017(K) Kerosene Atm Ambient - 40228 - 1
X40-D-0405(K) Kerosene Atm Ambient - 40228 - 1

Storage Tank- X40-D-0009(D) Diesel Atm Ambient - 54056 - 1


T&I (DO/DPK) X40-D-0009(K) Kerosene Atm Ambient - 54056 - 1
Day Tank
X40-D-0037(D) Diesel Atm Ambient - 45 - 1
(DIESEL)
Storage Tank-
X40-D-0501(G) Gasoline Atm Ambient - 54056 - 1
T&I (PG95/PG91)
Storage Tank
X40-D-XXX1(G) Gasoline Atm Ambient - 62781 - 1
(PG91)

Risktec Solutions DMCC Page A.5 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Operating Operating Flow Hole


Volume Note
Description Hazard Ref. Material Pressure Temp Rate Size
(m3) #
(kPaG) (°C) (m3/hr) (inch)
Storage Tank
X40-D-XXX2(G) Gasoline Atm Ambient - 62781 - 1
(PG95)
Storage Tank
X40-D-XXX3(D) Diesel Atm Ambient - 62781 - 1
(DO)
Vessels
Drain Vessel (HC) X40-D-0015A(G) Gasoline Atm Ambient - 1000 4
2
Drain Vessel (HC) X40-D-0015B(G) Gasoline Atm Ambient - 1000 4
Pumps
Booster Pumps
X40-G-0020(G) Gasoline 717 29.5 530.1 1000 10
(Gasoline)
Shipper Pumps
X40-G-0021(G) Gasoline 13842 29.5 530.1 1000 10
(Gasoline)
X40-G-0018(D) Diesel 857 29.5 744 1000 12 3
Booster Pumps
(Diesel/Kerosene) X40-G-0018(K) Kerosene 857 29.5 744 1000 12

Shipper Pumps X40-G-0019(D) Diesel 13795 29.5 744 1000 12


(Diesel/Kerosene) X40-G-0019(K) Kerosene 13795 29.5 744 1000 12
Booster Pumps
(Gasoline) - X40-G-XXX1(G) Gasoline 717 29.5 530.1 1000 10
Future
Booster Pumps X40-G-XXX2(D) Diesel 857 29.5 744 1000 12
(Diesel/Kerosene) 4
- Future X40-G-XXX2(K) Kerosene 857 29.5 744 1000 12

Shipper Pumps
(Gasoline) - X40-G-XXX3(G) Gasoline 13842 29.5 530.1 1000 10
Future
Packages/Skids
DPK Filtration
Skid - Circulation G-5101(K) Kerosene 522 29.5 662.5 1000
pumps
DPK Filtration
5
Skid - Water D-0024(K) Kerosene 522 29.5 662.5 1000
Coalescers
DPK Filtration
D-0025(K) Kerosene 122 29.5 662.5 1000
Skid - Clay Filters
Gasoline Custody
X40-U-0014A(G) Gasoline 276 29.5 909 1000 24
Metering Skid
Diesel Custody
X40-U-0014B(D) Diesel 408 29.5 803.7 1000 22
Metering Skid 6
Kerosene
Custody Metering X40-U-0014C(K) Kerosene 430 29.5 666.7 1000 22
Skid
X40-U-0014D(G) Gasoline 276 29.5 909 1000 24
Meter Prover Skid X40-U-0014D(D) Diesel 408 29.5 803.7 1000 22 7
X40-U-0014D(K) Kerosene 430 29.5 666.7 1000 22

Risktec Solutions DMCC Page A.6 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Operating Operating Flow Hole


Volume Note
Description Hazard Ref. Material Pressure Temp Rate Size
(m3) #
(kPaG) (°C) (m3/hr) (inch)
Lines
Line from
gasoline (PG91)
receiving
L1-30(G) Gasoline 276 29.5 3672 1000 30 -
manifold to
STORAGE
TANK(PG 91)
Line from
Storage Tanks
(PG 91) to L2-42(G) Gasoline 99 29.5 4240 1000 42 -
Booster Pumps
(Gasoline)
Line from the
Booster Pumps
(Gasoline) to the L3-20(G) Gasoline 717 29.5 530.1 1000 20 -
Shipper Pumps
(Gasoline)
Line from the
Shipper Pumps
(Gasoline) to the L4-20(G) Gasoline 15513.2 29.5 1000 20 -
YNJ-1 scraper
launcher
Line from
gasoline (PG95)
receiving
L5-30(G) Gasoline 276 29.5 3672 1000 30 -
manifold to
STORAGE
TANK(PG 91)
Line from
Storage Tanks
(PG 95) to L6-42(G) Gasoline 99 29.5 4240 1000 42 -
Booster Pumps
(Gasoline)
Line from diesel
receiving
manifold to L7-30(D) Diesel 408 29.5 4308 1000 30 -
Storage Tanks
(DO)
Line from the
Storage Tanks
(DO) to the L8-48(D) Diesel 122 29.5 4882 1000 48 -
Booster Pumps
(Diesel/Kerosene)
Line from the L9-24(D) Diesel 857 29.5 2232 1000 24 -
Booster Pumps
(Diesel/Kerosene)
to the Shipper L9-24(K) Kerosene 857 29.5 2232 1000 24 -
Pumps
(Diesel/Kerosene)
Line from the L10-24(D) Diesel 15513.2 29.5 - 1000 24 -
Shipper Pumps
(Diesel/Kerosene)
to the YNJ-2 L10-24(K) Kerosene 15513.2 29.5 - 1000 24 -
scraper launcher

Risktec Solutions DMCC Page A.7 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Operating Operating Flow Hole


Volume Note
Description Hazard Ref. Material Pressure Temp Rate Size
(m3) #
(kPaG) (°C) (m3/hr) (inch)
Line from
kerosene
receiving
L11-30(K) Kerosene 340 29.5 3086 1000 30 -
manifold to
Storage Tanks
(DPK)
Line from
Storage Tanks
(DPK) to Booster L12-48(K) Kerosene 122 29.5 4882 1000 48 -
Pumps
(Diesel/Kerosene)
Line from
Storage Tanks
L13-24(K) Kerosene 122 29.5 1325 1000 24 -
(DPK) to DPK
Filtration Skid.
Line from DPK
Filtration Skid to
L14-20(K) Kerosene 122 29.5 1325 1000 20 -
Storage Tanks
(DPK)
Pipelines
YNJ-1 Pipeline YNJ-1(G) Gasoline 15513.2 43.3 - - 20
YNJ-2(D) Diesel 15513.2 43.3 - - 24 8
YNJ-2 Pipeline
YNJ-2(K) Kerosene 15513.2 43.3 - - 24
Gasoline pipeline
YAS-30(G) Gasoline 1795 43.3 3500 - 30 -
from YASREF
Gasoline pipeline
SAM-30(G) Gasoline 1795 43.3 3672 - 30 -
from SAMREF
Gasoline pipeline
YR-24(G) Gasoline 1795 43.3 2727 - 24 -
from YR
Diesel pipeline
YAS-30(D) Diesel 1795 43.3 4308 - 24 -
from YASREF
Diesel pipeline
SAM-30(D) Diesel 1795 43.3 3082 - 24 -
from SAMREF
Diesel pipeline
YR-22(D) Diesel 1795 43.3 2411 - 24 -
from YR
Kerosene pipeline
SAM-30(K) Kerosene 1795 43.3 3086 - 24 -
from SAMREF
Kerosene pipeline
YR-22(K) Kerosene 1795 43.3 2000 - 24 -
from YR
Scrapers
Scraper Launcher
at YDH (YNJ-1 Scraper-YNJ-1(G) Gasoline 15513.2 29.5 - 1000 20 -
P/L)
Scraper Launcher Scraper-YNJ-2(D) Diesel 15513.2 29.5 - 1000 24 -
at YDH (YNJ-2
P/L) Scraper-YNJ-2(K) Kerosene 15513.2 29.5 - 1000 24 -

Risktec Solutions DMCC Page A.8 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Note 1 Hydrocarbon inventory in tanks is assumed to be 80% of tank volume.


Note 2 Based on the YDH PFDs, the materials that can flow into the vessel are diesel, gasoline and kerosene.
However, for the purpose of modelling, a worst case material, i.e. Gasoline, will be used.
Note 3 3x duty and 1x standby is assumed based on the pumps combined header flowrate provided in the PFDs.
Note 4 3x duty and 1x standby is assumed.
Note 5 This is a vendor package and the process conditions are not available. The operating pressure was assumed
based on a similar system considered in the NJBP BRA/QRA work carried for Mustang-HDP (Reference 1).
Note 6 3x Operating and 1x standby is assumed for each skid based on Reference 2.
Note 7 It is assumed that the prover is used 20% of the time.
Note 8 The Process conditions are consistent with a previous project carried for these pipelines (Reference 3).

Justification:
Hazard sources have been defined based on the YDH PFDs and Reference 2.

References:
1. Risktec (2016) Stage 3 Building Risk Assessment Report – North Jeddah Bulk Plant Expansion Project, Report
no. MHDP-07-R-01
2. Mustang-HDP (2016) Yanbu Distribution Hub Process Equipment List Issued for 60% FEL 3, Report No. PR-
E00103, Rev A
3. Risktec Solutions DMCC, Yanbu to Jeddah Product Pipelines Quantitative Risk Assessment (QRA) Report, Doc.
No. JZA-02-R-03, Issue 4.0, 14th October 2015.

Risktec Solutions DMCC Page A.9 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

ASSUMPTION SHEET

Project Title: Stage 1 & 2 BRA for Yanbu Distribution Hub

Assumption No.: A04 Revision: 2.0 Date: 26th June 2016

Subject: Congested Area Parameters

Assumption:
Congested areas and their associated parameters were identified based on desktop review of the plot plans.
The locations of the congested areas are shown in Attachment 1.
The congested area parameters are tabulated in Attachment 2. The parameters used in the assessment are
modified in line with the Saudi Aramco BRA Master Plan (Reference 1) in order to ensure unrealistic
overpressure are not predicted for the CAM areas where the length is significant greater than the width.
The following assumptions were applied for the congested areas associated with the piperacks:
1. As per Reference 1, the length of the piperack was limited to the 3 times of the piperack width or 50m
maximum. The lengths of long piperacks were therefore limited to 50m maximum considering that the
width of the piperacks is low. This is considered as worst case approach, i.e. higher congested area
volume. The effective length calculations were therefore not required for piperacks.
2. The CAM height for piperacks was half the height of the congested area identified (Reference 1).
3. Where no specific grids are evident, the number of grids in “L” direction was calculated from a
“L/10” ratio, i.e. one grid in “L” direction was assumed for every 10m length.

Justification:
Considered to be appropriate based on a review of Reference 1, which is also consistent with previous work
carried for a Saudi Aramco site.

References:
1. BRA Masterplan, Report No. 2517956-R-07, Issue 1

Risktec Solutions DMCC Page A.10 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

ASSUMPTION SHEET

Project Title: Stage 1 & 2 BRA for Yanbu Distribution Hub

Assumption No.: A05 Revision: 1.0 Date: 12th June 2016

Subject: Fluid Composition

Assumption:
Project specific fluid compositions have not been defined. As such the generic fluid compositions defined
in the FRED software was utilised (Reference 1). The compositions are as follows:
Diesel (Gas Oil)

Component Mol Fraction


n-Eicosane 0.4000
n-Tetradecane 0.4000
n-Decane 0.2000

Gasoline (typical)

Component Mol Fraction


1,3-Dimethyl-4-ethylbenzene 0.0239
1-2-4-Trimethylbenzene 0.0795
m-Xylene 0.1269
Toluene 0.1925
2-methyl heptane (iso-octane) 0.0515
2-Methyl pentane (iso-hexane) 0.2870
iso-Pentane 0.1654
n-Butane 0.0706
Propane 0.0027

Kerosene

Component Mol Fraction


n-Hexadecane 0.0318
n-Pentadecane 0.0839
n-Tetradecane 0.1619
n-Dodecane 0.2315
n-Undecane 0.2837
n-Decane 0.1453
n-Nonane 0.0437
n-Octane 0.0182

Risktec Solutions DMCC Page A.11 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Justification:
The data is consistent with previous work carried for Mustang-HDP/Saudi Aramco.

References:
1. Shell Global Solutions, Fire, Release, Explosion, Dispersion (FRED) Hazard Consequence Modelling
Package, Version 6.0.

Risktec Solutions DMCC Page A.12 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Attachment 1: Congested Area Locations

CA-02 CA-03 CA-04 CA-05

CA-06 CA-07

CA-20A to
CA-19A to CA-19J CA-20K
CA-08

CA-12A to
CA-01 CA12Z

CA-12AA/AB/AC

CA-18A to
CA18F
CA-10

CA-09

CA-16A to CA-16G
CA-17A to CA-17G
CA-14A to CA-14G CA-15A to CA-15G
CA-13A to CA-13I

CA-21 (removed)

CA-23
CA-11

CA-22

Risktec Solutions DMCC Page A.13 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Attachment 2: Congested Area Parameters

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 49 4 0.10 38 43 L 43 4 0.11
CA-01 DPK Filtration Skid DPK Filtration Skid W 19 2 0.10 2 Yes Yes - - W 19 2 0.11
H 5 2 0.10 - - H 5 2 0.10
L 37 4 0.10 24 30 L 30 3 0.21
CA-02 PS-003 PS-003 W 12 2 0.10 2 Yes Yes - - W 12 2 0.13
H 5 2 0.10 - - H 5 2 0.10
L 37 4 0.10 24 30 L 30 3 0.32
CA-03 PS-009 PS-009 W 12 2 0.10 2 Yes Yes - - W 12 2 0.10
H 5 2 0.10 - - H 5 2 0.10
L 48 4 0.10 20 31 L 31 3 0.19
CA-04 PS-001 PS-001 W 10 2 0.10 2 Yes Yes - - W 10 2 0.15
H 5 1 0.10 - - H 5 1 0.20
L 46 4 0.10 20 30 L 30 3 0.19
CA-05 PS-008 PS-008 W 10 2 0.10 2 Yes Yes - - W 10 2 0.15
H 5 1 0.10 - - H 5 1 0.10
L 64 4 0.10 52 58 L 58 4 0.12
CA-06 PS-010 PS-010 W 26 2 0.10 2 Yes Yes - - W 26 2 0.10
H 5 2 0.10 - - H 5 2 0.10
L 64 4 0.10 52 58 L 58 4 0.32
CA-07 PS-004 PS-004 W 26 2 0.10 2 Yes Yes - - W 26 2 0.10
H 5 2 0.10 - - H 5 2 0.10
L 63 4 0.10 50 56 L 56 4 0.32
CA-08 PS-002 PS-002 W 25 2 0.10 2 Yes Yes - - W 25 2 0.10
H 5 2 0.10 - - H 5 2 0.10
L 27 10 0.10 26 26 L 26 10 0.10
Shaded Parking
CA-09 Shaded Parking Area (External) W 13 3 0.10 2 Yes Yes - - W 13 3 0.10
Area (External)
H 3 2 0.10 - - H 3 2 0.10
L 45 15 0.10 34 39 L 39 13 0.12
Assembly Point &
Assembly Point & Shaded
CA-10 Shaded Parking W 17 3 0.10 2 Yes Yes - - W 17 3 0.10
Parking Area
Area
H 3 2 0.10 - - H 3 2 0.10
L 72 4 0.10 42 55 L 55 3 0.10
Custody Meter &
Custody Meter & Receiving
CA-11 Receiving W 21 3 0.10 2 Yes Yes - - W 21 3 0.10
Manifold
Manifold
H 5 2 0.10 - - H 5 2 0.10

Risktec Solutions DMCC Page A.14 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 28 5 0.10 - - L 28 - -
Pipe Rack (along PS-
CA-12A Pipe Rack W 24 5 0.10 2 No No - - W 24 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12AA Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12AB Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12AC Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12B Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12C Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12D Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12E Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12F Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12G Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12H Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12I Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -

Risktec Solutions DMCC Page A.15 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12J Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12K Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12L Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12M Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12N Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12O Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12P Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12Q Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12R Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12S Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12T Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12U Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -

Risktec Solutions DMCC Page A.16 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12V Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12W Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12X Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12Y Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (along PS-
CA-12Z Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
001/002/003/004/008/009/010)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13A Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13B Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13C Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13D Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13E Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13F Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13G Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -

Risktec Solutions DMCC Page A.17 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13H Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (east of pipe
CA-13I Pipe Rack W 25 5 0.10 2 No No - - W 25 - -
culvert/RC corridor)
H 2 2 0.10 - - H 2 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14A Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14B Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14C Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14D Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14E Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14F Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Rack (south of DO tanks
CA-14G Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0301/0302/0303)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15A Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15B Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15C Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -

Risktec Solutions DMCC Page A.18 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15D Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15E Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15F Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of DPK tanks
CA-15G Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0401/0402/0403/0404)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16A Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16B Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16C Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16D Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16E Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16F Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (south of PG91/PG95
CA-16G Pipe Rack tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0101/0102/0201/0202)
H 1 1 0.10 - - H 1 - -
L 28 3 0.10 - - L 28 - -
Pipe rack (north of PG91 tanks
CA-17A Pipe Rack W 9 3 0.10 2 No No - - W 9 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -

Risktec Solutions DMCC Page A.19 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-17B Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-17C Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-17D Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-17E Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-17F Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-17G Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-0204/0205)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-18A Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-XXX1/XXX2)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-18B Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-XXX1/XXX2)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-18C Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-XXX1/XXX2)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-18D Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-XXX1/XXX2)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-18E Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-XXX1/XXX2)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (north of PG91 tanks
CA-18F Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
X40-D-XXX1/XXX2)
H 1 1 0.10 - - H 1 - -

Risktec Solutions DMCC Page A.20 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19A Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19B Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19C Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19D Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19E Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19F Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19G Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19H Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19I Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of DO/DPK
CA-19J Pipe Rack W 8 3 0.10 2 No No - - W 8 - -
tanks X-40D-0304/0305/0405)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20A Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20B Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -

Risktec Solutions DMCC Page A.21 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Unit
Final
Use Length, 2 Effective Final Adjusted
Actual Dimensions Number Blockage Complexity Final Dimensions After Adjusted
CA Number CA Description Location With Roof? Effective x Region Length, CAM Blockage
(m) of Grids Ratio Factor CAM 2 Guidance (m) CAM Grids
Length? Width, Lo Le (m) Ratio in FRED
in FRED
(m)
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20C Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20D Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20E Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20F Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20G Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20H Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe rack (west of
CA-20I Pipe Rack PG91/PG95/DO tanks X40-D- W 8 3 0.10 2 No No - - W 8 - -
0501/0104/XXX3)
H 1 1 0.10 - - H 1 - -
L 50 5 0.10 - - L 50 - -
Pipe Culvert (RC
CA-20J Pipe Culvert (RC Corridor) W 8 3 0.10 2 No No - - W 8 - -
Corridor)
H 1 1 0.10 - - H 1 - -
L 130 5 0.15 72 97 L 97 4 0.20
Pipe Culvert (RC
CA-20K Pipe Culvert (RC Corridor) W 36 5 0.15 2 Yes Yes - - W 36 5 0.19
Corridor)
H 2 1 0.10 - - H 2 1 0.10
L 65 5 0.15 - - L 65 - -
Pipe Culvert (RC
CA-22 Pipe Culvert (RC Corridor) W 37 5 0.15 2 Yes No - - W 37 - -
Corridor)
H 2 2 0.10 - - H 2 - -
L 40 3 0.15 24 31 L 31 3 0.16
Pipe Culvert (RC
CA-23 Pipe Culvert (RC Corridor) W 12 2 0.15 2 Yes Yes - - W 12 2 0.18
Corridor)
H 5 2 0.10 - - H 2 2 0.10
Note: CA-21 is not used due to the congested area being removed during the design stages.

Risktec Solutions DMCC Page A.22 of A.22


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

APPENDIX B SEPARATION DISTANCES

Risktec Solutions DMCC Page B.1 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table B.1: Separation Distances between Hazard Sources & Buildings (Part 1 of 3)

Separation Distances between Hazard Sources & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Hazard Sources B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
X40-D-0015A(G) 963 554 539 668 1046 969 930 903 967 916
X40-D-0015B(G) 68 926 868 355 1819 1730 1600 1577 1716 1576
X40-G-0020(G) 641 273 215 298 1180 1089 949 926 1074 924
X40-G-0021(G) 150 786 728 215 1678 1588 1459 1436 1575 1435
X40-G-0018(D) 1068 156 214 727 775 685 525 504 667 500
X40-G-0018(K) 1068 156 214 727 775 685 525 504 667 500
X40-G-0019(D) 202 726 668 155 1619 1529 1399 1376 1516 1375
X40-G-XXX1(G) 562 352 294 219 1256 1166 1027 1005 1151 1003
X40-G-XXX2(K) 1029 117 175 688 811 721 563 542 702 538
X40-G-XXX2(D) 1029 117 175 688 811 721 563 542 702 538
X40-G-XXX3(G) 395 523 465 48 1420 1330 1197 1174 1316 1172
G-5101(K) 1193 281 339 852 662 574 403 384 553 377
D-0024(K) 1186 274 332 845 668 580 410 390 559 384
D-0025(K) 1180 268 326 839 674 585 416 396 564 390
X40-U-0014A(G) 1077 521 522 762 899 823 795 768 822 783
X40-U-0014B(D) 1065 522 521 751 914 837 808 781 836 796
X40-U-0014C(K) 1052 523 520 740 928 852 821 794 850 808
X40-U-0014D(G) 1079 524 525 764 900 824 796 770 823 785
X40-U-0014D(D) 1066 525 524 753 914 838 809 783 837 797
X40-U-0014D(K) 1054 526 523 742 929 852 822 796 851 810
L1-30(G) 1085 508 511 767 879 802 773 746 801 761
L2-42(G) 981 274 281 639 857 770 681 655 761 663
L3-20(G) 599 325 267 252 1217 1127 994 971 1113 970
L4-20(G) 152 814 756 245 1699 1610 1484 1460 1597 1460
L5-30(G) 1083 508 511 765 881 804 774 748 803 763
L6-42(G) 908 51 69 563 914 823 682 659 807 658
L7-30(D) 1091 507 511 771 872 795 766 740 794 754
L8-48(D) 1369 565 603 1027 515 440 445 420 441 441
L9-24(D) 1075 164 221 732 758 668 515 493 650 490
L9-24(K) 1071 160 217 728 761 671 519 497 653 494
L10-24(D) 205 741 683 173 1627 1538 1411 1388 1525 1387
L10-24(K) 207 739 681 171 1625 1536 1409 1386 1523 1385
L11-30(K) 1097 505 510 777 862 786 757 731 785 746

Risktec Solutions DMCC Page B.2 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Separation Distances between Hazard Sources & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Hazard Sources B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
L12-48(K) 1100 506 511 779 859 783 755 729 782 743
L13-24(K) 1344 553 589 1003 549 474 475 450 474 470
L14-20(K) 1344 553 589 1003 549 474 475 450 474 470
X40-G-0019(K) 202 726 668 155 1619 1529 1399 1376 1516 1375
Scraper-YNJ-1(G) 99 959 902 411 1872 1782 1638 1616 1766 1612
Scraper-YNJ-2(D) 113 961 904 416 1875 1785 1639 1618 1769 1614
Scraper-YNJ-2(K) 113 961 904 416 1875 1785 1639 1618 1769 1614
X40-G-0020(G) 632 282 224 289 1188 1098 958 935 1083 933
X40-G-0021(G) 140 798 740 227 1690 1600 1471 1448 1587 1447
X40-G-0018(D) 1074 162 220 733 770 680 519 498 661 494
X40-G-0018(K) 1074 162 220 733 770 680 519 498 661 494
X40-G-0019(D) 214 713 655 142 1606 1517 1386 1363 1503 1362
X40-G-XXX1(G) 569 345 287 226 1249 1159 1020 998 1144 996
X40-G-XXX2(K) 1022 110 168 681 817 727 570 549 709 545
X40-G-XXX2(D) 1022 110 168 681 817 727 570 549 709 545
X40-G-XXX3(G) 408 510 452 61 1408 1318 1184 1161 1304 1159
X40-G-0020(G) 623 291 233 280 1197 1107 967 944 1091 942
X40-G-0021(G) 130 811 753 240 1703 1613 1484 1461 1600 1460
X40-G-0018(D) 1081 169 227 740 763 674 512 492 655 487
X40-G-0018(K) 1081 169 227 740 763 674 512 492 655 487
X40-G-0019(D) 224 701 643 130 1595 1505 1374 1351 1491 1350
X40-G-XXX1(G) 578 336 278 235 1240 1150 1011 989 1135 987
X40-G-XXX2(K) 1016 104 162 675 823 733 576 555 715 551
X40-G-XXX2(D) 1016 104 162 675 823 733 576 555 715 551
X40-G-XXX3(G) 420 498 440 73 1396 1306 1172 1149 1292 1148
X40-G-0019(K) 214 713 655 142 1606 1517 1386 1363 1503 1362
X40-G-0019(K) 224 701 643 130 1595 1505 1374 1351 1491 1350
YNJ-1(G) 104 970 913 421 1883 1792 1648 1627 1777 1623
YNJ-2(D) 115 971 915 425 1885 1795 1650 1628 1779 1624
YNJ-2(K) 115 971 915 425 1885 1795 1650 1628 1779 1624
SAM-30(K) 1100 538 540 785 887 812 790 764 812 779
YAS-30(G) 1125 539 545 808 858 784 765 739 784 755
YAS-30(D) 1112 539 543 796 874 799 779 753 799 768
SAM-30(D) 1107 539 542 792 880 805 784 758 805 773
YR-22(D) 1104 540 543 790 884 809 788 762 809 777

Risktec Solutions DMCC Page B.3 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Separation Distances between Hazard Sources & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Hazard Sources B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
YR-22(K) 1097 538 540 783 890 815 793 766 815 782
SAM-30(G) 1122 539 544 805 862 788 768 742 788 758
YR-24(G) 1117 539 543 801 867 792 772 746 793 762

Risktec Solutions DMCC Page B.4 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table B.2: Separation Distances between Hazard Sources & Buildings (Part 2 of 3)

Separation Distances between Hazard Sources & Buildings (m)

Hazard Sources B-18 Sanitary B-19 Utility Water B-20 Custody


B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
B-11 OME Building B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-D-0015A(G) 930 917 906 979 535 776 737 1098 1103 197
X40-D-0015B(G) 1650 1557 1651 1669 882 878 551 1783 1782 1100
X40-G-0020(G) 1004 904 1010 1018 229 311 825 1131 1130 607
X40-G-0021(G) 1509 1416 1510 1528 742 750 543 1642 1641 970
X40-G-0018(D) 591 478 605 596 200 338 1184 706 704 537
X40-G-0018(K) 591 478 605 596 200 338 1184 706 704 537
X40-G-0019(D) 1450 1356 1451 1468 682 694 558 1582 1582 919
X40-G-XXX1(G) 1082 983 1086 1097 308 365 767 1210 1209 651
X40-G-XXX2(K) 628 516 641 634 161 312 1150 744 742 529
X40-G-XXX2(D) 628 516 641 634 161 312 1150 744 742 529
X40-G-XXX3(G) 1249 1154 1252 1266 479 510 651 1380 1379 760
G-5101(K) 475 354 494 475 325 435 1296 582 580 576
D-0024(K) 481 361 500 482 318 430 1290 589 587 573
D-0025(K) 487 367 505 487 312 425 1284 595 593 571
X40-U-0014A(G) 788 786 762 841 514 766 886 958 964 48
X40-U-0014B(D) 802 799 776 854 513 765 871 972 977 63
X40-U-0014C(K) 816 811 790 868 513 764 856 985 991 78
X40-U-0014D(G) 789 788 763 842 517 769 886 959 965 48
X40-U-0014D(D) 803 800 777 856 516 768 871 973 979 63
X40-U-0014D(K) 817 813 791 869 516 767 856 987 992 78
L1-30(G) 767 764 741 819 502 755 905 936 942 34
L2-42(G) 706 656 696 741 271 523 944 862 864 252
L3-20(G) 1045 951 1048 1063 280 373 762 1177 1176 601
L4-20(G) 1532 1442 1532 1552 770 787 505 1667 1667 976
L5-30(G) 768 766 743 821 502 754 903 938 944 36
L6-42(G) 737 639 743 751 54 300 1015 865 864 476
L7-30(D) 760 758 734 812 502 755 912 930 935 29
L8-48(D) 416 454 384 477 588 807 1264 589 596 338
L9-24(D) 576 470 587 585 206 367 1172 697 696 504
L9-24(K) 579 474 591 589 202 365 1168 701 700 502
L10-24(D) 1460 1369 1460 1479 697 718 525 1595 1594 914
L10-24(K) 1458 1367 1458 1477 695 716 525 1593 1592 913
L11-30(K) 751 749 725 803 501 754 921 921 926 24
L12-48(K) 748 747 722 801 502 754 924 918 924 22
L13-24(K) 449 483 417 509 575 799 1232 621 628 304

Risktec Solutions DMCC Page B.5 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Separation Distances between Hazard Sources & Buildings (m)

Hazard Sources B-18 Sanitary B-19 Utility Water B-20 Custody


B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
B-11 OME Building B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
L14-20(K) 449 483 417 509 575 799 1232 621 628 304
X40-G-0019(K) 1450 1356 1451 1468 682 694 558 1582 1582 919
Scraper-YNJ-1(G) 1696 1591 1702 1708 917 868 710 1819 1817 1200
Scraper-YNJ-2(D) 1699 1592 1705 1710 919 866 725 1820 1818 1208
Scraper-YNJ-2(K) 1699 1592 1705 1710 919 866 725 1820 1818 1208
X40-G-0020(G) 1013 913 1018 1027 238 317 819 1140 1139 612
X40-G-0021(G) 1521 1428 1522 1540 754 761 541 1654 1653 980
X40-G-0018(D) 585 472 600 590 206 342 1190 700 698 538
X40-G-0018(K) 585 472 600 590 206 342 1190 700 698 538
X40-G-0019(D) 1437 1343 1438 1455 669 682 563 1569 1569 909
X40-G-XXX1(G) 1075 976 1080 1090 301 360 772 1203 1202 646
X40-G-XXX2(K) 634 523 647 641 154 308 1143 751 749 528
X40-G-XXX2(D) 634 523 647 641 154 308 1143 751 749 528
X40-G-XXX3(G) 1236 1141 1239 1253 466 498 658 1367 1366 751
X40-G-0020(G) 1022 922 1027 1036 247 322 812 1149 1148 616
X40-G-0021(G) 1534 1441 1535 1553 767 774 538 1667 1666 991
X40-G-0018(D) 579 465 593 584 213 347 1196 693 691 540
X40-G-0018(K) 579 465 593 584 213 347 1196 693 691 540
X40-G-0019(D) 1425 1331 1427 1443 657 670 568 1557 1557 899
X40-G-XXX1(G) 1066 967 1071 1081 292 354 779 1194 1193 641
X40-G-XXX2(K) 640 529 653 647 148 304 1138 757 755 528
X40-G-XXX2(D) 640 529 653 647 148 304 1138 757 755 528
X40-G-XXX3(G) 1224 1129 1227 1241 454 488 665 1355 1354 742
X40-G-0019(K) 1437 1343 1438 1455 669 682 563 1569 1569 909
X40-G-0019(K) 1425 1331 1427 1443 657 670 568 1557 1557 899
YNJ-1(G) 1707 1602 1713 1719 928 879 711 1830 1828 1209
YNJ-2(D) 1709 1603 1715 1720 930 877 724 1831 1829 1216
YNJ-2(K) 1709 1603 1715 1720 930 877 724 1831 1829 1216
SAM-30(K) 781 783 753 835 532 784 902 951 957 35
YAS-30(G) 754 760 725 808 536 788 932 925 931 14
YAS-30(D) 768 773 741 823 534 787 916 939 945 23

SAM-30(D) 774 778 746 828 534 786 910 945 950 28

YR-22(D) 778 781 750 832 534 787 906 949 955 32

YR-22(K) 783 786 756 837 532 784 899 954 960 38

SAM-30(G) 757 763 729 812 535 787 928 928 934 15

YR-24(G) 762 767 734 816 534 787 923 933 939 18

Risktec Solutions DMCC Page B.6 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table B.3: Separation Distances between Hazard Sources & Buildings (Part 3 of 3)

Separation Distances between Hazard Sources & Buildings (m)


Hazard Sources
B-21 Oily Water Metering Shelter-Marafiq B-22 Operation Shelter-2

X40-D-0015A(G) 1211 960


X40-D-0015B(G) 318 33
X40-G-0020(G) 823 660
X40-G-0021(G) 404 154
X40-G-0018(D) 1231 1088
X40-G-0018(K) 1231 1088
X40-G-0019(D) 443 211
X40-G-XXX1(G) 750 581
X40-G-XXX2(K) 1193 1049
X40-G-XXX2(D) 1193 1049
X40-G-XXX3(G) 603 411
G-5101(K) 1353 1213
D-0024(K) 1346 1206
D-0025(K) 1340 1200
X40-U-0014A(G) 1317 1078
X40-U-0014B(D) 1306 1065
X40-U-0014C(K) 1294 1053
X40-U-0014D(G) 1319 1080
X40-U-0014D(D) 1308 1067
X40-U-0014D(K) 1296 1054
L1-30(G) 1323 1087
L2-42(G) 1194 990
L3-20(G) 795 615
L4-20(G) 415 145
L5-30(G) 1322 1085
L6-42(G) 1086 926
L7-30(D) 1328 1092
L8-48(D) 1582 1378
L9-24(D) 1244 1094
L9-24(K) 1241 1090
L10-24(D) 457 208
L10-24(K) 458 210
L11-30(K) 1334 1099
L12-48(K) 1336 1102
L13-24(K) 1559 1352

Risktec Solutions DMCC Page B.7 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Separation Distances between Hazard Sources & Buildings (m)


Hazard Sources
B-21 Oily Water Metering Shelter-Marafiq B-22 Operation Shelter-2

L14-20(K) 1559 1352


X40-G-0019(K) 443 211
Scraper-YNJ-1(G) 167 127
Scraper-YNJ-2(D) 155 142
Scraper-YNJ-2(K) 155 142
X40-G-0020(G) 815 651
X40-G-0021(G) 397 143
X40-G-0018(D) 1237 1094
X40-G-0018(K) 1237 1094
X40-G-0019(D) 453 224
X40-G-XXX1(G) 757 588
X40-G-XXX2(K) 1186 1042
X40-G-XXX2(D) 1186 1042
X40-G-XXX3(G) 614 424
X40-G-0020(G) 806 642
X40-G-0021(G) 389 131
X40-G-0018(D) 1244 1101
X40-G-0018(K) 1244 1101
X40-G-0019(D) 460 236
X40-G-XXX1(G) 765 597
X40-G-XXX2(K) 1181 1036
X40-G-XXX2(D) 1181 1036
X40-G-XXX3(G) 624 436
X40-G-0019(K) 453 224
X40-G-0019(K) 460 236
YNJ-1(G) 161 128
YNJ-2(D) 151 141
YNJ-2(K) 151 141
SAM-30(K) 1340 1100
YAS-30(G) 1364 1126
YAS-30(D) 1352 1113
SAM-30(D) 1347 1108
YR-22(D) 1345 1105
YR-22(K) 1338 1098
SAM-30(G) 1361 1123
YR-24(G) 1357 1118

Risktec Solutions DMCC Page B.8 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table B.4: Separation Distances between Congested Areas & Buildings (Part 1 of 3)

Distances between Congested Areas & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Congested Areas Description Location Receiving Utility Power B-03 RIB- B-04 RIB- B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Substation Substation XXX1 Remote XXX2 Remote Guard House Guard House Support Support
Building Building
Transformer Transformer I/O Building I/O Building (A) (B) Building (A) Building (B)
Yard Yard
DPK
CA-01 Filtration DPK Filtration Skid 1185 273 331 844 667 579 410 390 558 384
Skid
CA-02 PS-003 PS-003 1075 163 221 734 768 678 518 497 659 492
CA-03 PS-009 PS-009 1024 112 170 683 815 725 568 547 706 542
CA-04 PS-001 PS-001 638 276 218 295 1182 1092 951 929 1077 927
CA-05 PS-008 PS-008 577 337 279 234 1241 1151 1012 990 1136 988
CA-06 PS-010 PS-010 418 500 442 71 1398 1308 1174 1151 1294 1149
CA-07 PS-004 PS-004 224 703 645 132 1596 1506 1376 1353 1493 1352
CA-08 PS-002 PS-002 150 787 729 216 1679 1589 1460 1437 1576 1436
Shaded
CA-09 Parking Area Shaded Parking Area (External) 1762 861 916 1416 73 54 211 222 53 238
(External)
Assembly
Point & Assembly Point & Shaded
CA-10 1695 771 832 1349 246 192 89 116 166 113
Shaded Parking Area
Parking Area
Custody
Meter & Custody Meter & Receiving
CA-11 1053 525 522 741 930 853 822 796 852 810
Receiving Manifold
Manifold
Pipe Rack (along PS-
CA-12A Pipe Rack 1462 550 608 1120 416 335 138 124 310 110
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12B Pipe Rack 1422 509 567 1079 447 363 175 158 339 148
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12C Pipe Rack 1369 457 514 1026 491 404 225 206 382 198
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12D Pipe Rack 1317 405 462 974 535 447 275 255 425 249
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12E Pipe Rack 1264 352 410 921 581 492 327 306 472 301
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12F Pipe Rack 1213 302 359 870 627 537 377 355 518 352
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12G Pipe Rack 1161 250 307 817 675 585 429 407 566 404
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12H Pipe Rack 1108 198 254 764 724 634 482 459 616 457
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12I Pipe Rack 1055 147 203 711 773 683 534 512 665 509
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12J Pipe Rack 1004 99 152 660 822 732 586 563 715 561
001/002/003/004/008/009/010)

Risktec Solutions DMCC Page B.9 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Congested Areas Description Location Receiving Utility Power B-03 RIB- B-04 RIB- B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Substation Substation XXX1 Remote XXX2 Remote Guard House Guard House Support Support
Building Building
Transformer Transformer I/O Building I/O Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe Rack (along PS-
CA-12K Pipe Rack 951 59 103 607 872 782 638 616 765 614
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12L Pipe Rack 898 52 60 553 924 833 692 669 817 668
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12M Pipe Rack 845 87 48 500 975 884 745 722 869 721
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12N Pipe Rack 794 134 82 448 1024 934 797 774 919 773
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12O Pipe Rack 743 183 128 397 1075 984 848 826 970 825
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12P Pipe Rack 689 236 179 343 1127 1037 902 879 1022 878
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Q Pipe Rack 637 288 231 291 1179 1088 955 932 1074 931
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12R Pipe Rack 584 341 284 237 1231 1141 1009 986 1127 985
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12S Pipe Rack 534 393 335 187 1282 1192 1061 1038 1178 1037
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12T Pipe Rack 483 445 387 137 1333 1243 1113 1090 1229 1089
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12U Pipe Rack 434 495 438 91 1383 1293 1164 1141 1280 1140
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12V Pipe Rack 385 547 489 52 1434 1344 1216 1192 1331 1192
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12W Pipe Rack 336 599 541 53 1485 1395 1268 1244 1382 1244
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12X Pipe Rack 289 650 592 90 1535 1446 1319 1295 1433 1295
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Y Pipe Rack 244 702 644 137 1586 1497 1371 1347 1484 1347
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Z Pipe Rack 200 755 697 188 1639 1549 1423 1400 1536 1400
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AA Pipe Rack 161 808 750 240 1692 1603 1477 1454 1590 1454
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AB Pipe Rack 132 861 803 292 1744 1655 1530 1507 1643 1507
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AC Pipe Rack 1482 570 628 1141 419 341 136 128 315 109
001/002/003/004/008/009/010)
Pipe Rack (east of pipe
CA-13A Pipe Rack 1091 506 510 771 870 794 765 738 793 753
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13B Pipe Rack 1064 454 459 738 861 781 739 713 778 726
culvert/RC corridor)

Risktec Solutions DMCC Page B.10 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Congested Areas Description Location Receiving Utility Power B-03 RIB- B-04 RIB- B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Substation Substation XXX1 Remote XXX2 Remote Guard House Guard House Support Support
Building Building
Transformer Transformer I/O Building I/O Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe Rack (east of pipe
CA-13C Pipe Rack 1039 402 407 708 854 772 717 690 767 702
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13D Pipe Rack 1016 350 356 680 851 766 697 671 760 681
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13E Pipe Rack 995 298 305 655 850 764 682 656 756 664
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13F Pipe Rack 977 245 254 633 853 765 669 643 755 650
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13G Pipe Rack 961 193 205 614 859 770 661 636 758 640
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13H Pipe Rack 947 142 157 600 868 779 657 632 765 634
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13I Pipe Rack 937 90 113 590 881 790 656 633 775 633
culvert/RC corridor)
Pipe Rack (south of DO tanks
CA-14A Pipe Rack 1284 375 431 939 549 460 306 283 441 282
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14B Pipe Rack 1292 391 445 945 529 439 306 282 422 285
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14C Pipe Rack 1302 413 465 955 514 424 316 290 410 299
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14D Pipe Rack 1314 441 489 967 504 415 334 308 404 320
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14E Pipe Rack 1329 474 520 983 499 413 360 334 406 349
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14F Pipe Rack 1346 511 553 1001 501 419 392 366 415 384
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14G Pipe Rack 1365 551 590 1022 507 430 427 402 429 422
X40-D-0301/0302/0303)
Pipe rack (north of DPK tanks
CA-15A Pipe Rack 1246 338 394 901 584 494 345 322 476 321
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15B Pipe Rack 1254 356 409 907 565 475 345 321 459 324
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15C Pipe Rack 1264 381 431 917 551 461 355 329 448 337
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15D Pipe Rack 1277 411 458 930 542 454 371 345 443 356
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15E Pipe Rack 1292 447 490 946 538 452 395 369 445 383
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15F Pipe Rack 1310 486 526 966 540 458 425 399 453 416
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15G Pipe Rack 1329 528 565 987 547 469 458 433 468 452
X40-D-0401/0402/0403/0404)

Risktec Solutions DMCC Page B.11 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Congested Areas Description Location Receiving Utility Power B-03 RIB- B-04 RIB- B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Substation Substation XXX1 Remote XXX2 Remote Guard House Guard House Support Support
Building Building
Transformer Transformer I/O Building I/O Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe rack (south of PG91/PG95
CA-16A Pipe Rack tanks X40-D- 551 394 338 206 1268 1178 1053 1030 1165 1030
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16B Pipe Rack tanks X40-D- 569 409 355 234 1259 1171 1053 1029 1159 1031
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16C Pipe Rack tanks X40-D- 592 431 380 269 1253 1165 1056 1032 1154 1035
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16D Pipe Rack tanks X40-D- 618 458 410 310 1249 1162 1062 1037 1152 1041
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16E Pipe Rack tanks X40-D- 649 490 445 355 1247 1161 1070 1045 1153 1050
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16F Pipe Rack tanks X40-D- 682 526 484 403 1248 1163 1081 1055 1156 1063
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16G Pipe Rack tanks X40-D- 718 564 525 452 1251 1167 1095 1069 1161 1077
0101/0102/0201/0202)
Pipe rack (north of PG91 tanks
CA-17A Pipe Rack 683 583 542 427 1288 1204 1129 1103 1198 1110
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17B Pipe Rack 653 555 511 386 1287 1202 1119 1094 1195 1100
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17C Pipe Rack 618 521 474 336 1286 1200 1109 1083 1192 1089
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17D Pipe Rack 585 491 441 288 1288 1201 1100 1075 1191 1080
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17E Pipe Rack 557 466 414 244 1292 1204 1095 1070 1193 1073
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17F Pipe Rack 533 446 391 204 1298 1209 1092 1068 1197 1070
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17G Pipe Rack 514 432 375 172 1306 1217 1092 1069 1204 1069
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-18A Pipe Rack 518 734 683 368 1501 1416 1330 1304 1408 1310
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18B Pipe Rack 472 708 656 314 1500 1414 1321 1295 1406 1300
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18C Pipe Rack 428 686 632 260 1501 1414 1314 1289 1405 1292
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18D Pipe Rack 389 668 613 210 1505 1417 1309 1284 1406 1287
X40-D-XXX1/XXX2)

Risktec Solutions DMCC Page B.12 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Congested Areas Description Location Receiving Utility Power B-03 RIB- B-04 RIB- B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Substation Substation XXX1 Remote XXX2 Remote Guard House Guard House Support Support
Building Building
Transformer Transformer I/O Building I/O Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe rack (north of PG91 tanks
CA-18E Pipe Rack 352 654 597 159 1510 1421 1306 1282 1410 1284
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18F Pipe Rack 321 644 586 113 1517 1428 1306 1282 1415 1283
X40-D-XXX1/XXX2)
Pipe rack (west of DO/DPK
CA-19A Pipe Rack 1352 446 504 1015 560 478 279 267 453 252
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19B Pipe Rack 1301 395 453 964 599 515 322 308 491 294
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19C Pipe Rack 1249 344 401 912 640 554 367 351 531 340
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19D Pipe Rack 1197 292 350 861 683 596 414 397 574 387
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19E Pipe Rack 1145 241 298 809 728 640 463 444 618 436
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19F Pipe Rack 1093 191 247 757 773 684 512 493 664 485
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19G Pipe Rack 1041 141 197 705 819 730 561 542 710 535
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19H Pipe Rack 989 94 147 653 865 776 611 591 756 585
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19I Pipe Rack 937 56 99 601 912 823 661 641 804 635
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19J Pipe Rack 885 55 60 549 960 870 712 691 852 686
tanks X-40D-0304/0305/0405)
Pipe rack (west of
CA-20A Pipe Rack PG91/PG95/DO tanks X40-D- 756 161 108 421 1081 991 838 817 973 813
0501/0104/XXX3)
Pipe rack (west of
CA-20B Pipe Rack PG91/PG95/DO tanks X40-D- 705 211 156 370 1130 1040 889 868 1023 864
0501/0104/XXX3)
Pipe rack (west of
CA-20C Pipe Rack PG91/PG95/DO tanks X40-D- 652 263 206 317 1180 1090 941 920 1073 916
0501/0104/XXX3)
Pipe rack (west of
CA-20D Pipe Rack PG91/PG95/DO tanks X40-D- 599 315 258 265 1231 1140 993 972 1124 968
0501/0104/XXX3)
Pipe rack (west of
CA-20E Pipe Rack PG91/PG95/DO tanks X40-D- 547 366 309 214 1280 1190 1045 1023 1174 1020
0501/0104/XXX3)
Pipe rack (west of
CA-20F Pipe Rack PG91/PG95/DO tanks X40-D- 493 420 363 163 1332 1242 1098 1076 1226 1073
0501/0104/XXX3)

Risktec Solutions DMCC Page B.13 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-01 SS-XXX1 B-02 SS-XXX2
Congested Areas Description Location Receiving Utility Power B-03 RIB- B-04 RIB- B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Substation Substation XXX1 Remote XXX2 Remote Guard House Guard House Support Support
Building Building
Transformer Transformer I/O Building I/O Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe rack (west of
CA-20G Pipe Rack PG91/PG95/DO tanks X40-D- 441 472 414 114 1382 1292 1150 1128 1276 1125
0501/0104/XXX3)
Pipe rack (west of
CA-20H Pipe Rack PG91/PG95/DO tanks X40-D- 388 524 467 72 1434 1343 1202 1180 1328 1177
0501/0104/XXX3)
Pipe rack (west of
CA-20I Pipe Rack PG91/PG95/DO tanks X40-D- 335 577 520 53 1485 1395 1255 1232 1380 1230
0501/0104/XXX3)
Pipe rack (west of
CA-20J Pipe Rack PG91/PG95/DO tanks X40-D- 251 661 603 102 1566 1476 1338 1316 1461 1313
0501/0104/XXX3)
Pipe rack (west of
CA-20K Pipe Rack PG91/PG95/DO tanks X40-D- 200 713 655 149 1617 1527 1390 1367 1512 1365
0501/0104/XXX3)
Pipe Culvert
CA-22 (RC Pipe Culvert (RC Corridor) 1320 863 865 1043 1005 950 993 969 959 990
Corridor)
CA-23 PS-007 Slop Pump Shelter 1002 529 520 697 986 909 872 846 907 859

Risktec Solutions DMCC Page B.14 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table B.5: Separation Distances between Congested Areas & Buildings (Part 2 of 3)

Distances between Congested Areas & Buildings (m)


B-19 Utility B-20 Custody
B-18 Sanitary
Congested Areas Description Location B-12 B-14 B-15 Water Metering
B-11 OME B-16 IDAS B-17 IDAS Metering
Operation B-13 Musalla Chemical Operation Metering Shelter
Building Shelter-001 Shelter-002 Shelter-
Building Shelter Shelter Shelter- (Vendor
Marafiq
Marafiq Package)
DPK
CA-01 Filtration DPK Filtration Skid 481 361 499 481 317 432 1288 589 587 569
Skid
CA-02 PS-003 PS-003 584 470 598 589 207 345 1190 698 697 536
CA-03 PS-009 PS-009 632 521 644 639 156 311 1145 749 747 527
CA-04 PS-001 PS-001 1007 907 1012 1021 232 313 823 1134 1133 608
CA-05 PS-008 PS-008 1067 968 1072 1082 293 354 778 1195 1194 641
CA-06 PS-010 PS-010 1226 1130 1229 1243 456 489 664 1357 1356 743
CA-07 PS-004 PS-004 1427 1333 1428 1445 659 672 564 1559 1558 899
CA-08 PS-002 PS-002 1510 1417 1511 1528 743 751 541 1643 1642 969
Shaded
CA-09 Parking Area Shaded Parking Area (External) 123 272 118 147 901 1031 1744 151 164 829
(External)
Assembly
Point & Assembly Point & Shaded
CA-10 118 134 166 95 807 932 1673 146 155 842
Shaded Parking Area
Parking Area
Custody
Meter & Custody Meter & Receiving
CA-11 818 813 792 869 515 766 856 987 993 79
Receiving Manifold
Manifold
Pipe Rack (along PS-
CA-12A Pipe Rack 228 83 263 209 593 691 1529 312 309 700
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12B Pipe Rack 258 123 289 246 764 783 500 1661 1661 670
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12C Pipe Rack 301 176 327 296 817 831 495 1714 1714 634
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12D Pipe Rack 347 228 368 346 614 701 1559 297 294 601
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12E Pipe Rack 394 281 413 398 552 655 1490 352 350 570
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12F Pipe Rack 442 332 457 447 500 608 1440 404 402 544
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12G Pipe Rack 491 384 505 499 448 563 1392 455 454 520
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12H Pipe Rack 542 437 554 552 395 518 1342 508 506 502
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12I Pipe Rack 593 490 603 604 344 476 1295 559 557 487
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12J Pipe Rack 643 542 651 655 292 436 1246 611 610 479
001/002/003/004/008/009/010)

Risktec Solutions DMCC Page B.15 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-19 Utility B-20 Custody
B-18 Sanitary
Congested Areas Description Location B-12 B-14 B-15 Water Metering
B-11 OME B-16 IDAS B-17 IDAS Metering
Operation B-13 Musalla Chemical Operation Metering Shelter
Building Shelter-001 Shelter-002 Shelter-
Building Shelter Shelter Shelter- (Vendor
Marafiq
Marafiq Package)
Pipe Rack (along PS-
CA-12K Pipe Rack 694 595 702 708 239 397 1198 664 663 476
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12L Pipe Rack 747 649 753 761 187 363 1149 717 716 479
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12M Pipe Rack 799 702 805 814 137 335 1102 769 768 489
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12N Pipe Rack 850 754 855 866 88 312 1055 821 821 502
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12O Pipe Rack 901 806 905 918 47 296 1008 875 874 521
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12P Pipe Rack 954 860 958 971 49 289 962 928 927 545
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Q Pipe Rack 1007 913 1010 1024 90 293 917 980 979 573
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12R Pipe Rack 1060 967 1063 1078 139 306 874 1032 1031 606
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12S Pipe Rack 1111 1019 1113 1130 191 327 830 1086 1085 638
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12T Pipe Rack 1163 1071 1164 1182 243 355 788 1139 1138 674
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12U Pipe Rack 1213 1122 1215 1232 297 387 747 1193 1192 711
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12V Pipe Rack 1265 1174 1266 1284 348 424 708 1245 1244 751
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12W Pipe Rack 1317 1226 1317 1336 400 464 671 1297 1296 791
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12X Pipe Rack 1367 1277 1368 1387 451 505 638 1347 1347 833
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Y Pipe Rack 1419 1329 1419 1439 503 547 607 1399 1399 876
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Z Pipe Rack 1472 1382 1471 1492 554 593 577 1451 1451 921
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AA Pipe Rack 1525 1436 1525 1546 605 638 552 1502 1502 967
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AB Pipe Rack 1578 1489 1578 1599 657 684 530 1554 1554 1015
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AC Pipe Rack 234 75 274 204 710 733 513 1607 1607 735
001/002/003/004/008/009/010)
Pipe Rack (east of pipe
CA-13A Pipe Rack 758 756 733 811 501 754 914 928 934 28
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13B Pipe Rack 739 727 717 789 450 702 917 907 912 73
culvert/RC corridor)

Risktec Solutions DMCC Page B.16 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-19 Utility B-20 Custody
B-18 Sanitary
Congested Areas Description Location B-12 B-14 B-15 Water Metering
B-11 OME B-16 IDAS B-17 IDAS Metering
Operation B-13 Musalla Chemical Operation Metering Shelter
Building Shelter-001 Shelter-002 Shelter-
Building Shelter Shelter Shelter- (Vendor
Marafiq
Marafiq Package)
Pipe Rack (east of pipe
CA-13C Pipe Rack 724 701 704 769 398 651 923 889 893 124
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13D Pipe Rack 712 678 696 753 347 599 932 873 877 175
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13E Pipe Rack 703 658 691 740 296 548 944 861 863 227
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13F Pipe Rack 698 641 690 731 244 496 959 851 853 280
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13G Pipe Rack 697 629 693 725 194 445 976 844 845 332
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13H Pipe Rack 700 620 700 723 145 394 996 841 841 384
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13I Pipe Rack 707 616 711 725 99 344 1018 840 840 436
culvert/RC corridor)
Pipe Rack (south of DO tanks
CA-14A Pipe Rack 366 266 380 375 416 554 1342 489 489 545
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14B Pipe Rack 352 275 359 372 429 587 1325 490 491 504
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14C Pipe Rack 346 295 345 376 449 624 1310 496 499 465
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14D Pipe Rack 349 321 339 388 474 662 1297 508 512 429
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14E Pipe Rack 359 356 342 407 504 704 1286 526 531 396
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14F Pipe Rack 378 394 353 432 538 747 1277 548 554 368
X40-D-0301/0302/0303)
Pipe Rack (south of DO tanks
CA-14G Pipe Rack 402 435 371 461 576 792 1271 574 581 348
X40-D-0301/0302/0303)
Pipe rack (north of DPK tanks
CA-15A Pipe Rack 402 305 414 414 378 525 1304 528 528 520
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15B Pipe Rack 390 314 395 411 394 560 1287 529 530 477
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15C Pipe Rack 385 331 383 415 416 599 1271 535 538 436
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15D Pipe Rack 388 356 378 426 442 639 1258 547 550 398
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15E Pipe Rack 398 387 381 444 475 682 1247 563 568 362
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15F Pipe Rack 415 424 392 468 511 727 1238 585 590 332
X40-D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks
CA-15G Pipe Rack 438 463 409 496 550 773 1231 610 616 309
X40-D-0401/0402/0403/0404)

Risktec Solutions DMCC Page B.17 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-19 Utility B-20 Custody
B-18 Sanitary
Congested Areas Description Location B-12 B-14 B-15 Water Metering
B-11 OME B-16 IDAS B-17 IDAS Metering
Operation B-13 Musalla Chemical Operation Metering Shelter
Building Shelter-001 Shelter-002 Shelter-
Building Shelter Shelter Shelter- (Vendor
Marafiq
Marafiq Package)
Pipe rack (south of PG91/PG95
CA-16A Pipe Rack tanks X40-D- 1100 1013 1100 1121 350 449 685 1237 1237 604
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16B Pipe Rack tanks X40-D- 1096 1016 1093 1120 365 490 651 1237 1238 567
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16C Pipe Rack tanks X40-D- 1094 1021 1089 1121 389 533 620 1240 1241 532
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16D Pipe Rack tanks X40-D- 1095 1029 1087 1125 417 577 592 1245 1246 501
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16E Pipe Rack tanks X40-D- 1098 1040 1088 1132 451 625 567 1252 1254 473
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16F Pipe Rack tanks X40-D- 1105 1054 1091 1141 489 674 546 1262 1264 450
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16G Pipe Rack tanks X40-D- 1113 1070 1098 1153 529 722 531 1273 1276 433
0101/0102/0201/0202)
Pipe rack (north of PG91 tanks
CA-17A Pipe Rack 1149 1103 1134 1187 546 729 497 1308 1311 473
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17B Pipe Rack 1143 1092 1130 1180 517 692 510 1300 1302 487
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17C Pipe Rack 1137 1078 1127 1171 481 645 532 1291 1293 508
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17D Pipe Rack 1134 1068 1126 1164 449 599 558 1283 1285 534
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17E Pipe Rack 1133 1060 1128 1160 423 556 588 1279 1280 563
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17F Pipe Rack 1135 1055 1132 1159 402 515 621 1276 1277 596
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-17G Pipe Rack 1139 1052 1139 1160 388 477 656 1276 1276 632
X40-D-0204/0205)
Pipe rack (north of PG91 tanks
CA-18A Pipe Rack 1356 1300 1344 1391 692 823 316 1511 1514 691
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18B Pipe Rack 1351 1289 1341 1383 665 783 349 1503 1505 706
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18C Pipe Rack 1348 1280 1340 1378 642 746 388 1497 1498 724
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18D Pipe Rack 1347 1273 1341 1374 624 712 428 1493 1494 746
X40-D-XXX1/XXX2)

Risktec Solutions DMCC Page B.18 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-19 Utility B-20 Custody
B-18 Sanitary
Congested Areas Description Location B-12 B-14 B-15 Water Metering
B-11 OME B-16 IDAS B-17 IDAS Metering
Operation B-13 Musalla Chemical Operation Metering Shelter
Building Shelter-001 Shelter-002 Shelter-
Building Shelter Shelter Shelter- (Vendor
Marafiq
Marafiq Package)
Pipe rack (north of PG91 tanks
CA-18E Pipe Rack 1348 1269 1345 1373 609 679 472 1490 1491 771
X40-D-XXX1/XXX2)
Pipe rack (north of PG91 tanks
CA-18F Pipe Rack 1352 1266 1350 1374 599 650 517 1490 1490 798
X40-D-XXX1/XXX2)
Pipe rack (west of DO/DPK
CA-19A Pipe Rack 371 220 405 349 491 557 1467 441 436 705
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19B Pipe Rack 409 265 440 393 440 509 1420 489 484 677
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19C Pipe Rack 450 312 477 439 388 462 1373 538 534 650
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19D Pipe Rack 494 361 518 486 337 415 1326 587 584 627
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19E Pipe Rack 539 410 561 535 286 370 1280 638 635 608
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19F Pipe Rack 585 460 605 583 235 326 1234 688 685 593
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19G Pipe Rack 633 511 650 633 185 286 1188 739 736 582
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19H Pipe Rack 680 561 695 682 136 251 1143 789 787 575
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19I Pipe Rack 728 612 742 733 92 221 1099 840 838 573
tanks X-40D-0304/0305/0405)
Pipe rack (west of DO/DPK
CA-19J Pipe Rack 777 663 790 783 60 201 1055 891 889 576
tanks X-40D-0304/0305/0405)
Pipe rack (west of
CA-20A Pipe Rack PG91/PG95/DO tanks X40-D- 900 791 910 909 123 205 951 1019 1017 604
0501/0104/XXX3)
Pipe rack (west of
CA-20B Pipe Rack PG91/PG95/DO tanks X40-D- 950 842 959 960 171 229 911 1070 1068 622
0501/0104/XXX3)
Pipe rack (west of
CA-20C Pipe Rack PG91/PG95/DO tanks X40-D- 1002 895 1010 1012 222 262 871 1123 1121 644
0501/0104/XXX3)
Pipe rack (west of
CA-20D Pipe Rack PG91/PG95/DO tanks X40-D- 1053 947 1060 1064 273 300 833 1175 1173 670
0501/0104/XXX3)
Pipe rack (west of
CA-20E Pipe Rack PG91/PG95/DO tanks X40-D- 1103 999 1110 1115 324 342 797 1227 1225 698
0501/0104/XXX3)
Pipe rack (west of
CA-20F Pipe Rack PG91/PG95/DO tanks X40-D- 1156 1053 1162 1168 377 388 762 1280 1279 731
0501/0104/XXX3)

Risktec Solutions DMCC Page B.19 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


B-19 Utility B-20 Custody
B-18 Sanitary
Congested Areas Description Location B-12 B-14 B-15 Water Metering
B-11 OME B-16 IDAS B-17 IDAS Metering
Operation B-13 Musalla Chemical Operation Metering Shelter
Building Shelter-001 Shelter-002 Shelter-
Building Shelter Shelter Shelter- (Vendor
Marafiq
Marafiq Package)
Pipe rack (west of
CA-20G Pipe Rack PG91/PG95/DO tanks X40-D- 1207 1104 1212 1220 429 434 730 1332 1330 764
0501/0104/XXX3)
Pipe rack (west of
CA-20H Pipe Rack PG91/PG95/DO tanks X40-D- 1259 1157 1264 1272 482 482 701 1385 1383 801
0501/0104/XXX3)
Pipe rack (west of
CA-20I Pipe Rack PG91/PG95/DO tanks X40-D- 1311 1210 1315 1325 534 531 674 1437 1436 838
0501/0104/XXX3)
Pipe rack (west of
CA-20J Pipe Rack PG91/PG95/DO tanks X40-D- 1393 1293 1397 1408 618 610 636 1521 1519 901
0501/0104/XXX3)
Pipe rack (west of
CA-20K Pipe Rack PG91/PG95/DO tanks X40-D- 1444 1345 1448 1459 670 660 619 1572 1571 941
0501/0104/XXX3)
Pipe Culvert
CA-22 (RC Pipe Culvert (RC Corridor) 954 1003 913 1020 857 1109 973 1124 1132 339
Corridor)
CA-23 PS-007 Slop Pump Shelter 871 860 847 921 514 761 797 1039 1045 138

Risktec Solutions DMCC Page B.20 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table B.6: Separation Distances between Congested Areas & Buildings (Part 3 of 3)

Distances between Congested Areas & Buildings (m)


Congested Areas Description Location
B-11 OME Building B-12 Operation Building
CA-01 DPK Filtration Skid DPK Filtration Skid 1346 1205
CA-02 PS-003 PS-003 1238 1095
CA-03 PS-009 PS-009 1189 1044
CA-04 PS-001 PS-001 821 657
CA-05 PS-008 PS-008 765 596
CA-06 PS-010 PS-010 623 434
CA-07 PS-004 PS-004 461 234
CA-08 PS-002 PS-002 405 154
Shaded Parking Area
CA-09 Shaded Parking Area (External) 1941 1778
(External)
Assembly Point & Shaded
CA-10 Assembly Point & Shaded Parking Area 1847 1688
Parking Area
Custody Meter & Receiving
CA-11 Custody Meter & Receiving Manifold 1295 1053
Manifold
CA-12A Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1623 1482
CA-12B Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 424 154
CA-12C Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 397 115
CA-12D Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1639 1502
CA-12E Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1583 1441
CA-12F Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1531 1388
CA-12G Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1481 1336
CA-12H Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1430 1283
CA-12I Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1380 1232
CA-12J Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1329 1180
CA-12K Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1278 1127
CA-12L Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1227 1074
CA-12M Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1178 1022
CA-12N Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1127 969
CA-12O Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1076 916
CA-12P Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 1026 863
CA-12Q Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 978 811
CA-12R Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 930 760
CA-12S Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 880 706
CA-12T Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 832 654
CA-12U Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 783 600
CA-12V Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 738 549
CA-12W Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 693 498

Risktec Solutions DMCC Page B.21 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


Congested Areas Description Location
B-11 OME Building B-12 Operation Building
CA-12X Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 650 448
CA-12Y Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 606 397
CA-12Z Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 566 346
CA-12AA Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 527 298
CA-12AB Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 490 249
CA-12AC Pipe Rack Pipe Rack (along PS-001/002/003/004/008/009/010) 456 200
CA-13A Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1328 1093
CA-13B Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1297 1067
CA-13C Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1267 1044
CA-13D Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1239 1023
CA-13E Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1212 1004
CA-13F Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1186 987
CA-13G Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1162 973
CA-13H Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1141 962
CA-13I Pipe Rack Pipe Rack (east of pipe culvert/RC corridor) 1121 953
CA-14A Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1455 1302
CA-14B Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1470 1308
CA-14C Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1488 1317
CA-14D Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1507 1328
CA-14E Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1528 1341
CA-14F Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1551 1356
CA-14G Pipe Rack Pipe Rack (south of DO tanks X40-D-0301/0302/0303) 1576 1374
Pipe rack (north of DPK tanks X40-D-
CA-15A Pipe Rack 1418 1263
0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-D-
CA-15B Pipe Rack 1434 1270
0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-D-
CA-15C Pipe Rack 1452 1279
0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-D-
CA-15D Pipe Rack 1472 1290
0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-D-
CA-15E Pipe Rack 1493 1304
0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-D-
CA-15F Pipe Rack 1517 1320
0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-D-
CA-15G Pipe Rack 1542 1338
0401/0402/0403/0404)
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16A Pipe Rack 764 563
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16B Pipe Rack 793 578
0101/0102/0201/0202)

Risktec Solutions DMCC Page B.22 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


Congested Areas Description Location
B-11 OME Building B-12 Operation Building
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16C Pipe Rack 825 597
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16D Pipe Rack 858 621
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16E Pipe Rack 895 648
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16F Pipe Rack 933 679
0101/0102/0201/0202)
Pipe rack (south of PG91/PG95 tanks X40-D-
CA-16G Pipe Rack 973 713
0101/0102/0201/0202)
CA-17A Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 940 677
CA-17B Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 907 648
CA-17C Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 867 616
CA-17D Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 829 586
CA-17E Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 794 562
CA-17F Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 761 541
CA-17G Pipe Rack Pipe rack (north of PG91 tanks X40-D-0204/0205) 731 525
CA-18A Pipe Rack Pipe rack (north of PG91 tanks X40-D-XXX1/XXX2) 783 503
CA-18B Pipe Rack Pipe rack (north of PG91 tanks X40-D-XXX1/XXX2) 736 459
CA-18C Pipe Rack Pipe rack (north of PG91 tanks X40-D-XXX1/XXX2) 690 419
CA-18D Pipe Rack Pipe rack (north of PG91 tanks X40-D-XXX1/XXX2) 648 383
CA-18E Pipe Rack Pipe rack (north of PG91 tanks X40-D-XXX1/XXX2) 606 351
CA-18F Pipe Rack Pipe rack (north of PG91 tanks X40-D-XXX1/XXX2) 567 325
Pipe rack (west of DO/DPK tanks X-40D-
CA-19A Pipe Rack 1501 1374
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19B Pipe Rack 1450 1323
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19C Pipe Rack 1399 1271
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19D Pipe Rack 1348 1219
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19E Pipe Rack 1297 1167
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19F Pipe Rack 1246 1115
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19G Pipe Rack 1196 1063
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19H Pipe Rack 1145 1011
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19I Pipe Rack 1095 959
0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-40D-
CA-19J Pipe Rack 1044 907
0304/0305/0405)

Risktec Solutions DMCC Page B.23 of B.24


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Distances between Congested Areas & Buildings (m)


Congested Areas Description Location
B-11 OME Building B-12 Operation Building
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20A Pipe Rack 920 778
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20B Pipe Rack 870 726
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20C Pipe Rack 819 673
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20D Pipe Rack 769 620
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20E Pipe Rack 721 568
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20F Pipe Rack 670 514
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20G Pipe Rack 623 462
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20H Pipe Rack 575 409
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20I Pipe Rack 528 356
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20J Pipe Rack 457 272
0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO tanks X40-D-
CA-20K Pipe Rack 415 220
0501/0104/XXX3)
CA-22 Pipe Culvert (RC Corridor) Pipe Culvert (RC Corridor) 1576 1313
CA-23 PS-007 Slop Pump Shelter 1247 1001
Note: CA-21 is not used due to the congested area being removed during the design stages.

Risktec Solutions DMCC Page B.24 of B.24


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

APPENDIX C CONSEQUENCE RESULTS

Risktec Solutions DMCC Page C.1 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table C.1: Stage 2 BRA YDH Site Hazard Sources Consequence Results

Maximum Downwind Flammable Gas Dispersion


Release Scenario Discharge Jet Fire Results (Note 1) Pool Fire Results
Distance (m)
Distance to Thermal Distance to Thermal
Wind Radiation Level (m) Pool Radiation Level (m)
Mass Flow Flame Pool Flame
Scenario Fluid Speed Pasquill Diameter ¼ LFL ½ LFL LFL
(kg/s) Distance (m) 4.7 12.5 35 Height (m) 4.7 12.5 35
(m/s) (m)
kW/m2 kW/m2 kW/m2 kW/m2 kW/m2 kW/m2

L10-24(D)/Scraper-YNJ- Diesel 1.5 F 476.00 - - - - 25.02 32.08 40.76 25.70 - - - -


2(D) Diesel 5 D 476.00 - - - - 24.98 32.05 50.78 38.97 - - - -

L10-24(K)/Scraper-YNJ- Kerosene 1.5 F 462.00 - - - - 25.07 32.12 40.80 25.72 - - - -


2(K) Kerosene 5 D 462.00 - - - - 25.05 32.11 50.85 39.02 - - - -
Kerosene 1.5 F 238.00 - - - - 25.04 32.09 40.77 25.71 - - - -
L11-30(K)
Kerosene 5 D 238.00 - - - - 25.04 32.10 50.84 39.01 - - - -
Kerosene 1.5 F 142.40 - - - - 25.04 32.10 40.78 25.71 - - - -
L12-48(K)
Kerosene 5 D 142.40 - - - - 25.04 32.10 50.84 39.01 - - - -
Gasoline 1.5 F 213.20 68.05 195.11 143.66 107.61 25.03 30.43 40.40 25.86 - 189.72 109.03 69.38
L1-30(G)
Gasoline 5 D 213.20 73.28 201.02 149.99 113.89 24.90 30.32 50.62 39.53 - 108.46 69.02 44.13
Kerosene 1.5 F 142.40 - - - - 25.04 32.10 40.78 25.71 - - - -
L13-24(K)
Kerosene 5 D 142.40 - - - - 25.04 32.10 50.84 39.01 - - - -
Kerosene 1.5 F 142.40 - - - - 25.04 32.10 40.78 25.71 - - - -
L14-20(K)
Kerosene 5 D 142.40 - - - - 25.04 32.10 50.84 39.01 - - - -
Gasoline 1.5 F 127.50 55.37 179.52 129.49 94.22 25.03 30.43 40.40 25.86 - 189.75 109.04 69.39
L2-42(G)
Gasoline 5 D 127.50 59.65 184.13 134.40 99.04 24.81 30.24 50.54 39.46 - 108.09 68.78 43.98
Gasoline 1.5 F 107.70 71.64 199.32 147.42 111.21 25.00 30.41 40.38 25.85 - 189.55 108.92 69.31
L3-20(G)
Gasoline 5 D 107.70 77.14 205.52 154.20 117.95 24.74 30.19 50.48 39.34 - 107.80 68.60 43.86

L4-20(G)/Scraper-YNJ- Gasoline 1.5 F 329.00 112.21 244.53 190.46 152.72 25.06 30.46 40.42 25.88 - 189.99 109.18 69.48
1(G) Gasoline 5 D 329.00 120.79 252.27 198.95 161.66 24.98 30.38 50.70 39.59 - 108.82 69.24 39.84
Gasoline 1.5 F 213.20 68.05 195.11 143.66 107.61 25.03 30.43 40.40 25.86 - 189.72 109.03 69.38
L5-30(G)
Gasoline 5 D 213.20 73.28 201.02 149.99 113.89 24.90 30.32 50.62 39.53 - 108.46 69.02 44.13
Gasoline 1.5 F 127.50 55.37 179.52 129.49 94.22 25.03 30.43 40.40 25.86 - 189.75 109.04 69.39
L6-42(G)
Gasoline 5 D 127.50 59.65 184.13 134.40 99.04 24.81 30.24 50.54 39.46 - 108.09 68.78 43.98
Diesel 1.5 F 264.70 - - - - 25.04 32.09 40.77 25.71 - - - -
L7-30(D)
Diesel 5 D 264.70 - - - - 25.04 32.10 50.84 39.01 - - - -
Diesel 1.5 F 144.60 - - - - 25.03 32.09 40.77 25.71 - - - -
L8-48(D)
Diesel 5 D 144.60 - - - - 25.04 32.10 50.84 39.01 - - - -
Diesel 1.5 F 383.70 - - - - 25.03 32.08 40.77 25.71 - - - -
L9-24(D)
Diesel 5 D 383.70 - - - - 25.04 32.10 50.84 39.01 - - - -
Kerosene 1.5 F 378.00 - - - - 25.10 32.15 40.82 25.74 - - - -
L9-24(K)
Kerosene 5 D 378.00 - - - - 25.11 32.16 50.90 39.06 - - - -

Risktec Solutions DMCC Page C.2 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Maximum Downwind Flammable Gas Dispersion


Release Scenario Discharge Jet Fire Results (Note 1) Pool Fire Results
Distance (m)
Distance to Thermal Distance to Thermal
Wind Radiation Level (m) Pool Radiation Level (m)
Mass Flow Flame Pool Flame
Scenario Fluid Speed Pasquill Diameter ¼ LFL ½ LFL LFL
(kg/s) Distance (m) 4.7 12.5 35 Height (m) 4.7 12.5 35
(m/s) (m)
kW/m2 kW/m2 kW/m2 kW/m2 kW/m2 kW/m2
Diesel 1.5 F 170.20 - - - - 25.06 32.12 40.79 25.72 - - - -
X40-U-0014B(D)
Diesel 5 D 170.20 - - - - 25.07 32.12 50.87 39.03 - - - -
Gasoline 1.5 F 184.60 68.05 195.11 143.66 107.61 25.00 30.40 40.38 25.85 - 189.52 108.91 69.30
X40-U-0014A(G)
Gasoline 5 D 184.60 73.28 201.02 149.99 113.89 24.85 30.28 50.58 39.49 - 108.26 68.89 44.04
Kerosene 1.5 F 137.00 - - - - 25.05 32.10 40.78 25.72 - - - -
X40-U-0014C(K)
Kerosene 5 D 137.00 - - - - 25.04 32.10 50.84 39.01 - - - -
Diesel 1.5 F 170.20 - - - - 25.06 32.12 40.79 25.72 - - - -
X40-U-0014D(D)
Diesel 5 D 170.20 - - - - 25.07 32.12 50.87 39.03 - - - -
Gasoline 1.5 F 184.60 68.05 195.11 143.66 107.61 25.00 30.40 40.38 25.85 - 189.52 108.91 69.30
X40-U-0014D(G)
Gasoline 5 D 184.60 73.28 201.02 149.99 113.89 24.85 30.28 50.58 39.49 - 108.26 68.89 44.04
Kerosene 1.5 F 137.00 - - - - 25.05 32.10 40.78 25.72 - - - -
X40-U-0014D(K)
Kerosene 5 D 137.00 - - - - 25.04 32.10 50.84 39.01 - - - -
Gasoline 1.5 F 55.87 39.80 127.51 92.27 67.56 25.43 30.76 40.68 26.02 - 175.64 101.11 64.49
X40-D-0015A(G)
Gasoline 5 D 55.87 42.88 130.41 95.50 70.85 24.96 30.37 50.69 39.57 - 108.74 63.31 39.82
Gasoline 1.5 F 55.87 39.80 127.51 92.27 67.56 25.43 30.76 40.68 26.02 - 175.64 101.11 64.49
X40-D-0015B(G)
Gasoline 5 D 55.87 42.88 130.41 95.50 70.85 24.96 30.37 50.69 39.57 - 108.74 63.31 39.82
Diesel 1.5 F 34.11 - - - - 25.07 32.13 40.80 25.73 - - - -
X40-D-0037(D)
Diesel 5 D 34.11 - - - - 25.07 32.12 50.87 39.03 - - - -
Gasoline 1.5 F 107.70 71.64 199.32 147.42 111.21 25.00 30.41 40.38 25.85 - 189.55 108.92 69.31
X40-G-0020(G)
Gasoline 5 D 107.70 77.14 205.52 154.20 117.95 24.74 30.19 50.48 39.34 - 107.80 68.60 43.86
Gasoline 1.5 F 107.70 71.64 199.32 147.42 111.21 25.00 30.41 40.38 25.85 - 189.55 108.92 69.31
X40-G-0021(G)
Gasoline 5 D 107.70 77.14 205.52 154.20 117.95 24.74 30.19 50.48 39.34 - 107.80 68.60 43.86
Diesel 1.5 F 157.60 - - - - 25.07 32.12 40.80 25.72 - - - -
X40-G-0018(D)
Diesel 5 D 157.60 - - - - 25.07 32.12 50.87 39.03 - - - -
Kerosene 1.5 F 157.60 - - - - 25.11 32.16 40.82 25.74 - - - -
X40-G-0018(K)
Kerosene 5 D 157.60 - - - - 25.11 32.16 50.90 39.06 - - - -
Diesel 1.5 F 157.60 - - - - 25.07 32.12 40.80 25.72 - - - -
X40-G-0019(D)
Diesel 5 D 157.60 - - - - 25.07 32.12 50.87 39.03 - - - -
Kerosene 1.5 F 152.80 - - - - 25.04 32.10 40.78 25.71 - - - -
X40-G-0019(K)
Kerosene 5 D 152.80 - - - - 25.04 32.10 50.84 39.01 - - - -
Gasoline 1.5 F 107.70 71.64 199.32 147.42 111.21 25.06 30.46 40.42 25.88 - 190.02 109.19 69.49
X40-G-XXX1(G)
Gasoline 5 D 107.70 77.14 205.52 154.20 117.95 24.80 30.24 50.54 39.46 - 108.07 68.77 43.97
Diesel 1.5 F 157.60 - - - - 25.07 32.12 40.80 25.72 - - - -
X40-G-XXX2(D)
Diesel 5 D 157.60 - - - - 25.07 32.12 50.87 39.03 - - - -

Risktec Solutions DMCC Page C.3 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Maximum Downwind Flammable Gas Dispersion


Release Scenario Discharge Jet Fire Results (Note 1) Pool Fire Results
Distance (m)
Distance to Thermal Distance to Thermal
Wind Radiation Level (m) Pool Radiation Level (m)
Mass Flow Flame Pool Flame
Scenario Fluid Speed Pasquill Diameter ¼ LFL ½ LFL LFL
(kg/s) Distance (m) 4.7 12.5 35 Height (m) 4.7 12.5 35
(m/s) (m)
kW/m2 kW/m2 kW/m2 kW/m2 kW/m2 kW/m2
Kerosene 1.5 F 152.80 - - - - 25.10 32.15 40.82 25.74 - - - -
X40-G-XXX2(K)
Kerosene 5 D 152.80 - - - - 25.11 32.16 50.90 39.06 - - - -
Gasoline 1.5 F 107.70 71.64 199.32 147.42 111.21 25.00 30.41 40.38 25.85 - 189.55 108.92 69.31
X40-G-XXX3(G)
Gasoline 5 D 107.70 77.14 205.52 154.20 117.95 24.74 30.19 50.48 39.34 - 107.80 68.60 43.86
Kerosene 1.5 F 136.10 - - - - 25.04 32.10 40.78 25.71 - - - -
D-0024(K)
Kerosene 5 D 136.10 - - - - 25.04 32.10 50.84 39.01 - - - -
Kerosene 1.5 F 136.10 - - - - 25.04 32.10 40.78 25.71 - - - -
D-0025(K)
Kerosene 5 D 136.10 - - - - 25.04 32.10 50.84 39.01 - - - -
Kerosene 1.5 F 136.10 - - - - 25.04 32.10 40.78 25.71 - - - -
G-5101(K)
Kerosene 5 D 136.10 - - - - 25.04 32.10 50.84 39.01 - - - -
Note 1: Non-volatile liquids (e.g., kerosene, diesel, or gasoline) are unlikely to be able to sustain a two-phase jet fire, unless permanently piloted by an adjacent fire; even so, some liquid drop-out is likely and hence the formation of a pool. As such, jet fires can
be discounted from the assessment. However, as a conservative approach, jet fires from gasoline release (≤ 100 mm) have been included as the flow rates are relatively low and less energy is required to sustain ignition. The gasoline jet fire results from Stage 2
BRA are therefore based on 100mm release (Assumption A02, Appendix A).

Risktec Solutions DMCC Page C.4 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table C.2: Stage 2 BRA Pipeline Consequence Results

Maximum Downwind Flammable Gas Dispersion


Release Scenario Discharge Jet Fire Results (Note 1) Pool Fire Results
Distance (m)
Distance to Thermal Distance to Thermal
Wind Radiation Level (m) Pool Radiation Level (m)
Mass Flow Flame Pool Flame
Scenario Fluid Speed Pasquill Diameter ¼ LFL ½ LFL LFL
(kg/s) Distance (m) 4.7 12.5 35 Height (m) 4.7 12.5 35
(m/s) (m)
kW/m2 kW/m2 kW/m2 kW/m2 kW/m2 kW/m2
YNJ-1(G) Gasoline 1.5 F 329.00 149.71 235.30 189.00 157.75 75.00 62.00 251.72 166.31 102.84 385.00 257.00 134.18
YNJ-1(G) Gasoline 5 D 329.00 114.37 189.73 148.94 121.44 75.00 62.00 257.13 176.32 120.37 391.50 246.74 111.36
YNJ-2(D) Diesel 1.5 F 476.00 - - - - 89.00 61.00 227.64 150.94 103.48 - - -
YNJ-2(D) Diesel 5 D 476.00 - - - - 89.00 61.00 234.71 162.36 112.60 - - -
YNJ-2(K) Kerosene 1.5 F 462.00 - - - - 89.00 74.00 88.66 48.04 - - - -
YNJ-2(K) Kerosene 5 D 462.00 - - - - 89.00 74.00 109.58 50.46 - - - -
SAM-30(D) Diesel 1.5 F 625.80 - - - - 104.08 67.9 265.88 178.07 113.30 - - -
SAM-30(D) Diesel 5 D 625.80 - - - - 104.08 67.9 270.18 186.73 129.62 - - -
SAM-30(K) Kerosene 1.5 F 626.12 - - - - 103.47 83.09 100.50 55.35 - - - -
SAM-30(K) Kerosene 5 D 626.12 - - - - 103.47 83.09 123.67 57.89 - - - -
SAM-30(G) Gasoline 1.5 F 574.50 29.99 49.23 37.99 31.63 99.05 82.90 286.63 190.73 120.10 356.63 341.27 150.11
SAM-30(G) Gasoline 5 D 574.50 27.75 58.58 36.91 29.83 99.05 82.90 291.76 200.65 138.04 210.93 206.54 139.51
YAS-30(D) Diesel 1.5 F 656.90 - - - - 104.41 76.28 266.62 178.57 113.63 - - -
YAS-30(D) Diesel 5 D 656.90 - - - - 104.41 76.28 270.93 187.24 129.98 - - -
YAS-30(G) Gasoline 1.5 F 574.50 29.99 49.23 37.99 31.63 99.05 81.53 286.63 190.73 120.10 356.63 341.27 150.11
YAS-30(G) Gasoline 5 D 574.50 27.75 58.58 37.91 27.83 99.05 81.53 291.76 200.65 138.04 210.93 206.54 139.51
YR-22(D) Diesel 1.5 F 510.66 - - - - 92.06 62.35 238.21 159.39 101.00 - - -
YR-22(D) Diesel 5 D 510.66 - - - - 92.06 62.35 242.19 167.42 116.16 - - -
YR-22(K) Kerosene 1.5 F 410.89 - - - - 83.82 71.46 84.48 45.50 - - - -
YR-22(K) Kerosene 5 D 410.89 - - - - 83.82 71.46 104.59 47.80 - - - -
YR-24(G) Gasoline 1.5 F 553.96 29.99 48.23 37.99 31.63 97.27 74.76 282.00 187.63 118.08 353.42 338.01 148.57
YR-24(G) Gasoline 5 D 553.96 27.75 58.58 37.91 29.83 97.27 74.76 287.08 197.44 135.83 209.00 204.59 138.25
Note 1: Non-volatile liquids (e.g., kerosene, diesel, or gasoline) are unlikely to be able to sustain a two-phase jet fire, unless permanently piloted by an adjacent fire; even so, some liquid drop-out is likely and hence the formation of a pool. As such, jet fires can
be discounted from the assessment. However, as a conservative approach, jet fires from gasoline release (≤ 100 mm) have been included as the flow rates are relatively low and less energy is required to sustain ignition. The gasoline jet fire results from Stage 2
BRA are therefore based on 100mm release (Assumption A02, Appendix A).

Risktec Solutions DMCC Page C.5 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table C.3: Stage 2 BRA Storage Tanks Fire Consequence Results

Release Scenario Discharge Pool Fire Results


Distance to Thermal Radiation
Pool Level (m)
Wind Speed Mass Flow Pool Flame
Scenario Event Fluid Pasquill Diameter
(m/s) (kg/s) Height (m) 4.7 12.5 35
(m)
kW/m2 kW/m2 kW/m2
Bund Fire Gasoline 1.5 F 115.50 145.00 103.10 146.49 94.01 -
Bund Fire Gasoline 5 D 217.90 145.00 103.10 164.53 118.87 -
Rim Seal Fire Gasoline 1.5 F 24.83 28.33 33.16 42.77 27.15 -
X40-D-0016A(G)
Rim Seal Fire Gasoline 5 D 24.83 28.09 32.97 53.72 41.94 -
Tank Top Fire Gasoline 1.5 F 24.83 55.02 52.61 65.19 40.51 -
Tank Top Fire Gasoline 5 D 52.30 55.08 52.64 80.28 61.46 -
Bund Fire Gasoline 1.5 F 115.50 145.00 103.10 146.49 94.01 -
Bund Fire Gasoline 5 D 217.90 145.00 103.10 164.53 118.87 -
Rim Seal Fire Gasoline 1.5 F 24.83 28.33 33.16 42.77 27.15 -
X40-D-0016B(G)
Rim Seal Fire Gasoline 5 D 24.83 28.09 32.97 53.72 41.94 -
Tank Top Fire Gasoline 1.5 F 24.83 55.02 52.61 65.19 40.51 -
Tank Top Fire Gasoline 5 D 52.30 55.08 52.64 80.28 61.46 -
Bund Fire Gasoline 1.5 F 154.70 167.00 113.80 165.18 106.86 -
Bund Fire Gasoline 5 D 226.90 167.10 113.80 183.78 132.03 -
Rim Seal Fire Gasoline 1.5 F 24.83 28.33 33.16 42.77 27.15 -
X40-D-0016C(G)
Rim Seal Fire Gasoline 5 D 42.35 27.00 32.07 52.66 41.16 -
Tank Top Fire Gasoline 1.5 F 24.83 55.02 52.61 65.19 40.51 -
Tank Top Fire Gasoline 5 D 63.11 55.00 52.59 80.21 61.40 -
Bund Fire Gasoline 1.5 F 485.60 237.00 145.20 223.44 147.04 -
Bund Fire Gasoline 5 D 391.10 237.00 145.20 242.51 172.50 -
Rim Seal Fire Gasoline 1.5 F 24.83 39.33 41.66 51.34 31.99 -
X40-D-0104(G)
Rim Seal Fire Gasoline 5 D 24.83 39.01 41.42 64.26 50.01 -
Tank Top Fire Gasoline 1.5 F 24.83 77.09 66.50 85.66 53.74 -
Tank Top Fire Gasoline 5 D 64.40 77.00 66.45 101.92 76.47 -
Bund Fire Gasoline 1.5 F 115.50 145.00 103.10 146.49 94.01 -
Bund Fire Gasoline 5 D 191.70 145.00 103.20 164.59 118.91 -
Rim Seal Fire Gasoline 1.5 F 24.83 28.33 33.16 42.77 27.15 -
X40-D-0002A(G)
Rim Seal Fire Gasoline 5 D 27.10 28.00 32.90 53.64 41.92 -
Tank Top Fire Gasoline 1.5 F 24.83 55.02 52.61 65.19 40.51 -
Tank Top Fire Gasoline 5 D 24.83 44.88 45.66 70.06 54.20 -

Risktec Solutions DMCC Page C.6 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Release Scenario Discharge Pool Fire Results


Distance to Thermal Radiation
Pool Level (m)
Wind Speed Mass Flow Pool Flame
Scenario Event Fluid Pasquill Diameter
(m/s) (kg/s) Height (m) 4.7 12.5 35
(m)
kW/m2 kW/m2 kW/m2
Bund Fire Gasoline 1.5 F 115.50 145.00 103.10 146.49 94.01 -
Bund Fire Gasoline 5 D 191.70 145.00 103.20 164.59 118.91 -
Rim Seal Fire Gasoline 1.5 F 24.83 28.33 33.16 42.77 27.15 -
X40-D-0002B(G)
Rim Seal Fire Gasoline 5 D 47.59 28.01 32.90 53.65 41.88 -
Tank Top Fire Gasoline 1.5 F 24.83 55.02 52.61 65.19 40.51 -
Tank Top Fire Gasoline 5 D 24.83 44.88 45.66 70.06 54.20 -
Bund Fire Gasoline 1.5 F 154.70 167.00 113.80 165.18 106.86 -
Bund Fire Gasoline 5 D 154.70 127.40 94.29 148.92 108.23 -
Rim Seal Fire Gasoline 1.5 F 24.83 28.33 33.16 42.77 27.15 -
X40-D-0002C(G)
Rim Seal Fire Gasoline 5 D 47.59 28.01 32.90 53.65 41.88 -
Tank Top Fire Gasoline 1.5 F 24.83 55.02 52.61 65.19 40.51 -
Tank Top Fire Gasoline 5 D 52.30 55.00 52.59 80.21 61.40 -
Bund Fire Gasoline 1.5 F 485.60 237.00 145.20 223.44 147.04 -
Bund Fire Gasoline 5 D 391.10 237.00 145.20 242.51 172.50 -
Rim Seal Fire Gasoline 1.5 F 24.83 39.33 41.66 51.34 31.99 -
X40-D-0204(G)
Rim Seal Fire Gasoline 5 D 24.83 39.01 41.42 64.26 50.01 -
Tank Top Fire Gasoline 1.5 F 24.83 77.09 66.50 85.66 53.74 -
Tank Top Fire Gasoline 5 D 64.40 77.00 66.45 101.92 76.47 -
Bund Fire Gasoline 1.5 F 188.90 184.00 121.70 179.47 116.65 -
Bund Fire Gasoline 5 D 361.70 184.00 121.70 198.29 141.66 -
Rim Seal Fire Gasoline 1.5 F 24.83 34.04 37.68 47.07 29.53 -
X40-D-0205(G)
Rim Seal Fire Gasoline 5 D 32.98 33.00 36.87 58.43 45.62 -
Tank Top Fire Gasoline 1.5 F 24.83 67.01 60.33 76.29 47.72 -
Tank Top Fire Gasoline 5 D 42.63 67.02 60.34 92.13 69.63 -
Bund Fire Diesel 1.5 F 715.10 197.00 134.60 192.54 124.06 -
X40-D-0006A(D)
Bund Fire Diesel 5 D 715.10 197.00 134.60 209.58 146.56 -
Bund Fire Diesel 1.5 F 715.10 197.00 134.60 192.54 124.06 -
X40-D-0006B(D)
Bund Fire Diesel 5 D 715.10 197.00 134.60 209.58 146.56 -
Bund Fire Diesel 1.5 F 715.10 197.00 134.60 192.54 124.06 -
X40-D-0006C(D)
Bund Fire Diesel 5 D 715.10 197.00 134.60 209.58 146.56 -
Bund Fire Diesel 1.5 F 875.80 224.00 147.20 215.03 139.51 -
X40-D-0304(D)
Bund Fire Diesel 5 D 875.80 223.90 147.10 232.22 162.25 -
Bund Fire Diesel 1.5 F 875.80 224.00 147.20 215.03 139.51 -
X40-D-0305(D)
Bund Fire Diesel 5 D 875.80 223.90 147.10 232.22 162.25 -

Risktec Solutions DMCC Page C.7 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Release Scenario Discharge Pool Fire Results


Distance to Thermal Radiation
Pool Level (m)
Wind Speed Mass Flow Pool Flame
Scenario Event Fluid Pasquill Diameter
(m/s) (kg/s) Height (m) 4.7 12.5 35
(m)
kW/m2 kW/m2 kW/m2
Bund Fire Kerosene 1.5 F 156.30 185.10 128.90 182.72 117.16 -
Bund Fire Kerosene 5 D 156.30 184.90 128.80 199.53 139.53 -
Rim Seal Fire Kerosene 1.5 F 25.02 28.09 34.77 42.98 26.88 -
X40-D-0018A(K)
Rim Seal Fire Kerosene 5 D 25.02 28.00 34.69 53.64 41.18 -
Tank Top Fire Kerosene 1.5 F 25.02 55.03 55.48 65.78 40.24 -
Tank Top Fire Kerosene 5 D 25.02 54.99 55.45 79.92 59.80 -
Bund Fire Kerosene 1.5 F 156.30 185.10 128.90 182.72 117.16 -
Bund Fire Kerosene 5 D 156.30 184.90 128.80 199.53 139.53 -
Rim Seal Fire Kerosene 1.5 F 25.02 28.09 34.77 42.98 26.88 -
X40-D-0018B(K)
Rim Seal Fire Kerosene 5 D 25.02 28.00 34.69 53.64 41.18 -
Tank Top Fire Kerosene 1.5 F 25.02 55.03 55.48 65.78 40.24 -
Tank Top Fire Kerosene 5 D 25.02 54.99 55.45 79.92 59.80 -
Bund Fire Kerosene 1.5 F 156.30 185.10 128.90 182.72 117.16 -
Bund Fire Kerosene 5 D 156.30 184.90 128.80 199.53 139.53 -
Rim Seal Fire Kerosene 1.5 F 25.02 28.09 34.77 42.98 26.88 -
X40-D-0018C(K)
Rim Seal Fire Kerosene 5 D 25.02 28.00 34.69 53.64 41.18 -
Tank Top Fire Kerosene 1.5 F 25.02 55.03 55.48 65.78 40.24 -
Tank Top Fire Kerosene 5 D 25.02 54.99 55.45 79.92 59.80 -
Bund Fire Kerosene 1.5 F 156.30 205.10 138.40 199.30 128.70 -
Bund Fire Kerosene 5 D 156.30 204.90 138.30 216.35 151.12 -
Rim Seal Fire Kerosene 1.5 F 25.02 34.03 39.73 47.46 29.30 -
X40-D-0017(K)
Rim Seal Fire Kerosene 5 D 25.02 34.00 39.70 59.26 45.46 -
Tank Top Fire Kerosene 1.5 F 25.02 67.10 63.68 77.10 47.49 -
Tank Top Fire Kerosene 5 D 25.02 66.99 63.61 91.86 68.03 -
Bund Fire Kerosene 1.5 F 156.30 204.00 137.90 198.39 128.07 -
Bund Fire Kerosene 5 D 156.30 204.00 137.90 215.77 150.62 -
Rim Seal Fire Kerosene 1.5 F 25.02 34.03 39.73 47.46 29.30 -
X40-D-0405(K)
Rim Seal Fire Kerosene 5 D 25.02 34.00 39.70 59.26 45.46 -
Tank Top Fire Kerosene 1.5 F 25.02 67.10 63.68 77.10 47.49 -
Tank Top Fire Kerosene 5 D 25.02 67.00 63.61 91.87 68.03 -

Risktec Solutions DMCC Page C.8 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Release Scenario Discharge Pool Fire Results


Distance to Thermal Radiation
Pool Level (m)
Wind Speed Mass Flow Pool Flame
Scenario Event Fluid Pasquill Diameter
(m/s) (kg/s) Height (m) 4.7 12.5 35
(m)
kW/m2 kW/m2 kW/m2
Bund Fire Gasoline 1.5 F 485.60 237.00 145.20 223.44 147.04 -
Bund Fire Gasoline 5 D 485.60 237.00 145.20 242.51 172.50 -
Rim Seal Fire Gasoline 1.5 F 24.83 39.33 41.66 51.34 31.99 -
X40-D-0501(G)
Rim Seal Fire Gasoline 5 D 24.83 39.00 41.42 64.25 50.01 -
Tank Top Fire Gasoline 1.5 F 24.83 77.09 66.50 85.66 53.74 -
Tank Top Fire Gasoline 5 D 55.34 77.01 66.45 101.93 76.47 -
Bund Fire Diesel 1.5 F 505.90 237.10 153.10 225.85 146.99 -
Bund Fire Diesel 5 D 505.90 237.00 153.10 243.12 169.77 -
Rim Seal Fire Diesel 1.5 F 25.55 39.08 43.74 51.57 31.61 -
X40-D-0009(D)
Rim Seal Fire Diesel 5 D 25.55 39.00 43.67 64.03 48.84 -
Tank Top Fire Diesel 1.5 F 25.55 77.02 70.08 86.43 53.43 -
Tank Top Fire Diesel 5 D 25.55 76.99 70.06 101.69 74.41 -
Bund Fire Kerosene 1.5 F 490.90 237.10 153.10 225.85 146.99 -
Bund Fire Kerosene 5 D 490.90 237.00 153.00 243.07 169.74 -
Rim Seal Fire Kerosene 1.5 F 25.02 39.08 43.73 51.56 31.61 -
X40-D-0009(K)
Rim Seal Fire Kerosene 5 D 25.02 38.99 43.66 64.02 48.83 -
Tank Top Fire Kerosene 1.5 F 25.02 77.10 70.13 86.50 53.47 -
Tank Top Fire Kerosene 5 D 25.02 77.01 70.08 101.71 74.43 -
Bund Fire Gasoline 1.5 F 840.60 250.00 150.60 234.09 154.40 -
Bund Fire Gasoline 5 D 562.00 249.70 150.50 252.92 179.76 -
Rim Seal Fire Gasoline 1.5 F 24.83 37.00 39.92 49.42 30.87 -
X40-D-XXX1(G)
Rim Seal Fire Gasoline 5 D 24.83 37.01 39.94 62.31 48.57 -
Tank Top Fire Gasoline 1.5 F 24.83 73.03 64.04 81.89 51.31 -
Tank Top Fire Gasoline 5 D 54.51 72.99 64.02 98.01 73.67 -
Bund Fire Gasoline 1.5 F 840.60 250.00 150.60 234.09 154.40 -
Bund Fire Gasoline 5 D 562.00 249.70 150.50 252.92 179.76 -
Rim Seal Fire Gasoline 1.5 F 24.83 37.00 39.92 49.42 30.87 -
X40-D-XXX2(G)
Rim Seal Fire Gasoline 5 D 24.83 37.01 39.94 62.31 48.57 -
Tank Top Fire Gasoline 1.5 F 24.83 73.03 64.04 81.89 51.31 -
Tank Top Fire Gasoline 5 D 54.51 72.99 64.02 98.01 73.67 -
Bund Fire Diesel 1.5 F 875.80 227.00 148.60 217.59 141.28 -
X40-D-XXX3(D)
Bund Fire Diesel 5 D 875.80 227.00 148.60 234.82 164.03 -

Risktec Solutions DMCC Page C.9 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table C.4: Stage 2 BRA Storage Tanks Flammable Gas Dispersion Consequence Results

Release Scenario Pool Maximum Downwind Flammable Gas Dispersion Distance (m)
Wind Speed (m/s) Pasquill Mass Flow (kg/s)
Scenario Event Fluid Diameter (m) ¼ LFL ½ LFL LFL
Bund Vaporisation Gasoline 1.5 F 115.50 145.00 1206.44 692.20 439.54
Bund Vaporisation Gasoline 5 D 217.90 145.00 631.51 401.86 231.23
Spill on Roof Gasoline 1.5 F 24.83 28.33 195.70 123.42 78.54
X40-D-0016A(G)
Spill on Roof Gasoline 5 D 24.83 28.09 122.36 71.24 44.80
Tank Sunken Roof Gasoline 1.5 F 24.83 55.02 417.12 239.70 152.53
Tank Sunken Roof Gasoline 5 D 52.30 55.08 239.96 152.69 87.86
Bund Vaporisation Gasoline 1.5 F 115.50 145.00 1206.44 692.20 439.54
Bund Vaporisation Gasoline 5 D 217.90 145.00 631.51 401.86 231.23
Spill on Roof Gasoline 1.5 F 24.83 28.33 195.70 123.42 78.54
X40-D-0016B(G)
Spill on Roof Gasoline 5 D 24.83 28.09 122.36 71.24 44.80
Tank Sunken Roof Gasoline 1.5 F 24.83 55.02 417.12 239.70 152.53
Tank Sunken Roof Gasoline 5 D 52.30 55.08 239.96 152.69 87.86
Bund Vaporisation Gasoline 1.5 F 154.70 167.00 1390.05 797.54 506.44
Bund Vaporisation Gasoline 5 D 226.90 167.10 727.83 463.15 296.11
Spill on Roof Gasoline 1.5 F 24.83 28.33 195.70 123.42 78.54
X40-D-0016C(G)
Spill on Roof Gasoline 5 D 42.35 27.00 117.61 68.47 43.06
Tank Sunken Roof Gasoline 1.5 F 24.83 55.02 417.12 239.70 152.53
Tank Sunken Roof Gasoline 5 D 63.11 55.00 239.62 152.48 87.74
Bund Vaporisation Gasoline 1.5 F 485.60 237.00 1637.27 1032.54 657.05
Bund Vaporisation Gasoline 5 D 391.10 237.00 942.51 601.15 378.08
Spill on Roof Gasoline 1.5 F 24.83 39.33 271.69 171.34 109.03
X40-D-0104(G)
Spill on Roof Gasoline 5 D 24.83 39.01 169.94 98.94 62.23
Tank Sunken Roof Gasoline 1.5 F 24.83 77.09 584.46 368.08 233.73
Tank Sunken Roof Gasoline 5 D 64.40 77.00 335.45 213.46 122.83
Bund Vaporisation Gasoline 1.5 F 115.50 145.00 1206.44 692.20 439.54
Bund Vaporisation Gasoline 5 D 191.70 145.00 631.81 402.05 257.05
Spill on Roof Gasoline 1.5 F 24.83 28.33 195.70 123.42 78.54
X40-D-0002A(G)
Spill on Roof Gasoline 5 D 27.10 28.00 122.00 71.03 44.67
Tank Sunken Roof Gasoline 1.5 F 24.83 55.02 417.12 239.70 152.53
Tank Sunken Roof Gasoline 5 D 24.83 44.88 195.53 124.43 71.60
Bund Vaporisation Gasoline 1.5 F 115.50 145.00 1206.44 692.20 439.54
Bund Vaporisation Gasoline 5 D 191.70 145.00 631.81 402.05 257.05
Spill on Roof Gasoline 1.5 F 24.83 28.33 195.70 123.42 78.54
X40-D-0002B(G)
Spill on Roof Gasoline 5 D 47.59 28.01 122.03 71.05 44.68
Tank Sunken Roof Gasoline 1.5 F 24.83 55.02 417.12 239.70 152.53
Tank Sunken Roof Gasoline 5 D 24.83 44.88 195.53 124.43 71.60

Risktec Solutions DMCC Page C.10 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Release Scenario Pool Maximum Downwind Flammable Gas Dispersion Distance (m)
Wind Speed (m/s) Pasquill Mass Flow (kg/s)
Scenario Event Fluid Diameter (m) ¼ LFL ½ LFL LFL
Bund Vaporisation Gasoline 1.5 F 154.70 167.00 1390.05 797.54 506.44
Bund Vaporisation Gasoline 5 D 154.70 127.40 555.02 353.19 225.81
Spill on Roof Gasoline 1.5 F 24.83 28.33 195.70 123.42 78.54
X40-D-0002C(G)
Spill on Roof Gasoline 5 D 47.59 28.01 122.03 71.05 44.68
Tank Sunken Roof Gasoline 1.5 F 24.83 55.02 417.12 239.70 152.53
Tank Sunken Roof Gasoline 5 D 52.30 55.00 239.61 152.48 87.74
Bund Vaporisation Gasoline 1.5 F 485.60 237.00 1637.27 1032.54 657.05
Bund Vaporisation Gasoline 5 D 391.10 237.00 942.51 601.15 378.08
Spill on Roof Gasoline 1.5 F 24.83 39.33 271.69 171.34 109.03
X40-D-0204(G)
Spill on Roof Gasoline 5 D 24.83 39.01 169.94 98.94 62.23
Tank Sunken Roof Gasoline 1.5 F 24.83 77.09 584.46 368.08 233.73
Tank Sunken Roof Gasoline 5 D 64.40 77.00 335.45 213.46 122.83
Bund Vaporisation Gasoline 1.5 F 188.90 184.00 1530.92 878.36 557.76
Bund Vaporisation Gasoline 5 D 361.70 184.00 731.81 466.76 293.56
Spill on Roof Gasoline 1.5 F 24.83 34.04 235.12 148.28 94.36
X40-D-0205(G)
Spill on Roof Gasoline 5 D 32.98 33.00 143.75 83.69 52.63
Tank Sunken Roof Gasoline 1.5 F 24.83 67.01 508.00 319.93 185.76
Tank Sunken Roof Gasoline 5 D 42.63 67.02 291.98 185.80 106.91
Bund Vaporisation Gasoline 1.5 F 485.60 237.00 1637.27 1032.54 657.05
Bund Vaporisation Gasoline 5 D 485.60 237.00 860.64 550.32 336.07
Spill on Roof Gasoline 1.5 F 24.83 39.33 271.69 171.34 109.03
X40-D-0501(G)
Spill on Roof Gasoline 5 D 24.83 39.00 169.91 98.92 62.22
Tank Sunken Roof Gasoline 1.5 F 24.83 77.09 584.46 368.08 233.73
Tank Sunken Roof Gasoline 5 D 55.34 77.01 335.48 213.48 122.84
Bund Vaporisation Gasoline 1.5 F 840.60 250.00 1193.45 757.83 487.35
Bund Vaporisation Gasoline 5 D 562.00 249.70 906.84 531.16 309.85
Spill on Roof Gasoline 1.5 F 24.83 37.00 255.57 161.17 102.56
X40-D-XXX1(G)
Spill on Roof Gasoline 5 D 24.83 37.01 161.25 93.88 59.04
Tank Sunken Roof Gasoline 1.5 F 24.83 73.03 553.62 348.66 221.40
Tank Sunken Roof Gasoline 5 D 54.51 72.99 317.98 202.35 116.43
Bund Vaporisation Gasoline 1.5 F 840.60 250.00 1193.45 757.83 487.35
Bund Vaporisation Gasoline 5 D 562.00 249.70 906.84 531.16 309.85
Spill on Roof Gasoline 1.5 F 24.83 37.00 255.57 161.17 102.56
X40-D-XXX2(G)
Spill on Roof Gasoline 5 D 24.83 37.01 161.25 93.88 59.04
Tank Sunken Roof Gasoline 1.5 F 24.83 73.03 553.62 348.66 221.40
Tank Sunken Roof Gasoline 5 D 54.51 72.99 317.98 202.35 116.43

Risktec Solutions DMCC Page C.11 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table C.5: Stage 2 BRA Congested Area Explosions Results

Congested Area Explosion Source Distance to Explosion Overpressure (m)


Overpressure
Number Description Location (psi) 0.49 psi 0.59 psi 0.75 psi 1.00 psi 1.25 psi 1.31 psi 2.49 psi 3.00 psi

DPK Filtration
CA-01 DPK Filtration Skid 0.61 5.26 2.36 - - - - - -
Skid
CA-02 PS-003 PS-003 0.51 2.40 - - - - - - -
CA-03 PS-009 PS-009 0.51 2.44 - - - - - - -
CA-04 PS-001 PS-008 0.57 3.67 - - - - - - -
CA-05 PS-008 PS-009 0.56 3.48 - - - - - - -
CA-06 PS-010 PS-010 0.70 8.99 4.99 - - - - - -
CA-07 PS-004 PS-004 0.80 12.77 8.01 3.12 - - - - -
CA-08 PS-002 PS-002 0.80 12.77 8.01 3.12 - - - - -
Shaded Parking
CA-09 Shaded Parking Area (External) 1.77 25.25 19.74 14.09 8.89 5.75 5.18 - -
Area (External)
Assembly Point
Assembly Point & Shaded Parking
CA-10 & Shaded 3.37 65.55 52.84 39.78 27.79 20.54 19.23 5.82 3.33
Area
Parking Area
Custody Meter
CA-11 & Receiving Custody Meter & Receiving Manifold 0.83 12.53 8.13 3.62 - - - - -
Manifold
Pipe Rack (along PS-
CA-12A Pipe Rack 0.93 3.32 - - - - - - -
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AA Pipe Rack 0.93 14.87 10.21 5.43 - - - - -
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AB Pipe Rack 0.93 14.87 10.21 5.43 - - - - -
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12AC Pipe Rack 0.93 14.87 10.21 5.43 - - - - -
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12B Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12C Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12D Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12E Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12F Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12G Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12H Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12I Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12J Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)

Risktec Solutions DMCC Page C.12 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Area Explosion Source Distance to Explosion Overpressure (m)


Overpressure
Number Description Location (psi) 0.49 psi 0.59 psi 0.75 psi 1.00 psi 1.25 psi 1.31 psi 2.49 psi 3.00 psi

Pipe Rack (along PS-


CA-12K Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12L Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12M Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12N Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12O Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12P Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Q Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12R Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12S Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12T Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12U Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12V Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12W Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12X Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Y Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (along PS-
CA-12Z Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
001/002/003/004/008/009/010)
Pipe Rack (east of pipe culvert/RC
CA-13A Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13B Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13C Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13D Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13E Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13F Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13G Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)

Risktec Solutions DMCC Page C.13 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Area Explosion Source Distance to Explosion Overpressure (m)


Overpressure
Number Description Location (psi) 0.49 psi 0.59 psi 0.75 psi 1.00 psi 1.25 psi 1.31 psi 2.49 psi 3.00 psi

Pipe Rack (east of pipe culvert/RC


CA-13H Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (east of pipe culvert/RC
CA-13I Pipe Rack 0.93 14.87 10.21 5.43 14.87 10.21 5.43 14.87 10.21
corridor)
Pipe Rack (south of DO tanks X40-
CA-14A Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe Rack (south of DO tanks X40-
CA-14B Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe Rack (south of DO tanks X40-
CA-14C Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe Rack (south of DO tanks X40-
CA-14D Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe Rack (south of DO tanks X40-
CA-14E Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe Rack (south of DO tanks X40-
CA-14F Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe Rack (south of DO tanks X40-
CA-14G Pipe Rack 0.59 3.87 - - - - - - -
D-0301/0302/0303)
Pipe rack (north of DPK tanks X40-
CA-15A Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-
CA-15B Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-
CA-15C Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-
CA-15D Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-
CA-15E Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-
CA-15F Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (north of DPK tanks X40-
CA-15G Pipe Rack 0.59 3.87 - - - - - - -
D-0401/0402/0403/0404)
Pipe rack (south of PG91/PG95
CA-16A Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16B Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16C Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16D Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16E Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16F Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)
Pipe rack (south of PG91/PG95
CA-16G Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0101/0102/0201/0202)

Risktec Solutions DMCC Page C.14 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Area Explosion Source Distance to Explosion Overpressure (m)


Overpressure
Number Description Location (psi) 0.49 psi 0.59 psi 0.75 psi 1.00 psi 1.25 psi 1.31 psi 2.49 psi 3.00 psi

Pipe rack (north of PG91 tanks X40-


CA-17A Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-17B Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-17C Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-17D Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-17E Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-17F Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-17G Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-18A Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-18B Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-18C Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-18D Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-18E Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (north of PG91 tanks X40-
CA-18F Pipe Rack 0.59 3.87 - - - - - - -
D-0204/0205)
Pipe rack (west of DO/DPK tanks X-
CA-19A Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19B Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19C Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19D Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19E Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19F Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19G Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19H Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19I Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19A Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)

Risktec Solutions DMCC Page C.15 of C.16


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Area Explosion Source Distance to Explosion Overpressure (m)


Overpressure
Number Description Location (psi) 0.49 psi 0.59 psi 0.75 psi 1.00 psi 1.25 psi 1.31 psi 2.49 psi 3.00 psi

Pipe rack (west of DO/DPK tanks X-


CA-19B Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19C Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19D Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19E Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19F Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19G Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19H Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19I Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of DO/DPK tanks X-
CA-19J Pipe Rack 0.59 3.87 - - - - - - -
40D-0304/0305/0405)
Pipe rack (west of PG91/PG95/DO
CA-20A Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20B Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20C Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20D Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20E Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20F Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20G Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20H Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20I Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20J Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe rack (west of PG91/PG95/DO
CA-20K Pipe Rack 0.59 3.87 - - - - - - -
tanks X40-D-0501/0104/XXX3)
Pipe Culvert
CA-22 Pipe Culvert (RC Corridor) 2.34 48.73 38.38 27.73 17.96 12.05 10.99 - -
(RC Corridor)
CA-23 PS-007 Slop Pump Shelter 0.52 2.51 - - - - - - -
Note: CA-21 is not used due to the congested area being removed during the design stages.

Risktec Solutions DMCC Page C.16 of C.16


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

APPENDIX D STAGE 2 BRA RESULTS

Risktec Solutions DMCC Page D.1 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.1: Jet Flame Stage 2 BRA Results (Part 1 of 3)

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2
Receiving Utility Power B-06 Security Guard B-07 Security Guard B-09 Security B-10 Security
Hazard Sources Remote I/O Remote I/O B-05 FSF Building B-08 X-Ray Building
Substation Substation House (A) House (B) Support Building (A) Support Building (B)
Building Building
Transformer Yard Transformer Yard
X40-D-0015A(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-D-0015B(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged Not Impinged Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
G-5101(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
D-0024(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
D-0025(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014A(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014B(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014C(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014D(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014D(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014D(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L1-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L2-42(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L3-20(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L4-20(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L5-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L6-42(G) Not Impinged Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L7-30(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L8-48(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L9-24(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L9-24(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L10-24(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L10-24(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L11-30(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L12-48(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L13-24(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged

Risktec Solutions DMCC Page D.2 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2
Receiving Utility Power B-06 Security Guard B-07 Security Guard B-09 Security B-10 Security
Hazard Sources Remote I/O Remote I/O B-05 FSF Building B-08 X-Ray Building
Substation Substation House (A) House (B) Support Building (A) Support Building (B)
Building Building
Transformer Yard Transformer Yard
L14-20(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
Scraper-YNJ-1(G) Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
Scraper-YNJ-2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
Scraper-YNJ-2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged Not Impinged Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged Not Impinged Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YNJ-1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YNJ-2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YNJ-2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
SAM-30(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YAS-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YAS-30(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
SAM-30(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YR-22(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YR-22(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
SAM-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YR-24(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged

Risktec Solutions DMCC Page D.3 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.2: Jet Flame Stage 2 BRA Results (Part 2 of 3)

B-18 Sanitary B-19 Utility Water B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-D-0015A(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-D-0015B(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
G-5101(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
D-0024(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
D-0025(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014A(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged
X40-U-0014B(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014C(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014D(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged
X40-U-0014D(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-U-0014D(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L1-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged
L2-42(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L3-20(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L4-20(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L5-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged
L6-42(G) Not Impinged Not Impinged Not Impinged Not Impinged Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L7-30(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L8-48(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L9-24(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L9-24(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L10-24(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L10-24(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L11-30(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L12-48(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L13-24(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
L14-20(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged

Risktec Solutions DMCC Page D.4 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-18 Sanitary B-19 Utility Water B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-G-0019(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
Scraper-YNJ-1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
Scraper-YNJ-2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
Scraper-YNJ-2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YNJ-1(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YNJ-2(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YNJ-2(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
SAM-30(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YAS-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged
YAS-30(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
SAM-30(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YR-22(D) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
YR-22(K) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged
SAM-30(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged
YR-24(G) Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Not Impinged Impinged

Risktec Solutions DMCC Page D.5 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.3: Jet Flame Stage 2 BRA Results (Part 3 of 3)

B-21 Oily Water


B-22 Operation
Hazard Sources Metering Shelter-
Shelter-2
Marafiq
X40-D-0015A(G) Not Impinged Not Impinged
X40-D-0015B(G) Not Impinged Impinged
X40-G-0020(G) Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged
G-5101(K) Not Impinged Not Impinged
D-0024(K) Not Impinged Not Impinged
D-0025(K) Not Impinged Not Impinged
X40-U-0014A(G) Not Impinged Not Impinged
X40-U-0014B(D) Not Impinged Not Impinged
X40-U-0014C(K) Not Impinged Not Impinged
X40-U-0014D(G) Not Impinged Not Impinged
X40-U-0014D(D) Not Impinged Not Impinged
X40-U-0014D(K) Not Impinged Not Impinged
L1-30(G) Not Impinged Not Impinged
L2-42(G) Not Impinged Not Impinged
L3-20(G) Not Impinged Not Impinged
L4-20(G) Not Impinged Not Impinged
L5-30(G) Not Impinged Not Impinged
L6-42(G) Not Impinged Not Impinged
L7-30(D) Not Impinged Not Impinged
L8-48(D) Not Impinged Not Impinged
L9-24(D) Not Impinged Not Impinged
L9-24(K) Not Impinged Not Impinged
L10-24(D) Not Impinged Not Impinged
L10-24(K) Not Impinged Not Impinged
L11-30(K) Not Impinged Not Impinged
L12-48(K) Not Impinged Not Impinged
L13-24(K) Not Impinged Not Impinged
L14-20(K) Not Impinged Not Impinged

Risktec Solutions DMCC Page D.6 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-21 Oily Water


B-22 Operation
Hazard Sources Metering Shelter-
Shelter-2
Marafiq
X40-G-0019(K) Not Impinged Not Impinged
Scraper-YNJ-1(G) Not Impinged Not Impinged
Scraper-YNJ-2(D) Not Impinged Not Impinged
Scraper-YNJ-2(K) Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged
X40-G-0020(G) Not Impinged Not Impinged
X40-G-0021(G) Not Impinged Not Impinged
X40-G-0018(D) Not Impinged Not Impinged
X40-G-0018(K) Not Impinged Not Impinged
X40-G-0019(D) Not Impinged Not Impinged
X40-G-XXX1(G) Not Impinged Not Impinged
X40-G-XXX2(K) Not Impinged Not Impinged
X40-G-XXX2(D) Not Impinged Not Impinged
X40-G-XXX3(G) Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged
X40-G-0019(K) Not Impinged Not Impinged
YNJ-1(G) Not Impinged Impinged
YNJ-2(D) Not Impinged Not Impinged
YNJ-2(K) Not Impinged Not Impinged
SAM-30(K) Not Impinged Not Impinged
YAS-30(G) Not Impinged Not Impinged
YAS-30(D) Not Impinged Not Impinged
SAM-30(D) Not Impinged Not Impinged
YR-22(D) Not Impinged Not Impinged
YR-22(K) Not Impinged Not Impinged
SAM-30(G) Not Impinged Not Impinged
YR-24(G) Not Impinged Not Impinged

Risktec Solutions DMCC Page D.7 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.4: Jet Fire Heat Flux Stage 2 BRA Results (Part 1 of 3)

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Hazard Sources Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
X40-D-0015A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0015B(G) >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) 12.5-35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
G-5101(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0024(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0025(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014B(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014C(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L1-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L2-42(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L3-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L4-20(G) >35 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L5-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L6-42(G) <4.7 >35 >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L7-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L8-48(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L11-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L12-48(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L13-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L14-20(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-1(G) >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.8 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Hazard Sources Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
Scraper-YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) 12.5-35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) 12.5-35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-1(G) >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YAS-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YAS-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-22(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-22(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-24(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.9 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.5: Jet Fire Heat Flux Stage 2 BRA Results (Part 2 of 3)

B-18 Sanitary B-19 Utility Water B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-D-0015A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0015B(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
G-5101(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0024(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0025(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
X40-U-0014B(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014C(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
X40-U-0014D(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L1-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
L2-42(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L3-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L4-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L5-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
L6-42(G) <4.7 <4.7 <4.7 <4.7 >35 <4.7 <4.7 <4.7 <4.7 <4.7
L7-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L8-48(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L11-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L12-48(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L13-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L14-20(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.10 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-18 Sanitary B-19 Utility Water B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YAS-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
YAS-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-22(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-22(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
YR-24(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35

Risktec Solutions DMCC Page D.11 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.6: Jet Fire Heat Flux Stage 2 BRA Results (Part 3 of 3)

B-21 Oily Water


B-22 Operation
Hazard Sources Metering Shelter-
Shelter-2
Marafiq
X40-D-0015A(G) <4.7 <4.7
X40-D-0015B(G) <4.7 >35
X40-G-0020(G) <4.7 <4.7
X40-G-0021(G) <4.7 12.5-35
X40-G-0018(D) <4.7 <4.7
X40-G-0018(K) <4.7 <4.7
X40-G-0019(D) <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7
G-5101(K) <4.7 <4.7
D-0024(K) <4.7 <4.7
D-0025(K) <4.7 <4.7
X40-U-0014A(G) <4.7 <4.7
X40-U-0014B(D) <4.7 <4.7
X40-U-0014C(K) <4.7 <4.7
X40-U-0014D(G) <4.7 <4.7
X40-U-0014D(D) <4.7 <4.7
X40-U-0014D(K) <4.7 <4.7
L1-30(G) <4.7 <4.7
L2-42(G) <4.7 <4.7
L3-20(G) <4.7 <4.7
L4-20(G) <4.7 >35
L5-30(G) <4.7 <4.7
L6-42(G) <4.7 <4.7
L7-30(D) <4.7 <4.7
L8-48(D) <4.7 <4.7
L9-24(D) <4.7 <4.7
L9-24(K) <4.7 <4.7
L10-24(D) <4.7 <4.7
L10-24(K) <4.7 <4.7
L11-30(K) <4.7 <4.7
L12-48(K) <4.7 <4.7
L13-24(K) <4.7 <4.7
L14-20(K) <4.7 <4.7

Risktec Solutions DMCC Page D.12 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-21 Oily Water


B-22 Operation
Hazard Sources Metering Shelter-
Shelter-2
Marafiq
X40-G-0019(K) <4.7 <4.7
Scraper-YNJ-1(G) 12.5-35 >35
Scraper-YNJ-2(D) <4.7 <4.7
Scraper-YNJ-2(K) <4.7 <4.7
X40-G-0020(G) <4.7 <4.7
X40-G-0021(G) <4.7 12.5-35
X40-G-0018(D) <4.7 <4.7
X40-G-0018(K) <4.7 <4.7
X40-G-0019(D) <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7
X40-G-0020(G) <4.7 <4.7
X40-G-0021(G) <4.7 12.5-35
X40-G-0018(D) <4.7 <4.7
X40-G-0018(K) <4.7 <4.7
X40-G-0019(D) <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7
X40-G-0019(K) <4.7 <4.7
X40-G-0019(K) <4.7 <4.7
YNJ-1(G) 4.7-12.5 12.5-35
YNJ-2(D) <4.7 <4.7
YNJ-2(K) <4.7 <4.7
SAM-30(K) <4.7 <4.7
YAS-30(G) <4.7 <4.7
YAS-30(D) <4.7 <4.7
SAM-30(D) <4.7 <4.7
YR-22(D) <4.7 <4.7
YR-22(K) <4.7 <4.7
SAM-30(G) <4.7 <4.7
YR-24(G) <4.7 <4.7

Risktec Solutions DMCC Page D.13 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.7: Pool Fire Heat Flux Stage 2 BRA Results (Part 1 of 3)

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Hazard Sources Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
X40-D-0015A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0015B(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
G-5101(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0024(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0025(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014B(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014C(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L1-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L2-42(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L3-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L4-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L5-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L6-42(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L7-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L8-48(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L11-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L12-48(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L13-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.14 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Hazard Sources Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
L14-20(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-1(G) >35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-2(D) 12.5-35 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YAS-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YAS-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-22(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-22(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YR-24(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.15 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.8: Pool Fire Heat Flux Stage 2 BRA Results (Part 2 of 3)

B-18 Sanitary B-19 Utility Water B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-D-0015A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0015B(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
G-5101(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0024(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
D-0025(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014A(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5
X40-U-0014B(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014C(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5
X40-U-0014D(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-U-0014D(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L1-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
L2-42(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L3-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L4-20(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L5-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
L6-42(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L7-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
L8-48(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L9-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L10-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L11-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
L12-48(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
L13-24(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
L14-20(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.16 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-18 Sanitary B-19 Utility Water B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Metering Shelter- Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Marafiq (Vendor Package)
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
Scraper-YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0020(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0021(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0018(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-G-0019(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
YNJ-1(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7
YNJ-2(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35 <4.7 <4.7
YNJ-2(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
SAM-30(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
YAS-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
YAS-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
SAM-30(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
YR-22(D) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
YR-22(K) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 12.5-35
SAM-30(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35
YR-24(G) <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 >35

Risktec Solutions DMCC Page D.17 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.9: Pool Fire Heat Flux Stage 2 BRA Results (Part 3 of 3)

B-21 Oily Water


B-22 Operation
Hazard Sources Metering
Shelter-2
Shelter-Marafiq
X40-D-0015A(G) <4.7 <4.7
X40-D-0015B(G) <4.7 12.5-35
X40-G-0020(G) <4.7 <4.7
X40-G-0021(G) <4.7 <4.7
X40-G-0018(D) <4.7 <4.7
X40-G-0018(K) <4.7 <4.7
X40-G-0019(D) <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7
G-5101(K) <4.7 <4.7
D-0024(K) <4.7 <4.7
D-0025(K) <4.7 <4.7
X40-U-0014A(G) <4.7 <4.7
X40-U-0014B(D) <4.7 <4.7
X40-U-0014C(K) <4.7 <4.7
X40-U-0014D(G) <4.7 <4.7
X40-U-0014D(D) <4.7 <4.7
X40-U-0014D(K) <4.7 <4.7
L1-30(G) <4.7 <4.7
L2-42(G) <4.7 <4.7
L3-20(G) <4.7 <4.7
L4-20(G) <4.7 <4.7
L5-30(G) <4.7 <4.7
L6-42(G) <4.7 <4.7
L7-30(D) <4.7 <4.7
L8-48(D) <4.7 <4.7
L9-24(D) <4.7 <4.7
L9-24(K) <4.7 <4.7
L10-24(D) <4.7 <4.7
L10-24(K) <4.7 <4.7
L11-30(K) <4.7 <4.7
L12-48(K) <4.7 <4.7
L13-24(K) <4.7 <4.7
L14-20(K) <4.7 <4.7

Risktec Solutions DMCC Page D.18 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-21 Oily Water


B-22 Operation
Hazard Sources Metering
Shelter-2
Shelter-Marafiq
X40-G-0019(K) <4.7 <4.7
Scraper-YNJ-1(G) <4.7 <4.7
Scraper-YNJ-2(D) <4.7 <4.7
Scraper-YNJ-2(K) <4.7 <4.7
X40-G-0020(G) <4.7 <4.7
X40-G-0021(G) <4.7 <4.7
X40-G-0018(D) <4.7 <4.7
X40-G-0018(K) <4.7 <4.7
X40-G-0019(D) <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7
X40-G-0020(G) <4.7 <4.7
X40-G-0021(G) <4.7 <4.7
X40-G-0018(D) <4.7 <4.7
X40-G-0018(K) <4.7 <4.7
X40-G-0019(D) <4.7 <4.7
X40-G-XXX1(G) <4.7 <4.7
X40-G-XXX2(K) <4.7 <4.7
X40-G-XXX2(D) <4.7 <4.7
X40-G-XXX3(G) <4.7 <4.7
X40-G-0019(K) <4.7 <4.7
X40-G-0019(K) <4.7 <4.7
YNJ-1(G) 4.7-12.5 12.5-35
YNJ-2(D) 12.5-35 12.5-35
YNJ-2(K) <4.7 <4.7
SAM-30(K) <4.7 <4.7
YAS-30(G) <4.7 <4.7
YAS-30(D) <4.7 <4.7
SAM-30(D) <4.7 <4.7
YR-22(D) <4.7 <4.7
YR-22(K) <4.7 <4.7
SAM-30(G) <4.7 <4.7
YR-24(G) <4.7 <4.7

Risktec Solutions DMCC Page D.19 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.10: Flammable Gas Dispersion Stage 2 BRA Results (Part 1 of 3)

B-01 SS-XXX1 B-02 SS-XXX2


B-03 RIB-XXX1 B-04 RIB-XXX2 B-09 Security B-10 Security
Receiving Utility Power B-06 Security B-07 Security B-08 X-Ray
Hazard Sources Remote I/O Remote I/O B-05 FSF Building Support Building Support Building
Substation Substation Guard House (A) Guard House (B) Building
Building Building (A) (B)
Transformer Yard Transformer Yard
X40-D-0015A(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0015B(G) 1/2LFL-LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0020(G) A <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0021(G) A 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX1(G) A <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX3(G) A <1/4LFL <1/4LFL <1/4LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-U-0014A(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-U-0014D(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L1-30(G) part1 <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L2-42(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L3-20(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L4-20(G) 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L5-30(G) part1 <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L6-42(G) <1/4LFL LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Scraper-YNJ-1(G) 1/2LFL-LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0020(G) B <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0021(G) B 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX1(G) B <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX3(G) B <1/4LFL <1/4LFL <1/4LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0020(G) C <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0021(G) C 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX1(G) C <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX3(G) C <1/4LFL <1/4LFL <1/4LFL 1/2LFL-LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
YNJ-1(G) LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
YAS-30(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
SAM-30(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
YR-24(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.20 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.11: Flammable Gas Dispersion Stage 2 BRA Results (Part 2 of 3)

B-18 Sanitary B-19 Utility B-20 Custody


B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources B-13 Musalla Metering Shelter- Water Metering Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Marafiq Shelter-Marafiq (Vendor Package)
X40-D-0015A(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0015B(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0020(G) A <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0021(G) A <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX1(G) A <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX3(G) A <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-U-0014A(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL
X40-U-0014D(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL
L1-30(G) part1 <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL
L2-42(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L3-20(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L4-20(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
L5-30(G) part1 <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL
L6-42(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Scraper-YNJ-1(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0020(G) B <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0021(G) B <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX1(G) B <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX3(G) B <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0020(G) C <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-0021(G) C <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX1(G) C <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-G-XXX3(G) C <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
YNJ-1(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
YAS-30(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL
SAM-30(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL
YR-24(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL

Risktec Solutions DMCC Page D.21 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.12: Flammable Gas Dispersion Stage 2 BRA Results (Part 3 of 3)

B-21 Oily Water


B-22 Operation
Hazard Sources Metering
Shelter-2
Shelter-Marafiq
X40-D-0015A(G) <1/4LFL <1/4LFL
X40-D-0015B(G) <1/4LFL LFL
X40-G-0020(G) A <1/4LFL <1/4LFL
X40-G-0021(G) A <1/4LFL 1/4LFL-1/2LFL
X40-G-XXX1(G) A <1/4LFL <1/4LFL
X40-G-XXX3(G) A <1/4LFL <1/4LFL
X40-U-0014A(G) <1/4LFL <1/4LFL
X40-U-0014D(G) <1/4LFL <1/4LFL
L1-30(G) part1 <1/4LFL <1/4LFL
L2-42(G) <1/4LFL <1/4LFL
L3-20(G) <1/4LFL <1/4LFL
L4-20(G) <1/4LFL 1/4LFL-1/2LFL
L5-30(G) part1 <1/4LFL <1/4LFL
L6-42(G) <1/4LFL <1/4LFL
Scraper-YNJ-1(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-G-0020(G) B <1/4LFL <1/4LFL
X40-G-0021(G) B <1/4LFL 1/4LFL-1/2LFL
X40-G-XXX1(G) B <1/4LFL <1/4LFL
X40-G-XXX3(G) B <1/4LFL <1/4LFL
X40-G-0020(G) C <1/4LFL <1/4LFL
X40-G-0021(G) C <1/4LFL 1/4LFL-1/2LFL
X40-G-XXX1(G) C <1/4LFL <1/4LFL
X40-G-XXX3(G) C <1/4LFL <1/4LFL
YNJ-1(G) 1/2LFL-LFL LFL
YAS-30(G) <1/4LFL <1/4LFL
SAM-30(G) <1/4LFL <1/4LFL
YR-24(G) <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.22 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.13: Storage Tanks Pool Fire Heat Flux Stage 2 BRA Results (Part 1 of 3)

B-02 SS-XXX2
B-01 SS-XXX1
Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
Receiving B-05 FSF B-08 X-Ray
Hazard Sources Fire Event Substation Remote I/O Remote I/O Guard House Guard House Support Support
Substation Building Building
Transformer Building Building (A) (B) Building (A) Building (B)
Transformer Yard
Yard
X40-D-0016A(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016A(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016A(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016B(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016B(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016B(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016C(G) Bund Fire <4.7 4.7-12.5 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016C(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016C(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0104(G) Bund Fire <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0104(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0104(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0205(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0205(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0205(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0006A(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5 4.7-12.5 <4.7 4.7-12.5
X40-D-0006B(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0006C(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0304(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0305(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018A(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018A(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018A(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018B(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018B(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018B(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018C(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018C(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018C(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0017(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0017(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0017(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0405(K) Bund Fire <4.7 4.7-12.5 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0405(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0405(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.23 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-02 SS-XXX2
B-01 SS-XXX1
Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
Receiving B-05 FSF B-08 X-Ray
Hazard Sources Fire Event Substation Remote I/O Remote I/O Guard House Guard House Support Support
Substation Building Building
Transformer Building Building (A) (B) Building (A) Building (B)
Transformer Yard
Yard
X40-D-0009(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5 4.7-12.5 <4.7 4.7-12.5
X40-D-0009(D) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(D) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5 4.7-12.5 <4.7 4.7-12.5
X40-D-0009(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002A(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002A(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002A(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002B(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002B(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002B(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002C(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002C(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002C(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0204(G) Bund Fire <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0204(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0204(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0501(G) Bund Fire <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0501(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0501(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX1(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX2(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX1(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX1(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX2(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX2(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX3(D) Bund Fire 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.24 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.14: Storage Tanks Pool Fire Heat Flux Stage 2 BRA Results (Part 2 of 3)

B-19 Utility B-20 Custody


B-18 Sanitary Water Metering
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources Event B-13 Musalla Metering Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Shelter-Marafiq Shelter- (Vendor
Marafiq Package)
X40-D-0016A(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016A(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016A(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016B(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016B(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016B(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016C(G) Bund Fire <4.7 <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016C(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0016C(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0104(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0104(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0104(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0205(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0205(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0205(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0006A(D) Bund Fire <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0006B(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0006C(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0304(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0305(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018A(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018A(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018A(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018B(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018B(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018B(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018C(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018C(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0018C(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0017(K) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5
X40-D-0017(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0017(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0405(K) Bund Fire <4.7 <4.7 <4.7 <4.7 4.7-12.5 4.7-12.5 <4.7 <4.7 <4.7 <4.7
X40-D-0405(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0405(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.25 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-19 Utility B-20 Custody


B-18 Sanitary Water Metering
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS
Hazard Sources Event B-13 Musalla Metering Metering Shelter
Building Building Shelter Shelter Shelter-001 Shelter-002
Shelter-Marafiq Shelter- (Vendor
Marafiq Package)
X40-D-0009(D) Bund Fire <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(D) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(D) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(K) Bund Fire <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(K) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0009(K) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002A(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002A(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002A(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002B(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002B(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002B(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002C(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002C(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0002C(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0204(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0204(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0204(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0501(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7 <4.7
X40-D-0501(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-0501(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX1(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX2(G) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 4.7-12.5 <4.7 <4.7 <4.7
X40-D-XXX1(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX1(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX2(G) Tank Top Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX2(G) Rim Seal Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7
X40-D-XXX3(D) Bund Fire <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7 <4.7

Risktec Solutions DMCC Page D.26 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.15: Storage Tanks Pool Fire Heat Flux Stage 2 BRA Results (Part 3 of 3)

B-21 Oily Water


B-22 Operation
Hazard Sources Event Metering Shelter-
Shelter-2
Marafiq
X40-D-0016A(G) Bund Fire <4.7 <4.7
X40-D-0016A(G) Tank Top Fire <4.7 <4.7
X40-D-0016A(G) Rim Seal Fire <4.7 <4.7
X40-D-0016B(G) Bund Fire <4.7 <4.7
X40-D-0016B(G) Tank Top Fire <4.7 <4.7
X40-D-0016B(G) Rim Seal Fire <4.7 <4.7
X40-D-0016C(G) Bund Fire <4.7 <4.7
X40-D-0016C(G) Tank Top Fire <4.7 <4.7
X40-D-0016C(G) Rim Seal Fire <4.7 <4.7
X40-D-0104(G) Bund Fire <4.7 <4.7
X40-D-0104(G) Tank Top Fire <4.7 <4.7
X40-D-0104(G) Rim Seal Fire <4.7 <4.7
X40-D-0205(G) Bund Fire <4.7 <4.7
X40-D-0205(G) Tank Top Fire <4.7 <4.7
X40-D-0205(G) Rim Seal Fire <4.7 <4.7
X40-D-0006A(D) Bund Fire <4.7 <4.7
X40-D-0006B(D) Bund Fire <4.7 <4.7
X40-D-0006C(D) Bund Fire <4.7 <4.7
X40-D-0304(D) Bund Fire <4.7 <4.7
X40-D-0305(D) Bund Fire <4.7 <4.7
X40-D-0018A(K) Bund Fire <4.7 <4.7
X40-D-0018A(K) Tank Top Fire <4.7 <4.7
X40-D-0018A(K) Rim Seal Fire <4.7 <4.7
X40-D-0018B(K) Bund Fire <4.7 <4.7
X40-D-0018B(K) Tank Top Fire <4.7 <4.7
X40-D-0018B(K) Rim Seal Fire <4.7 <4.7
X40-D-0018C(K) Bund Fire <4.7 <4.7
X40-D-0018C(K) Tank Top Fire <4.7 <4.7
X40-D-0018C(K) Rim Seal Fire <4.7 <4.7
X40-D-0017(K) Bund Fire <4.7 <4.7
X40-D-0017(K) Tank Top Fire <4.7 <4.7
X40-D-0017(K) Rim Seal Fire <4.7 <4.7
X40-D-0405(K) Bund Fire <4.7 <4.7
X40-D-0405(K) Tank Top Fire <4.7 <4.7
X40-D-0405(K) Rim Seal Fire <4.7 <4.7
X40-D-0009(D) Bund Fire <4.7 <4.7

Risktec Solutions DMCC Page D.27 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-21 Oily Water


B-22 Operation
Hazard Sources Event Metering Shelter-
Shelter-2
Marafiq
X40-D-0009(D) Tank Top Fire <4.7 <4.7
X40-D-0009(D) Rim Seal Fire <4.7 <4.7
X40-D-0009(K) Bund Fire <4.7 <4.7
X40-D-0009(K) Tank Top Fire <4.7 <4.7
X40-D-0009(K) Rim Seal Fire <4.7 <4.7
X40-D-0002A(G) Bund Fire <4.7 <4.7
X40-D-0002A(G) Tank Top Fire <4.7 <4.7
X40-D-0002A(G) Rim Seal Fire <4.7 <4.7
X40-D-0002B(G) Bund Fire <4.7 <4.7
X40-D-0002B(G) Tank Top Fire <4.7 <4.7
X40-D-0002B(G) Rim Seal Fire <4.7 <4.7
X40-D-0002C(G) Bund Fire <4.7 <4.7
X40-D-0002C(G) Tank Top Fire <4.7 <4.7
X40-D-0002C(G) Rim Seal Fire <4.7 <4.7
X40-D-0204(G) Bund Fire <4.7 <4.7
X40-D-0204(G) Tank Top Fire <4.7 <4.7
X40-D-0204(G) Rim Seal Fire <4.7 <4.7
X40-D-0501(G) Bund Fire <4.7 <4.7
X40-D-0501(G) Tank Top Fire <4.7 <4.7
X40-D-0501(G) Rim Seal Fire <4.7 <4.7
X40-D-XXX1(G) Bund Fire <4.7 <4.7
X40-D-XXX2(G) Bund Fire <4.7 <4.7
X40-D-XXX1(G) Tank Top Fire <4.7 <4.7
X40-D-XXX1(G) Rim Seal Fire <4.7 <4.7
X40-D-XXX2(G) Tank Top Fire <4.7 <4.7
X40-D-XXX2(G) Rim Seal Fire <4.7 <4.7
X40-D-XXX3(D) Bund Fire <4.7 4.7-12.5

Risktec Solutions DMCC Page D.28 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.16: Storage Tanks Flammable Gas Dispersion Stage 2 BRA Results (Part 1 of 3)

B-01 SS-XXX1 B-02 SS-XXX2


Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Hazard Sources Event Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
X40-D-0016A(G) Bund Vapourisation 1/2LFL-LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0016A(G) Tank Sunken Roof <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016A(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016B(G) Bund Vapourisation 1/2LFL-LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0016B(G) Tank Sunken Roof <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016B(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016C(G) Bund Vapourisation 1/4LFL-1/2LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/2LFL-LFL
X40-D-0016C(G) Tank Sunken Roof <1/4LFL 1/2LFL-LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016C(G) Spill On Roof <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0104(G) Bund Vapourisation LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0104(G) Tank Sunken Roof 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0104(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0205(G) Bund Vapourisation 1/2LFL-LFL 1/2LFL-LFL 1/2LFL-LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0205(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0205(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0002A(G) Bund Vapourisation 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0002A(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0002A(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0002B(G) Bund Vapourisation 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0002B(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0002B(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0002C(G) Bund Vapourisation 1/4LFL-1/2LFL LFL LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/2LFL-LFL
X40-D-0002C(G) Tank Sunken Roof <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0002C(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0204(G) Bund Vapourisation LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0204(G) Tank Sunken Roof 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0204(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0501(G) Bund Vapourisation 1/2LFL-LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/2LFL-LFL
X40-D-0501(G) Tank Sunken Roof <1/4LFL 1/2LFL-LFL LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0501(G) Spill On Roof <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX1(G) Bund Vapourisation LFL 1/4LFL-1/2LFL 1/2LFL-LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX2(G) Tank Sunken Roof 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX1(G) Spill On Roof 1/2LFL-LFL <1/4LFL <1/4LFL 1/2LFL-LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX1(G) Bund Vapourisation <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX2(G) Tank Sunken Roof 1/4LFL-1/2LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX2(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.29 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.17: Storage Tanks Flammable Gas Dispersion Stage 2 BRA Results (Part 2 of 3)

B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Hazard Sources Event B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter -Marafiq
Package)
Bund
X40-D-0016A(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0016A(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016A(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0016B(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0016B(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0016B(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0016C(G) 1/4LFL-1/2LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL
Vapourisation
X40-D-0016C(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL
X40-D-0016C(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0104(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0104(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0104(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0205(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0205(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0205(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0002A(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL 1/2LFL-LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL
Vapourisation
X40-D-0002A(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL
X40-D-0002A(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0002B(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/2LFL-LFL <1/4LFL <1/4LFL LFL
Vapourisation
X40-D-0002B(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL
X40-D-0002B(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0002C(G) 1/4LFL-1/2LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL
Vapourisation
X40-D-0002C(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL
X40-D-0002C(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0204(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL LFL LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL
Vapourisation
X40-D-0204(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-0204(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-0501(G) 1/2LFL-LFL 1/2LFL-LFL 1/2LFL-LFL 1/2LFL-LFL LFL LFL 1/2LFL-LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0501(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/2LFL-LFL LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.30 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Hazard Sources Event B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter -Marafiq
Package)
X40-D-0501(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-XXX1(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/2LFL-LFL 1/4LFL-1/2LFL LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL
Vapourisation
X40-D-XXX2(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL 1/4LFL-1/2LFL LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL
X40-D-XXX1(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL
Bund
X40-D-XXX1(G) <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL
Vapourisation
X40-D-XXX2(G) Tank Sunken Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL LFL <1/4LFL <1/4LFL <1/4LFL
X40-D-XXX2(G) Spill On Roof <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL <1/4LFL 1/4LFL-1/2LFL <1/4LFL <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.31 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.18: Storage Tanks Flammable Gas Dispersion Stage 2 BRA Results (Part 3 of 3)

B-21 Oily Water


B-22 Operation
Hazard Sources Event Metering
Shelter-2
Shelter-Marafiq
Bund
X40-D-0016A(G) 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0016A(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0016A(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0016B(G) 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0016B(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0016B(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0016C(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL
Vapourisation
X40-D-0016C(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0016C(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0104(G) LFL LFL
Vapourisation
X40-D-0104(G) Tank Sunken Roof 1/4LFL-1/2LFL 1/4LFL-1/2LFL
X40-D-0104(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0205(G) 1/4LFL-1/2LFL 1/2LFL-LFL
Vapourisation
X40-D-0205(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0205(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0002A(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL
Vapourisation
X40-D-0002A(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0002A(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0002B(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL
Vapourisation
X40-D-0002B(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0002B(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0002C(G) 1/4LFL-1/2LFL 1/4LFL-1/2LFL
Vapourisation
X40-D-0002C(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0002C(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0204(G) 1/2LFL-LFL LFL
Vapourisation
X40-D-0204(G) Tank Sunken Roof <1/4LFL 1/4LFL-1/2LFL
X40-D-0204(G) Spill On Roof <1/4LFL <1/4LFL
Bund
X40-D-0501(G) 1/2LFL-LFL 1/2LFL-LFL
Vapourisation
X40-D-0501(G) Tank Sunken Roof <1/4LFL <1/4LFL
X40-D-0501(G) Spill On Roof <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.32 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

B-21 Oily Water


B-22 Operation
Hazard Sources Event Metering
Shelter-2
Shelter-Marafiq
Bund
X40-D-XXX1(G) 1/2LFL-LFL LFL
Vapourisation
X40-D-XXX2(G) Tank Sunken Roof 1/4LFL-1/2LFL 1/2LFL-LFL
X40-D-XXX1(G) Spill On Roof <1/4LFL 1/2LFL-LFL
Bund
X40-D-XXX1(G) <1/4LFL <1/4LFL
Vapourisation
X40-D-XXX2(G) Tank Sunken Roof <1/4LFL 1/4LFL-1/2LFL
X40-D-XXX2(G) Spill On Roof <1/4LFL <1/4LFL

Risktec Solutions DMCC Page D.33 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.19: Congested Area Explosions Stage 2 BRA Results (Part 1 of 3)

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
DPK Filtration
CA-01 DPK Filtration Skid 0.00 0.03 0.03 0.01 0.01 0.01 0.01 0.03 0.01 0.03
Skid
CA-02 PS-003 PS-003 0.00 0.03 0.03 0.01 0.00 0.01 0.01 0.01 0.01 0.01
CA-03 PS-009 PS-009 0.00 0.04 0.03 0.01 0.00 0.01 0.01 0.01 0.01 0.01
CA-04 PS-001 PS-001 0.01 0.01 0.03 0.01 0.00 0.00 0.00 0.00 0.00 0.00
CA-05 PS-008 PS-008 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
CA-06 PS-010 PS-010 0.03 0.03 0.03 0.15 0.01 0.01 0.01 0.01 0.01 0.01
CA-07 PS-004 PS-004 0.06 0.01 0.01 0.09 0.00 0.01 0.01 0.01 0.01 0.01
CA-08 PS-002 PS-002 0.09 0.01 0.01 0.04 0.00 0.00 0.01 0.01 0.00 0.01
Shaded
Shaded Parking Area
CA-09 Parking Area 0.01 0.01 0.01 0.01 0.22 0.32 0.07 0.07 0.30 0.07
(External)
(External)
Assembly
Point & Assembly Point &
CA-10 0.03 0.04 0.04 0.03 0.16 0.19 0.46 0.35 0.22 0.36
Shaded Shaded Parking Area
Parking Area
Custody
Meter & Custody Meter &
CA-11 0.01 0.03 0.03 0.01 0.01 0.01 0.01 0.01 0.01 0.01
Receiving Receiving Manifold
Manifold
Pipe Rack (along PS-
CA-12A Pipe Rack 001/002/003/004/008/ 0.00 0.01 0.01 0.00 0.01 0.01 0.03 0.03 0.01 0.04
009/010)
Pipe Rack (along PS-
CA-12AA Pipe Rack 001/002/003/004/008/ 0.06 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
009/010)
Pipe Rack (along PS-
CA-12AB Pipe Rack 001/002/003/004/008/ 0.10 0.01 0.01 0.06 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12AC Pipe Rack 001/002/003/004/008/ 0.01 0.03 0.01 0.01 0.03 0.04 0.12 0.12 0.04 0.16
009/010)
Pipe Rack (along PS-
CA-12B Pipe Rack 001/002/003/004/008/ 0.01 0.03 0.03 0.01 0.03 0.03 0.07 0.07 0.04 0.07
009/010)
Pipe Rack (along PS-
CA-12C Pipe Rack 001/002/003/004/008/ 0.01 0.03 0.03 0.01 0.03 0.03 0.06 0.06 0.03 0.06
009/010)
Pipe Rack (along PS-
CA-12D Pipe Rack 001/002/003/004/008/ 0.01 0.06 0.04 0.01 0.01 0.03 0.03 0.03 0.03 0.03
009/010)

Risktec Solutions DMCC Page D.34 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe Rack (along PS-
CA-12E Pipe Rack 001/002/003/004/008/ 0.01 0.07 0.06 0.01 0.01 0.01 0.03 0.03 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12F Pipe Rack 001/002/003/004/008/ 0.01 0.04 0.04 0.01 0.01 0.03 0.03 0.04 0.03 0.04
009/010)
Pipe Rack (along PS-
CA-12G Pipe Rack 001/002/003/004/008/ 0.01 0.04 0.03 0.01 0.03 0.03 0.04 0.04 0.03 0.04
009/010)
Pipe Rack (along PS-
CA-12H Pipe Rack 001/002/003/004/008/ 0.01 0.20 0.10 0.01 0.01 0.01 0.03 0.03 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12I Pipe Rack 001/002/003/004/008/ 0.01 0.46 0.23 0.03 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12J Pipe Rack 001/002/003/004/008/ 0.01 0.20 0.36 0.03 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12K Pipe Rack 001/002/003/004/008/ 0.01 0.10 0.07 0.01 0.01 0.01 0.03 0.03 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12L Pipe Rack 001/002/003/004/008/ 0.01 0.10 0.19 0.03 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12M Pipe Rack 001/002/003/004/008/ 0.01 0.07 0.12 0.03 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12N Pipe Rack 001/002/003/004/008/ 0.01 0.06 0.07 0.04 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12O Pipe Rack 001/002/003/004/008/ 0.01 0.04 0.06 0.04 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12P Pipe Rack 001/002/003/004/008/ 0.03 0.04 0.04 0.06 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12Q Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.04 0.07 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12R Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.03 0.10 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12S Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.03 0.16 0.01 0.01 0.01 0.01 0.01 0.01
009/010)

Risktec Solutions DMCC Page D.35 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe Rack (along PS-
CA-12T Pipe Rack 001/002/003/004/008/ 0.04 0.03 0.03 0.38 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12U Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.03 0.32 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12V Pipe Rack 001/002/003/004/008/ 0.04 0.01 0.03 0.17 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12W Pipe Rack 001/002/003/004/008/ 0.06 0.01 0.01 0.12 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12X Pipe Rack 001/002/003/004/008/ 0.07 0.01 0.01 0.06 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12Y Pipe Rack 001/002/003/004/008/ 0.07 0.01 0.01 0.09 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12Z Pipe Rack 001/002/003/004/008/ 0.09 0.01 0.01 0.06 0.01 0.01 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (east of pipe
CA-13A Pipe Rack 0.01 0.03 0.03 0.01 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13B Pipe Rack 0.01 0.03 0.03 0.01 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13C Pipe Rack 0.01 0.04 0.03 0.01 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13D Pipe Rack 0.01 0.04 0.04 0.01 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13E Pipe Rack 0.01 0.04 0.04 0.01 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13F Pipe Rack 0.01 0.06 0.06 0.01 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13G Pipe Rack 0.00 0.03 0.03 0.01 0.00 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13H Pipe Rack 0.01 0.09 0.07 0.03 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13I Pipe Rack 0.01 0.17 0.13 0.03 0.01 0.01 0.01 0.01 0.01 0.01
culvert/RC corridor)
Pipe Rack (south of
CA-14A Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14B Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)

Risktec Solutions DMCC Page D.36 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe Rack (south of
CA-14C Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14D Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14E Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14F Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14G Pipe Rack DO tanks X40-D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0301/0302/0303)
Pipe rack (north of
DPK tanks X40-D-
CA-15A Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15B Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15C Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15D Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15E Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15F Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15G Pipe Rack 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16A Pipe Rack 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)

Risktec Solutions DMCC Page D.37 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16B Pipe Rack 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16C Pipe Rack 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16D Pipe Rack 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16E Pipe Rack 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16F Pipe Rack 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16G Pipe Rack 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
D-0101/0102/
0201/0202)
Pipe rack (north of
CA-17A Pipe Rack PG91 tanks X40-D- 0.00 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17B Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17C Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17D Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17E Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17F Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17G Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)

Risktec Solutions DMCC Page D.38 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe rack (north of
CA-18A Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.06 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-18B Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.04 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-18C Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-18D Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-18E Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-18F Pipe Rack PG91 tanks X40-D- 0.01 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (west of
CA-19A Pipe Rack DO/DPK tanks X-40D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19B Pipe Rack DO/DPK tanks X-40D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19C Pipe Rack DO/DPK tanks X-40D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19D Pipe Rack DO/DPK tanks X-40D- 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19E Pipe Rack DO/DPK tanks X-40D- 0.00 0.03 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19F Pipe Rack DO/DPK tanks X-40D- 0.00 0.03 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19G Pipe Rack DO/DPK tanks X-40D- 0.00 0.03 0.03 0.01 0.00 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19H Pipe Rack DO/DPK tanks X-40D- 0.00 0.04 0.03 0.01 0.00 0.01 0.01 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19I Pipe Rack DO/DPK tanks X-40D- 0.00 0.07 0.04 0.01 0.00 0.00 0.01 0.01 0.01 0.01
0304/0305/0405)

Risktec Solutions DMCC Page D.39 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe rack (west of
CA-19J Pipe Rack DO/DPK tanks X-40D- 0.00 0.15 0.07 0.01 0.00 0.00 0.01 0.01 0.00 0.01
0304/0305/0405)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20A Pipe Rack 0.01 0.03 0.04 0.01 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20B Pipe Rack 0.01 0.03 0.03 0.01 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20C Pipe Rack 0.01 0.01 0.03 0.01 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20D Pipe Rack 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20E Pipe Rack 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20F Pipe Rack 0.01 0.01 0.01 0.03 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20G Pipe Rack 0.01 0.01 0.01 0.04 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20H Pipe Rack 0.01 0.01 0.01 0.07 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.01 0.01 0.01 0.15 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.03 0.01 0.01 0.06 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.03 0.01 0.01 0.04 0.00 0.00 0.00 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)

Risktec Solutions DMCC Page D.40 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-01 SS-XXX1 B-02 SS-XXX2
Receiving Utility Power B-03 RIB-XXX1 B-04 RIB-XXX2 B-06 Security B-07 Security B-09 Security B-10 Security
B-05 FSF B-08 X-Ray
Number Description Location Substation Substation Remote I/O Remote I/O Guard House Guard House Support Support
Building Building
Transformer Transformer Building Building (A) (B) Building (A) Building (B)
Yard Yard
Pipe Culvert Pipe Culvert (RC
CA-22 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
(RC Corridor) Corridor)
CA-23 PS-007 Slop Pump Shelter 0.03 0.06 0.06 0.04 0.03 0.03 0.03 0.03 0.03 0.03
Note: CA-21 is not used due to the congested area being removed during the design stages.

Risktec Solutions DMCC Page D.41 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.20: Congested Area Explosions Stage 2 BRA Results (Part 2 of 3)

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
DPK Filtration
CA-01 DPK Filtration Skid 0.01 0.03 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
Skid
CA-02 PS-003 PS-003 0.01 0.01 0.01 0.01 0.03 0.01 0.00 0.01 0.01 0.01
CA-03 PS-009 PS-009 0.01 0.01 0.01 0.01 0.04 0.01 0.00 0.01 0.01 0.01
CA-04 PS-001 PS-001 0.00 0.00 0.00 0.00 0.03 0.01 0.01 0.00 0.00 0.01
CA-05 PS-008 PS-008 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
CA-06 PS-010 PS-010 0.01 0.01 0.01 0.01 0.03 0.03 0.01 0.01 0.01 0.01
CA-07 PS-004 PS-004 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
CA-08 PS-002 PS-002 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.00 0.00 0.01
Shaded
Shaded Parking Area
CA-09 Parking Area 0.13 0.06 0.13 0.12 0.01 0.01 0.01 0.12 0.10 0.01
(External)
(External)
Assembly
Point & Assembly Point &
CA-10 0.33 0.31 0.23 0.39 0.04 0.04 0.01 0.44 0.44 0.04
Shaded Shaded Parking Area
Parking Area
Custody
Meter & Custody Meter &
CA-11 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01 0.01 0.16
Receiving Receiving Manifold
Manifold
Pipe Rack (along PS-
CA-12A Pipe Rack 001/002/003/004/008/ 0.01 0.04 0.01 0.01 0.01 0.00 0.00 0.01 0.01 0.00
009/010)
Pipe Rack (along PS-
CA-12AA Pipe Rack 001/002/003/004/008/ 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.00
009/010)
Pipe Rack (along PS-
CA-12AB Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12AC Pipe Rack 001/002/003/004/008/ 0.06 0.25 0.06 0.07 0.03 0.01 0.01 0.04 0.04 0.01
009/010)
Pipe Rack (along PS-
CA-12B Pipe Rack 001/002/003/004/008/ 0.04 0.09 0.04 0.04 0.03 0.01 0.01 0.03 0.03 0.01
009/010)
Pipe Rack (along PS-
CA-12C Pipe Rack 001/002/003/004/008/ 0.04 0.06 0.04 0.04 0.03 0.03 0.01 0.03 0.03 0.03
009/010)
Pipe Rack (along PS-
CA-12D Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.03 0.03 0.04 0.03 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12E Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.03 0.03 0.06 0.03 0.01 0.01 0.01 0.03
009/010)

Risktec Solutions DMCC Page D.42 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
Pipe Rack (along PS-
CA-12F Pipe Rack 001/002/003/004/008/ 0.03 0.04 0.03 0.03 0.04 0.03 0.01 0.03 0.03 0.03
009/010)
Pipe Rack (along PS-
CA-12G Pipe Rack 001/002/003/004/008/ 0.03 0.04 0.03 0.03 0.03 0.03 0.01 0.03 0.03 0.03
009/010)
Pipe Rack (along PS-
CA-12H Pipe Rack 001/002/003/004/008/ 0.01 0.03 0.01 0.01 0.15 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12I Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.49 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12J Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.35 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12K Pipe Rack 001/002/003/004/008/ 0.03 0.03 0.03 0.01 0.09 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12L Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.13 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12M Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.09 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12N Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.06 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12O Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.04 0.04 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12P Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.04 0.03 0.01 0.01 0.01 0.03
009/010)
Pipe Rack (along PS-
CA-12Q Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.03 0.03 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12R Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.03 0.03 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12S Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.03 0.03 0.01 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12T Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.03 0.03 0.03 0.01 0.01 0.01
009/010)

Risktec Solutions DMCC Page D.43 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
Pipe Rack (along PS-
CA-12U Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.03 0.03 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12V Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12W Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12X Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12Y Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (along PS-
CA-12Z Pipe Rack 001/002/003/004/008/ 0.01 0.01 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01
009/010)
Pipe Rack (east of pipe
CA-13A Pipe Rack 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01 0.01 0.39
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13B Pipe Rack 0.01 0.01 0.01 0.01 0.03 0.01 0.01 0.01 0.01 0.16
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13C Pipe Rack 0.01 0.01 0.01 0.01 0.04 0.01 0.01 0.01 0.01 0.10
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13D Pipe Rack 0.01 0.01 0.01 0.01 0.04 0.03 0.01 0.01 0.01 0.07
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13E Pipe Rack 0.01 0.01 0.01 0.01 0.04 0.03 0.01 0.01 0.01 0.06
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13F Pipe Rack 0.01 0.01 0.01 0.01 0.06 0.03 0.01 0.01 0.01 0.04
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13G Pipe Rack 0.01 0.01 0.01 0.01 0.03 0.01 0.00 0.00 0.00 0.01
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13H Pipe Rack 0.01 0.01 0.01 0.01 0.09 0.03 0.01 0.01 0.01 0.04
culvert/RC corridor)
Pipe Rack (east of pipe
CA-13I Pipe Rack 0.01 0.01 0.01 0.01 0.17 0.04 0.01 0.01 0.01 0.03
culvert/RC corridor)
Pipe Rack (south of
CA-14A Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14B Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14C Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)

Risktec Solutions DMCC Page D.44 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
Pipe Rack (south of
CA-14D Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14E Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14F Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)
Pipe Rack (south of
CA-14G Pipe Rack DO tanks X40-D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0301/0302/0303)
Pipe rack (north of
DPK tanks X40-D-
CA-15A Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15B Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15C Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15D Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15E Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15F Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15G Pipe Rack 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0401/0402/
0403/0404)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16A Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16B Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)

Risktec Solutions DMCC Page D.45 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16C Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16D Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16E Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16F Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks X40-
CA-16G Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
D-0101/0102/
0201/0202)
Pipe rack (north of
CA-17A Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.00 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17B Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17C Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17D Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17E Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17F Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17G Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-18A Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.00
0204/0205)
Pipe rack (north of
CA-18B Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)

Risktec Solutions DMCC Page D.46 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
Pipe rack (north of
CA-18C Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-18D Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-18E Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (north of
CA-18F Pipe Rack PG91 tanks X40-D- 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.00 0.00 0.01
0204/0205)
Pipe rack (west of
CA-19A Pipe Rack DO/DPK tanks X-40D- 0.01 0.03 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19B Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19C Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19D Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19E Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19F Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.03 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19G Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.03 0.01 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19H Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.04 0.03 0.00 0.01 0.01 0.01
0304/0305/0405)
Pipe rack (west of
CA-19I Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.06 0.03 0.00 0.00 0.00 0.01
0304/0305/0405)
Pipe rack (west of
CA-19J Pipe Rack DO/DPK tanks X-40D- 0.01 0.01 0.01 0.01 0.09 0.03 0.00 0.00 0.00 0.01
0304/0305/0405)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20A Pipe Rack 0.00 0.00 0.00 0.00 0.03 0.03 0.00 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)

Risktec Solutions DMCC Page D.47 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Congested Areas Explosion Overpressure at Buildings (psi)


B-20 Custody
B-18 Sanitary B-19 Utility
B-11 OME B-12 Operation B-14 Chemical B-15 Operation B-16 IDAS B-17 IDAS Metering
Number Description Location B-13 Musalla Metering Water Metering
Building Building Shelter Shelter Shelter-001 Shelter-002 Shelter (Vendor
Shelter-Marafiq Shelter-Marafiq
Package)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20B Pipe Rack 0.00 0.00 0.00 0.00 0.03 0.03 0.00 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20C Pipe Rack 0.00 0.00 0.00 0.00 0.03 0.01 0.00 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20D Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.00 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20E Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20F Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20G Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20H Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.00 0.00 0.00 0.00 0.01 0.01 0.01 0.00 0.00 0.00
X40-D-0501/
0104/XXX3)
Pipe Culvert Pipe Culvert (RC
CA-22 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.09
(RC Corridor) Corridor)
CA-23 PS-007 Slop Pump Shelter 0.03 0.03 0.03 0.03 0.01 0.04 0.04 0.00 0.00 0.22
Note: CA-21 is not used due to the congested area being removed during the design stages.

Risktec Solutions DMCC Page D.48 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.21: Congested Area Explosions Stage 2 BRA Results (Part 3 of 3)

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
DPK Filtration
CA-01 DPK Filtration Skid 0.01 0.01
Skid
CA-02 PS-003 PS-003 0.00 0.00
CA-03 PS-009 PS-009 0.00 0.00
CA-04 PS-001 PS-001 0.01 0.01
CA-05 PS-008 PS-008 0.01 0.01
CA-06 PS-010 PS-010 0.01 0.03
CA-07 PS-004 PS-004 0.03 0.04
CA-08 PS-002 PS-002 0.03 0.09
Shaded
Shaded Parking Area
CA-09 Parking Area 0.01 0.01
(External)
(External)
Assembly Point
Assembly Point &
CA-10 & Shaded 0.01 0.01
Shaded Parking Area
Parking Area
Custody Meter
Custody Meter &
CA-11 & Receiving 0.01 0.01
Receiving Manifold
Manifold
Pipe Rack (along PS-
CA-12A Pipe Rack 001/002/003/004/008 0.00 0.00
/009/010)
Pipe Rack (along PS-
CA-12AA Pipe Rack 001/002/003/004/008 0.01 0.06
/009/010)
Pipe Rack (along PS-
CA-12AB Pipe Rack 001/002/003/004/008 0.03 0.10
/009/010)
Pipe Rack (along PS-
CA-12AC Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12B Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12C Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12D Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12E Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)

Risktec Solutions DMCC Page D.49 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
Pipe Rack (along PS-
CA-12F Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12G Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12H Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12I Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12J Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12K Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12L Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12M Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12N Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12O Pipe Rack 001/002/003/004/008 0.01 0.01
/009/010)
Pipe Rack (along PS-
CA-12P Pipe Rack 001/002/003/004/008 0.01 0.03
/009/010)
Pipe Rack (along PS-
CA-12Q Pipe Rack 001/002/003/004/008 0.01 0.03
/009/010)
Pipe Rack (along PS-
CA-12R Pipe Rack 001/002/003/004/008 0.01 0.03
/009/010)
Pipe Rack (along PS-
CA-12S Pipe Rack 001/002/003/004/008 0.01 0.03
/009/010)
Pipe Rack (along PS-
CA-12T Pipe Rack 001/002/003/004/008 0.03 0.04
/009/010)
Pipe Rack (along PS-
CA-12U Pipe Rack 001/002/003/004/008 0.03 0.03
/009/010)

Risktec Solutions DMCC Page D.50 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
Pipe Rack (along PS-
CA-12V Pipe Rack 001/002/003/004/008 0.03 0.04
/009/010)
Pipe Rack (along PS-
CA-12W Pipe Rack 001/002/003/004/008 0.03 0.06
/009/010)
Pipe Rack (along PS-
CA-12X Pipe Rack 001/002/003/004/008 0.03 0.07
/009/010)
Pipe Rack (along PS-
CA-12Y Pipe Rack 001/002/003/004/008 0.03 0.06
/009/010)
Pipe Rack (along PS-
CA-12Z Pipe Rack 001/002/003/004/008 0.03 0.09
/009/010)
Pipe Rack (east of
CA-13A Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13B Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13C Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13D Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13E Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13F Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13G Pipe Rack pipe culvert/RC 0.00 0.00
corridor)
Pipe Rack (east of
CA-13H Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (east of
CA-13I Pipe Rack pipe culvert/RC 0.01 0.01
corridor)
Pipe Rack (south of
CA-14A Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)
Pipe Rack (south of
CA-14B Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)

Risktec Solutions DMCC Page D.51 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
Pipe Rack (south of
CA-14C Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)
Pipe Rack (south of
CA-14D Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)
Pipe Rack (south of
CA-14E Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)
Pipe Rack (south of
CA-14F Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)
Pipe Rack (south of
CA-14G Pipe Rack DO tanks X40-D- 0.00 0.00
0301/0302/0303)
Pipe rack (north of
DPK tanks X40-D-
CA-15A Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15B Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15C Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15D Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15E Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15F Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (north of
DPK tanks X40-D-
CA-15G Pipe Rack 0.00 0.00
0401/0402/
0403/0404)
Pipe rack (south of
PG91/PG95 tanks
CA-16A Pipe Rack 0.01 0.01
X40-D-0101/0102/
0201/0202)

Risktec Solutions DMCC Page D.52 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
Pipe rack (south of
PG91/PG95 tanks
CA-16B Pipe Rack 0.00 0.01
X40-D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks
CA-16C Pipe Rack 0.00 0.01
X40-D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks
CA-16D Pipe Rack 0.00 0.01
X40-D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks
CA-16E Pipe Rack 0.00 0.01
X40-D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks
CA-16F Pipe Rack 0.00 0.01
X40-D-0101/0102/
0201/0202)
Pipe rack (south of
PG91/PG95 tanks
CA-16G Pipe Rack 0.00 0.01
X40-D-0101/0102/
0201/0202)
Pipe rack (north of
CA-17A Pipe Rack PG91 tanks X40-D- 0.00 0.00
0204/0205)
Pipe rack (north of
CA-17B Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)
Pipe rack (north of
CA-17C Pipe Rack PG91 tanks X40-D- 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17D Pipe Rack PG91 tanks X40-D- 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17E Pipe Rack PG91 tanks X40-D- 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17F Pipe Rack PG91 tanks X40-D- 0.00 0.01
0204/0205)
Pipe rack (north of
CA-17G Pipe Rack PG91 tanks X40-D- 0.00 0.01
0204/0205)
Pipe rack (north of
CA-18A Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)

Risktec Solutions DMCC Page D.53 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
Pipe rack (north of
CA-18B Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)
Pipe rack (north of
CA-18C Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)
Pipe rack (north of
CA-18D Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)
Pipe rack (north of
CA-18E Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)
Pipe rack (north of
CA-18F Pipe Rack PG91 tanks X40-D- 0.01 0.01
0204/0205)
Pipe rack (west of
CA-19A Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19B Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19C Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19D Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19E Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19F Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19G Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19H Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19I Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)
Pipe rack (west of
CA-19J Pipe Rack DO/DPK tanks X-40D- 0.00 0.00
0304/0305/0405)

Risktec Solutions DMCC Page D.54 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Explosion Overpressure at
Congested Areas
Buildings (psi)
B-11 OME B-12 Operation
Number Description Location
Building Building
Pipe rack (west of
PG91/PG95/DO tanks
CA-20A Pipe Rack 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20B Pipe Rack 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20C Pipe Rack 0.00 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20D Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20E Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20F Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20G Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20H Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.01 0.01
X40-D-0501/
0104/XXX3)
Pipe rack (west of
PG91/PG95/DO tanks
CA-20I Pipe Rack 0.01 0.03
X40-D-0501/
0104/XXX3)
Pipe Culvert Pipe Culvert (RC
CA-22 0.01 0.03
(RC Corridor) Corridor)
CA-23 PS-007 Slop Pump Shelter 0.00 0.00

Risktec Solutions DMCC Page D.55 of D.56


Yanbu Distribution Hub Stage 1 & 2 BRA Document No: MHDP-08-R-01
Mustang-HDP Issue: 6.0

Table D.22: Summary of the Worst Case Explosion Results at the YDH Buildings

Worst Credible Explosion Level at the Building


Worst Damage Pulse Duration
Building Name Building Type Overpressure From Impulse (Pa.s)
Overpressure (psi) Overpressure (Pa) Level (ms)
(mbar)
B-01 SS-XXX1 Receiving Substation Transformer Yard B3 7 0.102 700 Minor CA-12AB 127.9 44.8
B-02 SS-XXX2 Utility Power Substation Transformer Yard B3 32 0.464 3200 Minor CA-12I 127.9 204.6
B-03 RIB-XXX1 Remote I/O Building B4 25 0.363 2500 Minor CA-12J 127.9 159.9
B-04 RIB-XXX2 Remote I/O Building B4 26 0.377 2600 Minor CA-12T 127.9 166.3
B-05 FSF Building B3 15 0.218 1500 Minor CA-10 50.9 38.2
B-06 Security Guard House (A) B3 29 0.421 2900 Minor CA-10 50.9 73.8
B-07 Security Guard House (B) B3 24 0.348 2400 Minor CA-10 50.9 61.1
B-08 X-Ray Building B3 22 0.319 2200 Minor CA-10 50.9 56.0
B-09 Security Support Building (A) B4 21 0.305 2103 Minor CA-09 50.9 109.5
B-10 Security Support Building (B) B4 19 0.276 1900 Minor CA-10 50.9 48.4
B-11 OME Building B5 23 0.334 2303 Minor CA-10 50.9 180.7
B-12 Operation Building B5 17 0.247 1700 Minor CA-12AC 127.9 108.7
B-13 Musalla B3 16 0.232 1560 Minor CA-10 50.9 109.5
B-14 Chemical Shelter B3 27 0.392 2703 Minor CA-10 50.9 119.7
B-15 Operation Shelter B4 34 0.493 3399 Minor CA-12I 38.2 217.4
B-16 IDAS Shelter-001 B3 3 0.044 303 Minor CA-23 862.1 12.4
B-17 IDAS Shelter-002 B3 3 0.044 303 Minor CA-23 932.6 12.4
B-18 Sanitary Metering Shelter-Marafiq B3 30 0.435 2999 Minor CA-10 95.1 76.3
B-19 Utility Water Metering Shelter-Marafiq B3 30 0.435 2999 Minor CA-10 95.3 76.3
B-20 Custody Metering Shelter (Vendor Package) B3 27 0.392 2703 Minor CA-13A 80 110.5
B-21 Oily Water Metering Shelter -Marafiq B3 2 0.029 200 Minor CA-12V 532 12.8
B-22 Operation Shelter-2 B3 7 0.102 703 Minor CA-12AB 141.4 45.0

Risktec Solutions DMCC Page D.56 of D.56


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 5.0

APPENDIX E STAGE 1 SCREENING


Table E1 shows the building Stage 1 screening process, which was performed in accordance with the SAES-B-014 building screening criteria (summarised in
Section 3.1.1).
Table E1: Stage 1 Building Screening

Occupancy Screening Functionality Screening


Is Building
Is Building
considered Building is
Permanent considered
Building Maximum Occupancy to be Occupied /
Building Name / to be Is building
Type Occupancy Loading Occupied Functionally
Temporary Occupied Functionally Justification
(no. of (Hours Per due to Significant?
due to Significant
people) Week) Maximum
Occupancy
Occupancy
Loading?
?
B-01 SS-XXX1 Receiving Substation Functionally
B3 Permanent 1 <300 No No Yes Note 3
Transformer Yard Significant
B-02 SS-XXX2 Utility Power Substation Functionally
B3 Permanent 1 <300 No No Yes Note 3
Transformer Yard Significant
Functionally
B-03 RIB-XXX1 Remote I/O Building B4 Permanent 2 <300 No No Yes -
Significant
Functionally
B-04 RIB-XXX2 Remote I/O Building B4 Permanent 2 <300 No No Yes -
Significant
B-05 FSF Building B3 Permanent 5 336 No Yes Yes - Occupied
B-06 Security Guard House (A) B3 Permanent 4 672 No Yes No - Occupied
B-07 Security Guard House (B) B3 Permanent 4 672 No Yes No - Occupied
B-08 X-Ray Building B3 Permanent 2 <300 No No No - Not any
B-09 Security Support Building (A) B4 Permanent 12 672 Yes Yes Yes - Occupied
B-10 Security Support Building (B) B4 Permanent 12 672 Yes Yes Yes - Occupied
B-11 OME Building B4 Permanent 60 3360 Yes Yes Yes - Occupied
B-12 Operation Building B5 Permanent 12 672 Yes Yes Yes - Occupied
B-13 Musalla B3 Permanent 50 1000 Yes Yes No - Occupied

Risktec Solutions DMCC Page E.1 of E.2


Stage 1 & 2 BRA for Yanbu Distribution Hub Document No: MHDP-08-R-01
Mustang-HDP Issue: 5.0

Occupancy Screening Functionality Screening


Is Building
Is Building
considered Building is
Permanent considered
Building Maximum Occupancy to be Occupied /
Building Name / to be Is building
Type Occupancy Loading Occupied Functionally
Temporary Occupied Functionally Justification
(no. of (Hours Per due to Significant?
due to Significant
people) Week) Maximum
Occupancy
Occupancy
Loading?
?
B-14 Chemical Shelter B3 Permanent 2 <300 No No No - Not any
B-15 Operation Shelter-1 B4 Permanent 8 448 Yes Yes No - Occupied
B-16 IDAS Shelter-001 B3 Permanent 4 <300 No No No - Not any
B-17 IDAS Shelter-002 B3 Permanent 4 <300 No No No - Not any
B-18 Sanitary Metering Shelter-Marafiq B3 Permanent 1 <300 No No No - Not any
B-19 Utility Water Metering Shelter- Functionally
B3 Permanent 1 <300 No No Yes Note 3
Marafiq Significant
B-20 Custody Metering Shelter (Vendor
B3 Permanent 2 <300 No No No - Not any
Package)
B-21 Oily Water Metering Shelter -
B3 Permanent 1 <300 No No No - Not any
Marafiq
B-22 Operation Shelter-2 B4 Permanent 8 448 Yes Yes No - Occupied
Note 1: People are expected to remain or take refuge in the building during an emergency. Possible reasons for people to remain in a building include a lack of suitable evacuation options
or the need for occupants to perform emergency shutdown procedures.
Note 2: The building is required for emergency response, such as fire stations or clinic.
Note 3: The building is necessary for continued operation or the safe shutdown of plant units that may be able to continue to operate or may be unaffected by an incident in another area
or the economic impact on operation of loss of the building is significant. This includes operations and control centre, or substations that control or provide power to multiple process units.

Risktec Solutions DMCC Page E.2 of E.2

You might also like