SEG - LEBANON

Project Executive Summary


ALEY COMMERCIAL CENTER

1 Data Date : Thursday, 6 June 2019

Program Data (ALT1)


Revision 1

Shoring Works Excavation Structural Works Water proofing Block work Plaster work

1 Construction Start Date : 1/Nov/08 8/Nov/08 9/Oct/09 15/Jan/10 8/Mar/10 13/Apr/10

2 Target 1 Completion Date : 31/Dec/09 16/Jan/10 2/Sep/10 26/Jun/10 27/Sep/10 30/Sep/10

3 Target 1 Construction Period : 425 434 328 162 203 170

4 Expected Completion Date : 5/Jan/10 28/Jan/10 16/Sep/10 21/Jul/10 21/Oct/10 25/Oct/10

5 Delay : -5 days -12 days -14 days -25 days -24 days -25 days

6 Target 1 Progress : 100.00% 95.00% 3.79% 0.00% 0.00% 0.00%

7 Actual Progress : 97.40% 83.00% 2.32% 0.00% 0.00% 0.00%

8 Variation : -2.60% -12.00% -1.47% 0.00% 0.00% 0.00%

Total Construction Target Budget

9 Original Target Cost as per BOQ : 664,600.91$ 1,328,254.00$ 4,697,004.97$ 555,615.83$ 437,451.17$ 667,644.68$

10 Total Approved Cost Variations : 162,683.14$ 0.00$ 8,200.00$ 0.00$ 0.00$ 0.00$

11 Approved Revised Target Price : 827,284.05$ 1,328,254.00$ 4,705,204.97$ 555,615.83$ 437,451.17$ 667,644.68$

12 Total Pending Cost Variations : 0.00$ 0.00$ 0.00$ 0.00$ 0.00$ 0.00$

10 Forecast Target Price Adjustments : 827,284.05$ 1,328,254.00$ 4,705,204.97$ 555,615.83$ 437,451.17$ 667,644.68$

Major Activities & Events

Activity / Event Date Description Remarks

Shoring Works Started 1/Nov/08 Additional Shoring and Piling works were implemented Time / Cost impact

Excavation Works Started 8/Nov/08 Excavation Works delayed due to additional shoring works

Blinding Works Started 13/Nov/09 On time as per Rev.01

Steel Fixing Works Started 15/Nov/09 On time as per Rev.01

1st Zone Casting of Raft Works 25/Nov/09 On time as per Rev.01

Vertical Works Started 1/Dec/09 Ahead Schedule Rev.01

Formwork for Basement 2 Level started 20/Dec/09 Ahead Schedule Rev.01

Precast Ribs Fixing 26/Dec/09 Ahead Schedule Rev.01

Comments on Progress / Area of Concern


Event Description Measurement

I Logic Due to some disturbances, the site is disabled to follow the methodology set in the Project programme.
1 As per programme the site is divided into 5 zones in basement, supposed to follow the logic sequence
respectively as follow: Zone1 – Zone1.1- Zone2 – Zone 3 and Zone 4. Actually the site completed all raft and
vertical works in Zone1 and started the 2nd basement floor works, hence other zones are still held for some
reasons.

2 the Site is trying to achieve progress where work is enabled, but 75.05% of the core activities are linked
directly to the delayed zones, meanwhile the project will loose productivity rates till the rest of work will be
enabled, and it will become impossible to recover since some structural activities are linked logically the way
that they cannot overlap.

3 All Block work, plastering and other related activities cannot start unless one floor is totally completed

II Milestone 1 The project is delayed 25 days of revised completion date; the F.D. milestone now is located at 25 Oct. 2010.

III Critical Path 1 Critical Path or Longest Path did not change in the current update, but some activities were dragged in
negative float but did not affect the Original Critical path.
Critical Path or Longest Path did not change in the current update, but some activities were dragged in
negative float but did not affect the Original Critical path.