SEG Lebanon Fanar Residential Complex Sheet 1 of 1

2012
Activity Activity Orig Act Rev0 Rev.0 Early Early Var Var JAN FEB MAR APR
ID Description Dur Dur Early Start Early Finish Start Finish ES EF 16 17 18

Fanar Residential Complex


Total 248 128 31AUG11A 07APR12 31AUG11A 25JUN12 0 -66

BLOCK B
BUILDING BI
3RD BASEMENT
BBI-SL1015 MEP 1ST FIX 18 12 02JAN12 21JAN12 18JAN12A 11FEB12 -14 -17 MEP 1ST FIX
BBI-SL1010 BLOCK WORK AND LINTELS 27 0 07FEB12 09MAR12 05MAR12* 07APR12 -22 -22 BLOCK WORK AND LINTELS
2ND BASEMENT
BBI-SL2015 MEP 1ST FIX 18 12 31JAN12 21FEB12 18JAN12A 11FEB12 11 8 MEP 1ST FIX
1ST BASEMENT
BBI-SL3000 VERTICAL ELEMENTS 18 0 07FEB12 28FEB12 21FEB12* 12MAR12 -11 -11 VERTICAL ELEMENTS
BBI-SL3005 1ST BASEMENT UPPER SLAB 12 0 29FEB12 13MAR12 13MAR12 26MAR12 -11 -11 1ST BASEMENT UPPER SLAB
BUILDING BII
3RD BASEMENT
BB2-SL1015 MEP 1ST FIX 18 17 05JAN12 25JAN12 12JAN12A 11FEB12 -6 -14 MEP 1ST FIX
2ND BASEMENT
BB2-SL2000 VERTICAL ELEMENTS 20 14 13JAN12 04FEB12 15JAN12A 22FEB12 -2 -14 VERTICAL ELEMENTS
BB2-SL2005 2ND BASEMENT UPPER SLAB 14 0 06FEB12 22FEB12 08FEB12A 28FEB12 -2 -5 2ND BASEMENT UPPER SLAB
BB2-SL2015 MEP 1ST FIX 18 0 17FEB12 08MAR12 14FEB12A 13MAR12 3 -4 MEP 1ST FIX
1ST BASEMENT
BB2-SL3000 VERTICAL ELEMENTS 18 0 23FEB12 14MAR12 29FEB12 20MAR12 -5 -5 VERTICAL ELEMENTS
BLOCK A
BUILDING AI
3RD BASEMENT
AAI-SL1000 VERTICAL ELEMENTS 18 0 26JAN12 08FEB12 01FEB12 22FEB12 -5 -11 VERTICAL ELEMENTS
AAI-SL1005 3RD BASEMENT UPPER SLAB 12 0 10FEB12 23FEB12 23FEB12 07MAR12 -11 -11 3RD BASEMENT UPPER SLAB
AAI-SL1015 MEP 1ST FIX 18 0 21FEB12 12MAR12 05MAR12 24MAR12 -11 -11 MEP 1ST FIX
2ND BASEMENT
AAI-SL2000 VERTICAL ELEMENTS 12 0 24FEB12 08MAR12 08MAR12 21MAR12 -11 -11 VERTICAL ELEMENTS
BUILDING AII
FOUNDATION & SLAB ON GRADE
AA2-ADD-03 EXCAVATION FOR WATER TANK 13 17 25JAN12 08FEB12 12JAN12A 13FEB12 11 -3 EXCAVATION FOR WATER TANK
AA2-ADD-05 WALL FOOTINGS CONSTRUCTION 15 8 01FEB12 18FEB12 23JAN12A 13FEB12 8 5 WALL FOOTINGS CONSTRUCTION
AA2-ADD-06 FOOTINGS FOR CORE WALL 12 0 01FEB12 25FEB12 01FEB12 15FEB12 0 9 FOOTINGS FOR CORE WALL
AA2-ADD-07 WATER TANK CONCRETE WORKS 30 0 10FEB12 15MAR12 14FEB12 19MAR12 -3 -3 WATER TANK CONCRETE WORKS
AA2-SL0005 FOUNDATION & SLAB ON GRADE 32 0 03FEB12* 15MAR12 14FEB12* 21MAR12 -8 -5 FOUNDATION & SLAB ON GRADE
AA2-ADD-08 STEEL FIXING FOR SLAB ON GRADE 15 0 27FEB12 14MAR12 16FEB12 03MAR12 9 9 STEEL FIXING FOR SLAB ON GRADE
3RD BASEMENT
AA2-SL1000 VERTICAL ELEMENTS 15 0 10MAR12 27MAR12 10MAR12 27MAR12 0 0 VERTICAL ELEMENTS
BLOCK C
ALL BUILDINGS
GENERAL ALL
C--CAG0010 EXCAVATION 120 128 31AUG11A 07APR12 31AUG11A 25JUN12 0 -66

Start Date 25OCT10 FCU6 SEG Lebanon Sheet 1 of 1


Early Bar
Finish Date 20JAN15 Fanar Residential Complex Date Revision Checked Approved
Progress Bar
Data Date 01FEB12 ONE MONTH LOOK AHEAD 30SEP10 REV-1
Critical Activity