Project Schedule for Selection of the MRO and the Type of Engine Maintenance Program

G-3 Consultants

Project Start Date 9/2/2019 (Monday) Week 1 Week 2 Week 3 Week 4


2 Sep 2019 9 Sep 2019 16 Sep 2019 23 Sep 2019
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
WORK
WBS TASK START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DAYS
1 Data Request - -
0.1 Kick Off Meeting Mon 9/02/19 Mon 9/02/19 1 1
0.1 Initial management interviews Tue 9/03/19 Thu 9/05/19 3 3

0.1 Workshops / Presentation (On site presence) Tue 9/03/19 Thu 9/05/19 3 3

2 Market Intelligence - -
2.1 Develop market overview and foresight Tue 9/03/19 Fri 9/06/19 4 4
2.2 Screen MRO capabilities in accordance to Muscat Airline needs Wed 9/04/19 Sat 9/07/19 4 3

2.3 Build potential MRO snapshot documentation Tue 9/03/19 Mon 9/09/19 7 5

3 Operational diagnostic and RFQ construction - -


3.1 Understand current organization and planned operation Tue 9/10/19 Fri 9/13/19 4 4
3.2 Build options in regards to terms and conditions Thu 9/12/19 Sat 9/14/19 3 2

3.3 Evaluate scenarios in terms of desired model and term Sat 9/14/19 Mon 9/16/19 3 1
3.4 Model financial implications and sensitivities Mon 9/16/19 Wed 9/18/19 3 3

3.5 Develop recommendations for service level clauses Wed 9/18/19 Tue 9/24/19 7 5
3.6 Discuss with Muscat Airline experts Wed 9/25/19 Sun 9/29/19 5 3

4 Monitoring tools - -
4.1 Jointly defines set of monitoring parameters (KPI) Wed 9/25/19 Sun 9/29/19 5 3

4.2 Develop monitoring material and dashboards Wed 9/25/19 Sun 9/29/19 5 3
4.3 Management discussion and adaptation Sun 9/29/19 Sun 9/29/19 1 0