Rumaitha / Shanayel Facilities Phase-Iii Part (A) - SMP Works: Ahec Project No: 027
Rumaitha / Shanayel Facilities Phase-Iii Part (A) - SMP Works: Ahec Project No: 027
Sr Corrective Department
No Description actions proposed responsible
Bidding Mistakes
1 Piping Field Painting
2 Flange to flange bollted joints
3 Full cosmetic painting
4 Pre-commissioning assistance in free
5 Low rates of steel structure modification
6 Toe plate for steel gratings
7
8
9
10
11
12
13
14
15
16
Construction problems
1 lack of Material department, warehouse,
2 Improper material control of spools, supports, tagging
3 Lack of quanlity control procedures, pipe supports tracing not implemented
4 Small bore done in shop which resulted in increased re-work
5 Scaffolding job done by AHEC but paid to kaefer on the instruction by PM
6 Stecon bonders not qualified but paid to STEcon on the instruction of PM
7 Improper utilization of manpower by construction department and mob/ demob not done as per required
8 Too many highly paid staff hired for the project which was not required considering the scale of project e.g 04 piping enginee
Mechanical CM, plus structure incharge, and piping incharge till end
9 Unnecessary hiring of subcontractor like prestige, Inhouse manpower performed the fabrication of supports very well when s
10 Lack of meetings for targets for construction team and followups
11 Key persons had their own companies and at the same time working in AHEC, giving more time to their own business, work w
12 Project higher person directed the stecon manager to GS which resulted in no work for AHEC, which would have been given t
13
14
15
16
17
18
partment
f reputation of the company
QS
everyone and give training