Professional Documents
Culture Documents
Elemental Cost Analysis - Form 1
Elemental Cost Analysis - Form 1
Proposed 48 unit of Four Story Shop-Office Lot including associated external works within lot boundries. PAM 2006 With Quantities
No problem in accessibility and the site condition generally is flat and slightly sloping.
Market Conditions :
Contract Particulars: Competitive Tender List
Type of Contract : PAM 2006 With Quantities Cost fluctuation Yes RM INT(JV) / L
No /
1 Substructure
1A Piling
1B Work Below Lowest Floor Finishes Reinforced concrete for pad footings, ground beams, column stumps and ground slab. Also
reinforced concrete for apron and walkaway.
2 Superstructure
2A Frame Reinforced concrete column, upper floor beam and roof beam.
2B Upper Floor
2C Roof Steel roof structure system on prefabricated timber roof trusses with a layer of single sided
aluminium foil with fibreglass wool insulation, uPVC rain water down pipes
2D Stairs Reinforced concrete stair construction finished with cement and sand trowelled smooth.
2G Internal Walls & Partitions 114mm thick brick wall reinforced with and including a layer of "Exmet" at every fourt course.
230mm thick brick party wall reinforced with and including a layer of "Exmet" at every fourt course.
3 Finishes
3B Internal Floor Finishes Cement render to floor and non-slip homogenous tiles to toilets
3C Internal Ceiling Finishes Gypsum ceiling board with skim coat
3D External Finishes Gypsum ceiling board with skim coat
Cement and sand plaster with weathershield paint to external wall and column.
INSTITUTION OF SURVEYORS MALAYSIA
BUILDING COST INFORMATION CENTER
ELEMENTAL COST ANALYSIS - Form 3 3 - Administrative Buildings
A - 4 - 1156
BRIEF SPECIFICATION
Gross Floor Area : 1156 m2 Tender date : 11-Jan-2013
ELEMENT SPECIFICATION
4 Fittings and Furnishings
5 Services
5A Sanitary appliances Generally, "Claytan" vitreous china white sanitary wares , "Lynx" counter top basin and "DOE" range
of tap fittings.
6 External Works
6A Site Works Site preparation and earthworks and all slope protection works including turfing.
Roadworks and car parks
6B Drainage Stormwater drainage systems, foul drainage system and water reticulation system which include all
the fittings and accessories.
BUILDING & EXTERNAL WORKS FOR CADANGAN MEMBINA 48 UNIT KEDAI PEJABAT 4 TIN
LOT 5198 (GRN 56267) & LOT 5199 (GRN 60083) JALAN SAKEH, MUKIM BANDAR MAHARANI, D
JOHOR DARUL TAKZIM UNTUK TETUAN LEONG HUP INDUSTRIES SDN. BHD. (Phase 1)
GENERAL SUMMARY
Contract
Item Description
Amount
A. PRELIMINARIES 189,008.82
Sub-total = 189,008.82
B. BUILDING WORKS
a) Type A (Corner Lot) 753,090.85
b) Type B (Intermediate Lot) 8,106,932.88
c) Type B (End Lot) 476,818.90
d) Type B (End Lot Single Lift) 497,097.38
e) Type C (Corner Lot) 1,119,798.67
Sub-total = 10,953,738.68
D. EXTERNAL WORKS
a) Roadworks 607,820.60
b) Drainage Works 200,420.00
c) Sewerage Works 87,900.00
d) Water Reticulation Works 223,725.00
e) Landscapping Works 31,740.00
Sub-total = 1,151,605.60
C:\Users\Yee\Desktop\ECA\48 Unit Shop Office Muar - Pangkal Murni\05 Claim - Building Works - P1\[Leong Hup Ind - YLT - Claim No. 14.xlsx]GSM
GENERAL SUMMARY
0.06875
12,994.72
753,090.85
11,525.05
41,788.85
13,779.27
6,043.30
15,381.53
2,182.19
79,175.13
856,785.75
Excavate trenches:-
2.1.2 Max. depth n.e. 1.00m deep for pile cap m3 9.30 1
2.1.3 Ditto; exc. 1.00m but n.e. 2.00m deep (Provisional m3 9.30 1
2.1.4 Max. depth n.e. 1.00m deep for lift pit m3 9.30 1
2.1.5 Ditto; exc. 1.00m but n.e. 2.00m deep (Provisional m3 9.30 1
2.1.6 Max. depth n.e. 0.25m deep for ground beam m3 9.30 1
2.1.7 Ditto; n.e. 1.00m deep fro ground beam m3 9.30 1
2.2 FRAME
Miscellaneous Item
2.2.26 EO for temporary boxing to form opening No. 242.50 1
FRAME
Total Carried To Summary of Building Work
ROOF CONSTRUCTION
Total Carried To Summary of Building Work
2.5 STAIRCASE
Landing Beam
2.5.7 12mm dia. Bar kg 3.50 1
2.5.8 20mm dia. Bar kg 3.50 1
STAIRCASE
Total Carried To Summary of Building Work
EXTERNAL WALL
Total Carried To Summary of Building Work
INTERNAL WALL
Total Carried To Summary of Building Work
2.9 DOOR
DOOR
Total Carried To Summary of Building Work
2.10 WINDOWS
WINDOWS
Total Carried To Summary of Building Work
Paving
2.13.1 25mm Thick; to Shop Office floors m2 14.00 1
2.13.2 25mm Thick; to external corridor m2 14.00 1
2.13.3 13mm Thick; to 50mm high drop m 1.80 1
2.13.4 13mm Thick; to 100mm high drop m 2.80 1
2.13.5 13mm Thick; to 150mm high drop m 3.80 1
Skim Coat
2.14.1 6mm Thick plainface to soffit of landing slab m2 4.80 1
2.14.2 6mm Thick plainface to soffit of landing beam m2 4.80 1
2.14.3 6mm Thick plainface to sloping soffit of staircase m2 4.80 1
2.14.4 6mm Thick plainface to open stringer edge m 3.80 1
Paving
2.14.5 25mm Thick; to landing slab m2 14.00 1
2.14.6 25mm Thick to tread; 250mm wide m 3.50 1
2.14.7 19mm Thick to undercut riser; 175mm high m 2.40 1
STAIRCASE FINISHES
Total Carried To Summary of Building Work
CEILING FINISHES
Total Carried To Summary of Building Work
2.16 PAINTING
External Painting
2.16.1 Walls and columns m2 6.30 1
2.16.2 Isolated columns m2 6.30 1
2.16.3 Exposed surfaces of 150mm x 150mm high wall c m 2.20 1
2.16.4 Exposed surfaces of window sill size 150mm x m 2.20 1
2.16.5 Exposed surfaces of window hood size 150mm x m 2.20 1
Internal Painting
2.16.6 Walls and columns m2 4.80 1
2.16.7 Soffit of concrete slab and sides and soffit of bea m2 4.80 1
2.16.8 Soffit of landing slab m2 4.80 1
2.16.9 Soffit of landing beam m2 4.80 1
2.16.10 Sloping soffit of staircase m2 4.80 1
2.16.11 Open stringer edge of staircase; 350mm wide (ext m 1.80 1
Metal Work
2.16.12 Door D3 No. 29.10 1
2.16.13 Door D4 No. 29.10 1
Woodwork Surfaces
2.16.14 Door D3 No. 48.50 1
2.16.15 Door D4 No. 48.50 1
Galvanised surfaces
2.16.16 Exposed surfaces of wall flashings m 3.80 1
2.16.17 Exposed surfaces of party wall caping m 3.80 1
2.16.18 Indemnity / Warranty for external painting Item
PAINTING
Total Carried To Summary of Building Work
6.2 23.56 0% -
6.2 23.56 0% -
1 GFA
Ground
1 24.88 18.54
Floor
1 24.38 5.28
Upper
3 24.96 18.54
Floor
(First floor to Third 3 24.48 5.28
Floor) opening DDT (3) 0.62 3.22
opening DDT (3) 0.76 3.10
opening DDT (3) 0.61 3.48
opening DDT (3) 0.61 3.28
opening DDT (3) 1.41 0.46
Total GFA
2 Circulation
2 2.45 7.57
Internal Division
3 Ground
Toilet area wall 3 2.40 0.15
Toilet area wall 2 2.00 0.15
Basin area wall 1 0.75 0.15
Wall area 1 35.46 0.15
Staircase wall 1 13.31 0.15
4 Roof Roof
1 24.70 5.28
External
5 Ground D2 1 5.18 3.60
window&door
D3 2 4.27 3.60
D4 1 3.96 3.60
D6 1 0.90 2.10
W4 2 0.60 0.45
230.66 230.66
64.41 64.41
295.06
231.33 694.00
64.66 193.98
2.01 (6.02)
2.36 (7.07)
2.12 (6.36)
2.00 (6.00)
0.65 (1.94)
860.59
1,155.65
77.88 77.88
2.73 5.46
0.14 0.28
9.28 18.57
102.19
Sub Total Total (m2)
0.18 0.54
0.15 0.30
0.06 0.06
2.66 2.66
1.00 1.00
- -
0.87 1.74
0.18 1.08
0.15 0.60
0.06 0.11
0.87 1.74
0.18 0.54
0.15 0.30
0.06 0.06
10.72
232.40 232.40
65.25 65.25
297.64
18.66 18.66
15.36 30.72
14.26 14.26
1.89 1.89
0.27 0.54
18.66 55.97
15.36 92.17
14.26 42.79
1.89 5.67
0.27 1.62
264.28
Sub Total Total (m2)
1.58 12.60
12.60