PROJECTS GROUP

01A2 (Reading)
BASIC DATA FOR FOSTER WHEELER PAGE: 1 OF 8
FLOWSHEET ENGINEERING STANDARD REV: 1
DRAUGHTING

REVISION ORIG REV 1 REV 2 REV 3 REV 4 REV 5


DATE SEPT 1986 JUNE 1994
ORIG.BY H P FERDINAND
APP.BY M T ROBERTS
SIGNATURE

Contract:

Client's Name:

Project Title:

Project Location:

Document Category: CLASS

CONTENTS

SECTION SUBJECT

1. PREPARATION

2. SYMBOLOGY

3. TITLE BLOCKS

4. BASIC DRAWING FORMATS

5. EQUIPMENT DATA

6. DRAWING SIZES

7. TEXT SIZES

8. DRAWING NUMBERING

9. REVISING DRAWINGS

10. LINE NUMBERING

11. DISTRIBUTION

12. SPECIAL PROJECT REQUIREMENTS

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP
01A2 (Reading)
PAGE: 2 FOSTER WHEELER BASIC DATA FOR
REV: 1 ENGINEERING STANDARD FLOWSHEET
DRAUGHTING

1.0 PREPARATION

1.1 Basic Data for Flowsheet Draughting shall be prepared by the Project
Co-ordinating Engineer, or Process Co-ordinating Engineer if there is no
Project Engineer, at the start of the project.

This information shall be used in setting up all Process type Flow


Diagrams and Engineering Flow Diagrams for the project and shall be
discussed with the Flowsheet Supervisor prior to the start of flowsheet
draughting.

1.2 This Engineering Standard does not replace ENG.STD. 50F2 (Reading)
which shall be used at all times for job specification development unless
client's standards overrule.

1.3 All sections of this Engineering Standard shall be filled in. If a section is
not applicable, enter N.A. in the appropriate remarks section. If data is
applicable but not available at the time of issue, enter LATER in the
appropriate section.

1.4 Section 12 SPECIAL PROJECT REQUIREMENTS, shall be used to clarify


unusual aspects of the project. It shall also be used whenever space in
the relevant remarks section is inadequate, in which case the remarks
section shall cross refer to section 12.

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP

BASIC DATA FOR 01A2 (Reading)


FLOWSHEET FOSTER WHEELER PAGE: 3
DRAUGHTING ENGINEERING STANDARD REV: 1

2.0 SYMBOLOGY

2.1 Will flowsheet symbology be in accordance with:-

a) ENG STD 50F2 section 8 YES NO

b) Client's own symbology YES NO

c) FW and client symbology (see para 2.4) YES NO

Remarks

2.2 If FW's symbols are to be used will there be any YES NO


deviations from ENG STD 50F2

Remarks

2.3 If client's own symbols are to be used full details shall be provided.

Remarks

2.4 If both FW and client's symbology are to be used specify order of


precedence.

Remarks

2.5 If symbology is the same or similar to a previous FW contract specify


contract number

Remarks

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP
01A2 (Reading)
PAGE: 4 FOSTER WHEELER BASIC DATA FOR
REV: 1 ENGINEERING STANDARD FLOWSHEET
DRAUGHTING

3.0 TITLE BLOCKS

3.1 Will the client's own logo be added to the YES NO


title blocks

If "YES'' details showing client's requirements shall be provided.

Remarks

3.2 Will the FW logo appear in the title blocks YES NO

Remarks

3.3 Is FW standard patent clause acceptable YES NO

Remarks

4.0 BASIC DRAWING FORMATS

4.1 Are there any special client's requirements YES NO


overriding the drawing formats of ENG. STD 50F2
Appendix N. (i.e. approval boxes, equipment
summaries, safety reviews etc)

If ''YES", details showing client's requirements shall be provided.

Remarks

4.2 Will there be an area on the EFDs reserved for YES NO


a notes column

Remarks

4.3 If "YES" to 4.2 where will the matching grid


be situated

a) Left-hand side of notes YES NO

b) Right-hand side of notes YES NO

Remarks

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP

BASIC DATA FOR 01A2 (Reading)


FLOWSHEET FOSTER WHEELER PAGE: 5
DRAUGHTING ENGINEERING STANDARD REV: 1

5. EQUIPMENT DATA

5.1 What are the basic pressure/temperature/flow units, dimensions, and


other required data to be inserted into equipment boxes (refer ENG.STD
50F2 Section 6).

Equipment Type Equipment Type

Equipment Type Equipment Type

Equipment Type Equipment Type

Remarks

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP
01A2 (Reading)
PAGE: 6 FOSTER WHEELER BASIC DATA FOR
REV: 1 ENGINEERING STANDARD FLOWSHEET
DRAUGHTING

6.0 DRAWING SIZES

6.1 What size of plots are to be produced during normal engineering


development.

a) Drawn AO on CAD, plot AO size YES NO

b) Drawn AO on CAD, plot A1 size YES NO

c) Drawn A1 on CAD, plot A1 size YES NO

Remarks

7.0 TEXT SIZES

7.1 Are text sizes as specified in ENG STD 50F2 YES NO


Section 7 acceptable

If "NO" full details must be provided.

Remarks

8.0 DRAWING NUMBERING

8.1 Will drawings be numbered in accordance with

a) ENG STD 50F2 Section 6 YES NO

b) Client's standards YES NO

Remarks

8.2 If client's numbering system is to be used, block allocations of the full


drawing numbers for each type of drawing shall be provided.

Remarks

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP

BASIC DATA FOR 01A2 (Reading)


FLOWSHEET FOSTER WHEELER PAGE: 7
DRAUGHTING ENGINEERING STANDARD REV: 1

9. REVISING DRAWINGS

9.1 Will the drawing revision sequence be in accordance YES NO


with normal FW procedures (Rev. 0, A, B, C etc)

If ''NO" the revision sequence to be adopted shall be provided

Remarks

9.2 How will revisions to drawings be highlighted

a) Revision sequence only within clouds YES NO

b) Revision sequence inside a triangle within YES NO


clouds

c) Arrows YES NO

Remarks

10.0 LINE NUMBERING

10.1 Will lines be numbered in accordance with:-

a) ENG STD 50F2 section 6 YES NO

b) Client's standards YES NO

10.2 If client's standards are to be used the total number of digits per line
shall as a minimum be provided

Remarks

A1 10.3 Will the Project Engineer be responsible for YES NO


draughting line lists (Engineering Procedure
FWEL/44/E04).

Remarks

10.4 If "YES" to 10.3 is the format identical to YES NO


ENG STD 50F2 Appendix P

Remark

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986


PROJECTS GROUP
01A2 (Reading)
PAGE: 8 FOSTER WHEELER BASIC DATA FOR
REV: 1 ENGINEERING STANDARD FLOWSHEET
DRAUGHTING

10.5 If "NO" to 10.4, full details of the required format shall be provided

Remarks

11.0 DISTRIBUTION

11.1 Will the Flowsheet section be responsible for YES NO


issuing flowsheets, line lists and change lists
(Engineering Procedure Appendix PEN/E04/01)

Remarks

12.0 SPECIAL PROJECT REQUIREMENTS

01A2-RDG.DOC UNCONTROLLED COPY  FOSTER WHEELER ENERGY LIMITED 1986