Date Project Code Engineer Site Name NE-ID

20-Feb-19 56A04KR Waseem Khan Jhand PTCL Exchange (9-8892)

20-Feb-19 56A04KR Waseem Khan Fateh Jang PTCL Exchange (9-8893)

20-Feb-19 56A04KR Asim Mustafa IBA-2 PTCL Exchange 8820

21-Feb-19 56A04KR Asim Mustafa IBA-1 PTCL Exchange (9-8819)

21-Feb-19 56A04KR Waseem Khan Bannu PTCL Exchange 8802

22-Feb-19 56A04KR Waseem Khan Pesh Cantt PTCL Exchange (9-8842)


Completion
Task
status

ND2 Board Dismantled Completed

ND2 Board Dismantled Completed

Pass Through Completed

Install the ND2 Board and update Fiber


connection Completed

LSX 02 Boards, & One DCP Board are


Dismantled for Peshawar. and Installed ND2
Board Completed

Install LSX+DCP and update fiber connection Completed


Day Date Team Task Site status

1 2/20/2019 Waseem Khan Dismantle the ND2 Fateh Jhang Complete

1 2/20/2019 Waseem Khan Dismantle the ND2 Jand Complete

2/21/2019 Asim Mustafa Install the ND2 and update


2 IBA-II, IBA-I Complete
Fiber connection

Dismantle the LSX+DCP &


2 2/21/2019 Waseem Khan Install the ND2 & update fiber Bannu Complete
connections

2/22/2019 Waseem Khan Install LSX+DCP and update


3 Peshawar Cant completed
fiber connection

4 2/23/2019 1 Troubleshooting on Site Site with Issue

4 2/23/2019 2 Troubleshooting on Site Site with Issue


Board HandeOver/Installation/Dismentling

Board Board
Site Name Task NE-ID-Subrack-Slot Hande Over Customer Signature Huawei Pesrson
Dismentled Installed

Dismantle the LSX+DCP &


Bannu II PTCL Install the ND2 & update
Exchange fiber connections

PESH Cantt Exhange Install LSX+DCP and update


fiber connection