CCK Engineering and Construction Co.,Ltd.

Client : Covestro Rev:.01

PROJECT: 12" Tower water pipe line work Date.: 17/05/62

MAN POWER LOADING

A. INDIRECT MANPOWER B. DIRECT MANPOWER

2562 2562
NO Position NO Position
May June July Aug May June July Aug

1 Project Manager 1 1 1 1 1 Foreman 3 3 3 3


2 Site Manager 1 1 1 1 2 Welder (Pipe ) 6 6 6 6
3 QA QC leader 1 1 1 1 3 Welder (Support ) 1 1 1 1
4 Safety Leader 1 1 1 1 4 Fitter (Piping) 18 18 18 18
5 Safety Technical 3 3 3 3 5 Fitter (Steel Structure) 3 3 3 3
7 Supervisor 1 1 1 1 6 Rigger 4 4 4 4
8 QA QC Inspector 2 2 2 2 7 Painter 3 0 0 5
9 Draftman 1 1 1 1 8 Rigger 4 4 4 4
10 Fire Watchman 5 5 5 5 9 Scaffolder 18 18 0 18
11 Erectrical 1 1 1 1
12 Document Controller 1 1 1 1
13 Material Controller 1 1 1 1
14 Site Admin 1 1 1 1
15 Store Keeper 1 1 1 1
16 Driver 1 1 1 1
TOTAL INDIRECT 22 22 22 22 TOTAL DIRECT 60 57 39 62

MAXIMUIM Indirect+direct = 84