10.04.

2019
ESTIMATE
S.No Description of the work Unit Quantity Rate/unit Amount
1 Laying of P.C.C 1:5:10 using good quality 40mm
aggregate, good quality m.sand and inclusive of
proper levelling, rammering before concreting,
Labour charges for concreting and curing etc.,
complete M3 1.28 4350.00 5585.40
2 Construction of RR masonry using cm 1:6 with
good quality of m.sand, and inclusive of all
labour charges, material charges etc., complete. M3 12.74 4625.00 58927.13
3 Construction of 6" thick hollow block masonry
with good quality of m.sand, and inclusive of all
labour charges, leading & lifting charges and
curing etc., complete. M2 47.00 880.00 41360.00
4 Plastering the walls using cm 1:5 with good
quality of m.sand and inclusive of labour
charges, proper scaffolding and curing etc.,
complete M2 13.38 330.00 4415.40
5 Applying two coats of cem wash for the plastered
area inclusive of all labour charges, cost of
materials etc., complete. M2 53.53 48.00 2569.44
6 Structural Works LS 231000.00
SUM 343857.37