Name of Work : REconstruction of Bridge at Km 64/8 of Thirukkattuppalli -

Sengippatti - Pattukkottai Road

Estimate Amount : Rs.740.5 Lakhs Job Code : NABARD RIDF XXI 2016 - 2016

Basic Data Adopted in this Estimate for the above Work


Schedule of Rates adopted in this estimate for the year : 2015-16
Bitumen / Emulsion
DATA of Bitumen DATA of Emulsion
VG10 : Rs.23656.00/MT Emulsion SS1 : Rs.47526.00/MT
VG30 : Rs.24456.00/MT Emulsion RS1 : Rs.28737.00/MT
VG40 : Rs.24956.00/MT Drum Deduction : Rs.1500.00/MT
Source : Manali Source : Irunkattukottai
C.G.S.T. in % : C.G.S.T. in % :
S.G.S.T. in % : S.G.S.T. in % :
Storage Charges : 5 %
Storage Charges : 5 % Deduct Drum Cost(-) : 1500/-
Conveyance Factor : 0.99924 Conveyance Factor : 1.690
Lead to Mid of Project Road: 376 Km Lead to Mid of Project Road: 346 Km

Terrian Classification (for conveyance) : Plains


Lead to CMP site Plains Hills
Metal Lead : 39 Km 10 Km
Bitumen Lead : 353 Km CMP to Work Site (GSB) : 51 Km

Cost of Fuel Details


Diesel : 54.31 /Lit
Furnace oil : 24821.06
Kerosene : 45.68 /Lit

Details of other allowances.


Night work : No Area Type : Hill Area 1
Area Details : Nilgiris 9m Paver involved: No

Road Data - Rev-17.6 1 Revised during - OCT. 2017


Metal lead to Site Metal lead
Chainage Name/ location of quarry Plain Hll
Km 0/0 - 1/0 Metal Qry1 67
Km 1/0 - 2/0 Metal Qry2 2
Km 2/0 - 3/0 Metal Qry3 3
Km 3/0 - 4/0 Metal Qry4 4
Km 4/0 - 5/0 Metal Qry5 5
Km 5/0 - 6/0 Metal Qry6 6

Gravel lead to site Gravel lead


Chainage Name/ location of quarry Plain Hll
Km 0/0 - 1/0 Grl Qry1 40
Km 1/0 - 2/0 Grl Qry2
Km 2/0 - 3/0 Grl Qry3
Km 3/0 - 4/0 Grl Qry4
Km 4/0 - 5/0 Grl Qry5
Km 5/0 - 6/0 Grl Qry6

Sand lead to site Sand lead


Chainage Name/ location of quarry Plain Hll
Km 0/0 - 1/0 Snd Qry1 58
Km 1/0 - 2/0 Snd Qry2
Km 2/0 - 3/0 Snd Qry3
Km 3/0 - 4/0 Snd Qry4
Km 4/0 - 5/0 Snd Qry5
Km 5/0 - 6/0 Snd Qry6

Road Data - Rev-17.6 2 Revised during - OCT. 2017


Carted Earth lead to site Carted Earth Lead
Name/ location of quarry Plain Hills
Km 0/0 - 1/0 Earth qry1 40
Km 1/0 - 2/0 Earth qry2
Km 2/0 - 3/0 Earth qry3
Km 3/0 - 4/0 Earth qry4
Km 4/0 - 5/0 Earth qry5
Km 5/0 - 6/0 Earth qry6

Road Data - Rev-17.6 3 Revised during - OCT. 2017


Highways Schedule of Rates for 2015-16
IRC HBG Metal Rates for 2015-16
Area : Hill Area 1, Location : Nilgiris, Locally Quarried Materials: Yes
Size Rate
90mm 367.00/Cum
75mm 410.00/Cum
63mm 531.00/Cum
53mm 645.00/Cum
46.50mm 865.00/Cum
45mm 865.00/Cum
37.50mm 883.00/Cum
26.50mm 835.00/Cum
25mm 835.00/Cum
22.40mm 1211.00/Cum
13.20mm 1124.00/Cum
11.20mm 763.00/Cum
6.70mm 566.00/Cum
6mm 566.00/Cum
5.60mm 566.00/Cum
4.75mm & Below 502.00/Cum

Labour Charges
Description Rate
Bitumen Sprayer Man 592.62/Day
Bitumen Raker Man 617.81/Day
Heat Master Operator 617.81/Day
Mini Hot Mix Plant Operator 617.81/Day
Gunnuting Plant Operator 517.05/Day
Gunnuting Gun Operator 562.13/Day
Road Mazdoor Gr.- I 446.60/Day
Road Mazdoor Gr.-II 400.40/Day
Head Mazdoor 460.60/Day

Road Data - Rev-17.6 4 Revised during - OCT. 2017


Hire charges for machinery
Hire Charges for Power Roller 855.00
Fuel For Roller per Hour 2.50
Hire Charges for Water Sprinkler per Day 1159.00
Fuel For Water Sprinkler per Hour (WBM) 3.50
Hire Charges for Mini Hot Mix Plant per Day 1674.00
Fuel for Mini Hot Mix Plant per Hour 15.00
Hire Charges for Bitumen Boiler per Day 202.00
Fuel for Bitumen Boiler per Day 25.00
Hire Charges for Vibrator Roller/ Hr 678.50
Water / KL 130.00
Fuel For Water Sprinkler per Hour (others) 3.25
Fuel For heating aggregate 45.00
Central Hot Mixing Plant-per day 9696.00
Vibratory Roller-per day 5428.00
Paver Finisher-per day 2447.00
Tipper Trucks-per day (10 Tonnes) 1094.00
Loader 5 cum capacity-per day 1205.00
Water tanker -per day 855.00
Motor grader-per day (110 HP) 13533.00
Pug mill-per day 6679.00
Generator-per day 5179.00
Tractor per hour 336.19
Tipper Trucks-per tonne /km 2.00
Fuel for water tanker per day 25.00
Rotovator per hour 17.00
Wet Mix Plant 75 tonne capacity/ day 834.88
Bitumen emulsion sprayer / 10 sqm 15.00
Paver Finisher (9m)-per hour -including fuel 2674.00
Pneumatic tyred roller including fuel per hr 1243.00
Tractor - Rotovator (including fuel per day) 2689.52
Water tanker for Mix in place method (GSB) 1909.52

Road Data - Rev-17.6 5 Revised during - OCT. 2017


PWD Schedule of Rates for 2015-16
ISS HBG Metal Rates for 2015-16
Area : Hill Area 1, Location : Nilgiris, Locally Quarried Materials: Yes
Size Rate
90mm 381.90/Cum
80mm 427.62/Cum
63mm 493.33/Cum
50mm 572.38/Cum
40mm 889.52/Cum
25mm 729.00/Cum
20mm 1238.10/Cum
12mm 1148.57/Cum
10mm 845.71/Cum
6mm 572.38/Cum
3mm 515.24/Cum
Rough Stone (Masonry) 393.33/Cum
Rough Stone (Revetment) 340.95/Cum
Bond Stones 567.00/Cum

Labour Charges
Description Rate
Carpenter - Ist Class 706.62/Day
Carpenter - IInd Class 646.97/Day
Fitter Ist Class (Pipe Laying/ Bar Bending) 628.40/Day
Fitter II Class (Pipe Laying/ Bar Bending) 583.34/Day
Mason I Class 631.40/Day
Mason II Class 565.60/Day
Mazdoor I Class 394.80/Day
Mazdoor II Class 357.00/Day
Head Mazdoor 408.80/Day
Painter / Varnisher I Class 578.03/Day
Painter / Varnisher II Class 536.93/Day
Wodder 467.99/Day

Road Data - Rev-17.6 6 Revised during - OCT. 2017


Rate of Materials (Other than Stones) PWD RATES 2015-16
Description Rate
Gravel 157.00/Cum
Well Gravel 142.86/Cum
Quarry Rubbish 85.14/Cum
Stone Dust 108.95/Cum
Crushed Stone Sand (M-Sand)
Sand for Mortar 176.40/Cum
Sand for Filling 168.00/Cum
Shell Lime (Slaked & Screened) 1223.81/Cum
Binding Wire (Black 18G) 39.11/Kg
Binding Wire (Galvanised - 18G) 39.11/Kg
Cost of Cement (including storage 5%) 6703.92/MT
Cost of Steel (including storage 5%) 45133.92/MT
Cost of Earth (as per 137 Industries (MMC 2) 62.00/Cum
Department dated 10.09.2014)
Rates of Works
Description Rate
Clearing Heavy Jungle 5.89/Sqm
Clearing Light Jungle 4.44/Sqm
Clearing Scrub Jungle 4.05/Sqm
Earth Work Excavation SS 20A 86.31/Cum
Earth Work Excavation SS 20B 708.40/Cum
Earth Work Excavation SS 20B for Foundation 1416.80/Cum
Refilling with excavated Sand 24.92/Cum
Refilling with excavated soil (other than Sand ) 28.38/Cum
Vibrator Charges for PCC rate per Cum. 44.31/Cum
Vibrator Charges for RCC rate per Cum. 68.14/Cum
Mixing Mortar Cement by Manual 83.92/Cum
Mixing Mortar Cement by Machine 111.37/Cum
Conveyance Charges for Plains and Hills
Rough Stone, Jelly,Sand,Gravel (Rs. Per Km )
Km Plain Hills
0 - 10 Km 8.69
10-20 Km 7.44
20-40 Km 6.40
40-80 Km 6.00
80 & Above 5.04

Road Data - Rev-17.6 7 Revised during - OCT. 2017


Cement Rate With Storage 2015-16

Cost of Cement as per PWD Schedule of Rates Rs.6400.00

Deduct loading and unloading charges (-) Rs.321.60


Rs.6078.40
Basic Cement Rate = 6078.40

Add Storage Charges at 5% of Basic Cost = 6078.40 X 5.00


= 303.92
100.00

Cost of Cement including Storage at 5% of Basic Rate= 6400 + 303.92

=Rs.6703.92/MT

Steel Rate with Storage Charges 2015-16

Cost of Steel as per PWD Schedule of Rates Rs.43000.00

Deduct loading and unloading charges (-) Rs.321.60


Rs.42678.40
Basic Steel Rate = 42678.40

Add Storage Charges at 5 % of Basic Cost = 42678.40 X 5.00 = 2133.92


100.00

Cost of Steel including Storage Charges at 5% of Basic Rate + 2133.92


= 43000

=Rs.45133.92/MT

Road Data - Rev-17.6 8 Revised during - OCT. 2017


Name of Work : REconstruction of Bridge at Km 64/8 of Thirukkattuppalli - Sengippatti - Pattukkottai Road

Job Code : NABARD RIDF XXI 2016 - 2016 Estimate Amount : 740.50 Lakhs
DATA ABSTRACT

Sl
Description Unit Rate
No.
GENERAL RATES (As Per Schedule of Rates)
1 Clearing Heavy Jungle /Sqm. 5.89

2 Clearing Light Jungle /Sqm. 4.44

3 Clearing Scrub Jungle /Sqm. 4.05

4 Earth Work Excavation SS 20A /Cum. 86.31

5 Earth Work Excavation SS 20B /Cum. 708.40

6 Earth Work Excavation SS 20B For Foundation /Cum. 1416.80

7 Refilling With Excavated Sand /Cum. 24.92

8 Refilling With Excavated Soil (Other Than Sand ) /Cum. 28.38

9 Picking the Existing BT Surface /Sqm. 12.06

10 GSB Grade - V Plant Mix /Cum. 1637.64

11 GSB Grade - III Plant Mix /Cum. 1714.42

12 Wet Mix Macadam /Cum. 1749.14

Road Data - Rev-17.6 9 Revised during - OCT. 2017


Sl
Description Unit Rate
No.
13 Crusher Run Macadam 300mm Thick /Cum. 1663.92

14 Prime Coat Over WBM / WMM Surface /Sqm. 60.74

15 Prime Coat Over CRM Surface /Sqm. 70.54

16 Tack Coat Over Primed Non-Bituminous GB /Sqm. 11.22

17 Tack Coat Over Existing BT Surface /Sqm. 15.82

18 Tack Coat Over Dry Lean Cement Surface /Sqm. 12.68

19 Dense Bituminous Macadam 50mm Thick Using CMP /Cum. 6239.52

20 Dense Bituminous Macadam 75mm Thick Using CMP /Cum. 5830.17

21 Bituminous Macadam 50mm Thick Using CMP /Cum. 5367.20

22 Bituminous Macadam 80mm Thick Using CMP /Cum. 5429.90

23 Close Graded Premix Carpet 20mm Thick (CMP) /Sqm. 122.98

24 C.G.P.C. 20mm Thick (CMP) Using Plastic Waste /Sqm. 122.25

25 Bituminous Concrete 30/ 40mm Thick Using CMP /Cum. 6672.58

26 B.C. 30/ 40mm Thick (CMP) Using Plastic Waste /Cum. 6624.38

27 Bituminous Concrete 50mm Thick Using CMP /Cum. 6424.88

Road Data - Rev-17.6 10 Revised during - OCT. 2017


Sl
Description Unit Rate
No.
Km 0/0 - Km 1/0 - Km 2/0 - Km 3/0 - Km 4/0 -
KM
1/0 2/0 3/0 4/0 5/0
28 Patch Work Using 45mm IRC Metal /Cum. 2445.25 2011.33 2020.02 2028.71 2037.40
29 Patch Work Using 13.20mm IRC Metal /Cum. 2704.25 2270.33 2279.02 2287.71 2296.40
30 Premix Carpet With Seal Coat using Mini Hot Mix Plant /Sqm. 178.44 162.82 163.13 163.45 163.76
31 BM 50mm (For Patch Work) using Mini Hot Mix Plant /Cum. 5367.92 4751.78 4764.14 4776.46 4788.80
32 Dry Lean Cement Concrete for Sub-Base /Cum. 3313.18
Km 5/0 -
KM
6/0
28 Patch Work Using 45mm IRC Metal /Cum. 2046.09
29 Patch Work Using 13.20mm IRC Metal /Cum. 2305.09
30 Premix Carpet With Seal Coat using Mini Hot Mix Plant /Sqm. 164.07
31 BM 50mm (For Patch Work) using Mini Hot Mix Plant /Cum. 4801.14
32 Dry Lean Cement Concrete for Sub-Base /Cum.

Road Data - Rev-17.6 11 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR GRANULAR SUB BASE

Granular Sub Base Grade - V

Cost of 53mm to 9.50mm Broken Stone

Cost of 53mmMetal @Rs 645.00 /Cum.


Cost of 46.50mmMetal @Rs 865.00 /Cum.
Cost of 45mmMetal @Rs 865.00 /Cum.
Cost of 37.50mmMetal @Rs 883.00 /Cum.
Cost of 26.50mmMetal @Rs 835.00 /Cum.
Cost of 25mmMetal @Rs 835.00 /Cum.
Cost of 22.40mmMetal @Rs 1211.00 /Cum.
Cost of 13.20mmMetal @Rs 1124.00 /Cum.
Cost of 11.20mmMetal @Rs 763.00 /Cum.

Average Rate @Rs 891.78 /Cum.

Cost of 9.50mm to 2.36mm Broken Stone

Cost of 6.70mm Metal @Rs 566.00 /Cum.


Cost of 6mm Metal @Rs 566.00 /Cum.
Cost of 5.60mm Metal @Rs 566.00 /Cum.
Cost of 4.75mm Metal @Rs 502.00 /Cum.
Cost of 2.36mm Metal @Rs 502.00 /Cum.

Average Rate @Rs 540.40 /Cum.

Cost of 2.36mm & Below of Sand

Cost of 4.75mm & BelowMetal @Rs 502.00 /Cum.

Average Rate @Rs 502.00 /Cum.

Road Data - Rev-17.6 12 Revised during - OCT. 2017


METAL RATE FOR GRANULAR SUB BASE (TABLE NO.400.1)

Granular Sub Base Grade - III

Cost of 46.50 - 26.50 mm Broken Stone


Cost of 46.50mmMetal @Rs 865.00 /Cum.
Cost of 45mmMetal @Rs 865.00 /Cum.
Cost of 37.50mmMetal @Rs 883.00 /Cum.
Cost of 26.50mmMetal @Rs 835.00 /Cum.
Average Rate of 46.50 - 26.50 mm @Rs 862.00 /Cum.

Cost of 26.50 - 4.75mm Broken Stone


Cost of 25mmMetal @Rs 835.00 /Cum.
Cost of 22.40mmMetal @Rs 1211.00 /Cum.
Cost of 13.20mmMetal @Rs 1124.00 /Cum.
Cost of 11.20mmMetal @Rs 763.00 /Cum.
Cost of 6.70mmMetal @Rs 566.00 /Cum.
Cost of 6mmMetal @Rs 566.00 /Cum.
Cost of 5.60mmMetal @Rs 566.00 /Cum.
Average Rate of 26.50 - 4.75 mm @Rs 804.43 /Cum.

Cost of 4.75mm & Below of Sand

Cost of 4.75mm & BelowMetal @Rs 502.00 /Cum.


Average Rate of 2.36 & Below @Rs 502.00 /Cum.

Road Data - Rev-17.6 13 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR
WET MIX MACADAM

Cost of 45mm to 22.40mm Broken Stone

Cost of 45mmMetal @Rs 865.00 /Cum.


Cost of 37.50mmMetal @Rs 883.00 /Cum.
Cost of 26.50mmMetal @Rs 835.00 /Cum.
Cost of 25mmMetal @Rs 835.00 /Cum.
Cost of 22.40mmMetal @Rs 1211.00 /Cum.

Average Rate @Rs 925.80 /Cum.

Cost of 22.40mm to 2.36mm Broken Stone

Cost of 22.40mm Metal @Rs 1211.00 /Cum.


Cost of 13.20mm Metal @Rs 1124.00 /Cum.
Cost of 11.20mm Metal @Rs 763.00 /Cum.
Cost of 6.70mm Metal @Rs 566.00 /Cum.
Cost of 6mm Metal @Rs 566.00 /Cum.
Cost of 5.60mm Metal @Rs 566.00 /Cum.
Cost of 4.75mm Metal @Rs 502.00 /Cum.

Average Rate @Rs 756.86 /Cum.

Road Data - Rev-17.6 14 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR
CRUSHER RUN MACADAM

Cost of 53mm to 45 mm Broken Stone


Cost of 53mmMetal @Rs 645.00 /Cum.
Cost of 46.50mmMetal @Rs 865.00 /Cum.
Cost of 45mmMetal @Rs 865.00 /Cum.
Average Rate of 53-45 mm @Rs 791.67 /Cum.

Cost of 45mm - 22.40mm Broken Stone


Cost of 45mmMetal @Rs 865.00 /Cum.
Cost of 37.50mm Metal @Rs 883.00 /Cum.
Cost of 26.50mm Metal @Rs 835.00 /Cum.
Cost of 25.00mm Metal @Rs 835.00 /Cum.
Cost of 22.40mm Metal @Rs 1211.00 /Cum.
Average Rate of 45mm - 22.40mm @Rs 925.80 /Cum.

Cost of 22.40 mm to 5.60mm Broken Stone


Cost of 13.20mm Metal @Rs 1124.00 /Cum.
Cost of 11.20mm Metal @Rs 763.00 /Cum.
Cost of 6.70mm Metal @Rs 566.00 /Cum.
Cost of 6 mm Metal @Rs 566.00 /Cum.
Cost of 5.6 mm Metal @Rs 566.00 /Cum.
Average Rate of 22.40mm - 5.60mm 717.00

Cost of 4.75mm & below @Rs 502.00 /Cum.

Road Data - Rev-17.6 15 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BM 50mm thick

For 26.50 mm to 13.20 mm IRC


0.180 Cum Cost of 25 & 22.40mm IRC at Rs. 1023.00 /cum. = 184.14
0.820 Cum Cost of 13.20mm IRC at Rs. 1124.00 /cum. = 921.68
Rate of metal 26.50-13.20mm for BM 50mm Rs. 1105.82

For 13.20 mm to 2.36 mm IRC


0.570 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 592.60 /cum. = 337.78
0.430 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 215.86
Rate of metal 13.20 - 2.36 mm for BM 50mm Rs. 553.64

For 2.36 mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 502.00

WORKING OUT METAL RATE FOR DBM 50mm thick

For 26.50mm to 13.20mm IRC


0.160 Cum Cost of 26.50 mm IRC at Rs. 835.00 /cum. = 133.60
0.370 Cum Cost of 25 & 22.40mm IRC at Rs. 1023.00 /cum. = 378.51
0.470 Cum Cost of 13.20mm IRC at Rs. 1124.00 /cum. = 528.28
Rate of metal 26.50-13.20mm for DBM 50mm Rs. 1040.39

For 13.20 mm to 2.36 mm IRC


0.550 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 592.60 /cum. = 325.93
0.450 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 225.90
Rate of metal 13.20-2.36mm for DBM 50mm Rs. 551.83

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 502.00

Road Data - Rev-17.6 16 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BM 80mm thick

For 37.5 mm to 13.20 mm IRC


0.100 Cum Cost of 37.50 mm IRC at Rs. 883.00 /cum. = 88.30
0.380 Cum Cost of 26.50mm IRC at Rs. 835.00 /cum. = 317.30
0.520 Cum Cost of 25, 22.40 & 13.20 mm IRC at Rs. 1056.67 /cum. = 549.47
Rate of Metal For 37.5 mm to 13.20 mm IRC BM (80mm thick) Rs. 955.07

For 13.20 mm to 2.36 mm IRC


0.830 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 592.60 /cum. = 491.86
0.170 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 85.34
Rate of Metal For 13.20 mm to 2.36 mm IRC BM (80mm thick) Rs. 577.20

For 2.36mm & below

1.000 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 502.00


Rate of Metal For 2.36mm & belowBM (80mm thick) Rs. 502.00

WORKING OUT METAL RATE FOR DBM 75mm thick

For 37.50 mm to 13.20 mm IRC


0.140 Cum Cost of 37.50 mm IRC at Rs. 883.00 /cum. = 123.62
0.490 Cum Cost of 26.50mm IRC at Rs. 835.00 /cum. = 409.15
0.370 Cum Cost of 25, 22.40 & 13.20 mm IRC at Rs. 1056.67 /cum. = 390.97
Rate of Metal For 37.50 mm to 13.20 mm IRC DBM (75mm thick) Rs. 923.74

For 13.20 mm to 2.36 mm IRC

0.370 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC


at Rs. 592.60 /cum. = 219.26
0.630 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 316.26
Rate of Metal For 13.20 mm to 2.36 mm IRC DBM (75mm thick) Rs. 535.52

For 2.36mm & below

1.00 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 502.00

Road Data - Rev-17.6 17 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BC 30/40mm thick

For 19.00 mm to 9.50 mm IRC


0.240 Cum Cost of 13.20mm IRC at Rs. 1124.00 /cum. = 269.76
0.760 Cum Cost of 11.20mm IRC at Rs. 763.00 /cum. = 579.88
Rate of Metal For 19.00 mm to 9.50 mm IRC BC (40mm thick) Rs. 849.64

For 9.50 mm to 2.36 mm IRC


0.660 Cum Cost of 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 550.00 /cum. = 363.00
0.340 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 170.68
Rate of Metal For 9.50 mm to 2.36 mm IRC BC (40mm thick) Rs. 533.68

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 502.00

Road Data - Rev-17.6 18 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR BC 50mm thick

For 26.50 mm to 13.20 mm IRC


0.160 Cum Cost of 25mm & 22.40mm IRC at Rs. 1023.00 /cum. = 163.68
0.840 Cum Cost of 13.20mm IRC at Rs. 1124.00 /cum. = 944.16
Rate of Metal For 26.50 mm to 13.20 mm IRC BC (40mm thick) Rs. 1107.84

For 13.2 mm to 2.36 mm IRC


0.730 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC
at Rs. 592.60 /cum. = 432.60
0.270 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 135.54
Rate of Metal For 13.2 mm to 2.36 mm IRC BC (40mm thick) Rs. 568.14

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 502.00 /cum. = 502.00

Road Data - Rev-17.6 19 Revised during - OCT. 2017


WORKING OUT METAL RATE FOR
CLOSED GRADED PREMIX CARPET
Cost of 13.20 mm to 11.20mm Broken Stone
Cost of 11.20 mm Metal @Rs 763.00 /Cum.

Average Rate of 13.20 - 11.20mm @Rs 763.00 /Cum.

Cost of 11.20 mm to 5.60 mm Broken Stone


Cost of 6.7 mm Metal @Rs 566.00 /Cum.
Cost of 6 mm Metal @Rs 566.00 /Cum.
Cost of 5.6 mm Metal @Rs 566.00 /Cum.

Average Rate of 11.20-5.6mm @Rs 566.00 /Cum.

Cost of 5.6 mm to 2.80mm Broken Stone

Cost of 4.75mm & below metal @Rs 502.00 /Cum.

Average Rate of 5.60-2.80mm @Rs 502.00 /Cum.

Road Data - Rev-17.6 20 Revised during - OCT. 2017


BITUMEN RATE TO SITE
VG 10 VG 30
VG 10 VG 30 CRMB 55
Basic Rate 23656.00 24456.00 18590.00
C.G.S.T. % 0.00 0.00 #VALUE!
S.G.S.T. % 0.00 0.00 #VALUE!
2974.40
Basic Rate 23656.00 24456.00 #VALUE!
Storage Charges 5% of basic price 1182.80 1222.80 929.50
24838.80 25678.80 929.50

Conveyance at Rs.0.99924 per km for 376 km 751.43 751.43 751.43


140 25590.23 26430.23 1680.93

round 2

EMULSION BITUMEN RATE TO SITE


Slow Setting - Rapid Setting-I
I For Tack for Tack Coat
Coat Application
Application (R/C Drums)
Basic Rate ( R/C47526.00
Drums) 28737.00
C.G.S.T. % 0.00 0.00
S.G.S.T. % 0.00 0.00
Basic Rate 47526.00 28737.00
Storage Charges 5% of basic price 2376.30 1436.85 0.00
Deduct Drum cost -1500.00 -1500.00
Conveyance at Rs.1.69 per km for 346 km 584.74 584.74
48987.04 29258.59

Road Data - Rev-17.6 21 Revised during - OCT. 2017


BITUMEN RATE TO CMP
VG 40 VG 30 VG 10
VG 40 VG 30 VG 10
Basic Rate 24956.00 24456.00 23656.00
C.G.S.T. % 0.00 0.00 0.00
S.G.S.T. % 0.00 0.00 0.00

Basic Rate 24956.00 24456.00 23656.00


Storage Charges 5% of basic price 1247.80 1222.80 1182.80
26203.80 25678.80 24838.80

Conveyance at Rs.0.99924per km for 353 km 705.46 705.46 705.46


26909.26 26384.26 25544.26

Selected Grade of Bitumen for BC VG30 26384.26

Road Data - Rev-17.6 22 Revised during - OCT. 2017


Name of Work REconstruction of Bridge at Km 64/8 of Thirukkattuppalli - Sengippatti - Pattukkottai Road

ROAD METAL RATE - SITE


Plains
Cost of
Lead in Km Kind of Cost of Stacking
Reach in Km Quarry material Total
Plains Hills Materials Conveyance Charges
Km 0/0 - 1/0 Metal Qry1 67 45 mm 865.00 451.30 2.98 1319.28
Km 0/0 - 1/0 Metal Qry1 67 26.50-13.20mm(BM) 1105.82 451.30 1557.12
67 13.20-2.36mm(BM) 553.64 451.30 1004.94
67 2.36 & below(BM) 502.00 451.30 953.30
Km 0/0 - 1/0 Metal Qry1 67 13.20mm 1124.00 451.30 2.98 1578.28
67 11.20mm 763.00 451.30 2.98 1217.28
67 6.70mm 566.00 451.30 2.98 1020.28
Km 0/0 - 1/0 Metal Qry1 67 25 mm IS metal (DLC) 729.00 451.30 1180.30
Km 0/0 - 1/0 Grl Qry1 40 Gravel 157.00 289.30 2.89 449.19
Km 0/0 - 1/0 Snd Qry1 58 Sand 168.00 397.30 2.89 568.19
Km 1/0 - 2/0 Metal Qry2 2 45 mm 865.00 17.38 2.98 885.36
Km 1/0 - 2/0 Metal Qry2 2 26.50-13.20mm(BM) 1105.82 17.38 1123.20
2 13.20-2.36mm(BM) 553.64 17.38 571.02
2 2.36 & below(BM) 502.00 17.38 519.38
Km 1/0 - 2/0 Metal Qry2 2 13.20mm 1124.00 17.38 2.98 1144.36
2 11.20mm 763.00 17.38 2.98 783.36
2 6.70mm 566.00 17.38 2.98 586.36
Km 1/0 - 2/0 Metal Qry2 2 25 mm IS metal (DLC) 729.00 17.38 746.38
Km 1/0 - 2/0 Grl Qry2 Gravel 157.00 #VALUE! 2.89
Km 1/0 - 2/0 Snd Qry2 Sand 168.00 #VALUE! 2.89
Km 2/0 - 3/0 Metal Qry3 3 45 mm 865.00 26.07 2.98 894.05
Km 2/0 - 3/0 Metal Qry3 3 26.50-13.20mm(BM) 1105.82 26.07 1131.89

Road Data - Rev-17.6 23 Revised during - OCT. 2017


ROAD METAL RATE - SITE
Plains
Cost of
Lead in Km Kind of Cost of Stacking
Reach in Km Quarry material Total
Plains Hills Materials Conveyance Charges
3 13.20-2.36mm(BM) 553.64 26.07 579.71
3 2.36 & below(BM) 502.00 26.07 528.07
Km 2/0 - 3/0 Metal Qry3 3 13.20mm 1124.00 26.07 2.98 1153.05
3 11.20mm 763.00 26.07 2.98 792.05
3 6.70mm 566.00 26.07 2.98 595.05
Km 2/0 - 3/0 Metal Qry3 3 25 mm IS metal (DLC) 729.00 26.07 755.07
Km 2/0 - 3/0 Grl Qry3 Gravel 157.00 #VALUE! 2.89
Km 2/0 - 3/0 Snd Qry3 Sand 168.00 #VALUE! 2.89
Km 3/0 - 4/0 Metal Qry4 4 45 mm 865.00 34.76 2.98 902.74
Km 3/0 - 4/0 Metal Qry4 4 26.50-13.20mm(BM) 1105.82 34.76 1140.58
4 13.20-2.36mm(BM) 553.64 34.76 588.40
4 2.36 & below(BM) 502.00 34.76 536.76
Km 3/0 - 4/0 Metal Qry4 4 13.20mm 1124.00 34.76 2.98 1161.74
4 11.20mm 763.00 34.76 2.98 800.74
4 6.70mm 566.00 34.76 2.98 603.74
Km 3/0 - 4/0 Metal Qry4 4 25 mm IS metal (DLC) 729.00 34.76 763.76
Km 3/0 - 4/0 Grl Qry4 Gravel 157.00 #VALUE! 2.89
Km 3/0 - 4/0 Snd Qry4 Sand 168.00 #VALUE! 2.89
Km 4/0 - 5/0 Metal Qry5 5 45 mm 865.00 43.45 2.98 911.43
Km 4/0 - 5/0 Metal Qry5 5 26.50-13.20mm(BM) 1105.82 43.45 1149.27
5 13.20-2.36mm(BM) 553.64 43.45 597.09
5 2.36 & below(BM) 502.00 43.45 545.45
Km 4/0 - 5/0 Metal Qry5 5 13.20mm 1124.00 43.45 2.98 1170.43
5 11.20mm 763.00 43.45 2.98 809.43

Road Data - Rev-17.6 24 Revised during - OCT. 2017


ROAD METAL RATE - SITE
Plains
Cost of
Lead in Km Kind of Cost of Stacking
Reach in Km Quarry material Total
Plains Hills Materials Conveyance Charges
5 6.70mm 566.00 43.45 2.98 612.43
Km 4/0 - 5/0 Metal Qry5 5 25 mm IS metal (DLC) 729.00 43.45 772.45
Km 4/0 - 5/0 Grl Qry5 Gravel 157.00 #VALUE! 2.89
Km 4/0 - 5/0 Snd Qry5 Sand 168.00 #VALUE! 2.89
Km 5/0 - 6/0 Metal Qry6 6 45 mm 865.00 52.14 2.98 920.12
Km 5/0 - 6/0 Metal Qry6 6 26.50-13.20mm(BM) 1105.82 52.14 1157.96
6 13.20-2.36mm(BM) 553.64 52.14 605.78
6 2.36 & below(BM) 502.00 52.14 554.14
Km 5/0 - 6/0 Metal Qry6 6 13.20mm 1124.00 52.14 2.98 1179.12
6 11.20mm 763.00 52.14 2.98 818.12
6 6.70mm 566.00 52.14 2.98 621.12
Km 5/0 - 6/0 Metal Qry6 6 25 mm IS metal (DLC) 729.00 52.14 781.14
Km 5/0 - 6/0 Grl Qry6 Gravel 157.00 #VALUE! 2.89
Km 5/0 - 6/0 Snd Qry6 Sand 168.00 #VALUE! 2.89
Km 0/0 - 1/0 Earth qry1 40 Earth for embankment 588.00 289.30 877.30
Km 1/0 - 2/0 Earth qry2 Earth for embankment 588.00 #VALUE!
Km 2/0 - 3/0 Earth qry3 Earth for embankment 588.00 #VALUE!
Km 3/0 - 4/0 Earth qry4 Earth for embankment 588.00 #VALUE!
Km 4/0 - 5/0 Earth qry5 Earth for embankment 588.00 #VALUE!
Km 5/0 - 6/0 Earth qry6 Earth for embankment 588.00 #VALUE!

Road Data - Rev-17.6 25 Revised during - OCT. 2017


ROAD METAL RATE FOR CMP
CMP Site: Km 103 of NGM Road
Metal Source: Mathiyathuparai Quarry
Lead in Km Cost of Cost of Stacking
Kind of Materials Total
Plains Hills material Conveyance Charges

39 10 53 - 9.5mm(GSB-V) 891.78 282.90 -- 1174.68


39 10 9.50-2.36mm(GSB-V) 540.40 282.90 -- 823.30
39 10 2.36mm & Below(GSB-V) 502.00 282.90 -- 784.90
39 10 46.5 - 26.5 mm(GSB-III) 862.00 282.90 -- 1144.90
39 10 26.50 - 4.75 mm(GSB-III) 804.43 282.90 -- 1087.33
39 10 4.75 mm&below (GSB-III) 502.00 282.90 -- 784.90
39 10 45 - 22.40mm(WMM) 925.80 282.90 -- 1208.70
39 10 22.40-2.36mm(WMM) 756.86 282.90 -- 1039.76
39 10 2.36 & below(WMM) 502.00 282.90 -- 784.90
39 10 53 - 45 mm(CRM) 791.67 282.90 -- 1074.57
39 10 45 - 22.40mm(CRM) 925.80 282.90 -- 1208.70
39 10 22.40 - 5.6 mm(CRM) 717.00 282.90 -- 999.90
39 10 26.50-13.20mm(BM) 1105.82 282.90 -- 1388.72
39 10 13.20-2.36mm(BM) 553.64 282.90 -- 836.54
39 10 2.36 & below(BM) 502.00 282.90 -- 784.90
39 10 37.5 - 13.20mm(BM) 955.07 282.90 -- 1237.97
39 10 13.20 - 2.36 mm(BM) 577.20 282.90 -- 860.10
39 10 2.36 mm & below(BM) 502.00 282.90 -- 784.90
39 10 26.50-13.20mm(DBM) 1040.39 282.90 -- 1323.29
39 10 13.20-2.36mm(DBM) 551.83 282.90 -- 834.73
39 10 2.36 & below(DBM) 502.00 282.90 -- 784.90
39 10 Stone Dust(DBM) 108.95 204.96 -- 313.91
39 10 37.50-13.20mm(DBM) 923.74 282.90 -- 1206.64
39 10 13.20-2.36mm(DBM) 535.52 282.90 -- 818.42
39 10 2.36 & below(DBM) 502.00 282.90 -- 784.90
39 10 13.20mm-11.20mm(CGPS) 763.00 282.90 -- 1045.90
39 10 11.20mm-5.60mm (CGPS) 566.00 282.90 -- 848.90
39 10 5.60mm-2.8mm (CGPS) 502.00 282.90 -- 784.90
39 10 2.80mm and below (CGPS) 502.00 282.90 -- 784.90
39 10 2.36 & below (BC 50) 502.00 282.90 -- 784.90
39 10 26.50 - 13.20mm(BC 50) 1107.84 282.90 -- 1390.74
39 10 13.20-2.36mm(BC 50) 568.14 282.90 -- 851.04
39 10 2.36 & below (BC) 502.00 282.90 -- 784.90
39 10 19.00-9.50mm(BC) 849.64 282.90 -- 1132.54
39 10 9.50-2.36mm(BC) 533.68 282.90 -- 816.58

Road Data - Rev-17.6 26 Revised during - OCT. 2017


CONSTRUCTION OF EARTHEN EMBANKMENT (Only for new formation of subgrade)
Formation of embankment with earth from quarrying place and compaction by power roller
(100% compaction) including cost and conveyance of the earth to worksite, including all labour
charges for laying, spreading etc, including all hire and fuel charges all tools and plants

Hire charges for Machineries

Power Roller8-10 tonne


Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1086.20
Total Hire charges per day including Fuel =Rs. 1941.20
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 1941.20 =Rs. 4.57 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2571.06
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2571.06 =Rs. 2.57 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.57 + 2.57 =Rs. 7.14 /Cum
Labour charges for Laying Earth for 100cum

2.00 Nos. of Mazdoor Ist Class @Rs. 446.60 /E =Rs. 893.20


Total Labour charges for laying earth per 100cum =Rs. 893.20

Total Labour charges for laying earth per Cum 893.20 =Rs. 8.93 /Cum
100
Total Hire and Labour charges = 7.14 + 8.93 =Rs. 16.07 /Cum

Cost of Earth (as per 137 Industries (MMC 2) =Rs. 62.00 /Cum
Department dated 10.09.2014)
Excavation Charges as per PWD rates (SS 20 B) =Rs. 506.00 /Cum
Seigniorage fee per cum ( GO (Ms) No. 6, Industries =Rs. 20.00 /Cum
(MMB1) Department dated 11.1.2001)
Cost of earth per cum at quarrying place =Rs. 588.00 /Cum

Road Data - Rev-17.6 27 Revised during - OCT. 2017


Earth work for formation of embankment (100% compaction)
(For new formation of subgrade)
Km 0/0 - 1/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. 877.30 /Cum. = 1017.67
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. = 16.07
Rate for 1.00 cum. Rs. 1033.74

Km 1/0 - 2/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

Km 2/0 - 3/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

Km 3/0 - 4/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

Km 4/0 - 5/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

Km 5/0 - 6/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.6 28 Revised during - OCT. 2017


Labour Charges for Patch Work with Bituminous Premix Materials
for 0.625 cum of Bituminous Materials
Picking the road surface 2" to 3" deep
1. In patches and cutting Mazdoor Ist Class 1.08 x 1/6 x 446.60 /No - 80.39

2. Removing the Picked up stuff Mazdoor Ist 1.08x1/8x 446.60 /No - 60.29

3. Brushing and Cleaning the Surface - - L. S. - - - 3.78

4. Spreading the Bitumen for Tack Coat excluding cost of Bitumen -L.S.- - 3.10

5. Premixing the chips with hot Bitumen in the drum mixer and laying
0.625 cum of metal with 44 kg per cum of chips excluding the cost of the
bitumen - - L. S. - - - 15.75

6. Levelling and tamping the premix in the patches and pot holes rolling etc - 4.73

7 Special tools such as wire brushes etc., - L. S. - - - 2.31

8. Regulation of Traffic - - L.S. - - - 2.50

9. Sundries such as barricading arrangements - L. S. - - - -172.85

Labour for laying 0.625 cum of Bituminlous materials -

Therefore for laying 1.00 cum of Bituminous materials 0/0.625 =

Rs. /Cum.

Picking 5cm to 10cm old metalled surface and sectioning 1Sqm.

Labour for 10Sqm.


Mazdoor Class-I 1/4 X 1.08 No. @ Rs.446.60 Each = Rs.120.58/10sqm.

Picking 5cm to 10cm old metalled surface and sectioning 1Sqm. = 12.06 /Sqm.

Road Data - Rev-17.6 29 Revised during - OCT. 2017


Patch work using 45mm IRC metal
Km 0/0 - 1/0 2 16
1.00 Cum. Cost of 45mm IRC at Rs. 1319.28 /cum. = 1319.28
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2445.25

Km 1/0 - 2/0 18
1.00 Cum. Cost of 45mm IRC at Rs. 885.36 /cum. = 885.36
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2011.33

Km 2/0 - 3/0 34
1.00 Cum. Cost of 45mm IRC at Rs. 894.05 /cum. = 894.05
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2020.02

Km 3/0 - 4/0 50
1.00 Cum. Cost of 45mm IRC at Rs. 902.74 /cum. = 902.74
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2028.71

Km 4/0 - 5/0 66
1.00 Cum. Cost of 45mm IRC at Rs. 911.43 /cum. = 911.43
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2037.40

Km 5/0 - 6/0 82
1.00 Cum. Cost of 45mm IRC at Rs. 920.12 /cum. = 920.12
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2046.09

98
1.00 Cum. Cost of 45mm IRC at Rs. /cum. =
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT =
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.6 30 Revised during - OCT. 2017


Patch work using 13.20mm IRC metal
Km 0/0 - 1/0 10 16
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1578.28 /cum. = 1578.28
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2704.25

Km 1/0 - 2/0 26
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1144.36 /cum. = 1144.36
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2270.33

Km 2/0 - 3/0 42
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1153.05 /cum. = 1153.05
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2279.02

Km 3/0 - 4/0 58
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1161.74 /cum. = 1161.74
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2287.71

Km 4/0 - 5/0 74
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1170.43 /cum. = 1170.43
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2296.40

Km 5/0 - 6/0 90
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1179.12 /cum. = 1179.12
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2305.09

106
1.00 Cum. Cost of 13.20 mm IRC at Rs. /cum. =
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT =
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.6 31 Revised during - OCT. 2017


BITUMINOUS MACADAM 50MM THICK USING MINI HOT MIX PLANT
Providing and Laying 50mm thick Bituminous Macadam using course aggregate and VG30
bitumen which shall consist of construction in a single course base/binder course confirming
to the specfication on a previously prepared base.(using Mini Hot Mix Plant and Power
Roller) including cost of material, labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 504 MORTH Rev-5 (Mix-in-place method)
Hire charges for Machineries

Mini Hot Mix Plant


Hire charges excluding fuel charges per hour 1674 /8 =Rs. 209.25
Fuel charges per hour diesel (running plant) 15.00 Lit x 54.31 /lit =Rs. 814.65
Fuel for heating aggregates per hour 45.00 Lit x 23.81 /lit =Rs. 1071.45
Total Hire charges including Fuel =Rs. 2095.35
Daily Out turn for BM 50mm thick = 75 sqm.
Hire charges of Mini Hot Mix Plantper 10 sqm. 2095.35 x 10 =Rs. 279.38
75
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day (Diesel)2.50 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1086.20
Total Hire charges per day including Fuel =Rs. 1941.20
Daily Out turn for BM 50mm thick = 300 sqm
Hire charges for BM 50mm thick per 10 sqm. 1941.20 x 10 =Rs. 64.71
300
Bitumen Boiler 750 lit capacity
Hire charges excluding fuel charges per day =Rs. 202.00
Fuel charges per day Kerosene 25.00 Lit x 45.68 /lit =Rs. 1142.00
Total Hire charges per day including Fuel =Rs. 1344.00
Hire and fuel charges of boiler per hour = 1344.00 /8 =Rs. 168.00
Daily Out turn of Bitumen Boiler per hour = 125 Kg.
Bitumen Required for BM 50mm thick per 10 sqm = 37 kg
Bitumen to be utilised for PC (14.6 kgs) 125x10/37 = 33.784 sqm
Hire charges for PC per 10 sqm = 1344x10 = 13440.00 = 49.73
8x33.784 270.27
Total Hire Charges for Machineries per 10 sqm =Rs. 393.82

Labour charges for BM 50mm thick per 1200sqm


83 Nos. Cost of Mazdoor Ist Class @Rs. 446.60 /E =Rs. 37067.80
55 Nos. Cost of Mazdoor IInd Class @Rs. 400.40 /E =Rs. 22022.00
Total Labour charges for BM 50mm thick per 1200sqm =Rs. 59089.80

Labour charges for BM 50mm thick per 10 sqm. 59089.80 x 10 =Rs. 492.42
1200

Total Hire and Labour charges per 10sqm = 393.82 + 492.42 =Rs. 886.24

Road Data - Rev-17.6 32 Revised during - OCT. 2017


BITUMINOUS MACADAM 50MM THICK (For Patch Works)
Km 0/0 - 1/0 3 16
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1557.12 /cum. = 311.42
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 1004.94 /cum. = 432.12
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 953.30 /cum. = 76.26
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2683.96
Rate per cum of 50 mm thick = 2683.96 /0.50 = Rs. 5367.92

Km 1/0 - 2/0 19
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1123.20 /cum. = 224.64
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 571.02 /cum. = 245.54
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 519.38 /cum. = 41.55
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2375.89
Rate per cum of 50 mm thick = 2375.89 /0.50 = Rs. 4751.78

Km 2/0 - 3/0 35
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1131.89 /cum. = 226.38
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 579.71 /cum. = 249.28
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 528.07 /cum. = 42.25
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2382.07
Rate per cum of 50 mm thick = 2382.07 /0.50 = Rs. 4764.14

Km 3/0 - 4/0 51
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1140.58 /cum. = 228.12
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 588.40 /cum. = 253.01
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 536.76 /cum. = 42.94
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2388.23
Rate per cum of 50 mm thick = 2388.23 /0.50 = Rs. 4776.46

Road Data - Rev-17.6 33 Revised during - OCT. 2017


BITUMINOUS MACADAM 50MM THICK (For Patch Works)
Km 4/0 - 5/0 67
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1149.27 /cum. = 229.85
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 597.09 /cum. = 256.75
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 545.45 /cum. = 43.64
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2394.40
Rate per cum of 50 mm thick = 2394.40 /0.50 = Rs. 4788.80

Km 5/0 - 6/0 83
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1157.96 /cum. = 231.59
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 605.78 /cum. = 260.49
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 554.14 /cum. = 44.33
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2400.57
Rate per cum of 50 mm thick = 2400.57 /0.50 = Rs. 4801.14

99
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. /cum. =
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. /cum. =
0.08 Cum. Cost of 2.36mm & below IRC at Rs. /cum. =
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire charges at Rs. 393.82 /10sqm =
10.00 Sqm Labour charges at Rs. 492.42 /10sqm =
Rate for 10 sqm =Rs.
Rate per cum of 50 mm thick = = Rs.

115
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. /cum. =
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. /cum. =
0.08 Cum. Cost of 2.36mm & below IRC at Rs. /cum. =
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire charges at Rs. 393.82 /10sqm =
10.00 Sqm Labour charges at Rs. 492.42 /10sqm =
Rate for 10 sqm =Rs.
Rate per cum of 50 mm thick = = Rs.

Road Data - Rev-17.6 34 Revised during - OCT. 2017


DRY LEAN CEMENT CONCRETE
Quantity Unit Rate Unit Amount
Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub-
base over a prepared sub-grade with coarse and
fine aggregate conforming to IS: 383, the size of
coarse aggregate not exceeding 25 mm,
aggregate cement ratio not to exceed 15:1,
aggregate gradation after blending to be as per
table 600-1, cement content not to be less than
150 kg/ cum, concrete strength not to be less
than 10 Mpa at 7 days, mixed at site, compacted
using vibrator, finishing and curing.

output = 10 cum
a) Labour
1.800 day Mason II CLass 404.00 /day 727.20
17.700 day Mazdoor I CLass 282.00 /day 4991.40
14.100 day Mazdoor II CLass 255.00 /day 3595.50
b) Machinery
10.000 cum Vibrator Charges 44.31 443.10
9757.20

Road Data - Rev-17.6 35 Revised during - OCT. 2017


DRY LEAN CEMENT CONCRETE
Km 0/0 - 1/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92 2234.75
1.00 Cum Cost of Sand at Rs. 568.19 /Cum 568.19
2802.94

Data for DLC


Crushed stone coarse aggregate of 25 mm as
9.00 Cum at Rs. 1180.30 /Cum 10622.70
per table 600-1 and conforming to clause
4.50 Cum Cost of CM at Rs. 2802.94 /Cum 12613.23
1.067 KL Cost of Water at Rs. 130.00 /KL 138.67
10.00 Cum Hire and labour for DLC (per 10 cum) at Rs. 9757.20 9757.20
33131.80

Rate per cum = 33131.8 /10 3313.18


Km 1/0 - 2/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92
1.00 Cum Cost of Sand at Rs.

Data for DLC


Crushed stone coarse aggregate of 25 mm as
9.00 Cum at Rs. 746.38 /Cum 6717.42
per table 600-1 and conforming to clause
4.50 Cum Cost of CM at Rs.
1.067 KL Cost of Water at Rs. 130.00 /KL
10.00 Cum Hire and labour for DLC (per 10 cum) at Rs. 9757.20

Rate per cum


Km 2/0 - 3/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92
1.00 Cum Cost of Sand at Rs.

Data for DLC


Crushed stone coarse aggregate of 25 mm as
9.00 Cum at Rs. 755.07 /Cum 6795.63
per table 600-1 and conforming to clause
4.50 Cum Cost of CM at Rs.
1.067 KL Cost of Water at Rs. 130.00 /KL
10.00 Cum Hire and labour for DLC (per 10 cum) at Rs. 9757.20

Rate per cum

Road Data - Rev-17.6 36 Revised during - OCT. 2017


DRY LEAN CEMENT CONCRETE
Km 3/0 - 4/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92
1.00 Cum Cost of Sand at Rs.

Data for DLC


Crushed stone coarse aggregate of 25 mm as
9.00 Cum at Rs. 763.76 /Cum 6873.84
per table 600-1 and conforming to clause
4.50 Cum Cost of CM at Rs.
1.067 KL Cost of Water at Rs. 130.00 /KL
10.00 Cum Hire and labour for DLC (per 10 cum) at Rs. 9757.20

Rate per cum

Km 4/0 - 5/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92
1.00 Cum Cost of Sand at Rs.

Data for DLC


Crushed stone coarse aggregate of 25 mm as
9.00 Cum at Rs. 772.45 /Cum 6952.05
per table 600-1 and conforming to clause
4.50 Cum Cost of CM at Rs.
1.067 KL Cost of Water at Rs. 130.00 /KL
10.00 Cum Hire and labour for DLC (per 10 cum) at Rs. 9757.20

Rate per cum


Km 5/0 - 6/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92
1.00 Cum Cost of Sand at Rs.

Data for DLC


Crushed stone coarse aggregate of 25 mm as
9.00 Cum at Rs. 781.14 /Cum 7030.26
per table 600-1 and conforming to clause
4.50 Cum Cost of CM at Rs.
1.067 KL Cost of Water at Rs. 130.00 /KL
10.00 Cum Hire and labour for DLC (per 10 cum) at Rs. 9757.20

Rate per cum

Road Data - Rev-17.6 37 Revised during - OCT. 2017


Granular Sub-Base with Close Graded Material (Table:- 400-1)

Description Unit Quantity Rate (Rs) Cost (Rs)


A Plant Mix Method
Construction of granular sub-base by providing close graded Material, mixing in a
mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in
uniform layers with motor grader on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as per clause 401
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 460.60 184.24
Mazdoor skilled day 2.000 446.60 893.20
Mazdoor day 8.000 400.40 3203.20
4280.64
b) Machinery
Wet Mix Plant 75 tonne capacity/ hr hour 6.000 104.36 626.16
Electric generator 125 KVA hour 6.000 647.38 3884.28
Water tanker 6 KL capacity 5 km lead with hour 4.500 276.59 1244.66
one trip per hour
Front end loader 1 cum bucket capacity hour 6.000 693.73 4162.38
Tipper 10 tonne; conveyance: 51 km tonne.km 450 x L 2.00 45900.00
Add 10 per cent of cost of carriage to 4590.00
cover loading and unloading
Motor Grader 110 HP hour 6.000 1691.63 10149.78
Vibratory roller 8-10 t hour 6.000 814.28 4885.68
75442.94
c) Material as per table 400-1
For Grading-V Material (Drainage/ Top Layer)
Cost of 53mm to 9.50mm Broken Stone cum 144.000 1174.68 169153.92
Cost of 9.50mm to 2.36mm Broken Stone cum 100.000 823.30 82330.00
Cost of 2.36mm & Below of Sand cum 43.000 784.90 33750.70
Cost of water KL 27.000 130.00 3510.00
288744.62
For Grading-III Material (Bottom Layer if thickness more than 300mm)
46.5 mm to 26.50 mm cum 101.000 1144.90 115634.90
26.5 mm to 4.75 mm cum 130.000 1087.33 141352.90
4.75 mm below cum 58.000 784.90 45524.20
Cost of water KL 27.000 130.00 3510.00
306022.00
(i) Rate per cum for grading-V Material
Cost for 225 cum = a+b+c 368468.20
Rate per cum = (a+b+c)/225 Rs.1637.64/Cum.

(ii) Rate per cum for grading-III Material


Cost for 225 cum = a+b+c 385745.58
Rate per cum = (a+b+c)/225 Rs.1714.42/Cum.

Road Data - Rev-17.6 38 Revised during - OCT. 2017


WET MIX MACADAM
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam
250 mm thick specification including premixing the materials with water at OMC in mechnanical
mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub
Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the
desired density including cost of material, labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 406 of MORTH Rev-5
Hire Charges for Machineries
Loader 5 Cum. Capacity
Hire charges excluding fuel charges per day =Rs. 1205.00
Fuel charges per day 80 lit.of diesel 54.31 /lit =Rs. 4344.80

Total Hire charges per day including Fuel =Rs. 5549.80


Total Hire charges per Hour including Fuel =Rs. 693.73

Tipper
Hire charges excluding fuel charges per day =Rs. 1094.00
Fuel charges per day 3.25lit.of diesel x 8hrs 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2506.06
Total Hire charges per Hour including Fuel =Rs. 313.26

Water Tankers
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day 25lit.of diesel 54.31 /lit =Rs. 1357.75
Total Hire charges per day including Fuel =Rs. 2212.75
Total Hire charges per Hour including Fuel =Rs. 276.59
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day 3.00lit.of diesel x 8hrs 54.31 /lit =Rs. 1303.44
Total Hire charges per day including Fuel =Rs. 6731.44
Total Hire charges per Hour including Fuel =Rs. 841.43

Motor Grader including fuel per Hour (Local Rate) =Rs. 1691.63
Base Mix Plant (pug mill) including fuel per hour (local rate) =Rs. 834.88

Total Hire Charges for machineries for 100 Cum of WMM


1. Loader for 6 Hours 693.73 /hr. =Rs. 4162.38
2. Base Mix Plant (Pug Mill) for 6 Hours 834.88 /hr. =Rs. 5009.28
3. Tipper for 24 Hours 313.26 /hr. =Rs. 7518.24
4. Water Tanker for 24 Hours 276.59 /hr. =Rs. 6638.16
5. Motor Grader for 4 Hours 1691.63 /hr. =Rs. 6766.52
6. Vibratory Roller for 6 Hours 841.43 /hr. =Rs. 5048.58
Total Hire Charges for machineries for 100 Cum of WMM =Rs. 35143.16

Total Hire Charges for machineries for 1.00 Cum of WMM =Rs. 351.43 /Cum.

Road Data - Rev-17.6 39 Revised during - OCT. 2017


Labour Charges for 100 cum of WMM
0.50 Nos. of Head Mazdoor @ Rs. 460.60 /E =Rs. 230.30
8.63 Nos. of Mazdoor Ist Class @ Rs. 446.60 /E =Rs. 3854.16
2.00 Nos. of Mazdoor IIst Class @ Rs. 400.40 /E =Rs. 800.80
Total Labour Charges of 100 cum of WMM =Rs. 4885.26

Total Labour Charges of 1.00 cum of WMM =Rs. 48.85 /Cum.


Total Hire and Labour charges = 351.43 + 48.85 =Rs. 400.28 /Cum.

WET MIX MACADAM 250 mm thick

0.396 Cum. Cost of 45-22.40mm IRC at Rs. 1208.70 /cum. = 478.65


0.528 Cum. Cost of 22.40-2.36mm IRC at Rs. 1039.76 /cum. = 548.99
0.396 Cum. Cost of 2.36mm IRC at Rs. 784.90 /cum. = 310.82
0.08 KL Cost of water at Rs. 130.00 / KL = 10.40
1.00 cum. Hire & Labour charges at Rs. 400.28 /cum. = 400.28
Rate for 1.00 cum. Rs. 1749.14

Road Data - Rev-17.6 40 Revised during - OCT. 2017


CRUSHER RUN MACADAM
Providing and laying, spreading and compacting graded stone aggregates to Crusher
Run Macadam specification including premixing the materials with water at OMC in
mechnanical mix plant carriage of mixed material by tipper to site laying in uniform
layers with pavers in Sub Base/ Base course on well prepared surface and compacting
with vibratory roller to acheive the desired density including cost of material, labour
charges, rentals for machinery, fuel and all other incidental charges etc., complete as
Hire charges for Machineries
Loader 5 Cum. Capacity
Hire charges excluding fuel charges per day =Rs. 1205.00
Fuel charges per day 80 lit.of diesel 54.31 /lit =Rs. 4344.80

Total Hire charges per day including Fuel =Rs. 5549.80


Total Hire charges per Hour including Fuel =Rs. 693.73

Tipper
Hire charges excluding fuel charges per day =Rs. 1094.00
Fuel charges per day 3.25lit.of diesel x 8hrs 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2506.06
Total Hire charges per Hour including Fuel =Rs. 313.26

Water Tankers
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day 25lit.of diesel 54.31 /lit =Rs. 1357.75
Total Hire charges per day including Fuel =Rs. 2212.75
Total Hire charges per Hour including Fuel =Rs. 276.59
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day 3.00lit.of diesel x 8hrs 54.31 /lit =Rs. 1303.44
Total Hire charges per day including Fuel =Rs. 6731.44
Total Hire charges per Hour including Fuel =Rs. 841.43

Motor Grader including fuel per Hour =Rs. 1691.63

Total Hire Charges for machineries for 100 Cum of CRM


1. Loader for 6 Hours 693.73 /hr. =Rs. 4162.35
2. Tipper for 24 Hours 313.26 /hr. =Rs. 7518.18
3. Water Tanker for 24 Hours 276.59 /hr. =Rs. 6638.16
4. Motor Grader for 4 Hours 1691.63 /hr. =Rs. 6766.52
5. Vibratory Roller for 6 Hours 841.43 /hr. =Rs. 5048.58
Total Hire Charges for machineries for 100 Cum of CRM =Rs. 30133.79

Total Hire Charges for machineries for 1.00 Cum of CRM =Rs. 301.34

Road Data - Rev-17.6 41 Revised during - OCT. 2017


Labour Charges for 100 cum of CRM
0.50 Nos. of Head Mazdoor @ Rs. 460.60 /E =Rs. 230.30
8.63 Nos. of Mazdoor Ist Class @ Rs. 446.60 /E =Rs. 3854.16
2.00 Nos. of Mazdoor IIst Class @ Rs. 400.40 /E =Rs. 800.80
Total Labour Charges of 100 cum of CRM =Rs. 4885.26

Total Labour Charges of 1.00 cum of CRM =Rs. 48.85


Total Hire and Labour charges per cum. = 301.34 + 48.85 =Rs. 350.19

CRUSHER RUN MACADAM 300mm THICK

0.09 Cum Cost of 53-45mm IRC 0.090 @Rs 1074.57 /cum 96.71
0.46 Cum. Cost of 45-22.40mm IRC 0.460 @Rs 1208.70 /cum 556.00
0.30 Cum. Cost of 22.40-5.6mm IRC 0.300 @Rs 999.90 /cum 299.97
0.46 Cum. Cost of 900mm Micron and below 0.460 @Rs 784.90 /cum 361.05
1.00 Cum Hire & Labour charges 1.00 @Rs 350.19 /cum 350.19
Rate for 1.00 cum. Rs. 1663.92

Road Data - Rev-17.6 42 Revised during - OCT. 2017


BITUMINOUS MACADAM 50MM THICK USING CMP
Providing and laying 50mm consolidated thick bituminous macadam using 0.20 cum fo 26.50-
13.20mm, 0.43 cum of 13.20-2.36mm and 0.08 cum of 2.36mm & below size IRC metal with 37
Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them
in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper
trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to
the required density etc., including labour for attending to paver to site etc., including hire charges
and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver
finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all
other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH
Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for BM = 135sqm. of 50 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 554.39


135
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 350sqm. of 50 mm thick

Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 23.27
350
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 46.80
135

Road Data - Rev-17.6 43 Revised during - OCT. 2017


4. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per hour Rs. 313.26
Out turn of Tipper Truck per hour = 135 sqm. of 50 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 139.23
135

Total hire charges for machineries per 10 sqm =


554.39+ 23.27+ 46.80+ 139.23
= 763.69 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 243.45


1200

RATE PER CUM OF 50MM THICK BITUMINOUS MACADAM

0.200 Cum Cost of 26.5-13.20mm IRC at Rs. 1388.72 /cum. = 277.74


0.430 Cum Cost of 13.20-2.36mm IRC at Rs. 836.54 /cum. = 359.71
0.080 Cum Cost of 2.36mm & below IRC at Rs. 784.90 /cum. = 62.79
37.00 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 976.22
10.00 Sqm Hire charges at Rs. 763.69 /10sqm = 763.69
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 2683.60

Rate per cum of 50 mm thick = 2683.60 = Rs. 5367.20


0.50

Road Data - Rev-17.6 44 Revised during - OCT. 2017


DENSE BITUMINOUS MACADAM 50MM THICK USING CMP
Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24 cum of 26.50-
13.20mm, 0..25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30/
VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site,
heating the bitumen and aggregate to required temperature and mixing them in required temperature in
central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the
mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted
by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at
site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,
Paver Finisher / 9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required,
including fuel and all other incidental charges etc., complete as per specification using CMP as per clause
505 MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for BM = 135sqm. of 50 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 554.39


135
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 320sqm. of 50 mm thick

Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 25.45
320
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 46.80
135

Road Data - Rev-17.6 45 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 135 sqm. of 50 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 139.23
135

Total hire charges for machineries per 10 sqm = 554.39+ 25.45+ 46.80+ 139.23
= 765.87 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 243.45


1200

RATE PER CUM OF 50MM THICK DENSE BITUMINOUS MACADAM

0.240 Cum Cost of 26.50 - 13.20mm IRC at Rs. 1323.29 /cum. = 317.59
0.250 Cum Cost of 13.20-2.36mm IRC at Rs. 834.73 /cum. = 208.68
0.230 Cum Cost of 2.36mm & below IRC at Rs. 784.90 /cum. = 180.53
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 313.91 /cum. = 0.00
53.20 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1403.64
10.00 Sqm Hire charges at Rs. 765.87 /10sqm = 765.87
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 3119.76

Rate per cum of 50 mm thick = 3119.76 = Rs. 6239.52


0.50

Road Data - Rev-17.6 46 Revised during - OCT. 2017


BITUMINOUS MACADAM 80MM THICK USING CMP
Providing and laying 80mm consolidated thick bituminous macadam using 0.64 cum fo 37.5 -
13.20mm, 0.44 cum of 13.2 - 2.36mm and 0.13 cum of 2.36mm and below size IRC metal with 62
Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them
in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper
trucks to paver site, spreading the mix to uniform thickness of 80mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to
the required density etc., including labour for attending to paver to site etc., including hire charges
and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,Paver Finisher / 9m paver
finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all
other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH
Rev-5.
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696.00 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for BM = 90sqm. of 75 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 831.58


90
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 250sqm. of 80 mm thick

Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 32.57
250

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 90 sqm. of 80 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 70.19
90

Road Data - Rev-17.6 47 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 90 sqm. of 75 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 208.84
90

Total hire charges for machineries per 10 sqm 831.58


= +32.57 +70.19 +208.84
= 1143.18 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1000sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 292.14


1000

RATE PER CUM OF 80MM THICK BITUMINOUS MACADAM

0.640 Cum Cost of 37.50-13.20mm IRC at Rs. 1237.97 /cum. = 792.30


0.440 Cum Cost of 13.20-2.36mm IRC at Rs. 860.10 /cum. = 378.44
0.130 Cum Cost of 2.36mm & below at Rs. 784.90 /cum. = 102.04
62.00 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1635.82
10.00 Sqm Hire charges at Rs. 1143.18 /10sqm = 1143.18
10.00 Sqm Labour charges at Rs. 292.14 /10sqm = 292.14
Rate for 10 sqm =Rs. 4343.92

Rate per cum of 80 mm thick = 4343.92 = Rs. 5429.90


0.80

Road Data - Rev-17.6 48 Revised during - OCT. 2017


DENSE BITUMINOUS MACADAM 75MM THICK USING CMP
Providing and laying 75mm consolidated thick Dense Bituminous macadam using 0.40 cum fo 37.50-
13.20mm, 0.35 cum of 13.20-2.36mm and 0.36 cum of 2.36mm & below size IRC metal with 71.30 kgs
of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP
site, heating the bitumen and aggregate to required temperature and mixing them in required temperature
in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the
mix to uniform thickness of 75mm with mechanical paver to the specified grades and cross sections and
consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc., including labour for
attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen
boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools
and plant required, including fuel and all other incidental charges etc., complete as per specification
using CMP as per clause 505 of MORTH rev-5.

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for DBM = 90sqm. of 75 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 831.58


90
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 220sqm. of 75 mm thick

Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 37.01
220

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 90 sqm. of 75 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 70.19
90

Road Data - Rev-17.6 49 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 90 sqm. of 75 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 208.84
90

Total hire charges for machineries per 10 sqm =831.58 37.01 70.19 208.84
= 1147.62 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1000sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 292.14


1000

RATE PER CUM OF 75MM THICK DENSE BITUMINOUS MACADAM

0.400 Cum Cost of 37.50-13.20mm IRC at Rs. 1206.64 /cum. = 482.66


0.350 Cum Cost of 13.20-2.36mm IRC at Rs. 818.42 /cum. = 286.45
0.360 Cum Cost of 2.36mm & Below IRC at Rs. 784.90 /cum. = 282.56
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 313.91 /cum. = 0.00
71.30 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1881.20
10.00 Sqm Hire charges at Rs. 1147.62 /10sqm = 1147.62
10.00 Sqm Labour charges at Rs. 292.14 /10sqm = 292.14
Rate for 10 sqm =Rs. 4372.63

Rate per cum of 75 mm thick = 4372.63 = Rs. 5830.17


0.75

Road Data - Rev-17.6 50 Revised during - OCT. 2017


Prime Coat Over WBM/ WMM Surface

Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen
(SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of
material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 446.60 /each =Rs 4466.00
16.00 Nos Mazdoor IIst Grade @Rs 400.40 /each =Rs 6406.40
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 400.40 /each =Rs 1601.60
Total Labour Charges per 500 sqm =Rs 12474.00

Total Labour Charges per 10 sqm = 12474.00 x10 Rs. 249.48


500
Rate for Prime Coat over WBM/ WMM surface

7.00 Kgs Cost of Bitumen Emulsion - SS1 @Rs 48987.04 /MT =Rs 342.91
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 249.48 /10sqm =Rs 249.48
Rate for 10 sqm =Rs 607.39

Rate per 1.00 sqm =Rs 60.74 /sqm

Prime Coat Over CRM/ Gravel base


Providing and laying Prime Coat over CRM/ Gravel base using 9 Kg of Emulsion Bitumen
(SS1) per 10 sqm for preparatory to another bituminous construction over it including cost of
material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 446.60 /each =Rs 4466.00
16.00 Nos Mazdoor IIst Grade @Rs 400.40 /each =Rs 6406.40
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 400.40 /each =Rs 1601.60
Total Labour Charges per 500 sqm =Rs 12474.00

Total Labour Charges per 10 sqm =


12474.00 x10 Rs. 249.48
500
Rate for Prime Coat over Crusher Run Macadam surface

9.00 Kgs Cost of Bitumen Emulsion (SS1) @Rs 48987.04 /MT =Rs 440.88
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 249.48 /10sqm =Rs 249.48
Rate for 10 sqm =Rs 705.36
Rate per 1.00 sqm =Rs 70.54 /sqm

Road Data - Rev-17.6 51 Revised during - OCT. 2017


Tack Coat Over Existing BT Surface

Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion
(RS1) per 10 sqm for preparatory to another bituminous construction over it including cost
of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 503 of MORTH Rev-5

Labour Charges per 500 sqm


5.00 Nos Mazdoor Ist Grade Preparing Surface @Rs 446.60 /each =Rs 2233.00
5.00 Nos Mazdoor IIst Grade(Applying TC)@Rs 400.40 /each =Rs 2002.00
Total Labour Charges per 500 sqm =Rs 4235.00

Total Labour Charges per 10 sqm = 4235.00 x10 Rs. 84.70


500
Rate for Tack Coat over Existing BT surface

2.00 Kgs Cost of RS-I Bitumen emulsion @Rs 29258.59 /MT =Rs 58.52
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 sqm Labour Charges @Rs 84.70 /10sqm =Rs 84.70
Rate for 10 sqm =Rs 158.22

Rate per 1.00 sqm =Rs 15.82 /sqm

Tack Coat Over Primed Surface

Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using
2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous
construction over it including cost of material, labour charges, rentals for machinery, fuel
and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm
3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 400.40 /each =Rs 1201.20
Total Labour Charges per 500 sqm =Rs 1201.20

Total Labour Charges per 10 sqm =


1201.20 x10 Rs. 24.02
500
Rate for Tack Coat over primed WBM / WMM Surface

2.50 Kgs Cost of RS-I Bitumen emulsion @Rs 29258.59 /MT =Rs 73.15
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 24.02 /10sqm =Rs 24.02
Rate for 10 sqm =Rs 112.17

Rate per 1.00 sqm =Rs 11.22 /sqm

Road Data - Rev-17.6 52 Revised during - OCT. 2017


Tack Coat over Dry Lean Cement Concrete Surface

Providing and laying Tack Coat over Dry Lean Cement Concrete surface using 3.00 Kg of
Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it
including cost of material, labour charges, rentals for machinery, fuel and all other incidental
charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm

3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 400.40 /each =Rs 1201.20
Total Labour Charges per 500 sqm =Rs 1201.20

Total Labour Charges per 10 sqm =


1201.20 x10 Rs. 24.02
500
Rate for Tack Coat over Dry Lean Cement Concrete Surface

3.00 Kgs Cost of RS-I Bitumen emulsion @Rs 29258.59 /MT =Rs 87.78
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 24.02 /10sqm =Rs 24.02
Rate for 10 sqm =Rs 126.80

Rate per 1.00 sqm =Rs 12.68 /sqm

Road Data - Rev-17.6 53 Revised during - OCT. 2017


PREMIX CARPET WITH SEAL COAT TYPE - A
Providing and laying compacting open graded premix carpet 20mm thick with a liquid seal
coat which shall consist of open graded carpet of 20mm thickness in a single course
composed of suitable small sized aggregates premixed with bituminous binder (VG30) with
application of liquid seal coat for sealing the voids in a bituminous surface conforming to
the specifications including cost of material, labour charges, rentals for machinery, fuel and
all other incidental charges etc., complete as per MORTH Rev-5 (Mix-in-place method)
Hire Charges for Machineries
Mini Hot Mix Plant
Hire charges excluding fuel charges per hour 1674 /8 =Rs. 209.25
Fuel charges per hour diesel (running plant) 15.00 Lit x 54.31 /lit =Rs. 814.65
Fuel for heating aggregates per hour 45.00 Lit x 23.81 /lit =Rs. 1071.45
Total Hire charges including Fuel =Rs. 2095.35
Daily Out turn for Premix Carpet = 180 sqm.
Hire charges of Mini Hot Mix Plantper 10 sqm. 2095.35 x 10 =Rs. 116.41
Power Roller 8-10 tonne 180
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day (Diesel)2.50 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1086.20
Total Hire charges per day including Fuel =Rs. 1941.20
Daily Out turn of road roller for Premix Carpet = 500 sqm
Daily Out turn for Seal Coat = 1000 sqm
Hire charges for Premix Carpet per 10 sqm. 1941.20 x 10 =Rs. 38.82
500
Hire charges for Seal Coat per 10 sqm. 1941.20 x 10 =Rs. 19.41
1000
Total hire charges for power roller (PC+SC)= =38.82 + 19.41 =Rs. 58.23
Bitumen Boiler 750 lit capacity
Hire charges excluding fuel charges per day =Rs. 202.00
Fuel charges per day Kerosene 25.00 Lit x 45.68 /lit =Rs. 1142.00
Total Hire charges per day including Fuel =Rs. 1344.00
For Premix carpet
Daily Out turn of Bitumen Boiler per hour 125 Kg.
Bitumen to be utilised for PC (14.6 kgs) 125x10/14.6 = 85.62 sqm
Hire charges for PC per 10 sqm = 1344x10 = 13440.00 = 19.62
8x85.62 684.96
For seal coat
Bitumen to be utilised for SC (9.80 kgs) 125x10/9.8 = 127.551 sqm
Hire charges for seal coat/ 10sqm = 1344x10 = 13440.00 = 13.17
8x127.551 1020.41
Total Hire Charges for Machineries per 10 sqm (PC+SC)= 116.41+58.23+19.62+13.17
Total Hire Charges for Machineries per 10 sqm (PC+SC) =Rs. 207.43
Labour charges for Premix Carpet with Seal Coat per 10sqm
0.75 Nos. Mazdoor Ist Class @Rs. 446.60 /E =Rs. 334.95
0.25 Nos. Mazdoor Ist Class @Rs. 446.60 /E =Rs. 111.65
Total Labour charges for Premix Carpet and Seal Coat per 10sqm =Rs. 446.60
Total Hire and Labour charges per 10sqm = 207.43 + 446.60 =Rs. 654.03

Road Data - Rev-17.6 54 Revised during - OCT. 2017


Premix carpet with Seal Coat
Km 0/0 - 1/0
0.18 Cum. Cost of 13.20mm IRC at Rs. 1578.28 /cum.= 284.09
0.09 Cum. Cost of 11.20mm IRC at Rs. 1217.28 /cum. = 109.56
0.09 Cum. Cost of 6.70mm IRC at Rs. 1020.28 /cum. = 91.83
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1784.41
Rate for 1 sqm. =Rs. 178.44 /sqm.

Km 1/0 - 2/0 21
0.18 Cum. Cost of 13.20mm IRC at Rs. 1144.36 /cum.= 205.98
0.09 Cum. Cost of 11.20mm IRC at Rs. 783.36 /cum. = 70.50
0.09 Cum. Cost of 6.70mm IRC at Rs. 586.36 /cum. = 52.77
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1628.18
Rate for 1 sqm. =Rs. 162.82 /sqm.

Km 2/0 - 3/0 42
0.18 Cum. Cost of 13.20mm IRC at Rs. 1153.05 /cum.= 207.55
0.09 Cum. Cost of 11.20mm IRC at Rs. 792.05 /cum. = 71.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 595.05 /cum. = 53.55
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1631.31
Rate for 1 sqm. =Rs. 163.13 /sqm.

Km 3/0 - 4/0 63
0.18 Cum. Cost of 13.20mm IRC at Rs. 1161.74 /cum.= 209.11
0.09 Cum. Cost of 11.20mm IRC at Rs. 800.74 /cum. = 72.07
0.09 Cum. Cost of 6.70mm IRC at Rs. 603.74 /cum. = 54.34
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1634.45
Rate for 1 sqm. =Rs. 163.45 /sqm.

Km 4/0 - 5/0 84
0.18 Cum. Cost of 13.20mm IRC at Rs. 1170.43 /cum.= 210.68
0.09 Cum. Cost of 11.20mm IRC at Rs. 809.43 /cum. = 72.85
0.09 Cum. Cost of 6.70mm IRC at Rs. 612.43 /cum. = 55.12
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1637.58
Rate for 1 sqm. =Rs. 163.76 /sqm.

Road Data - Rev-17.6 55 Revised during - OCT. 2017


Premix carpet with Seal Coat
Km 5/0 - 6/0 105
0.18 Cum. Cost of 13.20mm IRC at Rs. 1179.12 /cum.= 212.24
0.09 Cum. Cost of 11.20mm IRC at Rs. 818.12 /cum. = 73.63
0.09 Cum. Cost of 6.70mm IRC at Rs. 621.12 /cum. = 55.90
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1640.70
Rate for 1 sqm. =Rs. 164.07 /sqm.

126
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
147
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
168
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
189
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.

Road Data - Rev-17.6 56 Revised during - OCT. 2017


CLOSE GRADED PREMIX SURFACING 20MM THICK (Using Plastic Waste)
Providing laying and rolling of close graded premix carpet of compacted 20mm thickness
using using 0.0162 cum of 13.20-11.20mm, 0.1404 cum of 11.2-5.6mm, 0.0729 cum of 5.60-
2.80mm, 0.0405 cum of 2.80mm and below (Type B) graded HBG metal using 17.86kgs of
VG30 bitumen and 1.14Kgs of Waste Plastic for 10sqm including premixing at CMP,
conveyance by tipper lorry, laying by paver finisher and rolling by Vibratory Roller including
cost and conveyance of all materials, hire charges of all T&P all labour charges, fuel and and
all other incidental charges etc., Complete as per specification using CMP as per clause 508
of MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696.00 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for SDBC = 270sqm. of 25 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 277.19


270
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per Hour Rs. 814.28
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick

Hire Charges for Vibratory roller per 10sqm. = 814.28 X 10 =Rs. 16.29
500

4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per DAY Rs. 631.74

Out turn of Paver Finisher per hour = 270 sqm. of 25 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 23.40
270

Road Data - Rev-17.6 57 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 270 sqm. of 25 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 69.61
270

Total hire charges for machineries per 10 sqm =277.19 16.29 23.40 69.61
= 386.49 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 446.60 /each = 11790.24
20.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 8008.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 3572.80
Total Labour Charges per 2000sqm = 23371.04

Labour Charges per 10sqm. = 23371.04 X 10 =Rs. 116.86


2000

RATE 10SQM OF CLOSE GRADED PREMIX SURFACING 20MM THICK (Using Plastic waste)

0.0162 Cum Cost of 13.20mm -11.20mm Metalat Rs. 1045.90 /Cum. = 16.94
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 848.90 /Cum. = 119.19
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 784.90 /Cum. = 57.22
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 784.90 /Cum. = 31.79
17.86 Kg Cost of VG30 grade Bitumen at Rs. 26384.26 /MT = 471.22
1.14 Kg Cost of Waste Plastic at Rs. 20.00 /Kg = 22.80
10.00 Sqm Hire charges at Rs. 386.49 /10sqm = 386.49
10.00 Sqm Labour charges at Rs. 116.86 /10sqm = 116.86
Rate for 10 sqm =Rs. 1222.51

Rate per sqm of 20 mm thick = 1222.51 = Rs. 122.25


10

Road Data - Rev-17.6 58 Revised during - OCT. 2017


BITUMINOUS CONCRETE 30/40MM THICK USING CMP (using Plastic Waste)
Providing and laying Bituminous Concrete to 40 mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum
of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30/ VG40 bitumen and
3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to
CMP site, heating the bitumen and aggregate to required temperature and mixing them in required
temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver
site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades
and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density
etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-
30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic
roller and all other tools and plant required, including fuel and all other incidental charges etc.,
complete as per specification using CMP as per clause 507 of MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 440.25


170
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick

Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 20.36
400
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 37.16
170

Road Data - Rev-17.6 59 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 110.56
170

Total hire charges for machineries per 10 sqm 440.25+


= 20.36+ 37.16+ 110.56
= 608.33 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 243.45


1200

RATE PER SQM OF BITUMINOUS CONCRETE 30/ 40MM THICK (Using Plastic Waste)

0.130 Cum Cost of 19.00-9.50mm IRC at Rs. 1132.54 /cum. = 147.23


0.170 Cum Cost of 9.50 - 2.36mm IRC at Rs. 816.58 /cum. = 138.82
0.260 Cum Cost of 2.36 mm and below at Rs. 784.90 /cum. = 204.07
47.28 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1247.45
3.02 Kg Cost of Waste Plastic at Rs. 20.00 /Kg = 60.40
10.00 Sqm Hire charges at Rs. 608.33 /10sqm = 608.33
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 2649.75

Rate per cum = 2649.75/(10x0.04) = 6624.38

Road Data - Rev-17.6 60 Revised during - OCT. 2017


CLOSE GRADED PREMIX SURFACING 20MM COMPACTED THICK
Providing laying and rolling of close graded premix carpet of compacted 20mm thickness
using using 0.0162 cum of 13.20-11.20mm, 0.1404 cum of 11.2-5.6mm, 0.0729 cum of 5.60-
2.80mm, 0.0405 cum of 2.80mm and below (Type B) graded HBG metal using 19kg of VG30
bitumen for 10sqm including premixing at CMP, conveyance by tipper lorry, laying by paver
finisher and rolling by Vibratory Roller including cost and conveyance of all materials, hire
charges of all T&P all labour charges, fuel and and all other incidental charges etc., Complete
as per specification using CMP as per clause 508 of MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696.00 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for SDBC = 270sqm. of 25 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 277.19


270
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per Hour Rs. 814.28
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick

Hire Charges for Vibratory roller per 10sqm. = 814.28 X 10 =Rs. 16.29
500

4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per DAY Rs. 631.74
Out turn of Paver Finisher per hour = 270 sqm. of 25 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 23.40
270

Road Data - Rev-17.6 61 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 270 sqm. of 25 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 69.61
270

Total hire charges for machineries per 10 sqm =277.19 16.29 23.40 69.61
= 386.49 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 446.60 /each = 11790.24
20.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 8008.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 3572.80
Total Labour Charges per 2000sqm = 23371.04

Labour Charges per 10sqm. = 23371.04 X 10 =Rs. 116.86


2000

RATE 10SQM OF CLOSE GRADED PREMIX SURFACING 20MM COMPACTED THICK

0.0162 Cum Cost of 13.20mm -11.20mm Metalat Rs. 1045.90 /Cum. = 16.94
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 848.90 /Cum. = 119.19
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 784.90 /Cum. = 57.22
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 784.90 /Cum. = 31.79
19.00 Kg Cost of VG30 grade Bitumen at Rs. 26384.26 /MT = 501.30
10.00 Sqm Hire charges at Rs. 386.49 /10sqm = 386.49
10.00 Sqm Labour charges at Rs. 116.86 /10sqm = 116.86
Rate for 10 sqm =Rs. 1229.79

Rate per sqm of 20 mm thick = 1229.79 = Rs. 122.98


10

Road Data - Rev-17.6 62 Revised during - OCT. 2017


BITUMINOUS CONCRETE 30/40MM THICK USING CMP
Providing and laying Bituminous Concrete to 40 mm thick using 0.13 cum of 19.00-9.50mm,
0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG30/ VG40
bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site,
heating the bitumen and aggregate to required temperature and mixing them in required
temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to
paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic
Roller to the required density etc., including labour for attending to paver to site etc., including
hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver
Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required,
including fuel and all other incidental charges etc., complete as per specification using CMP as
per clause 507 of MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696.00 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 440.25


170
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick

Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 20.36
400
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 37.16
170

Road Data - Rev-17.6 63 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 110.56
170

Total hire charges for machineries per 10 sqm =440.25+ 20.36+ 37.16+ 110.56
= 608.33 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 243.45


1200

RATE PER SQM OF BITUMINOUS CONCRETE 30/40MM THICK

0.130 Cum Cost of 19.00-9.50mm IRC at Rs. 1132.54 /cum. = 147.23


0.170 Cum Cost of 9.50 - 2.36mm IRC at Rs. 816.58 /cum. = 138.82
0.260 Cum Cost of 2.36 mm and below at Rs. 784.90 /cum. = 204.07
50.30 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1327.13
10.00 Sqm Hire charges at Rs. 608.33 /10sqm = 608.33
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 2669.03

Rate per cum = 2669.03/(10x0.04) = 6672.58

Road Data - Rev-17.6 64 Revised during - OCT. 2017


BITUMINOUS CONCRETE 50MM THICK USING CMP
Providing and laying Bituminous Concrete to 50 mm thick using 0.22 cum of 26.5-13.20mm,
0.24 cum of 13.20-2.36mm and 0.26cum of 2.36 & below IRC HBG metal with 62.40 kgs of
VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing
them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix
by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with
mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne
Vibratory / Pneumatic Roller to the required density etc., including labour for attending to
paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen
boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all
other tools and plant required, including fuel and all other incidental charges etc., complete
as per specification using CMP clause 507 of MORTH.
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696.00 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 54.31 /lit =Rs. 1629.30
For heating the bitumen 25 litres of furnace oil 23.81 /lit =Rs. 595.25
For heating the aggregates : 170 litres of furnace oil 23.81 /lit =Rs. 4047.70
Hire Charges including fuel charges per hour Rs. 7484.25
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 7484.25 X 10 =Rs. 440.25


170.00
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 20.36
400.00
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 37.16
170.00

Road Data - Rev-17.6 65 Revised during - OCT. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 54.31 /lit =Rs. 176.51
Hire Charges including fuel charges per DAY Rs. 313.26
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 110.56
170.00

Total hire charges for machineries per 10 sqm 440.25+


= 20.36+ 37.16+ 110.56
= 608.33 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80

Labour Charges per 10sqm. = 29213.80 X 10 =Rs. 243.45


1200.00

RATE PER SQM OF BITUMINOUS CONCRETE 50MM THICK

0.220 Cum Cost of 26.5 - 13.20mm IRC at Rs. 1390.74 /cum. = 305.96
0.240 Cum Cost of 13.20 - 2.36mm IRC at Rs. 851.04 /cum. = 204.25
0.260 Cum Cost of 2.36 mm and below at Rs. 784.90 /cum. = 204.07
62.40 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1646.38
10.00 Sqm Hire charges at Rs. 608.33 /10sqm = 608.33
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 3212.44

Rate per cum = 3212.44/(10x0.05) = 6424.88

Road Data - Rev-17.6 66 Revised during - OCT. 2017


PROVIDING GRAVEL FOR BERMS INCL. COMPACTION
Providing and laying of Gravel including cost and conveyance of the same to work site
from approved quarry including stacking the same to departemental gauge for
premeasurement including all labour charges for laying, spreading etc., complete and as
directed by the departmental engineers for making up of low berms

Hire charges for Machineries

Power Roller 8-10 tonne


Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1086.20
Total Hire charges per day including Fuel =Rs. 1941.20
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 1941.20 =Rs. 4.57


425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2571.06
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2571.06 =Rs. 2.57


1000

Total Hire charges for Machineries per10sqm = 4.57 + 2.57 =Rs. 7.14

Labour charges for Laying U.S. Gravel for 100cum


2.00 Nos. Mazdoor Ist Class @Rs. 446.60 /E =Rs. 893.20
Total Labour charges for laying gravel per 100cum =Rs. 893.20

Total Labour charges for laying gravel per Cum 893.20 =Rs. 8.93
100
Total Hire and Labour charges = 7.14 + 8.93 =Rs. 16.07

Road Data - Rev-17.6 67 Revised during - OCT. 2017


Providing gravel for berms including compaction (100 % Compaction)

Km 0/0 - 1/0
1.16 Cum. Cost of Gravel at Rs. 449.19 /Cum. = 521.06
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. = 16.07
Rate for 1.00 cum. Rs. 537.13

Km 1/0 - 2/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

Km 2/0 - 3/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

Km 3/0 - 4/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

Km 4/0 - 5/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

Km 5/0 - 6/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

1.16 Cum. Cost of Gravel at Rs. /Cum. =


1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.

Road Data - Rev-17.6 68 Revised during - OCT. 2017


Earthwork for Berms
Earth Work for berms including Cost of earth work and compaction by power roller
(100% compaction)
Hire charges for Machineries
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1086.20
Total Hire charges per day including Fuel =Rs. 1941.20
Daily Out turn 425 Cum.
Hire charges of Power Roller per 10 sqm. 1941.20 =Rs. 4.57 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2571.06
Daily Out turn 1000 Cum.
Hire charges of Water Sprinklers per 10 sqm. 2571.06 =Rs. 2.57 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.57 + 2.57 =Rs. 7.14 /Cum
Labour charges for Laying Earth for 100cum
2.00 Nos. of Mazdoor Ist Class @Rs. 446.60 /E =Rs. 893.20
Total Labour charges for laying earth per 100cum =Rs. 893.20

Total Labour charges for laying earth per Cum 893.20 =Rs. 8.93 /Cum
100
Total Hire and Labour charges = 7.14 + 8.93 =Rs. 16.07 /Cum

1.00 Cum Excavation Charges as per PWD rates Rs.506.00/Cum =Rs. 506.00
1.00 Cum Hire and Labour Charges Rs.16.07/Cum =Rs. 16.07
Cost of earth per cum at worksite =Rs. 522.07 /Cum