Estimate Amount : Rs.740.5 Lakhs Job Code : NABARD RIDF XXI 2016 - 2016
Labour Charges
Description Rate
Bitumen Sprayer Man 592.62/Day
Bitumen Raker Man 617.81/Day
Heat Master Operator 617.81/Day
Mini Hot Mix Plant Operator 617.81/Day
Gunnuting Plant Operator 517.05/Day
Gunnuting Gun Operator 562.13/Day
Road Mazdoor Gr.- I 446.60/Day
Road Mazdoor Gr.-II 400.40/Day
Head Mazdoor 460.60/Day
Labour Charges
Description Rate
Carpenter - Ist Class 706.62/Day
Carpenter - IInd Class 646.97/Day
Fitter Ist Class (Pipe Laying/ Bar Bending) 628.40/Day
Fitter II Class (Pipe Laying/ Bar Bending) 583.34/Day
Mason I Class 631.40/Day
Mason II Class 565.60/Day
Mazdoor I Class 394.80/Day
Mazdoor II Class 357.00/Day
Head Mazdoor 408.80/Day
Painter / Varnisher I Class 578.03/Day
Painter / Varnisher II Class 536.93/Day
Wodder 467.99/Day
=Rs.6703.92/MT
=Rs.45133.92/MT
Job Code : NABARD RIDF XXI 2016 - 2016 Estimate Amount : 740.50 Lakhs
DATA ABSTRACT
Sl
Description Unit Rate
No.
GENERAL RATES (As Per Schedule of Rates)
1 Clearing Heavy Jungle /Sqm. 5.89
26 B.C. 30/ 40mm Thick (CMP) Using Plastic Waste /Cum. 6624.38
round 2
Hire charges of Power Roller per 10 sqm. 1941.20 =Rs. 4.57 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2571.06
Daily Out turn 1000 Cum.
Hire charges of Water Sprinklers per 10 sqm. 2571.06 =Rs. 2.57 /Cum
1000
Total Hire charges for Machineries per10sqm = 4.57 + 2.57 =Rs. 7.14 /Cum
Labour charges for Laying Earth for 100cum
Total Labour charges for laying earth per Cum 893.20 =Rs. 8.93 /Cum
100
Total Hire and Labour charges = 7.14 + 8.93 =Rs. 16.07 /Cum
Cost of Earth (as per 137 Industries (MMC 2) =Rs. 62.00 /Cum
Department dated 10.09.2014)
Excavation Charges as per PWD rates (SS 20 B) =Rs. 506.00 /Cum
Seigniorage fee per cum ( GO (Ms) No. 6, Industries =Rs. 20.00 /Cum
(MMB1) Department dated 11.1.2001)
Cost of earth per cum at quarrying place =Rs. 588.00 /Cum
Km 1/0 - 2/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.
Km 2/0 - 3/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.
Km 3/0 - 4/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.
Km 4/0 - 5/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.
Km 5/0 - 6/0
1.16 Cum. Cost of Earth incl. conveyanceat Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /cum. =
Rate for 1.00 cum. Rs.
2. Removing the Picked up stuff Mazdoor Ist 1.08x1/8x 446.60 /No - 60.29
4. Spreading the Bitumen for Tack Coat excluding cost of Bitumen -L.S.- - 3.10
5. Premixing the chips with hot Bitumen in the drum mixer and laying
0.625 cum of metal with 44 kg per cum of chips excluding the cost of the
bitumen - - L. S. - - - 15.75
6. Levelling and tamping the premix in the patches and pot holes rolling etc - 4.73
Rs. /Cum.
Picking 5cm to 10cm old metalled surface and sectioning 1Sqm. = 12.06 /Sqm.
Km 1/0 - 2/0 18
1.00 Cum. Cost of 45mm IRC at Rs. 885.36 /cum. = 885.36
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2011.33
Km 2/0 - 3/0 34
1.00 Cum. Cost of 45mm IRC at Rs. 894.05 /cum. = 894.05
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2020.02
Km 3/0 - 4/0 50
1.00 Cum. Cost of 45mm IRC at Rs. 902.74 /cum. = 902.74
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2028.71
Km 4/0 - 5/0 66
1.00 Cum. Cost of 45mm IRC at Rs. 911.43 /cum. = 911.43
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2037.40
Km 5/0 - 6/0 82
1.00 Cum. Cost of 45mm IRC at Rs. 920.12 /cum. = 920.12
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2046.09
98
1.00 Cum. Cost of 45mm IRC at Rs. /cum. =
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT =
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs.
Km 1/0 - 2/0 26
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1144.36 /cum. = 1144.36
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2270.33
Km 2/0 - 3/0 42
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1153.05 /cum. = 1153.05
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2279.02
Km 3/0 - 4/0 58
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1161.74 /cum. = 1161.74
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2287.71
Km 4/0 - 5/0 74
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1170.43 /cum. = 1170.43
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2296.40
Km 5/0 - 6/0 90
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1179.12 /cum. = 1179.12
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT = 1125.97
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs. 2305.09
106
1.00 Cum. Cost of 13.20 mm IRC at Rs. /cum. =
44 Kg Cost of VG10 Bitumen at Rs. 25590.23 /MT =
1.00 Cum. Labour charges at Rs. /cum. =
Rate for 1.00 cum. Rs.
Labour charges for BM 50mm thick per 10 sqm. 59089.80 x 10 =Rs. 492.42
1200
Total Hire and Labour charges per 10sqm = 393.82 + 492.42 =Rs. 886.24
Km 1/0 - 2/0 19
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1123.20 /cum. = 224.64
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 571.02 /cum. = 245.54
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 519.38 /cum. = 41.55
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2375.89
Rate per cum of 50 mm thick = 2375.89 /0.50 = Rs. 4751.78
Km 2/0 - 3/0 35
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1131.89 /cum. = 226.38
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 579.71 /cum. = 249.28
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 528.07 /cum. = 42.25
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2382.07
Rate per cum of 50 mm thick = 2382.07 /0.50 = Rs. 4764.14
Km 3/0 - 4/0 51
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1140.58 /cum. = 228.12
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 588.40 /cum. = 253.01
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 536.76 /cum. = 42.94
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2388.23
Rate per cum of 50 mm thick = 2388.23 /0.50 = Rs. 4776.46
Km 5/0 - 6/0 83
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1157.96 /cum. = 231.59
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 605.78 /cum. = 260.49
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 554.14 /cum. = 44.33
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 977.92
10.00 Sqm Hire charges at Rs. 393.82 /10sqm = 393.82
10.00 Sqm Labour charges at Rs. 492.42 /10sqm = 492.42
Rate for 10 sqm =Rs. 2400.57
Rate per cum of 50 mm thick = 2400.57 /0.50 = Rs. 4801.14
99
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. /cum. =
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. /cum. =
0.08 Cum. Cost of 2.36mm & below IRC at Rs. /cum. =
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire charges at Rs. 393.82 /10sqm =
10.00 Sqm Labour charges at Rs. 492.42 /10sqm =
Rate for 10 sqm =Rs.
Rate per cum of 50 mm thick = = Rs.
115
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. /cum. =
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. /cum. =
0.08 Cum. Cost of 2.36mm & below IRC at Rs. /cum. =
37.00 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire charges at Rs. 393.82 /10sqm =
10.00 Sqm Labour charges at Rs. 492.42 /10sqm =
Rate for 10 sqm =Rs.
Rate per cum of 50 mm thick = = Rs.
output = 10 cum
a) Labour
1.800 day Mason II CLass 404.00 /day 727.20
17.700 day Mazdoor I CLass 282.00 /day 4991.40
14.100 day Mazdoor II CLass 255.00 /day 3595.50
b) Machinery
10.000 cum Vibrator Charges 44.31 443.10
9757.20
Km 4/0 - 5/0
Cement Mortar
333.35 Kg. Cost of Cement (MORT&H Cl 601.3.3) at Rs. 6703.92
1.00 Cum Cost of Sand at Rs.
Tipper
Hire charges excluding fuel charges per day =Rs. 1094.00
Fuel charges per day 3.25lit.of diesel x 8hrs 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2506.06
Total Hire charges per Hour including Fuel =Rs. 313.26
Water Tankers
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day 25lit.of diesel 54.31 /lit =Rs. 1357.75
Total Hire charges per day including Fuel =Rs. 2212.75
Total Hire charges per Hour including Fuel =Rs. 276.59
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day 3.00lit.of diesel x 8hrs 54.31 /lit =Rs. 1303.44
Total Hire charges per day including Fuel =Rs. 6731.44
Total Hire charges per Hour including Fuel =Rs. 841.43
Motor Grader including fuel per Hour (Local Rate) =Rs. 1691.63
Base Mix Plant (pug mill) including fuel per hour (local rate) =Rs. 834.88
Total Hire Charges for machineries for 1.00 Cum of WMM =Rs. 351.43 /Cum.
Tipper
Hire charges excluding fuel charges per day =Rs. 1094.00
Fuel charges per day 3.25lit.of diesel x 8hrs 54.31 /lit =Rs. 1412.06
Total Hire charges per day including Fuel =Rs. 2506.06
Total Hire charges per Hour including Fuel =Rs. 313.26
Water Tankers
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day 25lit.of diesel 54.31 /lit =Rs. 1357.75
Total Hire charges per day including Fuel =Rs. 2212.75
Total Hire charges per Hour including Fuel =Rs. 276.59
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day 3.00lit.of diesel x 8hrs 54.31 /lit =Rs. 1303.44
Total Hire charges per day including Fuel =Rs. 6731.44
Total Hire charges per Hour including Fuel =Rs. 841.43
Total Hire Charges for machineries for 1.00 Cum of CRM =Rs. 301.34
0.09 Cum Cost of 53-45mm IRC 0.090 @Rs 1074.57 /cum 96.71
0.46 Cum. Cost of 45-22.40mm IRC 0.460 @Rs 1208.70 /cum 556.00
0.30 Cum. Cost of 22.40-5.6mm IRC 0.300 @Rs 999.90 /cum 299.97
0.46 Cum. Cost of 900mm Micron and below 0.460 @Rs 784.90 /cum 361.05
1.00 Cum Hire & Labour charges 1.00 @Rs 350.19 /cum 350.19
Rate for 1.00 cum. Rs. 1663.92
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 350sqm. of 50 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 23.27
350
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 46.80
135
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 139.23
135
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 320sqm. of 50 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 25.45
320
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 46.80
135
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 139.23
135
Total hire charges for machineries per 10 sqm = 554.39+ 25.45+ 46.80+ 139.23
= 765.87 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80
0.240 Cum Cost of 26.50 - 13.20mm IRC at Rs. 1323.29 /cum. = 317.59
0.250 Cum Cost of 13.20-2.36mm IRC at Rs. 834.73 /cum. = 208.68
0.230 Cum Cost of 2.36mm & below IRC at Rs. 784.90 /cum. = 180.53
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 313.91 /cum. = 0.00
53.20 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1403.64
10.00 Sqm Hire charges at Rs. 765.87 /10sqm = 765.87
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 3119.76
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 250sqm. of 80 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 32.57
250
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 90 sqm. of 80 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 70.19
90
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 208.84
90
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 220sqm. of 75 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 37.01
220
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 90 sqm. of 75 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 70.19
90
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 208.84
90
Total hire charges for machineries per 10 sqm =831.58 37.01 70.19 208.84
= 1147.62 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1000sqm = 29213.80
Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen
(SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of
material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 446.60 /each =Rs 4466.00
16.00 Nos Mazdoor IIst Grade @Rs 400.40 /each =Rs 6406.40
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 400.40 /each =Rs 1601.60
Total Labour Charges per 500 sqm =Rs 12474.00
7.00 Kgs Cost of Bitumen Emulsion - SS1 @Rs 48987.04 /MT =Rs 342.91
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 249.48 /10sqm =Rs 249.48
Rate for 10 sqm =Rs 607.39
9.00 Kgs Cost of Bitumen Emulsion (SS1) @Rs 48987.04 /MT =Rs 440.88
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 249.48 /10sqm =Rs 249.48
Rate for 10 sqm =Rs 705.36
Rate per 1.00 sqm =Rs 70.54 /sqm
Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion
(RS1) per 10 sqm for preparatory to another bituminous construction over it including cost
of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 503 of MORTH Rev-5
2.00 Kgs Cost of RS-I Bitumen emulsion @Rs 29258.59 /MT =Rs 58.52
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 sqm Labour Charges @Rs 84.70 /10sqm =Rs 84.70
Rate for 10 sqm =Rs 158.22
Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using
2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous
construction over it including cost of material, labour charges, rentals for machinery, fuel
and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm
3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 400.40 /each =Rs 1201.20
Total Labour Charges per 500 sqm =Rs 1201.20
2.50 Kgs Cost of RS-I Bitumen emulsion @Rs 29258.59 /MT =Rs 73.15
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 24.02 /10sqm =Rs 24.02
Rate for 10 sqm =Rs 112.17
Providing and laying Tack Coat over Dry Lean Cement Concrete surface using 3.00 Kg of
Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it
including cost of material, labour charges, rentals for machinery, fuel and all other incidental
charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm
3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 400.40 /each =Rs 1201.20
Total Labour Charges per 500 sqm =Rs 1201.20
3.00 Kgs Cost of RS-I Bitumen emulsion @Rs 29258.59 /MT =Rs 87.78
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 24.02 /10sqm =Rs 24.02
Rate for 10 sqm =Rs 126.80
Km 1/0 - 2/0 21
0.18 Cum. Cost of 13.20mm IRC at Rs. 1144.36 /cum.= 205.98
0.09 Cum. Cost of 11.20mm IRC at Rs. 783.36 /cum. = 70.50
0.09 Cum. Cost of 6.70mm IRC at Rs. 586.36 /cum. = 52.77
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1628.18
Rate for 1 sqm. =Rs. 162.82 /sqm.
Km 2/0 - 3/0 42
0.18 Cum. Cost of 13.20mm IRC at Rs. 1153.05 /cum.= 207.55
0.09 Cum. Cost of 11.20mm IRC at Rs. 792.05 /cum. = 71.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 595.05 /cum. = 53.55
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1631.31
Rate for 1 sqm. =Rs. 163.13 /sqm.
Km 3/0 - 4/0 63
0.18 Cum. Cost of 13.20mm IRC at Rs. 1161.74 /cum.= 209.11
0.09 Cum. Cost of 11.20mm IRC at Rs. 800.74 /cum. = 72.07
0.09 Cum. Cost of 6.70mm IRC at Rs. 603.74 /cum. = 54.34
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1634.45
Rate for 1 sqm. =Rs. 163.45 /sqm.
Km 4/0 - 5/0 84
0.18 Cum. Cost of 13.20mm IRC at Rs. 1170.43 /cum.= 210.68
0.09 Cum. Cost of 11.20mm IRC at Rs. 809.43 /cum. = 72.85
0.09 Cum. Cost of 6.70mm IRC at Rs. 612.43 /cum. = 55.12
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT = 644.90
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. = 654.03
Rate for 10 sqm. = 1637.58
Rate for 1 sqm. =Rs. 163.76 /sqm.
126
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
147
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
168
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
189
0.18 Cum. Cost of 13.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 11.20mm IRC at Rs. /cum. =
0.09 Cum. Cost of 6.70mm IRC at Rs. /cum. =
24.40 Kgs. Cost of VG30 Bitumen at Rs. 26430.23 /MT =
10.00 Sqm Hire and Labour Charges at Rs. 654.03 /10sqm. =
Rate for 10 sqm. =
Rate for 1 sqm. =Rs. /sqm.
3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per Hour Rs. 814.28
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick
Hire Charges for Vibratory roller per 10sqm. = 814.28 X 10 =Rs. 16.29
500
4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per DAY Rs. 631.74
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 23.40
270
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 69.61
270
Total hire charges for machineries per 10 sqm =277.19 16.29 23.40 69.61
= 386.49 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 446.60 /each = 11790.24
20.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 8008.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 3572.80
Total Labour Charges per 2000sqm = 23371.04
RATE 10SQM OF CLOSE GRADED PREMIX SURFACING 20MM THICK (Using Plastic waste)
0.0162 Cum Cost of 13.20mm -11.20mm Metalat Rs. 1045.90 /Cum. = 16.94
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 848.90 /Cum. = 119.19
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 784.90 /Cum. = 57.22
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 784.90 /Cum. = 31.79
17.86 Kg Cost of VG30 grade Bitumen at Rs. 26384.26 /MT = 471.22
1.14 Kg Cost of Waste Plastic at Rs. 20.00 /Kg = 22.80
10.00 Sqm Hire charges at Rs. 386.49 /10sqm = 386.49
10.00 Sqm Labour charges at Rs. 116.86 /10sqm = 116.86
Rate for 10 sqm =Rs. 1222.51
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 20.36
400
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 37.16
170
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 110.56
170
RATE PER SQM OF BITUMINOUS CONCRETE 30/ 40MM THICK (Using Plastic Waste)
3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per Hour Rs. 814.28
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick
Hire Charges for Vibratory roller per 10sqm. = 814.28 X 10 =Rs. 16.29
500
4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per DAY Rs. 631.74
Out turn of Paver Finisher per hour = 270 sqm. of 25 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 23.40
270
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 69.61
270
Total hire charges for machineries per 10 sqm =277.19 16.29 23.40 69.61
= 386.49 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 446.60 /each = 11790.24
20.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 8008.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 3572.80
Total Labour Charges per 2000sqm = 23371.04
0.0162 Cum Cost of 13.20mm -11.20mm Metalat Rs. 1045.90 /Cum. = 16.94
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 848.90 /Cum. = 119.19
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 784.90 /Cum. = 57.22
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 784.90 /Cum. = 31.79
19.00 Kg Cost of VG30 grade Bitumen at Rs. 26384.26 /MT = 501.30
10.00 Sqm Hire charges at Rs. 386.49 /10sqm = 386.49
10.00 Sqm Labour charges at Rs. 116.86 /10sqm = 116.86
Rate for 10 sqm =Rs. 1229.79
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 20.36
400
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 37.16
170
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 110.56
170
Total hire charges for machineries per 10 sqm =440.25+ 20.36+ 37.16+ 110.56
= 608.33 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 14737.80
25.00 Nos Mazdoor IInd Class @Rs. 400.40 /each = 10010.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 446.60 /each = 4466.00
Total Labour Charges per 1200sqm = 29213.80
3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 54.31 /lit =Rs. 135.78
Hire Charges including fuel charges per hour Rs. 814.28
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick
Hire Charges for Vibrator roller per 10sqm. = 814.28 X 10 =Rs. 20.36
400.00
4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 54.31 /lit =Rs. 325.86
Hire Charges including fuel charges per hour Rs. 631.74
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick
Hire Charges for paver finisher per 10sqm. = 631.74 X 10 =Rs. 37.16
170.00
Hire Charges for Tipper per 10sqm. = 313.26 x6x10 =Rs. 110.56
170.00
0.220 Cum Cost of 26.5 - 13.20mm IRC at Rs. 1390.74 /cum. = 305.96
0.240 Cum Cost of 13.20 - 2.36mm IRC at Rs. 851.04 /cum. = 204.25
0.260 Cum Cost of 2.36 mm and below at Rs. 784.90 /cum. = 204.07
62.40 Kg Cost of VG30 Bitumen at Rs. 26384.26 /MT = 1646.38
10.00 Sqm Hire charges at Rs. 608.33 /10sqm = 608.33
10.00 Sqm Labour charges at Rs. 243.45 /10sqm = 243.45
Rate for 10 sqm =Rs. 3212.44
Total Hire charges for Machineries per10sqm = 4.57 + 2.57 =Rs. 7.14
Total Labour charges for laying gravel per Cum 893.20 =Rs. 8.93
100
Total Hire and Labour charges = 7.14 + 8.93 =Rs. 16.07
Km 0/0 - 1/0
1.16 Cum. Cost of Gravel at Rs. 449.19 /Cum. = 521.06
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. = 16.07
Rate for 1.00 cum. Rs. 537.13
Km 1/0 - 2/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.
Km 2/0 - 3/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.
Km 3/0 - 4/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.
Km 4/0 - 5/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.
Km 5/0 - 6/0
1.16 Cum. Cost of Gravel at Rs. /Cum. =
1.00 Cum. Hire and Labour charges at Rs. 16.07 /Cum. =
Rate for 1.00 cum. Rs.
Total Hire charges for Machineries per10sqm = 4.57 + 2.57 =Rs. 7.14 /Cum
Labour charges for Laying Earth for 100cum
2.00 Nos. of Mazdoor Ist Class @Rs. 446.60 /E =Rs. 893.20
Total Labour charges for laying earth per 100cum =Rs. 893.20
Total Labour charges for laying earth per Cum 893.20 =Rs. 8.93 /Cum
100
Total Hire and Labour charges = 7.14 + 8.93 =Rs. 16.07 /Cum
1.00 Cum Excavation Charges as per PWD rates Rs.506.00/Cum =Rs. 506.00
1.00 Cum Hire and Labour Charges Rs.16.07/Cum =Rs. 16.07
Cost of earth per cum at worksite =Rs. 522.07 /Cum