Figure 3-4, Procoss macs balance.
‘Sludge Yild Without Primary Claifcation
‘Sludge Production,
a
Solids Retention Time, days
‘Sludge Vield With Primary Clarification
°c.
2080.
sore:
00/800, = 1520
12
‘788/800, = 0:
Primary Treotment
@ 60% TSS Removal
30% Inet in Pa
Eftuent TSS
Bee eeee
‘Sludge Production, y, Ib TSS/Ib BOD, Rem
BAOSOET TE2 3 ABCTEDIO TS 2) DDD
Solids Rototion Tima, dave
this procedure effectively with minor changes in the
design approach and negligible additional costs.
Where the primary clarifier must serve a dual function
of clarifying the wastewater as well as delivering a
concentrated sludge for digestion or dewatering, the
‘conventional primary clarifier design configuration is
inappropriate. This is particularly true for primary
clarifiers in smaller plants, where it may be necessary
to have 1.6-2.0 days SRT in the clarifier to croate a
1.0 to 1.5 m (8-5 ft) sludge blanket above the
sludge withdrawal pipe. The build-up of sludge to
produce a thicker underflow interferes with
Clarification (lower efficiency) and sometimes results
in gasification, odors, and tloating sludges.
However, in the new plants there is an easy remedy
for this problem. Construct the smaller clarifiers with
the standard thickener floor slope of 2.78:12. In larger
dlarifiers, use a dual slope clarifier where the inner
slope of 2.76:12 is the thickening zone and the outer
zone is 1:12. On a primary clarifier, only 40-50
percent of the diameter would be required for sludge
thickening; thus it is sufficient to modify the floor
slope at mid-radius.
Figure 3-5 shows the types of clarifier floor
configurations of which only three are suitable for
efficient combined clarification and thickening. Type A
is the design most commonly employed, but it iS not
suitable for combined clarification and thickening.
Types B, C and D all can provide much better
performance in terms of thickened sludge
Concentrations and lowest sludge inventory; hence,
they provide freshest sludge and highest flexibility in
terms of sludge removal and ease of operation,
Pertinent dimensions for a 30 ft diameter and 80 ft
diameter primary clarifier-thickener are also shown
in Table 3-2,
Process data used’ to construct the sludge level in
Table 3-2 are provided below. Underflow
concentrations were based ‘on general experiences
with sludge thickening,
RPS @ 120 mgf
WAS @ 80 mgi
Total =
1,000 ib TSSimgd
667 Ib TSSimgd
7,667 Ib TSSimgd
8.1 m (30 f) diameter @ 1.36 m3/m2d (800 galisq
fi:
TSSq (TSS removed) = 943 Ib TSSid
24 m (80 tt) diameter @ 32.6 mim2d (800 galisq
tay
TSSR = 6,706 lb TSSid
Sludge blanket depth in small clarifiers is a two-fold
problem in units with the 1:12 floor slope. As shown
in Table 3-2, the 1.0 day SRT sludge depth is only