Figure 42. Five stages of analysis in selection of @
‘dewatering process,
Stage Intl Serooning of
7 Dewatering Concepts
Stage Intl Cost
2 Evaluation
Stage Laboratory
3 Testing
Stage Fold Level,
3 Testing
Fal Evaluation
Stage Baced on Detaled
8 Design Perameters
Stage 4 - Field Pilot Testing
iF the plant is large andior the cake moisture content
is critical (and more than one dewatering method may
be feasible), pilot studies are often: warranted. Since
the sludge dewatering properties of even apparently
similar sludges may vary widely, pitt studies. greatly
reduce the risk of improperly ‘selecting and sizing
dewatering equipment. The cost of a thorough
‘evaluation is small compared to the benefits gained.
If it is necessary to test two types or more of
comparable dewatering equipment, the tests should
be conducted simultaneously to eliminate potential
differences related to the sludge composition. Sludge
variations, due to a number of reasons, can distort
the comparison. An example, shown in Table 4-1, is
the result of two series of tests conducted at the
‘same plant in Ohio.
Table 4-1 indicates that two dewatering studies at
the same facility produced widely different results.
Moreover, there was not a similar comparative
difference’ between the two types of equipment for
the winter and summer testing. The differences found
must also be considered in light of the degree of
optimization achieved. Short-term testing may not
have fully evaluated the range of operation or
‘optimized the critical chemical conditioning step.
The centrifuge data in Table 4-1, which was
produced by full-scale operation, ‘indicate the
magnitude of the problem that could have boon
encountered had the centrifuge installation been sized
27
fon winter test performance results. Production rate
and cake solids content were much lower in the
‘summer tests. The differences wore a result of storm
flows adding inert material to the sludge and changes
in industrial discharges. In the winter tests (Series 1),
‘storm flows had added inerts to the sludge; in the
‘summer tests (Series Il), a high TSS discharge from
a brewery had a more adverse impact on the
performance of the centrifuge than on the
performance of the diaphragm plate press.
Ideally, pilot testing should be carried out over an
oxtonded period of time. However, extendad testing is
often not practical. Test programs should evaluate a
sufficiently wide range of PS:WAS ratios to ensure
testing of worst-case situations, preferably during
colder weather when the sludge water viscosity and
secondary sludge yields are higher. Further, a full
range in operating capacity should be investigated to
determine the effect on cake solids and capital and
operating costs.
Stage 5 - Final Evaluation Based on Detailed
Design Parameters
After Stage 4 is completed, accurate scale-up and
sizing of equipment is performed by tho design
engineer with the aid of the equipment manufacturer.
‘AL this time, estimates of the capital cost, labor,
energy, chemical, and maintenance material
requirements for the dewatering process under
consideration can be refined. This information can be
supplomented with data from other plants using the
same process. The researching of similar equipment
porformance and the manufacturers" service record is
highly recommended. Additionally, the operating utility
can make input from performance and operational
probloms experienced in Stage 4 field evaluations.
Based on accurate capital and operation and
maintenance cost information, a final cost evaluation
can be made in conjunction with an evaluation of
other parameters. Stage § concludes with solaction of
the dewatering process and, in many cases, the
preferred manufacturer. All generic equipment is not
reated equally.
‘The equipment and supplier selected should have
widely demonstrated the capability to meet the design
requirements in either similar plants or by adequately
supervised pilot studies at the subject facility. When a
new design of equipment is employed, the
‘manufacturers’ prior practices need to be carefully
scrutinized and adequate safeguards provided to the
utility. Evaluations properly conducted will not stifle
new developments.
‘Throughout this five-stage process, many trade-
offs will have to be made. In many cases, the total
annual cost of two or more solids treatment systems
are essentially identical (+ 10%), and the decision
must be made on some basis other than cost.
Frequently, such a decision is based upon capital vs.