HK 1 2017

The PERI Magazine

Scope

PERI UP Access on the Express Rail Link Project


Express Rail Link Contract 810A, West Kowloon – Page 6

VST Heavy-Duty Shoring Towers supplied to WKCD


M+ Museum, West Kowloon Cultural District – Page 10

DUO Contributing to Cross-Border Transport Development


Liantang / Heung Yuen Wai Boundary Control Point, Liantang – Page 16
Dear Readers,

Welcome to our irst Hong Kong tion cost. The variety of building to enjoy this issue of PERI Scope,
edition of PERI Scope, showcasing projects ranges from building works and thereby familiarise yourself
six interesting projects, aswell as our on SCL train staitions, to the Hong with some of the exciting projects
work with the Construction Industry Kong Breast Cancer Foundation PERI are involved in, in Hong Kong.
Council and of our products which are Center, Ngau Chi Wan.
ideal for the Hong Kong construction As a family owned and operated
market, DUO, ALPHAKIT, and VST PERI has a number of products that company, PERI continues to be
Heavy Duty Shoring Towers. are tailor made for the Hong Kong 100% focused on the development
market. Our ALPHAKIT is a light of formwork and scaffolding systems
weight, high strength shoring system. that will create beneits for all of our
Our recent Civil Engineering projects It provides an allowable leg load customers. We irmly believe that the
stretch across the Hong Kong SAR. of 300 kN, and is completely man lourishing of Hong Kong as a pros-
The M+ Museum in the West handle-able, requiring no crane for perous and dynamic city lies, among
Kowloon Cultural District is the new assembly. It is ideal for heavy duty others, in the strength of its institutions
museum for visual culture in Hong civil works. In residential developments, and businesses, for that reason it is
Kong, focusing on 20th and 21st the Hong Kong construction industry our ambition to join efforts with public
century art, design and architecture, is facing tough challenges in the years organisation’s and private construction
and provides a fascinating challenge to come; a shortage of skilled workers, company’s to continue propelling
to construct. The West Kowloon Rail and a high demand for residential the development of our city.
Terminus, which will house the only buildings. PERI DUO is the solution.
station within the HKSAR section of A simple formwork system to build As ever, we thank you for your coni-
the Express Rail Line to the mainland, safely, quickly and economically. dence in PERI and look forward to
has an iconic roof structure, and will working together on your next project.
cut commute time to Guangzhou to Our hydraulic climbing systems, for
just 48 minutes. Further south, the cores, safety screens and formwork,
Shatin to Central Line Cross Harbour combine excellently with DUO form- Signature
Tunnel, contract SCL1121, was work to offer the optimal solution
accelerated thanks to PERI Formwork for residential and commercial high-
Systems TRIO and DUO. In the North rise projects.
of Hong Kong, at the Liantang Bound-
ary Control Point, PERI DUO is being Whilst PERI is well known for its
utilised to construct 11 buildings. formwork and scaffolding systems
This ultra light, labour saving formwork around the world, we are less well Rory O‘Gara
enables the construction cycle to be known here in Hong Kong, our Managing Director
accelerated and reduces the construc- newest market. I hope you ind time PERI (Hong Kong) Limited

Located at Billion Centre, Kowloon


PERI headquarters in Weissenhorn, Germany. Stockyard located at Tsin Shui Wai. Bay, our ofice is highly accessible.

2
Wall and Slab: one system.
Universal. Lightweight. Simple.

PERI DUO – the innovative formwork system

The universal lightweight formwork which is characterized


by its particularly low weight and very easy and simple
handling. Not only the fact that the material used is new
but also the overall concept. With an extremely small
number of different system components, walls, foundations, columns, slabs and beams can
be eficiently formed. In addition to the panels, including the formlining, most DUO accessories
are also made of a polymer-based composite material.

3
Overview of XRL Contract
810A Birdcage Scaffold

4
5
The West Kowloon Terminus Station nine long-haul and six shuttle plat- of façade, glass and cladding for this
North is the largest civil contract forms, customs and immigration feature roof. PERI Hong Kong provided
awarded for the Hong Kong Section of facilities, departure lounges, duty the client with onsite engineering
the Guangzhou-Shenzhen-Hong Kong free and other retail outlets on four support, project management and
Express Rail Link. Located in the heart levels. A key element of the project over 100 2D and 3D design drawings.
of Kowloon, the terminus will serve is the dramatic roof structure above The access scaffold has a number
as Hong Kong's international gateway the station entrance made up of of unique and bespoke features
to China. over 7,000 tonnes of steel trusses including access ways for construction
and elaborate support columns. vehicles, hoist wells, stair towers,
Leighton-Gammon Joint Venture are clear span openings for ongoing
constructing a 380,000 square metre PERI UP Access Scaffold has been concrete works below, working areas
underground terminus, which includes utilized for the complicated installation around mega columns, protection

Initial PERI UP installed to 60 m high. Multiple working levels throughout. Fully boarded safe working areas.

6
2,000 tons of PERI UP on the
Express Rail Link Project
Express Rail Link Contract 810A, Hong Kong

decks and integrated walkways for


ergonomic material and personnel
movement. PERI’s world leading
logistic ability enabled 2,000 tonnes
to be shipped and supplied over a
short period so that no delays were
caused. In one location a ticket booth
at basement level meant a large clear
spanning portal was required, here
PERI used their high load capacity
aluminum MULTIPROP to easily
over-come this and provided the JV
with a comprehensive solution.

As one of the safest scaffolding


systems in the world, PERI UP pro-
vides system integral advantages.
Not only during scaffold assembly
operations, but also when the scaf-
folding is being used. The continuous
metric grid afforded by the PERI UP increased both work safety and are integrated into the planning pro-
Flex Scaffold System ensures that eficiency. Scaffolding planning with cess and the scaffold equipment can
scaffolding installation, to suit building PERI CAD enables the PERI team be dynamically allocated to sub areas
geometry and site vehicles can be to coordinate proposed solutions in of the project based on the needs of
systematically and lexibly carried out; advance with the project partners. the various trades.
there is no time consuming tube and
itting assembly. The 250 mm height The features of PERI UP Scaffold As a result of this additional beneit, a
increments provides the opportunity System allowed the JV to build one project management team can access
to create safe working platforms. of the largest scaffolds ever construct- deviations in the execution compared
Moreover, the small number of diffe- ed in Hong Kong in a short period to what was planned.
rent system components accelerates of time, and to construct the scaffold
assembly while the resulting gap free safely, while matching the complex
installation achieved through the use building geometry. The 3D models Contractor
Leighton-Gammon JV
of system decking means there are provided by PERI gave clear direction
Field Service
no overlapping planks and subsequent to the frontline erectors, enabling PERI (Hong Kong)
tripping hazards during use. the drawings to be easily followed, Limited
thus reducing the requirement
Detailed 3D scaffold planning, as well to inspect as built structure. Other
as the early consultation and coordina- factors, such as material cost, work-
tion with all project participants has loads, erection time and service life
John Campbell,
Construction Director:
“PERI UP Scafold provides us with
The 3D design signiicantly increased site productivity.
great lexibility and high eiciency.
The system has a short learning
curve and with the simplicity of it,
we could stick to our planned
schedule of construction.

PERI‘s ability to deliver a huge


amount of high quality equipment
on such a short notice is the key
reason we chose PERI as our
partner, we believe that no other
company could have supported
us on this scale of project.”

7
PERI provided Typhoon Proof storage. PERI UP LGS
(Lattice Girder System) with 40 m clear span
Express Rail Link Contract 810A storage area, Hong Kong

Contractor
Leighton-Gammon JV
Field Service
PERI (Hong Kong)
Limited

Adrian Ferguson,
Sub Agent:
“We are delighted to work
alongside PERI with providing
our project and client with
technical solutions backed up
by enormous project experience
and ability. This system has
given our project a solution of
adaptable temporary storage
at a fraction of the cost of ware-
house rental”

External view of the temporary storage area . PERI are providing covered storage at two locations.

In addition to supplying access scaffold LGS (Lattice Girder System) structure travel on rails, allowing customers
on the Express Rail Link project, PERI is designed to accommodate large to easily slide the cover to the area
provided a total of 8,000 m2 of covered spans, high loads, and Hong Kong where works are on going. Due
storage to Leighton-Gammon JV. climate conditions. to the limited and costly supply
Four warehouses were provided with of covered storage in Hong Kong,
the use of PERI UP Flex Weather The roof is assembled in single LGS can be used as an alternative
Protection Roof LGS. This provided movable girder segments. By doing solution. With its high adaptability
LGJV with much needed dry storage so, it allows the easy opening of the and fast erection, complete weather
space for their façade and glass works. roof, e.g. for the delivery of materials. protection can be realized, with
The crane lifts the complete segment different inclinations and geometries
Temporary and protective rooing quickly and safely into position after to suit any requirement.
facilities can be quickly and easily pre-assembly on the ground.
realized. The system can be used PERI are looking forward to provid-
for jobsites during the typhoon It also provides a high level of safety ing weather protection solutions
season, allowing works to continue both during assembly as well as use. to further projects in Hong Kong so
without any delays, or as dry As an option, the roof can be designed you can build through the monsoon
storage facilities as in this case. as a movable version, whereby it can season.

On the basis of PERI UP Scaffolding System, LGS


One of the storage facilities constructed. provides dry storage space, at site or stockyard.

8
PERI UP Easy,
the new Facade Scaffold from PERI
A real alternative to Bamboo in Hong Kong

PERI UP Easy Facade Scaffolding Consistently following the metric grid Technical details
stands for simple and fast assembly. design, the system also includes a ■■ Standard coniguration with a
PERI UP Easy is lightweight among 1 m wide frame which can, as an 670 mm system width / 660 mm
the range of steel facade scaffolds alternative, be used with 25 cm steel decking width
on the market. In addition, it provides decks from the PERI UP Flex Modular ■■ For use as working scaffold in accor-
safety in the system, as the guardrail Scaffolding system. dance with DIN EN 12811-1:2004-03
for the next level is installed from ■■ Can be used as safety
the scaffolding level below using the Lightweight and roof edge safety scaffold
Easy Frame without any additional Fast working operations due to the low ■■ One-piece combi-decking with
components. Through the rosette weight of the individual components integrated protection against
nodes on the frame, the system can High level of safety lifting, can be loaded up to max
also be combined with the PERI UP At all times operatives are protected 2.00 kN/m² with FOS 3
Flex Modular Scaffolding. from falling due to advance guardrail ■■ One-piece steel decking with inte-
construction grated protection against lifting, can
The PERI UP Easy has a system Fast assembly be loaded up to 3.00 kN/m² with FOS 3
width of 670 mm. It can be used Assembly with virtually no couplings ■■ Gap-free decking surfaces
with either a one-piece board or with and a minimum of tools without separate gap coverings
two steel decks each 330 mm wide. Special application versatility ■■ Internal bracket decking, removable
The integrated protection against Can be combined with PERI UP Flex for use on external walls with a
lifting is featured in both decking system components thermal insulation system
versions. This is not only quick and ■■ Fast opening and closing of scaffold
safe but also allows the opening and bays, e.g. for the transport of
closing of individual scaffold bays, materials
e.g. for transporting materials.

Hongkong-Zhuhai-Macao Bridge (HZMB)


Project highlight

Straddling across Lingdingyang of Pearl River Estuary, the


Hongkong-Zhuhai-Macao Bridge (HZMB) is a mega-size sea
crossing linking three regions which are Hong Kong, Zhuhai
and Macao. The total length of the bridge is 42 km including
a 6 km long immersed tunnel PERI helped to construct.

Two hydraulically-operated shuttering machines were used


for the realization of 180 m long tunnel tubes with incremen-
tal launching. 33 tunnel elements were moved from the ield
factory, sealed with bulkheads and installed on the sea-bed.

The main contractor China Communications Construc-


tion Company Ltd. enjoyed enormous benefits:

■■ production of the bottom plate, outer walls


and slabs without ties
■■ industrial production of individual tunnel segment
■■ precise implementation of the project requirements

9
Timely construction with Contractor
Hsin Chong
Field Service
VST Heavy-Duty Shoring Towers PERI (Hong Kong)
Limited

M+ Museum, Hong Kong

Gabby Lu, Engineer,


production team:
“The high quality and
adaptability of the equip-
ment are the benchmark
of PERI. Basically, every
component of the VST
Tower is manually adjust-
able to it our require-
ments for a lawless
assembly.

Located in the centre of M+ Museum to be erected support. To do this an Most importantly, PERI
the West Kowloon Cultural without any interference ingenious arrangement of cares about our needs.
District, M+ is Hong Kong‘s to the existing structures. steel trusses and shoring We received enormous
new museum for visual The mega trusses will towers was planned. PERI support from all depart-
culture. The museum occu- transfer the loads from the provided a total of 60 VST ments especially the
pies an area of approxi- inished museum onto piles towers, with heights varying engineering team, who
mately 60,000 square built at each side of the cut from 6.50 m to 15.50 m provided us with compe-
metres, and is comprised and cover tunnel structure. and an average leg load of tent and professional
of a 14 storey tower, a 600 kN. For these towers technical advice
3 storey Podium and a The construction method several non-standard throughout.”
2 storey Basement. for these mega trusses is conigurations had to be
noteworthy. The dirt cover designed, notably, double
For the challenging con- of the tunnel is removed to legged towers, situations
struction of this building, allow a maximum loading where two legs had 15 m
on top of the MTR airport of 30k N/m2 on the top slab and 2 had 6.50 m and scheme, meaning clients
express line, one of the of the tunnel, as indicated towers with very small advise one day prior which
most important transporta- by the original designer of dimensions in plan view. tower would be erected
tion networks in Hong Kong, the tunnel. Our client, Hsin In addition, PERI performed and preassembly work
5 concrete-steel composite Chong, designed an intricate preassembly work at the would be arranged. Optimal
mega trusses are under temporary works scheme stockyard, provided site services were provided to
construction. The trusses in order to spread all the assistance with an on-site the client, hence reducing
span above the rail tunnel in construction loads and supervisor, and followed labor costs and time con-
West Kowloon, enabling the obtain suficient area of a “just-in-time” delivery suming tasks.

Telescopic base & head plate allow site


tolerances to be easily achieved. All
M+ Museum will overlook connections are pinned for fast assembly
Victoria Harbour. Overview of VST Towers in use. and high bending moment connection.

10
Fast assembly. High load-bearing.
VARIOKIT Heavy Duty Shoring Tower VST

Heavy-duty shoring towers with a high load capacity. Standard heights of up to


40m are possible – proof is provided for larger heights on an individual basis.
Operating the head spindle when fully load is possible.

Fast assembly
with bolted connections and pre-assembled tower segments up to 10 m.

Simple height adjustment


through moving hydraulics with which the head spindle can be operated
when under full load.

Cost-effective solution
as all system components are available in the PERI stockyards.

11
Bespoke solutions for every project
Civil Engineering group and Tunnel Expert team

VST Heavy-Duty Shoring Towers and VRB Heavy-Duty Truss Girders were used in the construction of this challenging Bridge project.

Civil Engineering group


With over 64 subsidiaries around the
world, PERI Germany works closely
with each to ensure maximum
customer satisfaction is attained.
Our centralized engineering team in
Weissenhorn specializes in bridge
building, tunnel construction and civil
engineering, based on the VARIOKIT ■■ Expert support for our clients ■■ Our global project database brings
Engineering Construction Kit. With in all stages of their project international solutions and experi-
years of knowledge and expertise, ence directly to the Hong Kong
the team works closely with each sub- ■■ Involvement in customer market
sidiary to provide bespoke solutions. discussions (project expertise,
As a result, they are able to offer cus- experience, teamwork) ■■ The eficient design of our VARIOKIT
tomers a tailor-made overall concept, by PERI engineers allows unlimited
even for complex and material-inten- ■■ Internal
coordination of project construction solutions to be realised
sive project requirements. handling including material and rented, which reduces the
lows worldwide requirement for bespoke fabrication,
Tunnel Expert team thereby offering large savings
PERI tunnel expert team collaborates
closely with various specialists on
all levels of planning and execution
throughout the development of tunnel Supporting structure with PERI VARIOKIT
construction. PERI tunnel construction Engineering Construction Kit enables quick
formwork movements, saving time and VARIOKIT Engineering Construction Kit provides
solutions are based on either our
construction costs. system solutions for tunnel construction.
VARIOKIT Engineering Construction
equipment or bespoke design and
fabrication, depending on project
requirements such as programme,
duration or concrete pressures. Our
tunnel experts support PERI custom-
ers with technical advice and planning
services from one source. They will
also ind the most cost-effective
solution on the basis of the customer´s
own portfolio and PERI rental parks
which are available worldwide.

12
RCS Climbing Protection Screen
Flexible. Adaptable. Crane-free. Maximum protection.

The RCS Climbing Protection Screen together with Guardrails provide gap-free protection for work carried
out on the building shell loors. The screen completely encloses the top loors of the building shell which
are under construction. The enclosure protects site personnel against falling and strong winds at great
heights, thereby enhancing construction eficiency. Landing platforms can be integrated in the RCS protection
panel solution, allowing fast and simple transport of materials. The screen at the same time is served as
widely visible advertising space.

13
Cross Harbour Tunnel accelerated Contractor
Penta-Ocean-China
State JV
with PERI System Formwork Field Service
PERI (Hong Kong)
Limited
Shatin to Central Link Contract 1121 , Cross Harbour Section

SCL 1121 will extend East Rail Line PERI TRIO was supplied for a 5 month onsite formwork instructor for the irst
from Hung Hom. The Cross Harbour period to enable Penta-Ocean-China two months of construction to assist site
Section includes the construction of State JV to accelerate the completion personnel and familiarize the operatives
the 4th harbour railway tunnel in Hong of the tunnel segments. The TRIO with the system. The embedded safety,
Kong, and it connects Hung Hom and panels were supplied with propping, ixed tie positon and integrated platform
Causeway Bay Typhoon Shelter. This access walkways, certiied crane lifting access signiicantly reduced safety risks
1.7 km cross-harbour tunnel beneath device, formwork ties and handrails. It on site, thereby minimizing the super-
Victoria Harbour will be built by using was a simple case of lifting the panels vision requirements. TRIO proved once
immersed tube tunnel construction from the delivery vehicle directly into again that can perform in many markets,
method, comprising tunnel units position so that rebar could be placed and we look forward to utilizing this pro-
pre-cast at the casting yard in Shek O. and concrete poured. PERI provided an duct on many more projects in Hong Kong.

PROP Range to meet all requirements

As a global leader in the manufacturing of shoring systems, PERI provides clients with enormous lexibility
by offering a wide range of props that can suit virtually any geometry as well as different loads.

PEP Ergo B PEP Ergo E MULTIPROP HD 200 VST


30 kN 50 kN 90 kN 200 kN 700 kN

14
PERI demonstrated high competence
in building construction
Hong Kong Breast Cancer Foundation Center, Hong Kong

The new center of Hong Kong Breast


Cancer Foundation (HKBCF) is current-
ly under construction in Ngau Chi
Wan, Kowloon. Granted by the Hong
Kong Government, the site spans
about 6,000 square feet. The center
is scheduled to open in the second
quarter of 2017 and is designated
to provide breast health education,
screening and other services to
women with high risk for breast
cancer who live in Kowloon and the
New Territories. All system components are below 25 kg The couplers it exactly into the openings in
which enables complete manual operation. the panel frames and are mounted without tools.

PERI supplied approximately 500 m2


of DUO Formwork to facilitate the
construction of this two-storey Following the success of this project, will be utilized for the sofits, allow-
building. DUO was employed for Chun Wo, one of the leading con- ing the formwork to be cycled imme-
the construction of various structures struction companies in Hong Kong, diately while the scaffold remains
which include walls, columns, lift is currently collaborating with PERI behind until the slab has reached
shafts and T-Junction walls. to design a monolithic formwork full strength. This unique feature will
solution utilising DUO on another of provide signiicant savings, a safe
Due to its low weight, all work can their interesting projects, the New working environment and cut cycle
be carried out by hand. In addition, the Territories West Regional Ofice and times of formwork. PERI look for-
formwork system is very simple and Water Resources Education Centre ward to closely working with Chun
thus easy to handle. The good quality of the Water Supplies Department. Wo to build a better Hong Kong for
of the system components guarantees everyone.
a high reusability and at the same time For the monolithic pour, a quick strip
provides good wall surface results. beam erected on a PERI UP Scaffold

15
PERI DUO contributing to
cross-border transport development
Liantang / Heung Yuen Wai Boundary Control Point, Hong Kong

Contractor
Leighton Contractors
(Asia) Ltd.
Subcontractor
United Engineering
Safe Work Ltd.
Field Service
PERI (Hong Kong)
Limited

Jack Maharjan,
Project Manager:
“DUO provides us with great
lexibility compared to traditional
formwork. Its extremely light weight
enables faster manual erection and
striking. With DUO, construction
time and labour cost are reduced,
and the safety standard together
with the quality of concrete surface
formed is enhanced. We are more
than happy to recommend PERI
DUO Formwork to others.”

As the seventh land crossing between structures. The total construction no longer a constraint in the construc-
China and Hong Kong, Liantang/Heung loor area of all buildings in the project tion speed, rather the availability of
Yuen Wai Boundary Control Point is about 157,400 square metres. substantial work fronts.
(BCP) will connect with the Shenzhen Seeing the advantages of DUO,
Eastern Corridor and provide an access subcontractor United Engineering The X-Ray Vehicle Inspection Inbound
to eastern Guangdong, facilitating have embraced the system and are wall, was one of many structures
future regional cooperation and enjoying the labour and cost saving completed with DUO. The 12 m high
development. beneits. United Engineering need wall was poured in 2 lifts of 6 m.
to deliver 150,000 m2 of formed The unique features of DUO allowed
Leighton Asia is the sole contractor concrete, and DUO is helping them the form to be assembled by hand on
for the construction of a passenger achieve their targets. the irst pour, before being struck in
terminal building and nine other main gangs and lifted easily to the next pour.
ancillary buildings including ire and Over 1000 m2 of DUO Formwork Panel
police bases, vehicle examination is currently being cycled to achieve Columns, T-Junction walls, pile caps,
buildings and a number of bridge impressive results. The formwork is monolithic pours and standard build-
ings are among the many structures
that United Engineering have utilised
the system on, and the results have
been the same in each case; a good
concrete inish, fast assembly, a high
level of safety and reduced labour
requirement. DUO offers a real
alternative to traditional formwork
methods in Hong Kong.

Reducing crane usage to the


minimum level, DUO provides
simplicity and enhances eficiency
throughout the entire construction
process.

16
Engaging with customers
DUO workshop and seminar with HKCIC

Group picture of 28 formwork carpenters who attended a DUO seminar at our stockyard. Sales Engineer Jeff Leung is presented
a certiicate by CIC representative.

PERI embraced the opportunity to PERI as the leading manufacturer eficient, versatile and economic. One
connect with the one and only statuto- of formwork and scaffolding systems, of our main interests is to continue work-
ry body in the Hong Kong construction basic concept regarding the use ing with the CIC and our clients in joint
industry, the Construction Industry of PERI DUO and a practical session efforts to ensure the safety of workers.
Council (CIC). On 4 July 2016, PERI’s where participants could experience DUO Formwork incorporates scaffolding
irst HK customer training was held one of the most powerful features components that can be combined with
at the Council’s training centre in of the product – the extremely low other PERI scaffolding to ensure greater
Kowloon Bay. weight. safety. We irmly believe that the lou-
rishing of Hong Kong as a prosperous
Following the success of the irst Being aware of the challenges and dynamic city lies, among others, in
workshop, PERI organized another that Hong Kong faces, a shortage the strength of its institutions, for that
DUO Formwork and Plywood seminar of workers and the need to meet a reason it is on our best interest to join
for CIC formwork instructors at our high demand for new residential efforts with the Construction Industry
stockyard on 29 December 2016. properties in a short time, DUO aims Council and other public and private
The seminar was comprised of the to be the best ally of the Construction organizations to continue propelling the
following sessions: introduction of Industry in Hong Kong because it is development of our city.

ALPHAKIT
New 300 kN crane independent shoring for medium to heavy bridge construction

ALPHAKIT is the new construction kit for shoring solutions


up to 25 m height and span. The system features few
lightweight individual components and quick-connect itting
pins for tower and truss applications.

Easy pre-assembly without a crane


with easy to handle, lightweight individual components

Fast assembly
due to high load-bearing fasteners with only 2 itting
pins per connection

Only few components


with variable application make the system simple and
cost-eficient

17
PERI participating in building Contractor
Leighton – LNS JV
Field Service
a sustainable environment PERI (Hong Kong) Limited

Harbour Area Treatment Scheme Stage 2A, Hong Kong

Circular Shaft Form constructed with VARIO GT 24 Girder Wall Formwork and the RCS Rail Climbing System.

To restore Hong Kong‘s Harbour to a shaft to Leighton – LNS JV. VARIO both productivity and eficiency were
more natural and healthier condition, panels were pre-assembled on the achieved. Various shaft shapes were
the Government implemented the ground to reduce the requirements to constructed, including elliptical and
Harbour Area Treatment Scheme work at height. Due to the 125 mm circular, all of which were climbed
(HATS), which is one of the most hole arrangement of the climbing rails, using PERI hydraulic climbing systems.
important environmental protection the platforms can be climbed in any PERI provided on site support through-
programmes ever undertaken in Hong increment of 125 mm, therefore the out the project, offered advice during
Kong. The HATS Stage 2A involved the climbing height could be optimally assembly, installation, climbing and
construction of a sewage conveyance adapted to suit the respective storey dismantling. PERI look forward to
system on the Southern part of Hong height. A fast, reliable and trouble-free working closely with both contractors
Kong Island. PERI provided a solution operation was ensured during the again in the future, and on many more
of combining VARIO GT 24 Girder Wall hydraulic climbing of the shaft lining climbing projects in Hong Kong.
Formwork with the RCS Rail Climbing formwork. With PERI’s comprehensive
System for the construction of the engineering solution, the JV ensured

VARIO elements in a circular arrangement,


VARIO GT 24 wall panels can be man-handled. pre-assembled on ground. Turnbuckle arrangement for simple striking.

18
NEW – ACS Core 400 Climbing System
Single Stroke Self-Climbing Formwork

The new PERI ACS Core 400 Climbing System makes forming concrete
cores on high-rise buildings faster, safer and more eficient than ever before.
The new heavy duty hydraulics lift the entire platform, placing boom,
formwork and suspended external platforms to the next level in only 20 minutes.
Reduced assembly times result in labor savings and increased safety.

■■ Comfortable, high load-bearing


working platform
■■ Economical anchor technology
■■ Quick, safe climbing in one lift

19
Korea
Seoul
Japan
Tokyo

Hong Kong
Stockyard
Regional Distribution Center
All delivery times < 14 days

Thailand Philippines
Bangkok Manila
Vietnam
Ho Chi Minh Philippines
Cebu

Malaysia
Kuala Lumpur
Singapore

Indonesia
Batam

PERI logistic capabilities in South East Asia

Our storage facility in Tin Shui Wai, New Territories, spans over 5,000 square

HK en 04 | 2017 1.0eb 794179 © PERI GmbH


meters, and is backed up with the largest logistics network among all formwork
companies in Asia. With continuous development, PERI strives to be the largest
formwork, scaffolding and shoring provider in Hong Kong.

The PERI Stockyards across the APAC region enable us to handle projects of all
sizes and specifications. We permanently store the comprehensive PERI product
portfolio in big quantities. As a result, we are always able to deliver according to
the requirements of your project. Furthermore, an efficient Supply Chain
Management guarantees fast handling of your order.

The photos used in this brochure feature certain situations PERI (Hong Kong) Limited
at particular moments on various construction sites. Formwork Shoring Engineering
Additional images, e.g. regarding safety and anchor details, 19D, Tower B, Billion Centre
cannot always be considered as conclusive or final.
1 Wang Kwong Road
These are subject to the risk assessment carried out
by the contractor.
Kowloon Bay
Tel. +852 3102 7900
© PERI GmbH Fax +852 3188 9258
info @perihk.com
www.perihk.com

You might also like