1. Background/Introduction
Arcadis had completed the PCM service at Hilton Saigon Hotel for DW/Pilling
& basement packages ( 5 basements) and a part of superstructure work refer to
Construction License by SGCL Company ( Client of Hilton Saigon Hotel) .
However, we are missing the Company Performance Certificate Grade 1 as the
current Law, and all current documents need to be reviewed and re signing by 3
rd party company ( Bidder).
The project is suspension due to Legal issue ( for Superstructure package) . The
Bidder can check all project legal documents relating to scope of service. All
project documents was located at Site office. The main contractor for structural
packages is Cotteccons company.
NOTE: Arcadis had a right function for Project Management and Cost
Consultant Service. We can warranty for the practical quality management at
site.
EXCLUDE
- the project schedule, safety, cost and other ongoing work packages will not
included in this scope
- the current project document such as EI , NCR, Transmittal , correspondence
letter will not included . we can sharing these documents as information only
The RFP will be sent via email . Any RFI or Queries should be sent and feedback within
2 working days.
Respondents to this RFP must submit one original and 1 copies of their proposal ( hard
copies PDF or Scaned file with Company Stamp . Responses must be received no later
than July 5, 2018. Responses should be clearly marked “RFP-CM Services” and mailed
or delivered to the contact person listed above.
5. Procedure
The Bidder can propose the schedule for review and approval - Timeline not to exceed
3 weeks