PREDIMECIONAMIENTO

1) LOSAS ALIGERADAS
s/c = 250 kg/m2
h = 4,65/25 = 0,186 = 20cm

2) VIGAS
s/c = 250 kg/m2

Peso aligerado = 350


Peso de acabado = 100
Tabiqueria = 150
WD = 600
WL = 250

𝐿�/4 /√𝑊� = 0.385


a) Viga Principal
PREDIMENSIONAMIENTO

LOSAS ALIGERADAS

S/C = 250 Kg/m2


base =
4.65/25 =0.186 = 20 b= 30/2 = 15
cm cm
b= 42/2 = 21
VIGAS cm

S/C = 250 Kg/m2

Peso aligerado = 350


Peso acabado= 100
Tabiqueri= 150

WD = 600
WL = 250

WU = 1120 Kg/m2
WU = 0.112 Kg/cm2

VIGAS PRINCIPALES

Ln= 4.65

h = 𝐿�/ 0.389046912
(4/√𝑊�) = ��/
(4/√��) =
h= 40 cm

base = 20 cm

b= (𝑎�𝑐ℎ𝑜 𝑡𝑟𝑖𝑏�𝑡𝑎𝑟𝑖𝑜)/20 = 0.171


(3.70+3.15)/(2/20)= 20 cm
b= 17cm

b ≥ 25 25 m
= 25m

VIGAS PRINCIPALES
h= 40
b= 25 m
VIGAS SECUNDARIAS METRADOS DE CARGA

h =3.70/2 =0.31 = 35 cm Peso A ligerado = 350


Tabiqueria = 120
acabado = 100
b= 30/2 = 15 peso viga = 100
cm
peso columna = 60
b= 42/2 = 21 730
cm
b > 25 cm = 25 cm P= 980 Kg/m2

porlotanto: P1 = 1010 X14,385 = 14528,85


h = 35 cm P2 = 1010 X 9,5175 = 9612,68
b = 25 cm P3 = 1010 X 7,77 = 7847,70
P3 = 1010 X 5,36 = 5413,6

COLUMNAS C1 = b + d = ((1,10 ∗14528,,85 ∗10)/(0.25


∗210)) =3044,14
Areas tributarias
b = 35 H = 35
C1 =((3.75+4.75)/2)
∗((3.70+3.15)/2) = 14.385 cm C2 = b + d = ((1,25∗9612,68 ∗10)/(0.25
∗210)) =2233,80
C2 =(4.50/2+1.15) ∗((3.15+3.15)/2 )=
10.71 cm b = 30 H = 30

C3 = b + d = ((1,25 ∗7847,7 ∗10)/(0.25


C3 =((4.65+3.75)/2) ∗(3.70/2 )= ∗210)) =1868,5
7.77 cm
b = 30 H = 30
C4 =(4.50/2+1.15)∗ 3.15/2 = cm
C4 = b + d = ((1,50 ∗5413,6∗10)/(0.25
∗210)) =1433.43
b = 30 H = 30
s/c = 250

28,,85 ∗10)/(0.25

2,68 ∗10)/(0.25

7,7 ∗10)/(0.25

3,6∗10)/(0.25