Project No: Document No: WI-SR-13

Production No: Revision No: 0

Steelwork Repair Flowchart


Ship Repair Steelwork
Page 1 of 1 SAFETY · HEALTH · ENVIRONMENT · QUALITY

QC & Steel Foreman


Mark Up Wasted
Areas

QC Provide Drawing
and Material
Specification

Steel Foreman
marks up plate for
insert

Plate cut and edge


prepared

Steel Foreman
submits Inspection
Request to QC

QC & Foreman
Fit up Inspection No
Passed?
Yes

Proceed with root


welding procedure

Steel Foreman
submits Inspection
Request

Grind out root and Grind out weld and


QC & Foreman
No edge prepare insert edge prepare insert
Root Inspection
Passed?
Yes

Proceed with cap Steel Foreman


TPI MPI finished
submits Inspection No
weld procedure weld
Request
Passed?
Yes

End