Professional Documents
Culture Documents
Final Inception Report en
Final Inception Report en
Tajikistan
INCEPTION REPORT
Dushanbe to Uzbek Border Road Improvement Project:
Review of Road Standards and Road Sector Institutional Reform
September 2016
• SUBMITTED BY:
2 INCEPTION REPORT
R
Established : Verified : Approved:
DATE E
M.POURASHRAF E. ADHAMI O. YATIMOV Modifications
Team Leader
V Project Director Project Supervisor
B
3 INCEPTION REPORT
CONTENTS
ABBREVIATIONS
ACKNOWLEDGEMENTS
The information presented in this report and the conclusions reached are based on
information provided to the Consultant by the Ministry of Transport.
We would like to express our gratitude to Ministry staff who have fully co-operated with our
team and provided valuable input during the Inception Phase.
6 INCEPTION REPORT
1. EXECUTIVE SUMMARY
This Inception Report is the first deliverable prepared under the European Bank for
Reconstruction and Development (EBRD) project the “Dushanbe to Uzbek Border Road
Improvement Project: Review of Road Standards and Road Sector Institutional Reform” –
the Project.
The report describes the activities carried out during the inception phase and our
preliminary findings, and proposals for the remainder of the project, including an updated
work plan for up to the end of August 2017.
Prior to the Inception Phase, the Technical Assistance Team met with the Minister of
Transport and key Directors in the MoT to present the objectives of the Technical
Assistance project and receive strategic direction from the MoT on project’s scope and
activities.
The inception phase took place during the period from the 17th August to 30th September
2016. The entire TA team was mobilised for this phase with the objective of conducting a
preliminary fact-finding exercise and meeting the project beneficiary and key stakeholders
as well as collecting all relevant data and reports.
Project infrastructure was established at the MoT’s building and a coordinator was
appointed to support the TA team.
Meetings were held with various stakeholders including the Minister of Transport,
the European Bank for Reconstruction and Development, GUSADs and private
construction and consulting companies.
The project’s Terms of Reference (ToR) was fully reviewed in preparation for
planning the input of the TA team.
Key technical, financial and legislative documentations were reviewed to understand
the current institutional organisation of the road sector.
Information was collected on past studies, projects, standards, and senior MoT
managers were formally interviewed.
Visits to 5 GUSAD subdivisions situated in the Sughd region and 4 situated in the
Republican Subordination region were undertaken.
Visits of MoT facilities such as the laboratory at the Road Survey and Research
Institute and axel load control stations were undertaken.
Data was collected from different sources such as The Tajik Geological Survey, and
the Tajik Chamber of Commerce.
Visits to a few segments of recently rehabilitated republican roads and unrestored
FSU built roads, in order to understand the differences in standards actually applied
to design and the quality of the maintenance works.
The TA Team visited the construction site of the Khujand-Isfara Road and
interviewed MoT’s representatives and the resident engineer about the standards
applied in detail design and the quality control of construction materials.
The findings of the Inception Phase indicate that the technical and management practices
in the road sector need to be strengthened. This priority will be reflected in the
recommendations to be generated for a revised set of road sector standards and proposals
for the institutional reform of the road sector.
7 INCEPTION REPORT
The initial findings are summarized, under the two components of the assignments, as
follow:
Review of Road Standards - During the inception period the TA Team has
acquired substantial knowledge of the current situation regarding the application of
standards in Tajikistan.
Tajikistan’s road network was built prior to 1991 according to the SNiP construction
code and the GOST standards for materials and workmanship, which were
developed during the Soviet times. They are technically sound and based on
scientific and engineering research, but suffer certain shortcomings with respect to
pavement life cycle cost optimization and road safety.
After the breakup of the USSR, the GOST standards and SNiP codes acquired a
new status as the regional standards. They are at present administered and
updated by the Euro-Asian Council for Standardization, Metrology and Certification
(EASC), a standards setting organization chartered by the Commonwealth of
Independent States.
Some of the CIS countries have adopted all or some of the GOST standards in
addition to their own nationally developed standards. For example, we are informed
that Kazakhstan and Russia have adapted and updated a number of SNiP
construction codes, but have maintained the GOST standards without major
modifications.
However, in the past ten years, a substantial number of road rehabilitation projects
in Tajikistan have been financed by IFIs, especially in the framework of the CAREC
program financed by the ADB which focuses on the rehabilitation of international
transport corridors in Tajikistan.
The ADB has produced its own technical specifications for ADB financed road
rehabilitation projects, which are derived mainly from the AASHTO 1993 Pavement
Construction Guide.
The TA Team visited a number of completed road projects, such as Ayni -Panjkent
road, Dushanbe-Khujand road, Dushanbe-Uzbek Border road and Dushanbe-Norak
road. The TA team has observed the following shortcomings:
We are convinced that, as a member of the CIS, Tajikistan has taken the right
approach to national standards, by seeking conformity with other CIS members.
In our opinion, the SNiP codes and GOST standards, as updated by the EASC,
should be appropriate for Tajikistan. However the country must develop some
specific standards reflecting the specific geography of Tajikistan and prepare design
manuals, catalogues and guides to complement (or in some cases supersede) the
EASC sourced standards.
During Phase 1, working with the MoT, we will prioritize the needs for new or
revised standards and review the updated SNiP construction codes and especially
those produced by the Agency on Building and Architecture, as well as review and
comment on the ADB specifications for pavement construction.
This will form the basis for formulating a strategy to be implemented during Phase 2.
After the breakup of the Soviet Union in 1991 and the ensuing Civil war, the network
went into disrepair and according to the assessment conducted in 2007, more than
80% of the network was in a poor or very poor condition and required total
rehabilitation.
The organization of the road maintenance has not evolved since the Soviet era. The
back bone of this organization is 62 regional maintenance units or GUSAD
Subdivisions which operate under the direction of 6 Regional Road Maintenance
Units or GUSADs.
The GUSADs are attached to the Department of Road Construction & Maintenance
of the MoT, which allocates their annual budget and supervises their spending and
performance.
9 INCEPTION REPORT
There are many legal, technical, financial and operational shortcomings in this
organization, as what used to work in the Soviet times is no longer viable in a
market economy.
The main problem for road maintenance remains the lack of financing and budget
allocations, especially for preventive maintenance.
The JICA and the EBRD have taken a lead role in this respect by funding the
supply of urgently needed maintenance equipment to GUSADs. However, supplying
equipment only offers a temporary relief, but does not address the core problem of
lack of autonomous sustainable funding mechanism and private sector participation
in road maintenance.
In recent years, the MoT has outsourced maintenance works on some sections of
the Republican Roads using performance-based contracts which has produced
satisfactory results.
However, there are factors that limit outsourcing at larger scale such as the low
financial capacity of Tajik private contractors to take on larger projects. Theses
weaknesses could be overcome by more effective government policy and support
for SMEs...
The TA team will propose a set of reforms to the current way of managing, funding
and monitoring the road network in Tajikistan.
We will also consider a set of institutional reforms to align the MoT with the best
road asset management practices as defined in ISO55000 series. A proposal for the
institution of a second generation road fund will be reviewed as part of this study.
A key reform would be the creation of a dedicated autonomous Road Agency with
responsibility for the overall management of the MoT's present and future road
network.
10 INCEPTION REPORT
The Ministry has requested technical assistance from the EBRD to review and revise the
standards and specifications for road sector construction and maintenance in Tajikistan.
This review will be applicable to the “Dushanbe to Uzbek Border Road Improvement
Project” as well as the broader road sector in the country. In particular, this review will
provide an opportunity to reform the road sector with an emphasis on improving road safety
and quality, and increasing private sector participation in road maintenance.
The standards currently in place for the road sector in Tajikistan are mostly derived from the
Soviet-era GOST standards and SNiP construction codes.
Although these standards are still applicable, they require adequate funding levels that
have not been available to Tajikistan since independence.
The loss of expertise in the road sector from both public and private sources has led to
reluctance to consider alternate strategies, methods and solutions.
As a result of the continued implementation of the old standards the country is incurring
unnecessarily high costs which combined with low funding levels leads to the sub-par
implementation of those standards.
1. To review and revise key standards that govern highway design and construction,
including standards for road safety, and the management of the country’s road
sector with the aim of leading to a safer and more cost-effective outcome,
responsive to the needs of a market-oriented economy and allow the introduction of
productivity enhancing technology;
2. To prepare a “Road Sector Institutional Reform Strategy and Action Plan” to help
establish a more sustainable institutional framework for the road sector, including
the introduction of more commercial approaches to the management of the road
network and the road funding environment that is likely to prevail in the medium to
long term.
In addition to the expected results, the project will also prepare and submit an Inception
Report and a Final Report.
The design of our approach is firmly founded on addressing the above key issues in a
systematic and structured manner.
12 INCEPTION REPORT
“Law of the Republic of Tajikistan about roads and road activities”, initially published on
May 10th 2002 and amended on March 15th 2016. (The amendment is not ratified yet)
According to the above law, the Ministry of Transport (MoT) is primarily responsible for the
development and maintenance of roads and the road transport.
According to the law, there is two classes of public roads in Tajikistan (Republican and
local).
Sections of Republican Roads which are subject to the International Transport Treaties
signed by the Republic of Tajikistan, are referred to as International Roads.
It should be noted that according to the law, the municipalities are owners and managers of
local roads, but in reality the municipalities do not have the financial means and technical
expertise for maintaining roads situated in their jurisdiction, so important local roads are
maintained and managed by the MoT.
Although the FSU classification of roads has no official status in Tajikistan, the indexing
system is still used on plans and in technical literature.
Regarding the construction works and the road network maintenance, the law clearly
promotes private sector participation and competitive bidding as stated below:
Article 21. The Competition in road Activities
“Road authorities help develop the competition and the market for road activities. Relations with the
entities performing the road work must be on a contractual basis. Award of contracts on activities of
construction and rehabilitation of roads must be enacted on the tender basis. In contract activities it
is not admitted the overlap of functions of the customer and the contractor in the same entity”.
TA’s Comments:
Considering the Article 21, the GUSAD’s activities are not in conflict with the law as they
only do routine and periodic maintenance and no rehabilitation or construction works.
13 INCEPTION REPORT
TA’s recommendations:
In order to be in conformity with the law, the Government should help develop the
competition and the market for road construction and rehabilitation activities.
The Tajik private contractors need to be supported by the Government in this regard.
In recent years, the MoT has started outsourcing some road maintenance works, based on
performance-based contracts. These contracts are financed from the MoT’s budget and to
date some 4.0 Million USD of contracts have been awarded to the private sector.
The maintenance of the following road links has been awarded to the private companies:
Signing of Contracts in October 25, 2013 for the period of 3 years with
LLC “Gayur-1” for the Vahdat Obi-Garm section (0-76 km) and Branch of
SC “IRS” for the Nurobod-Nimich section (120-193 km).
These projects were treated as pilot project by the MoT, both contracts are closed and
finalized now.
Annual expenditure on road maintenance (excluding external funds) is shown in the
following table:
The following graph depicts the current situation from which the following observations can
be made:
- The yearly expenditure on routine maintenance has increased at a fast rate, with the
average rate of increase 4.0 Million Somoni per year during the last 15 years.
Per the Indian Technocrats’ Report (2007)1 the funding requirements for routine and
periodic maintenance was estimated at 20.0 Million USD per year, but the available budget
at that time covered only 30% of maintenance needs.
According to the EBRD financed 2009 study “Road Maintenance Management Plan” the
road maintenance needs for the road network will increase from 30 Million USD to 50
Million USD in 2025.
In the next phases of study, the Technical Assistance Team will examine and update the
findings of the previous studies and propose a realistic maintenance budget.
We have also visited the small testing laboratory in the Tajik Technical University, which
accepts assignments from other government agencies. Their capacity is limited and they
are organized to carry tests per GOST procedures.
The only private laboratory available belongs to the Tajik Private Consulting Company
Avtostrada LLC, which is said to own equipment necessary to carry in-situ tests for bridge
foundations.
1
TA No 4294 TAJ: Strengthening Implementation of Road Maintenance Financial System” provided by Intercontinental
Consultants and Technocrats Pvt. Ltd (India). ADB 2007
19 INCEPTION REPORT
The MoT operates a laboratory for its own construction projects the “Road Inspection
Laboratory” in Dushanbe, we have not visited this laboratory during the Inception period,
but we are informed that this laboratory is only capable of basic tests.
We have no information about the MoT staff who will operate the van and how the data will
be stored, analyzed and used.
20 INCEPTION REPORT
The JICA has provided MoT with a set of 6 DRIMS devices (Dynamic Response Intelligent
Monitoring System) which are deployed in Khatlon GUSAD and Hissar GUSAD subdivision.
This JICA project aims to transfer the latest IRI measurement technology, called Dynamic
Response Intelligent Monitoring System (DRIMS), to Tajikistan.
IRI values can be easily obtained, using ordinary cars or light trucks equipped with DRIMS
that consists of laptop, GPS, accelerometer, and road monitor.
The JICA has trained the GUSADs’ staff necessary for operation and data handling of these
devices.
21 INCEPTION REPORT
The project has been launched in 2015 to improve maintenance management capacity of
roads and bridges.
although there were stations deployed in the past for a limited time and for specific projects,
but these stations did not cover the whole network.
Some of GUSADs are recently supplied by the WB with automatic traffic recording
equipment, but to this date none are deployed.
The pictures below were taken at Vahdat GUSAD Subdivision:
22 INCEPTION REPORT
Hissar control station - The permanent control station visited is situated close to
Dushanbe on the Shahrino-Dushanbe link; only the east bound traffic is controlled by the
Hissar District police brigade.
This station is equipped with a single wheel scale and a weighing bridge. The weighing
bridge had technical issues and was not operational at the time of our visit.
We interviewed the officer in charge of the station, who informed us about their control
procedures:
- They measure the axle load, but only the gross vehicle weight (which is the sum of
individual axle loads) is controlled and if the gross weight is over 40 tons a penalty ticket
is issued.
- Only semitrailers trucks are controlled, with all other types of trucks going through the
station without control.
- The International semitrailers coming from Uzbekistan with TIR signs are not controlled,
as they are supposed to be already controlled at the border crossing.
- They control some 15 semitrailers per 24 hours and less than 3 tickets are issued.
- The overloaded semitrailers are immobilized on the board of the carriageway; they are
released once the driver is back with proof of payment.
23 INCEPTION REPORT
24 INCEPTION REPORT
Warzob control station - This station is built and operated by a private company
“Innovative Road Solutions”, which oversees Dushanbe-Chanak toll road.
The axle weighing station is of dynamic low speed type and the controls are done on a
separate platform outside the road at 39Km from Dushanbe.
All truck types are diverted from the main road and sent to the control lane, with only the
southbound traffic being controlled.
The axle loads and gross weights are controlled and compared with the Tajik regulations,
and fines issued and paid in cash on the spot per the following table.
Axel and gross weight overload fines applied at the Warzob control station
Axel Type Axel Weight Fine
Single axel 10 Tons 35.00 Somoni
Tandem axel 18 Tons 49.00 Somoni
Tridem axel 22.5 Tons 70.00 Somoni
Gross weight 40 Tons 52.50 Somoni
25 INCEPTION REPORT
26 INCEPTION REPORT
Kyrgyzstan border station - This station is brand new but is not yet commissioned. The
station is equipped with a weighing bridge and only gross truck weights can be controlled
for the international truck traffic entering Tajikistan.
“The National Target Development Strategy for the Transport Sector, horizon 2010-2025”.
This is an ambitious program which will rehabilitate all International Corridors and many
segments of Republican Roads in the country.
The 2010-2015, “short term” part of this strategic plan is already accomplished, the 2015-
2020 “Mid-term” part is being implemented at present, and the 2020-2025 “Long-term” part
is in the planning stage at the MoT.
Tajikistan has signed many international conventions regarding transit traffic and
international road corridors. Below we have reproduced the schematic map of the
international corridors crossing Tajikistan.
28 INCEPTION REPORT
Census Data - The census data seems to be available and we have requested an
appointment with the Tajikistan Agency for Statistics to obtain the geo-localized census
data, but so far no appointment has been granted. The geo-localized data will be useful to
produce the map of classified road network of Tajikistan.
General Road Transport Data - The Economic Analysis and Forecasting Department of
the MoT has compiled data regarding the freight transit through the custom border posts
and regarding car registration in Tajikistan.
Road Traffic data - A few dispersed traffic counts data can be found in the feasibility
reports of implemented or ongoing projects, but there has been no systematic effort by the
MoT to compile traffic data on the country’s road network.
The Consultant has some indication of the situation gained through considering the
population centers and car ownership indicators.
We have produced a map of population centers of Tajikistan and as can be seen, the main
population centers (population more than 10 000) are situated to the north-east and south-
east of Tajikistan.
We have also studied car ownership rates in Tajikistan for 2009-2016 which is quite low
compared to the neighboring countries and compared to the west European countries.
In 2009 there was 1 passenger car available for every 28 Tajik citizens. In 2016, according
to car registration statistics, there is 1 passenger car available for every 22 Tajik citizens.
29 INCEPTION REPORT
This is far from the situation in the neighboring Kazakhstan which is 1 car for every 5
citizens based on the World Bank statistics.
The rate of increase of cars registered in Tajikistan in the period 2009-2016 is around 4%
per year, and if this trend continues the road traffic in Tajikistan will at least double in the
next twenty years.
In conclusion, the MoT should prepare for a substantial increase in the road traffic in
coming years, especially in north-east and south-east road networks of Tajikistan.
30 INCEPTION REPORT
The above weakness is further compounded by the large multimillion dollar projects,
financed by IFIs, which often favor larger international contractors. This means the role of
local private contractors is at best limited to a supporting role as sub-contractors. Parceling
the larger projects to smaller lots may enable Tajik contractors to take the lead in some
contracts and hence help build their capacity.
Furthermore, JICA and EBRD have supplied equipment to GUSADs in order to enable
them to better deal with periodic maintenance works. The procurement of equipment has
31 INCEPTION REPORT
been accompanied with training and technical assistance missions. Although this has had
positive impact on improving the level of service being provided by GUSADs, it has
inadvertently strengthened their position as monopolists at the expense of the private
contractors. As far as we are aware, there has been no internationally led initiatives to
increase the capacity of private sector road contractors in Tajikistan.
As stated previously, the MoT has a legal obligation to promote the participation of the
private sector in the road construction and maintenance sector (Article 21 of the Tajik Law
regarding Road Related Activities).
According to our interviews with stake holders and the review of existing reports, up to the
year 2013 the MoT has not given enough support to develop the activities of private
contractors.
Starting in 2013, the MoT signed performance based contracts with a few private
contractors. However, there has not been a coordinated effort to encourage grouping of
private contractors to take on larger contracts or parceling of high value projects to smaller
lots to allow local private contractors to bid.
As far as the road maintenance is concerned, the GUSADs have a number of private
suppliers of materials and rental of equipment, but all maintenance works is performed by
GUSADs.
Regarding the institutional support of the Road Sector, the main contributors have been the
JICA, the WB and the EBRD.
Sughd Region and the eastern part of Khatlon Region, the target areas of the project, face
a particularly acute shortage of road maintenance equipment despite the key role the
regions play in goods transportation not only for domestic transportation between regions
but for international transportation with neighboring countries.
This project will supply GUSADs in charge of maintaining main roads in Sughd Region and
the eastern part of Khatlon Region with road maintenance equipment. This will allow
GUSADs to properly maintain roads in their jurisdictions, thereby contributing to more
efficient transportation throughout Tajikistan and surrounding areas. By providing
equipment, this project will enable GUSADs to perform periodic road maintenance, such as
overlay works.
JICA has provided GUSADs in other regions with equipment through grant aid to Tajikistan,
and with this project, four out of the six GUSADs in Tajikistan will have received new
equipment from JICA.
The project was extended by six months to November, 2016 with the purpose of expanding
the target area to include Sughd Kulob and Khalton GUSADs in adition to Hissor GUSAD
subdivision.
The loan and grant funds will be used to finance the purchase of road maintenance
equipment and spare parts, including graders, excavators, trucks and laboratory equipment.
Tendering for the above equipment is expected to begin in late 2016 or early 2017.
The 1999 Minsk convention of CIS countries, sets maximum dimensions and weights for
international traffic to ensure Member States cannot restrict the circulation of vehicles which
comply with these limits from performing international transport operations within their
territories.
We have reviewed the axel load regulations in Tajikistan, and in the CIS countries and to
ease understanding, we have produced the following schematic drawings for the most
current types of trucks using the Tajik road network.
33 INCEPTION REPORT
34 INCEPTION REPORT
35 INCEPTION REPORT
In Tajikistan, the vehicle gross weight is limited to 40 Tons whereas in the convention
between the CIS countries, the vehicle gross weight is limited to 38 Tons.
In recent years, the European Union countries have adopted heavier vehicle gross
weights, up to 44 Tons without increasing axel loads. This increase has economic
benefits, as it reduces the Ton per Kilometer cost of goods transported without putting
much additional stress on the infrastructures.
The Russian Federation and Kazakhstan are already aligned with the EU countries and
have adopted the 44Tons maximum gross weight.
Two Tajik organizations that are active in the field of construction standards are the “The
Committee for Construction and Architecture Under the Government of Republic of
Tajikistan” and “The Agency of Standardization, Metrology, Certification & Trade Inspection
under the Government of the Republic of Tajikistan”.
During the next stage, the Consultant will interview authors of these documents and
compare these standards with the original SNiP from which they are derived.
37 INCEPTION REPORT
Project risks will be monitored throughout the project in consultation with the management
of the MoT.
Comments
This is a brief activity as the situation has
become clear during the inception period.
Comments
This is a brief activity as the situation has
become clear during the inception period.
39 INCEPTION REPORT
Analysis
3 General overview of the institutions which
The Tajik Standard Institute is in charge of
are involved in setting and enforcing
setting and enforcing standards on the
standards.
national level, but road design and
construction standards are not in their
domain of activity.
Comments
After meeting with the Committee for
Buildings and Architecture, we will have a
clearer idea of how to proceed with the
enforcement of standards.
Propositions
The TA team will propose a set of reforms to
the current way of managing, funding and
monitoring the road network in Tajikistan as
well as the establishment of complementary
road construction, and design standards.
These proposals will assist in reducing total
life cycles costs for road users and the
government in Tajikistan.
Propositions
The TA Team will propose Tajikistan specific
design and installation manual for road
restraint devices and signing and marking.
The cost effectiveness of road asset
management will be accounted for.
40 INCEPTION REPORT
Comments
The reform of the road sector organization
and funding, including the creation of an
autonomous road agency and the
establishment of a new standard pavement
catalogue, will help address the road
network’s poor performance issue.
Propositions
The lessons learned in other countries with
similar infrastructure and economic
environments, which have conducted
successful reforms of the road sectors, will
be benchmarked and compared to the Tajik
situation to come up with proposals to reform
the road sector in a more sustainable and
effective way.
Propositions
The emphasis in identifying alternative
41 INCEPTION REPORT
Propositions
The TA Team envisages to put in place a
foundation for the Standard Catalogue of
Tajik Pavement. In case of availability of
data, the Catalogue will take account of the
regional climatic and geologic and hydrologic
conditions, especially in the mountainous
areas where specific construction and
maintenance standards will be considered.
Use of local materials and labour intensive
methods will be considered.
42 INCEPTION REPORT
Propositions
44 INCEPTION REPORT
Propositions
- The MoT should make its instrumented
van operational as soon as possible.
Propositions
- The MoT should provide standard
procedures for quality control and road
work supervision.
Propositions
- The TA Team will review procurement
laws, and will propose amendments if
needed.
Based on this review, the consultants should Analysis
18 articulate the principles that can be used to - SNiP codes and GOST standards are
generate revised standards, or produce reviewed and updated by the EASC and
addendums to existing standards, and the Tajik Committee on Building and
assess the benefits which could be expected Architecture.
from these proposed changes. Propositions
- In Phase 1 of our study we will define
principals that will be used to generate
Tajikistan specific standards, design
guides and manuals.
The consultants must work closely with MoT Analysis
19 to ensure that this phase of the study
addresses the key concerns and objectives - The MoT is understaffed.
of the Ministry. - Young engineers are rarely interested in
institutional studies; they generally prefer
road construction projects.
Propositions
- The MoT should do its best to put
together a Standardization Committee.
Analysis
20 At the end of Phase 1 the consultants will
prepare a report which will set out (i) their - The current situation became clear
assessment of the current situation, (ii) the during the inception phase.
criteria which should be applied when - The criteria should be established.
revising road standards, (iii) the economic
and other benefits which can be expected
from the adoption of new/revised standards, Propositions
and (iv) an assessment of the institutional - The Phase 1 activity will be brief,
and legal regime under which road - The Phase 2 activity will be substantial
standards are currently formulated, adopted and should be started as soon as
and enforced. possible.
Analysis
21 The consultant’s Phase 1 report should set
out their detailed proposals for their work - The TA Team has already preliminary
46 INCEPTION REPORT
programme for Phase 2, with specific ideas of the standards that should be
reference to the road standards which is redrafted or should be prepared from
proposed should be re-drafted scratch.
Propositions
- The Phase 1 of study will be short to give
enough time to phase 2 which is a
substantial undertaking.
country.
Propositions
Propositions.
Propositions
The consultant will review the outsourcing
possibilities for routine and periodic
maintenance works as an alternative
approach to the existing GUSADs. This does
not mean that the present GUSADs
resources and capabilities would be disposed
of. On the contrary, any road maintenance
privatization solution should be accompanied
by the integration of GUSDAs staff and
facilities in the new arrangement.
Part of the proposed reform to privatization of
road maintenance may include the
introduction of performance-based
contracting as this procedure has proved its
worth around the world. This will involve a
program for contracting out the routine and
periodic works to be carried out for specific
periods of time (e.g.3-5 years).
A number of other institutional reforms will be
considered including the creation of a road
agency; the establishment of a road asset
management system; the creation of road
management and maintenance manuals and
standards (see above), training of
government staff and contractors on modern
road asset management processes and
procedures, etc.
52 INCEPTION REPORT
4.4.1. Meetings
The technical Assistance Team met stakeholders of the project during the inception phase,
Total of 25 meetings were held during the inception period the list and date of meetings
are shown with the minutes of important meeting in the Annex 6.1.
We have visited Sughd Regional GUSAD and five of its subdivisions as follows:
This GUSAD subdivision reports directly to the Dushanbe GUSAD, it has been the recipient
of equipment supplied by the JICA.
This GUSAD has both cold mix and hot mix capabilities, the hot asphalt is bought from the
state owned asphalt plant, the cold mix is prepared on site.
The TA Team visited this GUSAD subdivision on September 6th 2016 and interviewed the
Director Mr Karim RASOULOV.
TA’s Comments:
This GUSAD has obtained equipment from JICA, but the overall mechanical service &
maintenance capabilities of this GUSAD seems inadequate.
Equipment are serviced on the unpaved open yard, the mechanical workshop seems to
be underequipped and no scheduled maintenance program was available.
55 INCEPTION REPORT
The staff is not trained to work with the lathe machine supplied by JICA, this equipment is
unused lack of a trained technicians.
This company was initially state owned, the company was founded in 1965, it was under
the stewardship of the Ministry of Transport till it was privatized in 2004.
This is a mid-sized company with a staff of 50 persons, which comprises 2 engineers and
16 technicians.
The company has capabilities in bridge works (steel and concrete), earthworks and
unpaved roads and road drainage works.
Since 2004 the company has been awarded a few bridge construction projects, the most
important was a steel decked suspended bridges constructed on the Panj River.
This bridge which is nearly 100m long provides the link between Tajikistan and Afghanistan,
the project was financed by the Agha Khan Foundation and the contracting authority was
the Tajik Ministry of Agriculture.
This company has not any important construction work right now, to keep the staff occupied
the company has accepted the construction of a high school in the Roudaki District, the
client is the Rudaki District Government.
The annual company turn-over during the past ten years was less than 1 Million USD per
year.
The majority of the equipment owned by the company is more than thirty years old, and are
sourced from the FSU.
The company director was very enthusiastic about performance based road and bridge
maintenance contracts; they are specially interested in the Rudaki District’s maintenance
works.
Equipment Directorate N° 3
This company is a heritage of FSU system of organization of state owned companies, there
were three equipment Directorate in Tajikistan at the time of Soviet Union, they were all
founded in1967 in order to construct planned projects of the central planning agency of the
Soviet Union in the domains of buildings and roads.
Since 1992 the Equipment Directorates has been privatized, the majority shareholder is the
Ministry of Construction who detains 51% percent of shares and private parties detain the
rest.
In the recent years the main clients of this company have been municipalities, the United
Nations and they have also done subcontracting works.
58 INCEPTION REPORT
The main type of works performed was, Dushanbe Airport Runway overlay (with a French
Company), Dushanbe to Rudaki District Road (22 Km), urban streets in Dushanbe,
Dushanbe Hospital, river protection works, buildings, sport complexes and short span
bridges.
The total staff working at this company is around 300 persons, of whom 12 are engineers
and managers and 30 skilled technicians and operators, the rest are semi-skilled workers.
Right now this company has no pending construction contract, its cash flow is based on
equipment rentals to private contractors.
Autostrada LLC
This consulting engineers company is founded in 1996 by some of faculty members of the
Technical University of Dushanbe.
Since 1997 this company has designed and supervised many road and bridge projects in
Tajikistan.
The ADB financed projects Khowling-Vassé (86Km) was detail designed by this company in
association with the Australian SMEC.
The Shourabad-Shorgon was designed and supervised by this company in Association with
the Lebanese company SPECTRUM.
The main client of this company is the municipality of Dushanbe, many urban boulevards in
Dushanbe were designed and supervised by this company.
The staff is around 70, of whom 56 are engineers and the rest are technicians and
supporting staff.
The company is equipped with the necessary design softwares like CAD Civil 3D and LIRA
structural design software.
The company owns its own headquarter building and materials laboratory that can perform
essential tests on asphalt and concrete.
Nearly all of the MoT engineers have obtained their degree in this university, the university
has currently 35 undergraduate students (four-year cursus), and 14 graduate students (6-
year cursus).
The pedagogic material is in Russian and books supplied to students or available in the
library are in Russian and also are sourced from the Russian Federation.
Only GOST standards and SNiP construction codes are promoted in this university, the
students and faculty members have scant knowledge of other standards.
There is a small materials laboratory available and operational, which had some
commercial activities for state owned companies in the past, but right now the laboratory
functions exclusively on research projects of graduate students.
59 INCEPTION REPORT
This Agency does not create any new standards, it only manages and updates existing
standards, which are exclusively FSU sourced GOST standards updated by the EASC.
The agency owns a modest testing laboratory in Qorgonteppeh, but the bulk of testing for
certification is outsourced.
The Agency does not manage SNiP construction codes, this task is transferred to the
Committee on Building and Architecture under the Government of Tajikistan..
During the inception phase one change were made to the international team by introducing
a new Highway Engineer. The change was approved by EBRD and MoT.
Total 740
61 INCEPTION REPORT
Phase 2:
Task 2 – Detailed Review and Revision of Standards
Phase 3
Task 3- Road Sector Financing
Task 4- Road Sector Institutional Reform and Action Plan
The proposed work programme is prepared during the Inception Phase and refined to align
it with the priorities of the MoT as outlined during the Project Kick off Meeting in presence
of the Minister.
The project deliverables with respective planned dates of submission are as follows:
Project Deliverables
N° Document title Planned
Submission date
1 Draft Inception Report October 03rd 2016
2 Inception Report November 03rd 2016
3 Report on Principles for Drafting New Road Design Standards December 30th 2016
4 Report on the Institution of a Road Agency November 30th 2017
5 Report on GUSADs December 30th 2017
6 Report on the Introduction of a Commercial Approach April 15th 2017
7 Report Road Sector Institutional Reform Strategy and Action Plan May 22nd 2017
8 Draft Final Report June 15th 2017
9 Final Report August 01st 2017
In the following pages, we have updated our 12-month general work plan (was included
initially in our technical proposal) and also we have provided a detailed and thematic 6-
month work plan.
62 INCEPTION REPORT
Inception Phase
Draft Inception Report New Year Nowrouz Holidays Draft Final Final Report
Inception Report Holidays Report
6- ANNEXES
List of Important Meetings
Date Entity/Participants Purpose of the meeting
19 August 2016 MoT, Foreign Investment Cooperation Unit, Project start requirements.
Mr Olim Yatimov Logistics and perspectives
23 August 2016 MoT, Road Construction & Maintenance Data Request
Dept., Mr Noureddine Ghorbanov Planning of GUSAD visits
24 August 2016 EBRD, Mr Rahmonberdiev & Ms Solieva Courtesy meeting
25 August 2016 MoT, Economic Analysis, Forecasting Dept. Data Collection
Ms Shoyeste Saidmoradeva
26 August 2016 MoT, Maintenance Planning, Evaluation Unit Data collection
Mr Abdollah Ziazadeh
29 August 2016 MoT, Road Construction Unit, Mr Allaeddin Data Collection
Enayatshaov
30 August 2016 The Road Research Institute, Mr Olimjon Data Collection
Kholdorof
31 August 2016 MoT, Minister & head of MoT departments Project Kickoff meeting
1 September MoT Data collection
2016 Road Research Laboratory Testing capabilities
Nina Pavlovna Kharlamova
2 September Chamber of Commerce and Industries of Data Collection
2016 Tajikistan, Construction sector activities
Ms Monzura Rostamova Akramovna
5 September Tajikistan Geological Survey Geological Map
2016 Rahmonbek Dolatbekowitch Bakhdolatov Seismic map
6 September Vahdat GUSAD Subdivision Data collection
2016 Norak GUSAD Subdivision Operational Issues
Mr Karm Rasulov of Vahdat
Mr Safar Saidov of Norak
7 September Shahrino GUSAD Subdivision Data Collection
2016 Tursunzoda GUSAD Subdivision Operational Issues
Mr Ibodollo Rustamov of Shahrino
Mr Subhonkulov Tursunzoda
14 September Ayni GUSAD Subdivision Data collection
2016 Panjkent GUSAD Subdivision Operational issues
Mr Ismatolloh Sattar of Ayni
Mr Fakhreddin Alibeykev of Panjekent
15 September Istarafshan GUSAD Subdivision Data collection
2016 Khujand GUSAD Subdivision Operational issues
Mr Sabourov Nouman of Istarafshan
Ms Hajera Latifi of Khujand
16 September Konibodom GUSAD Subdivision Data collection
2016 Isfara GUSAD Subdivision Operational issues
Mr Karimjon Samiev of Konibodom
Mr Khallagh of Isfara
EBRD Project
Review of Road Standards
Road Sector Institutional Support
Minutes of Meeting
Saturday August 20th 2016
Dushanbe, Ministry of Transport
Mr Evgueni Startsev
Highway Engineer, Corporate evgstartsev@gmail.com
Solutions 90 788 7728
Mr Fazliddin Odinaev
joff_85@mail.ru
Logistics , Corporate Solutions 93 414 9697
The following subjects were discussed and follow-up actions were proposed.
2- MoT Archives
The Technical Assistance Team wishes to obtain clearance for access to the paper and electronic
archives of the MoT, in order to be able to retrieve all past reports and documents pertaining to applied
standards and road maintenance.
Mr Yatimov O. will organize a meeting with the head of the 1-Research Design and Survey Institute, Mr
Olim Kholdorov and his deputy Mr Mohamed Rasoul Rafie.
Mr Yatimov O. made available the paper copy of five progress reports to the Team.
On electronic Support
- Strengthening Implementation of Road Maintenance Funding System (ADB, 2008)
Volume 1 to Volume 5;
- Power Point Presentation of Transport Sector Results for year 2015.
- Summary of International investments in Tajikistan (2016)
- Road sector investments and projects in Tajikistan (2016)
- Legal status of the Ministry of Transport. (2011)
On paper support:
- Asian Highways 2004 (United Nations Economic and Social Commission for Asia and the Pacific)
- SNIP Standards (Revisions 81, 01, 2017).
- Construction Norms Tajikistan for reception of finished work.
- Laws of Republic of Tajikistan (Procurement of goods and services 2012)
EBRD Project
Review of Road Standards
Road Sector Institutional Support
Ministry of Transport
Corporate Solutions
Consulting
Mr Medard POURASHRAF Team Leader, pourashraf1@gmail.com
Mr Evgueny STARTSEV Highway Engineer, evgstartsev@gmail.com
Mr Fazliddin ODINAEV Logistics, joff_85@mail.ru
After Power Point presentation by the Technical Assistance Team, the following orientations and
conclusions were announced:
1- Mr Rustam Valizoda is in charge of coordination between the MoT staff and the Technical
Assistance Team.
2- All of MoT departments should cooperate and interact with the Technical Assistance Team in
all phases of the assignment.
3- This assignment is only a foundation work and will certainly not address all issues related to
standards and road sector reforms.
4- New standards cannot be implemented unless they have the force of law, the process of
amending existing laws will be long, the necessary measures should be undertaken by the
MoT as soon as the phase 2 of the assignment is completed.
5- All international and regional conventions signed by the Republic of Tajikistan in the transport
sector should be accounted for, not any standard will be accepted if it is in contradiction with
signed conventions.
6- The Technical Assistance Team should research the current and future standards in the CIS
countries, compatibility of standards with those of the CIS countries and in particular with
neighboring countries should be sought.
7- Of particular importance are methods of pavement design which must apply heavier truck axel
loads of the Post-Soviet era, serious consideration should be given to the AASHTO method of
pavement design.
8- The Team should consider CAREC program which extends up to 2030, of special interest are
the road user safety issues treated in the CAREC program.
9- The Road sector reform proposals should take into account the social and economic
characteristics of different regions.
LONDON 36 BYRON HILL ROAD, HARROW ON THE HILL - MIDDLESEX - UNITED KINGDOM HA20HY
TEL: +44 (0)2084237711 - FAX: +44 (0)2084237766 - E-MAIL: INFO.UK@CSCL.BIZ