Annexure‐04

Energy Pac Power Generation Ltd.
SGFL 4000 BPD CFP PROJECT
Civil Work Package 3

RESPONSIBILITY MATRIX
NO. DESCRIPTION OF WORKS EPGL Vendor
1.00 DESIGN & ENGINEERING
1.01 Detail Drawings & Design √
2.00 INSURANCE
2.01 Workmen's compensation Insurance √
3.00 MATERIALS, CONSUMABLES AND CONSTRUCTION
Supply of all Materials (except Rod, Cement and Stone Chips) as per BOQ, 
3.01
Drawing & Work Order

3.02 Loading, Unloading, Carrying, Storing of all Construction materials at site √
Supply of all Machineries, Tools & Equipments e.g. Pile Rig, Mixture Machine, 
3.03 Vibrator Machine, Excavator, Dump Truck, Compactor, Shuttering materials  √
etc. to perform and required for this job
Any machine or equipment to be calibrated and certificate to be submited to 
3.04
Concern Engineer for this job

Supply of skill Manpower and Supervisory Engineer & Staff as required to 
3.05
execute this job

3.06 Security of materials & Equipment of vendor √
3.07 Equipment  & Supervisory manpower list or site management organogram √
Construction and drinking water to be arranged by vendor at the convenient 
3.08
place of the site upon approval of EPGL

3.09 Surveyor & Total station (updated calibration certificate is required) √
4.00 TEMPORARY FACILITIES

4.01 Space for temporary site office & material storage will be provided by EPGL √
Space for Manpower/Labour accomodation will be arranged by vendor 
4.02
outside project site

Construction of temporary site office, storage, labour shed, etc. to be done by 
4.03
vendor

4.04 Temporary lighting for night shift work √
Electric power supply & arrangment for Fabrication & Construction Works at 
4.05
Site with Diesel Generator

4.06 Site cleaning up after completion of work each day √
5.00 QA/QC
5.01 Inspection, Reports and Checklist √ √
5.02 QA/QC Supervisor √ √
6.00 SAFETY & SECURITY
6.01 Facilities & other materials for safety & security of respective scope √
6.02 Provision of Safety Inspector to check PPE √ √
7.00 TESTING
7.01 Material Testing & Report submission √
7.02 Cylinder test from SUST/BUET √
8.00 WARRANTY
8.01 Warranty for Civil Work 12 months from the date of COD √
9.00 Settlement of any Local Disturbances √
10.00 Accidental situation handling facility √
11.00 Risk to mitigate discontinuous/unavailability of materials supply √
12.00 Alternative arrangement for bad weather  √