Energy Pac Power Generation Ltd.
SGFL 4000 BPD CFP PROJECT
Civil Work Package 3
RESPONSIBILITY MATRIX
NO. DESCRIPTION OF WORKS EPGL Vendor
1.00 DESIGN & ENGINEERING
1.01 Detail Drawings & Design √
2.00 INSURANCE
2.01 Workmen's compensation Insurance √
3.00 MATERIALS, CONSUMABLES AND CONSTRUCTION
Supply of all Materials (except Rod, Cement and Stone Chips) as per BOQ,
3.01
Drawing & Work Order
√
3.02 Loading, Unloading, Carrying, Storing of all Construction materials at site √
Supply of all Machineries, Tools & Equipments e.g. Pile Rig, Mixture Machine,
3.03 Vibrator Machine, Excavator, Dump Truck, Compactor, Shuttering materials √
etc. to perform and required for this job
Any machine or equipment to be calibrated and certificate to be submited to
3.04
Concern Engineer for this job
√
Supply of skill Manpower and Supervisory Engineer & Staff as required to
3.05
execute this job
√
3.06 Security of materials & Equipment of vendor √
3.07 Equipment & Supervisory manpower list or site management organogram √
Construction and drinking water to be arranged by vendor at the convenient
3.08
place of the site upon approval of EPGL
√
3.09 Surveyor & Total station (updated calibration certificate is required) √
4.00 TEMPORARY FACILITIES
4.01 Space for temporary site office & material storage will be provided by EPGL √
Space for Manpower/Labour accomodation will be arranged by vendor
4.02
outside project site
√
Construction of temporary site office, storage, labour shed, etc. to be done by
4.03
vendor
√
4.04 Temporary lighting for night shift work √
Electric power supply & arrangment for Fabrication & Construction Works at
4.05
Site with Diesel Generator
√
4.06 Site cleaning up after completion of work each day √
5.00 QA/QC
5.01 Inspection, Reports and Checklist √ √
5.02 QA/QC Supervisor √ √
6.00 SAFETY & SECURITY
6.01 Facilities & other materials for safety & security of respective scope √
6.02 Provision of Safety Inspector to check PPE √ √
7.00 TESTING
7.01 Material Testing & Report submission √
7.02 Cylinder test from SUST/BUET √
8.00 WARRANTY
8.01 Warranty for Civil Work 12 months from the date of COD √
9.00 Settlement of any Local Disturbances √
10.00 Accidental situation handling facility √
11.00 Risk to mitigate discontinuous/unavailability of materials supply √
12.00 Alternative arrangement for bad weather √