Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Thermal-Structural Modeling and Temperature Control

of Roller Compacted Concrete Gravity Dam


Abdallah I. Husein Malkawi1; Saad A. Mutasher2; and Tony J. Qiu3

Abstract: A coupled thermal-structural analysis is carried out using both a two- and a three-dimensional finite-element method. The
computer program ANSYS is used and simulates the construction process of a roller compacted concrete 共RCC兲 dam. Thermally induced
stresses are computed for the 60 m high RCC Tannur Dam in Jordan. The actual temperature distribution in the body of the dam measured
by thermocouples is compared with that obtained by ANSYS; generally, a good agreement is obtained. The study demonstrates that
detailed thermal stress analysis should be performed for large RCC dams to provide a basis to minimize and control the occurrence of
thermal cracking.
DOI: 10.1061/共ASCE兲0887-3828共2003兲17:4共177兲
CE Database subject headings: Thermal stresses; Finite element method; Dams, concrete; Cracking; Temperature effects.

Introduction Several techniques are reported in the literature for designers


to evaluate the thermal performance of concrete, the structural
In roller compacted concrete 共RCC兲 dams, large quantities of con- configuration, and construction requirements. These techniques
crete are usually placed to form a monolithic mass-concrete struc- range from complex three-dimensional finite-element analysis
ture. During placement of RCC, heat will generate by the hydra- methods to simple manual computation. Tatro and Schrader
tion of cement. Cement tends to liberate a substantial amount of 共1992兲, for example, provide specific guidance for performing a
heat, which leads to a rise in the temperature in the body of the thermal study for RCC structures. The U.S. Army Corps of Engi-
dam. After the peak temperature is reached, the concrete, some- neers, in Engineering Technical Letter 共ETL兲 1110-2-542 共U.S.
times over a period of years, cools, to a stable temperature. Such 1997兲, provides design guidance for implementing a range of
reductions in the temperature usually lead to the following. thermal analysis techniques. In this ETL, background and ex-
1. Surface gradient cracking. This generally occurs when the amples for performing several levels of less complex analyses are
reservoir is first filled. A thermal gradient develops between presented. Zhang and Garga 共1996兲 used a two-dimensional
the cooled surface and the hot concrete core. This change in finite-element method for simulating the construction process of
the temperature can generate undesirable surface thermal an RCC dam. Concrete temperature and the thermally induced
stresses, which can lead to cracking at the surface of the stresses were determined with a personal microcomputer. Truman
dam. et al. 共1991兲 used the finite-element program ABAQUS along with
2. Mass gradient cracking. This occurs well after the dam is user developed subroutines and experimentally derived material
completed, with the cooling of the central mass of the dam. properties to analyze by incremental construction the thermal
A volume reduction will occur and if such a reduction of the loads of a pile-founded mass concrete lock and dam structure.
volume is externally restrained, as it will be by the rock Forbes and Williams 共1998兲 discussed thermal stress modeling,
foundation, sufficient strain can develop, causing cracking use of high sand RCC mixes, and in situ modification of RCC for
through the dam body. the Cadiangullong Dam. They provided a good understanding of
the thermal condition, and, as a result, thermal stresses and con-
1
PhD, Professor of Geotechnical Engineering and President of traction joint spacing were determined. Ishikawa 共1991兲 demon-
ASCE—Jordan International Group, Civil Engineering Dept., Jordan strated numerically that thermal cracks might be avoided to a
Univ. of Science and Technology, Irbid 22110, Jordan. E-mail:
certain degree by determining the optimum construction method.
mhusein@just.edu.jo
2
Research Assistant, Civil Engineering Dept., Jordan Univ. of Science Ayotte et al. 共1997兲 presented details of the experimental and nu-
and Technology, Irbid 22110, Jordan. E-mail: sama64@yahoo.com merical thermal studies undertaken for a large-scale mass con-
3
Senior Engineer, Gutteridge Haskins & Davey Pty Ltd., 15 Astor crete structure. The study presents a modified step-by-step ap-
Terrace, Brisbane Qld 4000, GPO Box 668, Brisbane Qld 4001, Australia. proach, which improved the stress modeling within the available
E-mail: tonyគqiu@ghd.com.au commercial software. Crichton et al. 共1999兲 presented a thermal-
Note. Discussion open until April 1, 2004. Separate discussions must structural analysis using the ANSYS computer program to assess
be submitted for individual papers. To extend the closing date by one the effect of heat of hydration in RCC structural stresses. The
month, a written request must be filed with the ASCE Managing Editor.
effect of using simple linear elastic material properties on the
The manuscript for this paper was submitted for review and possible
publication on May 15, 2001; approved on July 3, 2002. This paper is calculated stresses has been compared to a more complex time
part of the Journal of Performance of Constructed Facilities, Vol. 17, variant material modulus and creep analysis. They concluded that
No. 4, November 1, 2003. ©ASCE, ISSN 0887-3828/2003/4- the simple models overestimate the initial stresses and underesti-
177–187/$18.00. mate or cannot predict the long-term tensile stresses.

JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003 / 177


Fig. 1. Typical cross section and thermocouple locations

In this paper, the determination of the thermal and structural Tannur Dam is constructed of high paste content RCC, placed in
stresses and temperature control requirements is described for the 300 mm thick layers with a facing made of grout enriched roller
60 m high Tannur RCC Dam in Jordan. Temperature distribution compacted concrete 共GE-RCC兲. The concrete is designed to have
with time, concrete placement temperature limits, and joint spac- a very low air void content and to achieve maximum strength and
ing requirements to minimize cracking are also discussed. density with minimum permeability and with a good bond be-
tween layers. The dam is founded on limestone of the Wadi As Sir
and Fuheis, Hummar Shueib Formation. A two-layer cement
Description of Dam grout curtain will limit the quantity of seepage.
The upstream face of the dam is vertical, with a batter of 1:1
The Tannur Dam is the first completed RCC dam in the Middle below Elevation 356 to the foundation level. The stepped down-
East. It is a concrete gravity dam, approximately 60 m high, built stream face has a slope of 0.8共H兲: 1共V兲 共Fig. 1兲.
to impound the floodwater of the Wadi Al Hasa. It retains a res- This profile has been adopted to reduce vertical stresses by a
ervoir at an elevation of 400 m above sea level 共ASL兲 with a more distributed loading, and to achieve higher compressive
16.8⫻106 m3 capacity. The dam is situated some 50 km south of stresses at the upstream heel due to the vertical loading—thus
Karak. The yield of the reservoir will help satisfy the future water reducing tensile stresses at the location under seismic loading.
demand for industry and agriculture in the southern Ghors. The The dam is a straight structure 242 m long at the crest.

178 / JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003


Table 1. Predicted Rolled Compacted Concrete Placement Temperature
Mean Aggregate Aggregate
monthly Mean crushing stocking Mixing Transportation Final
2
temperature annual Difference 3 Difference Subtotal added temperature added added temperaturea
Month 共°C兲 共°C兲 共°C兲 共°C兲 共°C兲 共°C兲 共°C兲 共°C兲 共°C兲 共°C兲
January 10 18.2 ⫺8.2 ⫺5.47 12.73 1.1 13.83 1.1 ⫺0.6 14.3
February 11.1 18.2 ⫺7.1 ⫺4.73 13.47 1.1 14.57 1.1 0 15.7
March 13.6 18.2 ⫺4.6 ⫺3.07 15.13 1.1 16.23 1.1 0.6 17.9
April 17.8 18.2 ⫺0.4 ⫺0.27 17.93 1.1 19.03 1.1 0.6 20.7
May 21.5 18.2 3.3 2.2 20.4 1.1 21.5 1.1 1.1 23.7
June 24.5 18.2 6.3 4.2 22.4 1.1 23.5 1.1 1.1 25.7
July 25.5 18.2 7.3 4.87 23.07 1.1 24.17 1.1 1.7 27
August 25.6 18.2 7.4 4.93 23.13 1.1 24.23 1.1 1.7 27
September 24.2 18.2 6 4 22.2 1.1 23.3 1.1 1.1 25.5
October 21.3 18.2 3.1 2.07 20.27 1.1 21.37 1.1 0.6 23
November 16.4 18.2 ⫺1.8 ⫺1.2 17 1.1 18.1 1.1 0 19.2
December 6.7 18.2 ⫺11.5 ⫺7.67 10.53 1.1 11.63 1.1 ⫺0.6 12.2
a
Average⫽21.

Temperature Control Requirements Table 2 shows the actual data recorded for the RCC placement
temperature for the time period between June and October of
Significant thermal induced stresses are developed as a result of 2000. It is shown, for example, that the month of June had an
the heat of hydration of the cementitious materials in RCC dams. average recorded temperature of 25.5°C, whereas the calculated
The temperature distribution through the dam and its evolution temperature for the same month 共Table 1兲 is about 25.7°C.
with time depend on the following: The average monthly ambient air temperature is shown in
• RCC concrete properties, Table 3. RCC placement was assumed to take place in the cooler
• Climatic factors, months of the year—i.e., from December of 1999 to the end of
• Construction procedure, April of 2000. The aggregate production and stockpiling started in
• Thickness of lifts, the summer. Based on the average ambient air temperature from
• Initial temperature of lifts, and December to April of 12°C, an average RCC placement tempera-
• Interval between their successive placements.
These thermally induced stresses can be significant enough to
induce cracks in the RCC.
Recent developments in sophisticated software based on ad-
vanced numerical methods, together with the continually increas- Table 2. Average Actual Data Record of Rolled Compacted
ing power of computers allow complex analyses for such thermal- Concrete Placement Temperature during Construction
structural problems. The ANSYS computer program based on the Month Temperature Temperature
finite-element method was used to analyze the thermal behavior 共2000兲 at day 共°C兲 at night 共°C兲
of the Tannur Dam. The desired outcome of the numerical analy-
May 24.28 23.2
sis was
June 25.52 25.16
• To determine the spatial distribution of temperature and its
July 25.8 25.7
evolution with time,
August 26.15 25.7
• To determine the stress distribution during and following the
September 24.4 23.4
dam construction and at the time of reservoir filling,
October 24.7 24
• To identify the appropriate joint spacing to minimize the de-
velopment of transverse cracking, and
Table 3. Average Monthly Air Temperature
• To determine the concrete placement temperature limits.
Ambient air
Month temperature 共°C兲
Concrete Placement Temperature January 10
February 11.1
The temperature of the concrete aggregate has the greatest influ- March 13.6
ence on the initial temperature of the fresh RCC. Due to the low April 17.8
volume of mix water and the minor temperature difference of the May 21.5
water compared to the aggregate, the water temperature has a
June 24.5
much less significant effect on the overall temperature. Table 1
July 25.5
provides the basis for estimating the aggregate temperature and
August 25.6
approximating the RCC placement temperature used in the analy-
September 24.2
sis. Since aggregate production will be done concurrently with the
October 21.3
RCC placement, stockpile temperatures should closely parallel
November 16.4
the average monthly ambient temperatures. Some heat is added
December 6.7
because of screening, crushing, and transportation activities.

JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003 / 179


Table 4. Properties Adopted for Thermal Analysis
Property Value
Density 2,400 kg/m3
Elastic modulus 18 GPa
Poisson’s ratio 0.2
Coefficient of thermal expansion 6.5E⫺6/°C
Specific heat 963 J/kg °C
Thermal conductivity 2.6 J/s•m °C
Film 共convection兲 coefficient 共air兲 15 J/s•m2
Film 共convection兲 coefficient 共water兲 570 J/s•m2
Heat generation of RCC 309 J/g at 28 days
Placement temperature 20 °C
Foundation rock temperature 18 °C

ture of 20°C was adopted. A water temperature of 18°C was as-


sumed in the reservoir upon filling and 18°C was assumed for the Fig. 3. Experimental results of heat of hydration for Jordanian ce-
foundation rock. ment

Material Properties and Environmental Conditions


analysis. The element has one degree of freedom for temperature
at each node. This is a higher-order element that has eight nodes,
The model properties used were assessed from available data and
is suitable for simulating irregular shapes, and is applicable to the
typical RCC properties. The density, modulus, Poisson’s ratio,
study of a two-dimensional steady-state or transient thermal
specific heat, and thermal conductivity are given in Table 4. A
analysis. Also, the model can be analyzed structurally by replac-
convection coefficient for air was used, which is consistent with
ing it with the equivalent structural element PLANE82. This is a
moderate wind speed. A typical coefficient of thermal expansion
higher-order element; it also has eight nodes but has two degrees
of 6.5⫻10⫺6 /°C was adopted for the concrete.
of freedom, allowing movement in both the x direction and the y
Heat generation rates adopted for the 125 kg/m3 cement ⫹75
direction. This is a powerful tool available in the ANSYS program
kg/m3 pozzolan mixture were based on the heat of hydration of
that allows the stresses to be obtained in a coupled thermal-
the Jordanian ordinary portland cement 共OPC兲 plus that of the
structural analysis due to a change in temperature with time. A
pozzolan being 20% of that for the OPC. Heat of hydration of 309
plane strain model was adopted for the two-dimensional analysis
J/g at 28 days was determined from testing the Jordanian OPC.
of the maximum cross section of the dam. Fig. 2 shows the mesh
of the cross section of the dam.
Two-Dimensional Model Analysis

The dam was modeled as a two-dimensional transient heat trans- Heat of Hydration
fer model using a birth and death procedure to simulate the real
construction process of the dam. The dam is divided into 19 lay- Heat of hydration as a function of time was obtained from several
ers. Each layer has a thickness of 3 m, constructed in 10 days, and tests performed in the laboratory. Fig. 3 shows the heat of hydra-
the last layer has a thickness of 2 m. The PLANE77 element type, tion produced with time for Jordanian cement with and without
available in the ANSYS library, was used in the finite-element the addition of pozzolan. In this study, the heat of hydration was
simulated as a ramp input, as shown in Fig. 4.

Fig. 2. Two-dimensional finite-element model—mesh Fig. 4. Heat of hydration as ramp input

180 / JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003


induced strain⫽ 共 C th 兲共 dT 兲共 K R 兲共 K f 兲 (1)
where C th ⫽coefficient of thermal expansion; dT⫽temperature
difference; K R ⫽structure restraint factor; and K f ⫽foundation re-
straint factor.
To determine the spacing of the RCC blocks, the following
parameters are adopted. The peak internal temperature⫽37.7°C
共determined from 2D analysis兲. The minimum temperature 共based
on the annual temperature cycle兲⫽6.7°C 共taken from Table 3兲.
The coefficients K R and K f are both equal to 1.0 for a conserva-
tive assumption and the maximum strain at the foundation base
共Tatro and Schrader 1992兲. The coefficient of thermal expansion
(C th ) is strongly influenced by the type of aggregate in the RCC
mix; for the Tannur Dam, the aggregate is limestone/dolomite
limestone. A typical value for the coefficient of thermal expansion
Fig. 5. Predicted adiabatic temperature for Jordanian cement
for the RCC mass for the Tannur Dam is taken as 6.5 E-6/°C
共Neville and Brooks 1994兲.
Adiabatic Temperature Rise „ T ab … The calculated induced strain is 201.5 ␮mm. Therefore, the
excess strain is 121.1 ␮mm. Based on the crest length of the
An adiabatic system is a system in which heat is neither allowed Tannur Dam being 242 m, the total crack width expected is about
to enter nor leave. Therefore, adiabatic temperature rise is the 29.4 mm. Assuming a permissible crack width of 2.5 mm, the
change in the temperature of the concrete due to heat of hydration estimated total number of RCC blocks is 12. Each would have a
of the cement under adiabatic conditions. It is the measure of the length of 20 m. However, the actual size of the constructed blocks
heat evolution of the concrete mixture in a thermal analysis. In a was about 15 m. This number was established earlier in the design
very large mass of concrete, temperatures near the center of the report 共Howard Humphreys 1995兲 considering a presumptive
mass will be approximately equal to the sum of the placement and value for the heat of hydration rate of 440 J/g at 28 days.
adiabatic temperatures. However, near the surfaces, the tempera-
ture will be close to the ambient air temperature. The magnitude Surface Gradient Cracking
of the adiabatic temperature rise and the shape of the curve can
vary significantly for different concrete mixtures. Typical values In an RCC dam, the surface of the dam cools faster than the
for the adiabatic temperature rise of the mass of concrete range interior body. This causes a temperature gradient between the
from 11–19°C at five days to 17–25°C at 28 days. Fig. 5 shows cooled surface and the hot interior mass. Such a difference will
the predicted adiabatic temperature rise for RCC in the Tannur result in a thermal gradient that is likely to generate undesirable
Dam determined by the ANSYS program for a placement tempera- thermal stresses and that may cause cracks to develop at the ex-
ture of 20°C, where the rate of heat of hydration was simulated as terior surface. This is not expected to be a structural problem
a ramp input as shown in Fig. 4. unless the cracks extend through to the drainage gallery, where
the leakage of water may increase. The method proposed by Tatro
and Schrader 共1992兲 was used in the analysis to calculate the
Crack Analysis surface gradient cracking. Table 5 shows the cracking analysis for
a depth of 9.0 m. It is observed that no surface cracking occurs
RCC, like other concrete, has an ability to absorb some of the during the first three days. However, by 14 days the cracking is
strain resulting from the tensile stresses generated by the cooling apparent, based on the RCC tensile strength quoted by Tatro and
process. This ability is referred to as the tensile strain capacity. Schrader 共1992兲. Therefore, appropriately spaced joints are nec-
The laboratory test reported by Dunstan 共1981兲 showed that a essary to control the cracks that are predicted to occur. From
typical value of the tensile strain capacity is 80 ␮mm. The tensile Table 5, the incremental strain is 111.36 ␮mm; therefore, the
strain capacity of the RCC is not large enough to withstand this excess strain is 31.36 ␮mm. Based on a crest length of 242 m for
strain without cracking; therefore, joints are required in the con- the Tannur Dam, and considering a crack width of 2.5 mm, the
crete to avoid cracking. total number of blocks to avoid such cracks is about four, at a
spacing of 60 m.

Mass Gradient Cracking Three-Dimensional Model Analysis


The mass gradient strain usually is determined by the following A 3D analysis was also carried out for the Tannur RCC Dam. Fig.
equation: 6 shows the geometry of the dam and its main dimensions. The

Table 5. Surface Cracking Analysis for Depth of 9 m


Temperature Incremental Modulus of Incremental Total Maximum
Period difference strain elasticity stress stress tensile
共days兲 共°C兲 共␮mm兲 共MPa兲a 共MPa兲 共MPa兲 stress 共MPa兲a
0–3 8.6 55.93 9,655 0.54 0.54 0.62
3–14 7.8 50.43 17,310 0.873 1.413 1.13
14 –28 0.77 5.0 18,758 0.09 1.5 1.45
a
Adopted from Tatro and Schrader 共1992兲.

JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003 / 181


Fig. 6. Geometry of Tannur Dam for 3D analysis; L⫽15, 30, and
45 m

Fig. 8. Thermal boundary conditions for thermal analysis

length of the dam is divided into 12 blocks. Each block is 20 m


long, and one of these blocks, with different lengths of 15, 30, and
45 m, was modeled with finite-element mesh, as shown in Fig. 7.
A Solid70 element type was used for the thermal analysis. This
element has eight nodes, with a single degree of freedom tem-
perature at each node. Fig. 8 shows the boundary conditions for
the thermal analysis. A Solid65 element type was used for the
structural analysis. This element has three degrees of freedom,
permitting movements in the x, y, and z directions. Fig. 9 shows
the boundary conditions for the structural analysis. The step-by-
step analysis of the construction simulation process allows the
determination of the temperature and stress distributions for each
added lift.

Fig. 9. Structural boundary conditions for structural analysis

Fig. 10. Temperature prediction at center of dam at 355 m elevation


Fig. 7. Three-dimensional finite-element model—mesh with 20°C rolled compacted concrete placement temperature

182 / JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003


Fig. 11. Comparison of thermal analysis predictions and actual read-
ings of thermocouples from April until end of June at elevation of
365 m ASL

Finite-Element Results Fig. 13. Actual temperature contours at end of rolled compacted
concrete placement
Two-Dimensional Results
The temperature distribution shown in Fig. 10 is for the specific maximum of 26°C and with the reduction of the cement content
location at an elevation of 355 m ASL—i.e., 12 m above the base to 120 kg/m3 starting in July. In all cases, the overall temperature
of the dam. This shows that the maximum RCC temperature is in the body of the dam did not exceed 43°C.
approximately 37.7°C. It is shown that the temperature reached its Fig. 12 shows the measured temperature through November 7
maximum in the first 10 days due to the high rate of hydration compared to that predicted by ANSYS. It should be clearly under-
that remained constant for a long period of time because heat stood that during the months of August and September no RCC
transfer from the core of the dam to the surface is very slow. placement took place, and consequently readings of thermo-
Further, the heat conduction due to the construction of the over- couples were not made. Fig. 13 shows the actual temperature
lying layers of RCC prevents internal heat loss from the con- contours measured at the end of construction of the dam. Heat of
structed lift surface. hydration testing during the construction of the dam established
Fig. 11 shows a comparison between the predicted temperature that the actual heat of hydration of the cement in use is 309 J/g.
rise and the actual thermocouple readings at an elevation of 365 Fig. 14 shows the predicted temperature for different nodal
m ASL, covering a period of 90 days between April and the end points at different locations. The results demonstrate that the tem-
of June. Generally, a good agreement has been obtained. The perature at the surface is affected by the environmental condi-
small differences between the predicted and the actual readings tions, and the temperature in the center of the dam is essentially
could be attributed to the change of the RCC placement tempera- unaffected by the ambient temperature.
ture. The placement temperature used for the analysis is 20°C. From the two-dimensional analysis, plots for the temperature
The actual maximum temperature in the dam by November 7 contour and stress distributions in the body of the dam for the
was about 40°C. This rise in temperature is attributed to the different constructed lifts are shown in Fig. 15. The maximum
change of RCC placement temperature during the hot summer temperature recorded after the end of construction was 37.7°C in
months, starting from June through September. The placement of the core of the dam.
RCC continued until August 8, 2000 and resumed on September
24, with the variation of RCC placement temperature reaching a

Fig. 12. Comparison of thermal analysis predictions and actual read- Fig. 14. Predicted temperature history at 365 m ASL elevation
ings of thermocouples until November 7 at elevation of 365 m ASL measured from upstream face

JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003 / 183


Fig. 15. Two-dimensional temperature and stress distribution for different constructed lifts: 共a兲 temperature distribution at Lift 3; 共b兲 stress
distribution at Lift 3; 共c兲 temperature distribution at Lift 6; 共d兲 stress distribution at Lift 6; 共e兲 temperature distribution at Lift 12; 共f兲 stress
distribution at Lift 12; 共g兲 temperature distribution at Lift 19; 共h兲 stress distribution at Lift 19

184 / JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003


Fig. 16. Three-dimensional temperature and principal stress distribution in body for block length of 15 m: 共a兲 temperature distribution at end of
casting for half of 15 m block length; 共b兲 principal stress at end of casting for half of 15 m block length; 共c兲 temperature distribution at end of
heat of hydration for half of 15 m block length; 共d兲 principal stress at end of heat of hydration for half of 15 m block length; 共e兲 temperature
distribution after one year for half of 15 m block length; 共f兲 principal stress after one year for half of 15 m block length

Three-Dimensional Results
Three different blocks of 15, 30, and 45 m lengths were modeled.
These blocks were taken at the central monolith in the dam. The
maximum temperature recorded after the end of construction was
37.7°C for a 15 m block length, as shown in Fig. 16. After one
year, a gradual decrease in temperature of the dam core is ob-
served. Similar trends were observed for block lengths of 30 and
45 m. It is predicted that the temperature of the inner core of the
dam will coincide with the mean annual temperature, but this will
take many years.
Fig. 16 shows the predicted temperature and principal stress
contours developed in the dam body for a block length of 15 m.
Fig. 17. Predicted temperature at elevation of 355 m ASL for three-
The results indicate that the maximum principal stresses decrease
dimensional model
with decreasing temperatures of the dam.

JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003 / 185


Fig. 18. Principal stresses at center of dam for 15 m block length

Fig. 17 shows the predicted temperature for two different


nodal points at two locations for the three-dimensional model.
Again the results demonstrate that the temperature at the surface
is affected by the environmental conditions and the temperature in Fig. 20. Principal stress path along upstream face for different block
the center of the dam is almost unaffected by air temperatures. lengths
Fig. 18 represents the principal stresses at the center of the
dam for a block length of 15 m for different heights of the dam.
The results indicated that the first peak tensile stress occurs
shortly after placement of the RCC layers. The tensile stress then
increases and remains nearly constant during construction before Conclusion
reducing because of the effect of the reservoir load on the up-
stream face. It also shows that the peak tensile stresses occur The Tannur RCC Dam is constructed with a crest length of 242 m
within 10 days of placement. and 17 contraction joints at approximately 15 m spacing. How-
Fig. 19 represents the cross-valley stress 共z direction兲 for a ever, from the computational results presented in this study, it is
point at the center of the base of the dam for different block concluded that a 20 m average joint spacing is satisfactory to
lengths. Again, the first peak stresses occur shortly after the place- accommodate contraction openings of up to 2.5 mm if cracking is
ment of the RCC layers. to be avoided. It was observed that if the RCC temperature is
Fig. 20 shows the principal stress path along the upstream face being raised to 26°C, the maximum peak temperature in the core
for different block lengths. The results indicated that the stress of the dam could reach 43°C, which is less than the predicted
developed for a block length of 15 m is lower than that for block peak temperature of 45°C established in the design report to cause
lengths of 30 and 45 m. At a location of 30 m elevation above the cracks in the dam. Furthermore, in the design report 共Howard
base of the dam, the peak value of the principal stress is 0.42 MPa Humphreys 1995兲, it was concluded that the design criteria re-
for a 15 m block length, whereas for 30 and 45 m block lengths quire that the RCC have a compressive strength of 20 MPa, and a
the peak stress increases to 0.94 and 1.1 MPa, respectively. tensile strength of over 1.35 MPa.
The dam does not experience tensile stresses in excess of the
tensile strength of the concrete. The tensile thermal stresses due to
a temperature drop in the interior of an RCC gravity dam are
partially compensated by the action of the weight of the concrete
and water pressure.
Results are very sensitive to the time of the year, the ambient
air temperature, the RCC placement temperature, and the rate of
heat of hydration.
In conclusion, a thermal stress analysis using a finite-element
method showed that the method is efficient and reliable. The tem-
peratures and the stress distribution in the dam as predicted by the
finite-element method are reasonable and predict the evolution of
temperature and thermal stress with time. Using a commercially
available finite-element program and the available laboratory
data, the incremental construction process of a mass-concrete
structure can be modeled to produce results that can be used in
practical applications. The results from the analysis correlate
Fig. 19. Cross-valley stress 共z direction兲 at center of base of dam for
closely with the actual thermal data obtained from the construc-
different block lengths
tion instrumentation.

186 / JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003


Acknowledgments high sand RCC mixes and in-situ modification of RCC used for
construction of Cadiangullong Dam NSW.’’ ANCOLD Bulletin, Syd-
The writers thank Brian Forbes and Francisco Andriolo for their ney, Australia.
discussions, advice, and ideas given at the start of and during the Howard Humphreys Consulting Engineers. 共1995兲. ‘‘The study and de-
preparation of this paper. The writers also thank the owner of sign of Tannur Dam.’’ Design Rep., Vol. III, prepared for Jordan Val-
ley Authority.
Tannur Dam, the Jordan Valley Authority, for allowing them to
Ishikawa, M. 共1991兲. ‘‘Thermal stress analysis of concrete dam.’’ Com-
prepare this paper for publication. put. Struct., 40共2兲, 347–352.
Neville, A. M., and Brooks, J. J. 共1994兲. Concrete technology, Long-
man’s, Singapore.
References Tatro, S., and Schrader, E. 共1992兲. ‘‘Thermal analysis for RCC—A prac-
tical approach.’’ Proc., Roller Compacted Concrete III, ASCE, New
Ayotte, E., Massicotte, B., Houde, J., and Gocevski, V. 共1997兲. ‘‘Model- York, 389– 406.
ing the thermal stresses at early ages in a concrete monolith.’’ ACI Truman, K. Z., Petruska, D., Ferhi, A., and Fehl, B. 共1991兲. ‘‘Nonlinear,
Mater. J., 94共6兲, 577–587. incremental analysis of mass-concrete lock monolith.’’ J. Struct. Eng.,
Crichton, A. J., Benzenati, I., Qiu, T. J., and Williams, J. T. 共1999兲. 117共6兲, 1834 –1851.
‘‘Kinta RCC Dam—Are over-simplified thermal-structure analyses U.S. Army Corps of Engineers. 共1997兲. ‘‘Thermal studies of mass con-
valid?’’ Proc., ANCOLD Conf. on Dams. crete structures.’’ Engineering Technical Letter 1110-2-542, Washing-
Dunstan, M. R. H. 共1981兲. ‘‘Rolled concrete for dam—laboratory trial of ton, D.C.
high fly ash content concrete.’’ CIRIA Technical Note 105, London. Zhang, Z., and Garga, V. K. 共1996兲. ‘‘Temperature and temperature in-
Forbes, B. A., and Williams, J. T. 共1998兲. ‘‘Thermal stress modeling, duced stresses for RCC dams.’’ Dam Eng., VII共2兲.

JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES © ASCE / NOVEMBER 2003 / 187

You might also like