Professional Documents
Culture Documents
Thermal-Structural Modeling and Temperat
Thermal-Structural Modeling and Temperat
Abstract: A coupled thermal-structural analysis is carried out using both a two- and a three-dimensional finite-element method. The
computer program ANSYS is used and simulates the construction process of a roller compacted concrete 共RCC兲 dam. Thermally induced
stresses are computed for the 60 m high RCC Tannur Dam in Jordan. The actual temperature distribution in the body of the dam measured
by thermocouples is compared with that obtained by ANSYS; generally, a good agreement is obtained. The study demonstrates that
detailed thermal stress analysis should be performed for large RCC dams to provide a basis to minimize and control the occurrence of
thermal cracking.
DOI: 10.1061/共ASCE兲0887-3828共2003兲17:4共177兲
CE Database subject headings: Thermal stresses; Finite element method; Dams, concrete; Cracking; Temperature effects.
In this paper, the determination of the thermal and structural Tannur Dam is constructed of high paste content RCC, placed in
stresses and temperature control requirements is described for the 300 mm thick layers with a facing made of grout enriched roller
60 m high Tannur RCC Dam in Jordan. Temperature distribution compacted concrete 共GE-RCC兲. The concrete is designed to have
with time, concrete placement temperature limits, and joint spac- a very low air void content and to achieve maximum strength and
ing requirements to minimize cracking are also discussed. density with minimum permeability and with a good bond be-
tween layers. The dam is founded on limestone of the Wadi As Sir
and Fuheis, Hummar Shueib Formation. A two-layer cement
Description of Dam grout curtain will limit the quantity of seepage.
The upstream face of the dam is vertical, with a batter of 1:1
The Tannur Dam is the first completed RCC dam in the Middle below Elevation 356 to the foundation level. The stepped down-
East. It is a concrete gravity dam, approximately 60 m high, built stream face has a slope of 0.8共H兲: 1共V兲 共Fig. 1兲.
to impound the floodwater of the Wadi Al Hasa. It retains a res- This profile has been adopted to reduce vertical stresses by a
ervoir at an elevation of 400 m above sea level 共ASL兲 with a more distributed loading, and to achieve higher compressive
16.8⫻106 m3 capacity. The dam is situated some 50 km south of stresses at the upstream heel due to the vertical loading—thus
Karak. The yield of the reservoir will help satisfy the future water reducing tensile stresses at the location under seismic loading.
demand for industry and agriculture in the southern Ghors. The The dam is a straight structure 242 m long at the crest.
Temperature Control Requirements Table 2 shows the actual data recorded for the RCC placement
temperature for the time period between June and October of
Significant thermal induced stresses are developed as a result of 2000. It is shown, for example, that the month of June had an
the heat of hydration of the cementitious materials in RCC dams. average recorded temperature of 25.5°C, whereas the calculated
The temperature distribution through the dam and its evolution temperature for the same month 共Table 1兲 is about 25.7°C.
with time depend on the following: The average monthly ambient air temperature is shown in
• RCC concrete properties, Table 3. RCC placement was assumed to take place in the cooler
• Climatic factors, months of the year—i.e., from December of 1999 to the end of
• Construction procedure, April of 2000. The aggregate production and stockpiling started in
• Thickness of lifts, the summer. Based on the average ambient air temperature from
• Initial temperature of lifts, and December to April of 12°C, an average RCC placement tempera-
• Interval between their successive placements.
These thermally induced stresses can be significant enough to
induce cracks in the RCC.
Recent developments in sophisticated software based on ad-
vanced numerical methods, together with the continually increas- Table 2. Average Actual Data Record of Rolled Compacted
ing power of computers allow complex analyses for such thermal- Concrete Placement Temperature during Construction
structural problems. The ANSYS computer program based on the Month Temperature Temperature
finite-element method was used to analyze the thermal behavior 共2000兲 at day 共°C兲 at night 共°C兲
of the Tannur Dam. The desired outcome of the numerical analy-
May 24.28 23.2
sis was
June 25.52 25.16
• To determine the spatial distribution of temperature and its
July 25.8 25.7
evolution with time,
August 26.15 25.7
• To determine the stress distribution during and following the
September 24.4 23.4
dam construction and at the time of reservoir filling,
October 24.7 24
• To identify the appropriate joint spacing to minimize the de-
velopment of transverse cracking, and
Table 3. Average Monthly Air Temperature
• To determine the concrete placement temperature limits.
Ambient air
Month temperature 共°C兲
Concrete Placement Temperature January 10
February 11.1
The temperature of the concrete aggregate has the greatest influ- March 13.6
ence on the initial temperature of the fresh RCC. Due to the low April 17.8
volume of mix water and the minor temperature difference of the May 21.5
water compared to the aggregate, the water temperature has a
June 24.5
much less significant effect on the overall temperature. Table 1
July 25.5
provides the basis for estimating the aggregate temperature and
August 25.6
approximating the RCC placement temperature used in the analy-
September 24.2
sis. Since aggregate production will be done concurrently with the
October 21.3
RCC placement, stockpile temperatures should closely parallel
November 16.4
the average monthly ambient temperatures. Some heat is added
December 6.7
because of screening, crushing, and transportation activities.
The dam was modeled as a two-dimensional transient heat trans- Heat of Hydration
fer model using a birth and death procedure to simulate the real
construction process of the dam. The dam is divided into 19 lay- Heat of hydration as a function of time was obtained from several
ers. Each layer has a thickness of 3 m, constructed in 10 days, and tests performed in the laboratory. Fig. 3 shows the heat of hydra-
the last layer has a thickness of 2 m. The PLANE77 element type, tion produced with time for Jordanian cement with and without
available in the ANSYS library, was used in the finite-element the addition of pozzolan. In this study, the heat of hydration was
simulated as a ramp input, as shown in Fig. 4.
Finite-Element Results Fig. 13. Actual temperature contours at end of rolled compacted
concrete placement
Two-Dimensional Results
The temperature distribution shown in Fig. 10 is for the specific maximum of 26°C and with the reduction of the cement content
location at an elevation of 355 m ASL—i.e., 12 m above the base to 120 kg/m3 starting in July. In all cases, the overall temperature
of the dam. This shows that the maximum RCC temperature is in the body of the dam did not exceed 43°C.
approximately 37.7°C. It is shown that the temperature reached its Fig. 12 shows the measured temperature through November 7
maximum in the first 10 days due to the high rate of hydration compared to that predicted by ANSYS. It should be clearly under-
that remained constant for a long period of time because heat stood that during the months of August and September no RCC
transfer from the core of the dam to the surface is very slow. placement took place, and consequently readings of thermo-
Further, the heat conduction due to the construction of the over- couples were not made. Fig. 13 shows the actual temperature
lying layers of RCC prevents internal heat loss from the con- contours measured at the end of construction of the dam. Heat of
structed lift surface. hydration testing during the construction of the dam established
Fig. 11 shows a comparison between the predicted temperature that the actual heat of hydration of the cement in use is 309 J/g.
rise and the actual thermocouple readings at an elevation of 365 Fig. 14 shows the predicted temperature for different nodal
m ASL, covering a period of 90 days between April and the end points at different locations. The results demonstrate that the tem-
of June. Generally, a good agreement has been obtained. The perature at the surface is affected by the environmental condi-
small differences between the predicted and the actual readings tions, and the temperature in the center of the dam is essentially
could be attributed to the change of the RCC placement tempera- unaffected by the ambient temperature.
ture. The placement temperature used for the analysis is 20°C. From the two-dimensional analysis, plots for the temperature
The actual maximum temperature in the dam by November 7 contour and stress distributions in the body of the dam for the
was about 40°C. This rise in temperature is attributed to the different constructed lifts are shown in Fig. 15. The maximum
change of RCC placement temperature during the hot summer temperature recorded after the end of construction was 37.7°C in
months, starting from June through September. The placement of the core of the dam.
RCC continued until August 8, 2000 and resumed on September
24, with the variation of RCC placement temperature reaching a
Fig. 12. Comparison of thermal analysis predictions and actual read- Fig. 14. Predicted temperature history at 365 m ASL elevation
ings of thermocouples until November 7 at elevation of 365 m ASL measured from upstream face
Three-Dimensional Results
Three different blocks of 15, 30, and 45 m lengths were modeled.
These blocks were taken at the central monolith in the dam. The
maximum temperature recorded after the end of construction was
37.7°C for a 15 m block length, as shown in Fig. 16. After one
year, a gradual decrease in temperature of the dam core is ob-
served. Similar trends were observed for block lengths of 30 and
45 m. It is predicted that the temperature of the inner core of the
dam will coincide with the mean annual temperature, but this will
take many years.
Fig. 16 shows the predicted temperature and principal stress
contours developed in the dam body for a block length of 15 m.
Fig. 17. Predicted temperature at elevation of 355 m ASL for three-
The results indicate that the maximum principal stresses decrease
dimensional model
with decreasing temperatures of the dam.