Methodology of Construction/Expansion Joint

1) CREATION OF THE JOINT BY HEAVY DUTY CUTTER

After Construction of CC Road, Creating a Grove having 6mm width and 100mm depth with heavy duty
cutter at every 5mtr distance.

Preparing Grove by Heavy Duty Cutter

2) CLEANING OF THE JOINT IN TWO STEPS

Step-1 Cleaning of the surface and surrounding pavement of the routed joint out of any debris by Wind
Blower/Manually.

Step-2 Cleaning inside of joint with Air Blower out of any loose material or debris before sealant application.

3) APPLICATION OF SEALENT
Apply of sealant (per attached Data Sheet) at application temperature based on material specification and
recommended manufacturer temperature into the joint after cleaning of joint.
Sealant Material shall be used as per Tender Specification and MoRT&H Specification 602.2.10 page no
268.

Sealant Material: Sika Polysulphide Pour Grade (Confirms to: BS 5212 – 1990)

4) SPREADING CEMENT ON TOP OF THE APPLIED SEALANT


If needed, manual cement application on top of the sealed joint helps faster curing time and traffic
opening when lane closure is critical.