Professional Documents
Culture Documents
Manual Sacs Inplace Analysis
Manual Sacs Inplace Analysis
CONTENTS
1. GENERAL
2. SCOPE OF WORK
3. REFERENCE
4. CONSTRUCTION METHOD
5. INSPECTION
6. FLOW CHART
7. ILLUSTRATION
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD
1. GENERAL
This methode use for excavation in all kinds of soils, back filling, and scraping to
describe the sequences and requirements of this work in this Project
2. SCOPE
This is to assure that the requirements of excavation, back filling and scraping follow the
standards, contract specifications and client requirements. To obtain good workmanship
and safety in all activities .
3. REFERENCE
4. CONSTRUCTION METHOD
4.1. Excavation
Excavation and loading will be done by Excavator. Excavated material will be loaded
by Dump Truck go to the designated area or disposal area.
4.3. Scraping
a. Stripping and removing of topsoil.
b. Loading and hauling of tripped topsoil to the stockpile area or final disposal
area.
c. Removal of contaminating matter, such as trees, branches, stumps, roots and
grass.
d. Grading, sloping, compacting and other relevant work for proper stockpiling,
whether temporary or permanent.
5. INSPECTION
The inspection control points shall be same as per the control diagram in the Quality
Plan .
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD
6. FLOW CHART
EXCAVATION
START
PREPARATION OF
EQUIPMENT
EXCAVATION
SELECTED MATERIAL
EXCAVATED
AND LOADING
HAULING DISPOSAL
AREA
FINISH
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD
6. FLOW CHART
BACKFILLING
START
PREPARATION OF
EQUIPMENT
SELECTED MATERIAL
AND HAULING
SPREADING AND
COMPACTING
NO
CHECK
YES
FINISH
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD
6. FLOW CHART
SCRAPING
START
PREPARATION OF
EQUIPMENT
STRIPPING AND
REMOVING
LOADING AND
HAULING
FINISH
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
ROCK EXCAVATION Date BY CHD APVD
Turning Zone untuk Giant Breaker Turning Zone untuk Excavator Area Parking DT
1. Rock zone area was excavated by Giant Breaker
2. Excavator loading material excavated and loaded by Dump Truck
Turning Zone untuk Giant Breaker Rolling Area untuk Turning Zone untuk Excavator Area Parking DT
Dozer
1. Rock zone area was excavated by Giant Breaker
2. Material excavated was collected by Bulldozer at Loading Area
3. Material excavated at loading area was loaded by Dump Truck get into Disposal area
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
EXCAVATION FOR SMALL AREA Date BY CHD
Supervisor
Supervisor
DT
Trafic Oficer
Public Transport
AWAS !
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
EXCAVATION FOR LARGE AREA Date BY CHD
Supervisor
Supervisor
Rev.
0
APVD
Supervisor
Supervisor
Rev.
0
APVD
Supervisor
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
BACKFILLING Date BY CHD
Supervisor
Water Tanker
Supervisor
Water Tanker
Re compaction after water pouring
Supervisor
Supervisor
Embankment
Rev.
0
APVD
Water Tanker
Rev.
0
APVD