Job No. : Rev.

CONSTRUCTION METHOD Doc. No. : 0


OF
EARTH WORK Date BY CHD APVD

CONTENTS

1. GENERAL

2. SCOPE OF WORK

3. REFERENCE

4. CONSTRUCTION METHOD

5. INSPECTION

6. FLOW CHART

7. ILLUSTRATION
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD

1. GENERAL

This methode use for excavation in all kinds of soils, back filling, and scraping to
describe the sequences and requirements of this work in this Project

2. SCOPE

This is to assure that the requirements of excavation, back filling and scraping follow the
standards, contract specifications and client requirements. To obtain good workmanship
and safety in all activities .

3. REFERENCE

3.1. Owner Specification

4. CONSTRUCTION METHOD

4.1. Excavation
Excavation and loading will be done by Excavator. Excavated material will be loaded
by Dump Truck go to the designated area or disposal area.

4.2. Back filling


a. Selection and loading of backfill material at the stockpile area and / or
desidnated place.
b. Hauling of backfill material from stockpile area and / or designated place.
c. Spreading of backfill material in layers.
d. Compacting of backfill material in layers.
e. Moisture control.
f. Final grading after backfilling.

4.3. Scraping
a. Stripping and removing of topsoil.
b. Loading and hauling of tripped topsoil to the stockpile area or final disposal
area.
c. Removal of contaminating matter, such as trees, branches, stumps, roots and
grass.
d. Grading, sloping, compacting and other relevant work for proper stockpiling,
whether temporary or permanent.

5. INSPECTION

The inspection control points shall be same as per the control diagram in the Quality
Plan .
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD

6. FLOW CHART
EXCAVATION

START

PREPARATION OF
EQUIPMENT

EXCAVATION

SELECTED MATERIAL
EXCAVATED
AND LOADING

HAULING DISPOSAL
AREA

FINISH
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD

6. FLOW CHART
BACKFILLING

START

PREPARATION OF
EQUIPMENT

SELECTED MATERIAL
AND HAULING

SPREADING AND
COMPACTING

NO
CHECK

YES

FINISH
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
EARTH WORK Date BY CHD APVD

6. FLOW CHART
SCRAPING

START

PREPARATION OF
EQUIPMENT

STRIPPING AND
REMOVING

LOADING AND
HAULING

FINISH
Job No. : Rev.
CONSTRUCTION METHOD Doc. No. : 0
OF
ROCK EXCAVATION Date BY CHD APVD

Turning Zone untuk Giant Breaker Turning Zone untuk Excavator Area Parking DT
1. Rock zone area was excavated by Giant Breaker
2. Excavator loading material excavated and loaded by Dump Truck

Turning Zone untuk Giant Breaker Rolling Area untuk Turning Zone untuk Excavator Area Parking DT
Dozer
1. Rock zone area was excavated by Giant Breaker
2. Material excavated was collected by Bulldozer at Loading Area
3. Material excavated at loading area was loaded by Dump Truck get into Disposal area
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
EXCAVATION FOR SMALL AREA Date BY CHD

Supervisor

Supervisor

DT
Trafic Oficer
Public Transport
AWAS !
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
EXCAVATION FOR LARGE AREA Date BY CHD

Supervisor
Supervisor
Rev.
0

APVD

Supervisor

Supervisor
Rev.
0

APVD

Supervisor
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
BACKFILLING Date BY CHD

Supervisor

Dropping Material Distance is arranged to provide designed layer thicness

Water Tanker
Supervisor

Water Tanker
Re compaction after water pouring
Supervisor

Designed Tihicknes For Each Layer


Backfilling Costruction commence layer by layer properly
Job No. :
CONSTRUCTION METHOD Doc. No. :
OF
EXCAVATION OVER EMBANKMENT Date BY CHD
AREA

Supervisor

Embankment
Rev.
0

APVD

Water Tanker
Rev.
0

APVD