TIME SCHEDULE

Paket Kegiatan : Supervisi Pembangunan Prasarana Pengendalian Banjir Sungai Kampar di Desa Teratak Kec. Rumbio Jaya Kabupaten Kampar
Satker : PJSA WS Indragiri-Akuaman, WS Kampar, WS Rokan, WS Siak Provinsi Riau
PPK : Sungai dan Pantai I
Sumber Dana : APBN
Tahun Anggaran : 2019

BULAN I (APRIL-MEI) BULAN II (MEI-JUNI) BULAN III (JUNI-JULI) BULAN IV (JULI-AGUSTUS) BULAN V (AGUSTUS-SEPT.) BULAN VI (SEPT.-OKT.) BULAN VII (OKT.-NOV.)
10/04/19 17/04/19 25/04/19 02/05/19 10/05/19 17/05/19 25/05/19 01/06/19 09/06/19 16/06/19 24/06/19 01/07/19 09/07/19 16/07/19 24/07/19 31/07/19 08/08/19 15/08/19 23/08/19 30/08/19 07/09/19 14/09/19 22/09/19 29/09/19 07/10/19 14/10/19 22/10/19 29/10/19
BOBOT
NO. URAIAN s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d KETERANGAN
(%)
16/04/19 24/04/19 01/05/19 09/05/19 16/05/19 24/05/19 31/05/19 08/06/19 15/06/19 23/06/19 30/06/19 08/07/19 15/07/19 23/07/19 30/07/19 07/08/19 14/08/19 22/08/19 29/08/19 06/09/19 13/09/19 21/09/19 28/09/19 06/10/19 13/10/19 21/10/19 28/10/19 05/11/19
MGG 1 MGG 2 MGG 3 MGG 4 MGG 5 MGG 6 MGG 7 MGG 8 MGG 9 MGG 10 MGG 11 MGG 12 MGG 13 MGG 14 MGG 15 MGG 16 MGG 17 MGG 18 MGG 19 MGG 20 MGG 21 MGG 22 MGG 23 MGG 24 MGG 25 MGG 26 MGG 27 MGG 28
1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
I. BIAYA LANGSUNG PERSONIL
A. Tenaga Ahli Profesional 100.00
1 Ketua Tim 45.685 RENC. 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740 1.523 1.740
REAL.
B. Tenaga Penunjang
1 Asisten Ahli Bidang Sipil 16.591 RENC. 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632 0.553 0.632
REAL.
2 Surveyor 2.628 RENC. 0.409 0.467 0.409 0.467 0.409 0.467
REAL. 90.00
3 Juru Gambar/Tenaga Administrasi 8.656 RENC. 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330
REAL.
II. BIAYA LANGSUNG NON-PERSONIL
II.1 Perjalanan Dinas
1 Ketua Tim 1.618 RENC. 0.116 0.231 0.231 0.231 0.231 0.231 0.231 0.116
REAL.
2 Asisten Ahli Bid. Sipil 1.618 RENC. 0.116 0.231 0.231 0.231 0.231 0.231 0.231 0.116 80.00
REAL.
3 Surveyor 0.462 RENC. 0.116 0.116 0.116 0.116
REAL.
II.2 Biaya Kantor
A. Bahan/Perlengkapan Kantor
1. Komputer + Printer (Sewa) 2.312 RENC. 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881 0.0771 0.0881
REAL. 70.00
2. Bahan Kantor / ATK 1.734 RENC. 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661 0.0578 0.0661
REAL.
3 Sewa Meja Tulis dan Kursi 1.850 RENC. 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705 0.0617 0.0705
REAL.
B. Komunikasi/Surat Menyurat
1. Telepone/Fax, dan Surat Menyurat 0.925 RENC. 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352 0.0308 0.0352
60.00
REAL.
II.3 BIAYA SARANA DAN PRASARANA SUPERVISI
A. Biaya Sarana
1 Sewa Waterpass 3.468 RENC. 0.405 0.462 0.405 0.462 0.405 0.462 0.405 0.462
REAL.
2 Sewa Theodolite 3.468 RENC. 0.405 0.462 0.405 0.462 0.405 0.462 0.405 0.462
REAL.
50.00
3 Tenaga Lokal 2.477 RENC. 0.289 0.330 0.289 0.330 0.289 0.330 0.289 0.330
REAL.
4 Bahan Survey 0.149 RENC. 0.074 0.074
REAL.
5 Sewa Kendaraan Roda 2 + BBM 2.081 RENC. 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793 0.0694 0.0793
REAL.
B. Biaya Prasarana 40.00
1. Sewa Mess 1.618 RENC. 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617 0.0539 0.0617
REAL.
2 Sewa Drone 0.495 RENC. 0.1651 0.1651 0.1651
REAL.
II.4 BIAYA PEMBUATAN GAMBAR
A. Biaya Pembuatan Gambar Pelaksanaan
1 Gambar Pelaksanaan 0.595 RENC. 0.5945 30.00
REAL.
II.5 BIAYA PEMBUATAN LAPORAN
1 Rencana Mutu Kontrak (RMK) 0.099 RENC. 0.0991
REAL.
2 Laporan Pendahuluan 0.099 RENC. 0.0991
REAL.
3 Laporan Bulanan (3 x 7 bulan) 0.347 RENC. 0.0495 0.0495 0.0495 0.0495 0.0495 0.0495 0.0495 20.00
REAL.
4 Laporan Justifikasi Teknis/Kajian Teknis 0.099 RENC. 0.0991
5 Laporan Penunjang: REAL.
- Lap. Topografi ( Lap. Pengukuran Awal dan Akhir ) 0.099 RENC. 0.0495 0.0495
REAL.
6 Laporan Akhir 0.198 RENC. 0.1982
10.00
REAL.
7 Laporan Backup Data Final Quantity/Quality 0.149 RENC. 0.1486
REAL.
8 Master Copy Laporan & Gambar ( External Harddisk ) 0.330 RENC. 0.3303
REAL.
9 Foto Dokumentasi 0.149 RENC. 0.1486
REAL.
-
JUMLAH 100.00
RENCANA 4.81 5.02 4.82 5.04 3.18 3.10 2.72 3.15 3.18 3.10 2.72 3.15 3.34 3.10 2.72 3.15 3.18 3.10 2.72 3.15 3.18 3.10 3.89 4.41 4.80 4.94 2.72 4.52
KOMULATIF RENCANA 4.81 9.83 14.65 19.69 22.87 25.97 28.68 31.84 35.01 38.12 40.83 43.98 47.33 50.43 53.14 56.30 59.47 62.58 65.29 68.45 71.62 74.73 78.61 83.02 87.82 92.76 95.48 100.00
REALISASI
KOMULATIF REALISASI
DEVIASI

DISETUJUI OLEH : PEKANBARU, 10 APRIL 2019


PPK SUNGAI DAN PANTAI I DIBUAT OLEH :
SNVT PELAKSANAAN JARINGAN SUMBER AIR PT. WANDRA CIPTA ENGINEERING CONSULTANT
WS INDRAGIRI-AKUAMAN, WS. KAMPAR, WS. ROKAN,
WS. SIAK PROVINSI RIAU

DANANG SUKMANA, ST. M.Eng. YOFIE HASUDUNGAN PARNINGOTAN MARPAUNG, ST.


NIP. 19880606 201012 1 002 TEAM LEADER