Initial Process Time Duration Requirment

Admin personal to visit places and search


Location of Collection Point Search Visit Approval
the desired location
Signing of Agreement (Site
Preparation Sign Legal Assistant
Owner/Franchisee)
IF Franchisee. Visit to Head Office
Security Deposit Cheque received
(Frenchisee)
No. of Days after
After Signing of Agreements Date Verified By
Approval
Rennovation Plan 10 Days Design, color scheme, Interior
Renovation Layout Circulation (after
5 Days
agreement )

Renovation 15 ays Carpenter, Mason, Plumber, Painter


( Agreement for future Set up working)
Fruniture 5 Days To be purchased
Purchase/Provision of PC/Printer/Barcode
15 Days
printer/Centrifuge IT Staff needed
Staff hiring 15 Days
Sign Board 10 Days Sign Board Company
Marketing Flyer 15 Days Marketing person will be required.
Designing of Marketing Material
IT related matters 15 Days IT Staff needed to establish Software and
Networking process
Inspection by Manager before Opening &
3 Weeks
Picture sharing with management
Point Opening 25Days (Max)
At the day of
Issuance of Memo
Opening
Record updation on all printed stationary
Record updation on website
Before Opening:
Share % decided (if franchised location)
Staffing Responsibility (MDC/Franchisee)
Staff (Franchisee /MDC) 15 working days
Orientation/Training at Main Lab (After hiring)
Staff on job training at Regional
10 days
Collection Centers
Approval of Manager/Director